HomeMy WebLinkAboutContract 42789-CO1 (2)City of Fort Worth
Change Order Request
CITY SECRETARY
CONTRACT NO. Y:~ l ~ °1 -co l
Change Order No . Date T PW Project No . Fund ing (FAC )
1 (one) 2/28/12 R 107 541200 0357000
Facil ity and Project Des cription City Secretary Contract No .
Auto Pound Renovation 42789
ORIGINAL CONTRACT AMOUNT ................................................................ $179 ,950
EXTRAS TO DATE .................................................................... . $ 0
CREDITS TO DATE ................................................................... . $ 0
CONTRACT COST TO DATE ................................................................................................. . $ 179 ,950
AMOUNT OF PROPOSED CHANGE ORDER ........................................................................... . $ 3 ,510
REVISED CONTRACT AMOUNT ............................................................................................ . $ 183,460
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS ........................................................... . $ 25 ,000
REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS ............................. : ........................... . $ 21,490
ADDITIONAL FUNDING (IF NECESSARY) ................................... --.......................................... . 0
l
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL:
Provide all labor and materials as per attached :
PCR 1 -delete lay in ceilings and provide gyp board ceil ings in rooms 101 ,102 and 103
As per Energy Code requirements
PCR 2-Add additional column furring in room 104
PCR 3-delete epoxy floor paint in Break room 104
PCR 4-replace door 101 with new 3-0 X 7-0 door and frame
TOTAL ADD
, OfflCIAL RECORD
CITY SECRETARY
fT, WORTH, TX
\ -Aaa
Add
(Deduct)
Add
$1 ,966
$ 317
($ 363)
$1 ,590
$ 3 ,510
~
It is understoo d and agreed that the acceptance of this Change Order by the co ntractor constitutes an accord and satisfaction and rep resents paym ent in fu ll (both time
and mon ey ) fo r all costs aris ing out of, or incid ental to , the above C hange Order
Contractor's Name
Imperial Construction , Inc.
Origina l Contract Ti me Ad ditional Appro ved Time To Da te Approve d Contract Time To Date Add itiona l Tim e For T his Chan ge Order
90 cd O cd 90 cd O cd
Contractor-Tegrity Contractors , Inc
~ w\.ctwtT\~
Date /
~c)../i)__
Architectural Services Manager Date
()4; f. S: liJJL ~
Date
3/B/lz
Date
Distri but ion :
File
Constructi on Manager
Project Manager 1/..!.~../-.:..;._;,..;;.;.~~~~++-----'"tr"U
Co ntractor
03 -09 -12
Change Request: 1
Date: 2/23/2012
To: City of Fort Worth From: Eddie Whitworth
401 West 13th Tegrity Contractors , Inc
Fort Worth , Texas 76102 106 East University Dr . #100
Attn : Alan Bagamery McKinney, Texas 75069
Re: Police Auto Pound Facility
Provide and install gyp. board ceiling in lieu of lay-in tile and grid as per city
' in Rooms #101, 102 and 103
Credit for lay-in grid system
Provide and install new gyp. Board ceiling
Materials and labor to tape, bed and paint ce iling
Materials and labor to install replace wall between Rm #102
and #103 as per request
Provide and install (5) access panels in ceilings
See attached
Subtotal $
Tegrity Profit & Overhead $
Bond Fee $
Total $
1,735 .00
173.50
57 .26
1~
The Contract Time will be changed by ( 0 ) days.
$ (1 ,390 .00 )
$ 1,740 .00
$ 495 .00
$ 650 .00
$ 240.00
" \ \~IP ·
®
MATR I X
Februa,y 15, 2012
Tegrity Contractors, Inc.
106 E. University, McKinney, TX 75069
ATTN: Eddie Whitworth
Re: Brennan Auto Pound-Ceiling Change & Additional Wall
Matrix Interiors is pleased to quote on the above referenced project as follows
Delete acoustic ceiling panels & grid DEDUCT $1,390.00
Install Suspended drywall ceiling ADD $1,740.00
Frame Additional wall between fitness are & restroom ADD $ 650.00
Our exclusions and inclusions are listed below. This quote expires in 30 davs .
EXCLUSIONS
* Any work not specifically noted on the plans or below
* Any work outside our scope or the areas shown
* Any work at existing conditions not noted
* Payment / performance bond
* Demolition of any kind
* Clean of other trades or dumpsters
* Stocking of items F.B.O . (ie frames, doors)
* Caulking or sealing of penetrations by others
* Corner guards, chair rails or any wall protection
* Reveals or any special accessories
* Millwork, finished carpentry or finished wood
* Any wood framing
* Any Sales Tax
* Any engineering or stamped shop drawings
* Any water proofing or exterior sealants
* Any exterior finishes
* Any ceiling or roof deck insulation
* Any FRP
* Any after-hours work
* Any repair or replacement of existing ceiling tile or grid
INCLUSIONS
* Work as shown on plans dated 7 /18 /11
* Install Drywall on metal stud framing
* Interior wall sound batt insulation
* Delete the installation of acoustic ceilings
* Add framing & installing a suspended gyp board ceiling in both restrooms & fitness area
Please call if you need additional information.
Sincerely,
Chip Smith
1::.06 Tappan Cirde i Carrollton, TX 75006 I F'H: 972-245-1022 J FAX: 972-245-::.4
wwvv .matrixi nterior .com
Catapult Painting, LLC
4105 W Spring Creek Pkwy, Ste 604
Plano, TX 75024
PHONE: 972-596-4118 FAX: 972-767-4557
E-MAIL: info@sambecca .com
REQUESTED BY:
Tegrity Contractors, Inc.
106 E. University, Ste 100
McKinney , TX 75071
EXTRA
Description
Estimate
Date Estimate#
2/16 /2012 19350
PRICING VALID FOR 60 DAYS
PROJECT NAME
Vehic le Impound Facility Alterations
2500 Brennan Avenue
Ft Worth, TX 76106
PO 11-36-09-7000
Total
Ceiling change from 2x2 lay in Ceiling to Sheet Rock Ceiling (roo ms #101, 102 , 103)
PRICE COMPLETE: 495.00
-
We look forward to working with y ou. I Total I $495 .00
RX Datemme 02/23/2012 13:34 214 343 4072
Feb 23 12 D2:23p COMMERCIAL DPNGS . 214 343 4072
COMMERCIAL 0PENINGS 9 INC~
-------------------------------
10990 PETAL ST .. SUITE 700 • DALLAS , TEXAS 75236 • (214) 343-0080 • FAX (214) 343-4072
PROPOSAL
DATE 1cuo1u, ~....-?\.J
Bid Dote~ r)3
RE p ,..1 c..i ........ ,
I 7
P.001
p. 1
We propose to furnish the materials described and priced below per section ____ of the specifications, with
exceptions (if any) as noted.
I -w ~ H. M f,, /""' 1 o'"\. o ~ S"'J '-i .I(-c~ ""-._.~ s'"" -k...
(10
q, &A.L~ c.~ c; -==t {t I 1t o -~
h\n.l..L') -* t. <a~.::-(~ccs;_s ?~eG
oc:::i
f'--'--1.~ i. fv..t( ..s~ 4 ~ 3~ -·-
lo4 ;1'-t / '/. .3 ~
t).O ..i.1.-s-~ '--1. x·.}. I...\ Ac...,:...,.e:.5.'i. f"'-~S ~ {[ ~y / -IU JC, 2 ~
;)._-\J-..x\J-. A<Le...Ss ec.,..~s ~ ~ ~ ~ o_:. ~ + t.\.S --j dl.\o
1. No sales , use or tax of any kint1 is included in the atwv~ quotali1>n unless otherwise noted.
2. Terms are net 30 days from invoice date . No retainage is allowed .
]. Shipment ot materials will be 6 to 8 weeks after receipt of approved shop drawings unless otherwise noted .
4. We do not furnish or install gla:;s, hardware, weatherstr ipping, rubber 5i lencers nor any other acce~sories unless npted above.
5. Upon acceptance of this proposal. this document will become part of the contract documents .
6. All sates are subject to credit approval.
Accepted by: COMMERCIAL OPENINGS, INC.
~J.--+,.;..=----===-
Date ~ ...... l. ;>/ I -!:, ______ _ Date ____ _
CR# Date
1 2/23/2012
Subject
Tegrity Contractors Inc . Change Or der Requ es t Log
Fort Worth Auto Pound Facility
Amount Approved
Gyp . Board Ceilings Rm#101, 102 and 103 $ 1,965.76
Totals $ 1,965 .76 $
Disapproved
-$ -
Possible Future COR's
Breakroom Column and Ceilinq
Credit for Eooxv Floor Paint in Rm #104
Replace Door #101
T :\J o b Folders -Current\Jobs 2011\11-36 Vehicle Impound Facility\Change Orders\11 -36 COR Log .x is
2/23/2012
Total Approved
$ -
$ -
Change Request: 2
Date: 2/23/2012
To: City of Fort Worth
401 West 13th
Fort Worth , Texas 76102
Attn: Alan Bagamery
Re: Police Auto Pound Facility
From: Edd ie Whitworth
Tegrity Contractors , Inc
106 East Univers ity Dr . #100
McKinney, Texas 75069
Provide labor and materials to furr-out around column uncovered during demo
and add ceiling tile and grid to tie in ceilings in Breakroom #104
Labor and materials $ 280.00
See attached
Subtotal $ 280.00
Tegrity Profit & Overhead $ 28 .00
Bond Fee $ 9 .24
~
Total $ ?64 'gtl/,
The Contract Time will be changed by ( 0 ) days.
@
MATRIX
February 20, 2012
Tegrity Contractors, Inc .
106 E. University, McKinney, TX 75069
ATTN: Eddie Whitworth
Re: Brennan Auto Pound-A dditional Work @ Breakroom
Matrix Interiors is pleased to quote on the above referenced project for the sum of$280.0 0
Our exclusions and inclusions are listed below . This quote expires in 3 0 d avs.
EXCLUS IO NS
* Any work not specifically noted on the plans or below
* Any work outside our scope or the areas shown
* Any work at existing conditions not noted
* Payment / performance bond
* Demolition of any kind
* Clean of other trades or dumpsters
* Stocking of items F.B.O . (ie frames , doors)
* Caulking or sealing of penetrations by others
* Comer guards, chair rails or any wall protection
* Reveals or any special accessories
* Mill work, finished carpentry or finished wood
* Any wood framing
* Any Sales Tax
* Any engineering or stamped shop drawings
* Any water proofing or exterior sealants
* Any exterior finishes
* Any ceiling or roof deck insulation
* Any FRP
* Any after-hours work
* Any repair or replacement of existing ceiling tile or grid
INCLUSIO NS
* Work requested on 2-20-12
* Install Drywall on metal stud framing around relocated beam
* Install new ceiling tile & grid in vestibule area of the break room
Please call if you need additional information.
Sincerely,
Ch ip Smith
12.06 Tappan Circle I Carrollton, TX 75006 ! PH: 972-2.45-1022 i F/\X: 972-245-24
·www.rnatrixinterior.com
CR# Date
1 2/23/2012
2 2/23/2012
Subject
Tegr ity Co ntractors In c. Change Order Request Lo g
Fort Worth Auto Pound Facility
Amount Approved
Gyp. Board Ceilings Rm#101 , 102 and 103 $ 1,965.76
Breakroom Column and Ceilino $ 317 .24
Totals $ 2 ,283 .00 $
Disapproved
-$ -
Possible Future COR's
Credit for Eooxv Floor Paint in Rm #104
Replace Door #101
T:\Job Folders -Current\Jobs 2011\11 -36 Vehicle Impound Facility\Change Orders\11-36 COR Log .xis
2/23/2012
Total Approved
$ -
$ -
·'
Change Request: 3
Date: 2/23 /2012
To: City of Fort Worth
401 West 13th
Fo rt Worth , Tex as 76102
Attn : Alan Bagamery
Re: Police Auto Pound Facility
Credit for Epoxy floor paint in Breakroom #104
Labor and material cred it'
See attached
Subtotal
Tegrity Profit & Overhead
Bond Fee
Total
$
$
$
$
The Contract Time will be changed by ( 0 ) days.
(32 0.00 )
(32 .00 )
(10.56)
From: Edd ie Wh itworth
Tegrity Contractors , Inc
106 East Un ivers ity Dr. #1 00
. McKinney, Te x as 75069
$ (32 0.00 )
Catapult Painting, LLC
4105 W. Spring Creek Pkwy, Suite 60 4
Plano , TX 750 24
(972) 596-4118 (972 ) 767-4557 fa x
Customer
Tegrity Contractors, Inc .
I 06 E . University , Ste I 00
McKinney, TX 75071
Description
Credit --Ap p li cation of ep oxy to floor in g
We ap preci ate yo ur busin ess !
Credit Memo
Date
2/22/2012
Ship To
Vehic le Impound Facility Alte ra tion s
2500 Brennan Aven ue
Ft Worth , TX 76106
PO 11-36-09 -7000
Qty Rate
320 .00
Credit Total
Credit No .
5493
P .O . No .
Amount
-320 .00
$-320.00
CR# Date
1 2/23/2012
2 2/23/2012
3 2/23/2012
Tegrity Cont r actors Inc . Ch ange Ord er Requ est Log
Fort Worth Auto Pound Facility
Subject Amount Approved
Gyp . Board Ceilings Rm#101 , 102 and 103 $ 1,965 .76
Breakroom Column and Ceiling $ 317 .24
Credit for Eooxv Floor Paint in Rm #104 $ (362 .56)
Totals $ 1,920.44 $
Disapproved
-$ -
Possible Future COR's
Reolace Door #101
T :\Job Folders -Current\Jobs 2011\11-36 Vehicle Impound Fa cility\Change Orders\11-36 COR Log .xis
2/23/2012
Total Approved
$ -
$ -
Change Request: 4
Date: 2/23/2012
To: City of Fort Worth From:
401 West 13th
Fort Worth, Texas 76102
Attn: Alan Bagamery
Re: Police Auto Pound Facility
Materials and Labor to Replace existing door #101 as per city request
Materials and Labor to remove existing Door/Frame,
Demo CMU and tooth in CMU at opening as required
Door, Frame and Hardware
See attached
Subtotal $ 1,403 .00
Tegrity Profit & Overhead $ 140.30
Bond Fee $ 46 .30
Total $ ~ i
The Contract Time will be changed by ( 0 ) days.
Eddie Whitworth
Tegrity Contractors , Inc
106 East University Dr. #100
McKinney, Texas 75069
$ 1,000 .00
$ 403 .00
~ ,-,,sqtJ.
HBA Incorporated
Co1icrete/Den10/Proposal
DATE: February 22 , 2012
13 843 Salm on Dri ve,
Fri sco, TX 7503 5
Phone (2 14 ) 407-70 23
COMPANY: Tegrity Contractors. Inc. PROJECT: Fort Worth Impound
106 E . Univ ersity
McKinney, Texas 75069
Attn: Eddie
We propose to supply all labor, equipment, and materials to:
SCOPE: CHANGE ORDER #1
• Cut existing 3-0 X 7-0 door ope ning 5 " larger and tooth in CMU at jambs, set door
frame and grout door jambs.
Pricing ....................... $ 1 ,000.00 plus applicable taxes .
TOTAL .............................. $ 1,000.00 PLUS APPLICABLE TAXES.
SCHEDULE:
One to Two (1-2) week's lead time
INCLUSIONS:
• Working hours t o be 7 am to 3:30 pm per day Monday thru Friday .
• Cleanup of spoils to be placed in dumpster supplied by G .C .
EXCLUSIONS/ QUALIFICATIONS:
• Wood trim, plaster, tile , granite, painting and or coatings
• Asphalt patch back
• Plans, permits, fees of any kind, testing, inspections, survey, bonds , engineering,
import or export of fill soils , stained concrete, waterproofing, water stop, dewatering,
French drain, irrigation, rock, caulking, shoring of walls , lay out of or purchase of
embeds, traffic control, efflorescence removal, precast concrete items , dry packing or
Page 1 of 2
Tegrity Contractors. Inc .
106 E. University
McKinney, Texas 75069
Fort Worth Impound
grouting of beam or joist pockets. Power, water, parking and toilets, unless identified
above as being part of the scope, to be provided to HBA , Inc . without cost.
• Saw-cut, demo and placement of concrete in existing slab, or new chase 's provided
for MEP is excluded due to failure to identify locations on the drawings. This can be
added at a later date once these areas have been identified.
• All permits for construction, street and sidewalk rentals by others.
• Excludes all demo.
• Excludes grouting of stone tile flooring, replacement of new or missing stone tiles .
• Excludes patching of stair and landing imperfections, pour back of plumbing
trenches, and gutters at new curb locations. No gutters were identified or detailed on
drawings .
Grade to be given to HBA plus or minus + / -ready for concrete.
Hubs and Bench Marks to be provided to HBA by others.
All work to be completed in a substantial and workmanlike manner according to
standard practices. Any changes or extra work will be charged at time and material,
plus 15% for overhead and profit.
PAYMENT SCHEDULE:
Progress payments billed on a monthly basis due within thirty days of billing.
Balances over 30 days old are subject to 1.5% interest per month.
This proposal shall be made part of any contract covering this work. If the owner or
prime contractor subsequently requests HBA, Inc . to sign its own form of contract,
this proposal will be deemed to be part of that contract and will supersede any other
conflicting terms of that contract, unless this proposal or any paragraph or part is
expressly excluded by all parties .
Submitted: Contractor:
Accepted by:
Title:
Terry Maitland Dated :
Page 2 of 2
RX Date/Time 02/23/2012 13:34 214 343 4072
Feb 23 12 02:23p COMMERCIAL OPNGS 214 343 4072
COMMERCIAL 0PENINGS 9 INCo
10!:!90 PETAL ST .. SUITE 700 • DALLAS. TEXAS 75238 • (214) 343-0080 • FAX (214) 343-4072
PROPOSAL
DATE ~ ...... "'-.3 I Ouo \e 6
Bid Date~ <')l
Rf p rl c..l "'\.•·,
' ~
P.001
p. 1
We propose to furnish the materials described and priced below per section ____ of the specifications, with
1 _ w~ +lM f.-·""' Su'L D 0 S"J"i ~ CJ:>'"'-""~ s"'-~
q_ ,,,.,c)•"'-O(I" "> ~ , 'ff I 1f O o _:l_ /
1. No sales, use or tax or any kind is inclutlecJ in the alJovt quotation unless otherwise noted .
2. Terms are net 30 days from invoice date. No retainaga is allowed.
3. Shipment of mater ials will be 6 to 8 weeks after receipt of approved shop draw ings unless otherwise noted .
\ l\-t>
+?l\'.J
''B 35 4' ~03c:o
4. We do not furnish or install glass, hardware, weatherstr ipp ing, rubber silencers nor any other acccs:.orico unless noted above .
5. Upon acceptance of this proposal , this document will become part of the contract documents.
6. All sales are subject to credit approval.
Accepted by: COMMERCIAL OPENINGS, INC.
~J-+----
Date R.......-:i. )/ I~--·----Date ____ _ --····-·· ------
CR# Date
1 2/23/2012
2 2/23/2012
3 2/23/2012
4 2/23/2012
Tegrity Contrac tors Inc. Chan ge Order Requ est Lo g
Fort Worth Auto Pound Facility
Subject Amount Approved
Gyp . Board Ceilings Rm#101 , 102 and 103 $ 1,965.76
Breakroom Column and Ceilinq $ 317 .24
Credit for Eooxy Floor Paint in Rm #104 $ (362 .56)
Replace Door #101 $ 1,589.60
Totals $ 3 ,510 .04 $
Disapproved
-$ -
Possible Future COR's
T :\Job Folders -Current\J o bs 2011\11 -36 Vehicl e Impound Facility\Change Orders\11-36 COR Log .x is
2/23/2012
Total Approved
$ -
$ -