HomeMy WebLinkAboutContract 42749-CO2 (2)FORT WORTH . ~ City of Fort Worth Change Order Request Project Namel Grassland Court Extended Drainage Design Client Project #(s)I P227-207280047983 / P253-607170047983 Project Description Grassland Court , Crosswind Drive , & Skylake Drive CITY SECRETARY . CONTRACT NO. 4l].l/lJ-{tu City Sec # 427 49 .__ _____ __. Contractor! Tr i-Tech Construction City Project Mgr. I Felipe Pulido Change Order# 2 Date 4/24/2012 City Inspector Jerry Taliaferro Dept. TPW Water Contract Time Original Contract Amount $2 ,071 ,874 .60 $158 ,661 .20 Extras to Date $45 ,000 .00 Credits to Date Pend ing Change Orders (in M&C Process) Contract Cost to Date $2,116 ,874 .60 $158 ,661.20 IAmount of Proposed Change Order ~.00 $0.00 Revised Contract Amount $2 ,116 ,874 .60 $158 ,661 .20 Original Funds Available for Change Orders $66 ,920 .00 Remain ing Funds Available for this CO $21 ,920 .00 $0 .00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER This change order is necessary to delete two existing pay items adding one . Totals (CD) $2 ,230 ,535 .80 $45 ,000 .00 $2,275 ,535 .80 $2 ,275 ,535 .80 $66 ,920 .00 $21 ,920 .00 2.02% $2,788 ,169.75 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX 280 280 280 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to , the above Change Order. Contractor's Com an Name Tr i-Tech Construction M&C Number o 5 -11-12 Al0:23 IN 06 -25 -1 2 P0 3 :14 I N . 'I FORT WORTH . ~ City of Fort Worth Change Order Request City Sec# 42749 Project Name! Grassland Court Extended Drainage Design Cl ient Project #(s)j P227-207280047983 / P253-607170047983 .___ _____ ____. Project Description Grassland Court , Crosswind Drive , & Skylake Drive Contractor! Tri-Tech Construction Change Order # 2 Date City Project Mgr .I Felipe Pulido City Inspector Jerry Taliaferro Dept. TPW Water Original Contract Amount $2 ,071 ,874 .60 $158 ,661 .20 Extras to Date $45 ,000 .00 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $2 ,116 ,874 .60 $158 ,661 .20 !Amount of Proposed Change Order $0.00 $0.00 Revised Contract Amount $2 ,116 ,874 .60 $158 ,661 .20 Original Funds Available for Change Orders $66 ,920 .00 Remaining Funds Available for this CO $21 ,920 .00 $0.00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER Th is change order is necessary to delete two ex isting pay items adding one . Totals $2 ,230 ,535 .80 $45 ,000.00 $2 ,275 ,535 .80 $2 ,275 ,535 .80 $66 ,920 .00 $21 ,920.00 2.02% $2,788 ,169 .75 4/24/2012 Contract Time (CD) 280 280 280 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to , the above Change Order. Contractor's Com an Name Contractor Name Contract Si nature Date Tri -Tech Construction Inspector/Inspection Suoervisor Date Project Manager/Program Manager Date Assistant Director (Dept) Date Director, Contracting Department (Dept) Date Assistant City Attorney Date Assistant City Manager Date Council Action if required) M&C Number I I M&C Date Approved I I I I FORT WORTH . ~ City of Fort Worth Change Order Request City Sec# 427 49 Project Name! Grassland Court Extended Drainage Design " ------~ Client Project #(s)j P227-207280047983 / P253-607170047983 Project Description Grassland Court , Crosswind Drive , & Skylake Drive Contractor! Tri-Tech Construction City Project Mgr.! Felipe Pulido Change Order# 2 Date City Inspector Jerry Taliaferro Dept. TPW Water Original Contract Amount $2 ,071 ,874.60 $158 ,661 .20 Extras to Date $45 ,000 .00 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $2 ,116 ,874 .60 $158 ,661 .20 !Amount of Proposed Change Order $0.00 $0.00 Revised Contract Amount $2 ,116 ,874 .60 $158 ,661 .20 Original Funds Available for Change Orders $66 ,920 .00 Remaining Funds Available for this CO $21 ,920 .00 $0 .00 Addit ional Funding (if necessary) ' CHANGE ORDERS to DA TE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER This change order is necessary to delete two existing pay items adding one . J t,,( ~ J U/1l!II Totals $2 ,230 ,535 .80 $45 ,000 .00 $2 ,275 ,535.80 $2 ,275 ,535.80 $66 ,920 .00 $21 ,920 .00 2.02% $2,788 ,169 .75 4/24/2012 Contract Time (CD) 280 280 280 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to , the above Change Order . Contracto~s Com an Name Contractor Name Tri-Tech Construction -1 e,,, / " ~ .,, Ins Date Date / // I . I ,,. Assistant Director De t Date Date Li I Assistant Cit Att Date Date ; /;> M&C Number IV t0t i I I fORTWORTH .. ~ City of Fort Worth Change Order Request City Sec # 427 49 Project Name! Grassland Court Extended Drainage Design Client Project #(s)j P227-207280047983 I P253-607170047983 ~------~ Project Description Grassland Court , Crosswind Drive , & Skylake Drive Contractor! Tr i-Tech Construction City Project Mgr .j Felipe Pulido Change Order # 2 Date ~-----------------' City Inspector Jerry Tal iaferro Dept. TPW Water Original Contract Amount $2 ,071 ,874 .60 $158 ,661 .20 Extras to Date $45 ,000 .00 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $2 ,116 ,874.60 $158 ,661 .20 !Amount of Proposed Change Order $0.00 $0.00 Revised Contract Amount $2,116 ,874 .60 $158 ,661 .20 Original Funds Available for Change Orders $66 ,920 .00 Remaining Funds Available for this CO $21 ,920 .00 $0 .00 Additiona l Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER This change order is necessary to delete two existing pay items adding one . Totals $2 ,230 ,535 .80 $45 ,000 .00 $2 ,275 ,535 .80 $2,275 ,535 .80 $66 ,920 .00 $21 ,920 .00 2.02% $2,788 ,169 .75 4/24/2012 Contract Time (CD) 280 280 280 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full {both time and money) for all costs arising out of , or incidental to , the above Change Order . Contractor's Compan Name Contractor Name Contract Si nature Date Tri-Tech Construction } Inspector/Inspection Supervisor Date Project Manager/Program Manager Date Assistant Director (Dept) Date Director , Contracting Department (Dept) Date Assistant City Attorney Date Assistant City Manager Date -~ ,/ I .., ~ . ' . . . . ' Council Action if required) M&C Number I -I M&C Date Approved I I I FORT WORTH ----.---City of Fort Worth Change Order Additions Project Name Grassland Court Extended Drainage Design Client Project # P227-20728004 7983 / P253-60717004 7983 Project Description Grassland Court, Crosswind Drive, & Skylake Drive Contractor Tri-Tech Construction City Sec# Change Order# 2 Date 4/24/2012 City Project Mgr. Felipe Pulido ._____._ _____________ __, City Inspector Jerry Taliaferro ADDITIONS 111::.M Ut~vKlt-' I IUN Ut:t" I I..Jty unit Unit vOSt {',j 11 u· x 8' Ji:, WI Environmental Snout/ Install I r'W 1.UU ta :ji:.:'.U ,UUU .uu TPW Water Sub l otal Additions Change Order Additions Page 1 of 1 42749 IOtal :ji:.:'.U ,UUU.UU $20 ,000 .00 $0.00 :ji:.:'.U ,UUU.UU ,. FORT WORTH ----.,....--City of Fort Worth Change Order Deletions Project Name Grassland Court Extended Drainage Design Client Project# P227-20728004 7983 / P253-60717004 7983 Project Description Grassland Court, Crosswind Drive , & Skylake Drive Contractor Tri-Tech Construction City Sec# Change Order # 2 Date 4/24/2012 City Project Mgr . Felipe Pulido .____._ _____________ ___, City Inspector I Jerry Ta liaferro DELETIONS lltM -'~~f...c"<lt"' I IUN Ut:i" I Uty Unit Unit l,;OSt 36 ox o Manno1e w1tn ::;reel casing I t"'VV l .UU 1 :jitl ,UUU.UL 38 6 x 6 Manho le with Env1romental Snout 1·Pw 1.UU 1 $12 ,UUU .UL TPW Water Sub Total Deletions Change Order Deletions Page 1 of 1 42749 IOtal :jitl ,UUU .UU :jil:.:'.,UUU .UU $20 ,000 .00 $0 .00 :ji:.:'.U ,UUU.UU M/WBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 PROJECT SUMMARY SHEET (Change Order Attachment) PROJECT NAME : BuySpeed No (T/PW): BuySpeed No (Water): City Project No : Academy Blvd.-Grassland Court P0-112-000707 44 Pending 00479 Contract No: CS42749 Actual change order amount was zero D.O .E. No: 5419 Attach ment to Change Order No : 2 Today's Date: 4/24/12 TOTAL P227 P253 Original Contract Amou nt: $ 2,230,535.80 $ 2 ,071 ,874.60 $ 158 ,661.20 Extra s to Date: Credi ts to Date : Contract Amount to Date : Amount of Proposed Change Order: (Additions) Amount of Proposed Change Order: (Deletions) Revised Contract Amount: Contingency Funds Ava il. for Admin . Change Orders: Remain ing Funds Available for Change Orders: Additional Funding (if necessary): $ 45,000.00 $ 45,000 .00 $ $ $ $ $ 2,275,535.80 $ $ 20,000.00 $ $ (20,000.00) $ $ 2,275,535.80 $ $ $ $ 66,920.00 $ 21,920.00 $ $ 2 ,116,874.60 $ 20 ,000 .00 (20 ,000.00) $ 2,116 ,874.60 $ 66 ,920 .00 $ 21 ,920 .00 $ $ Prepared By : Christy Ezernack T/PW Const ruction Services 158 ,661.20 158 ,661 .20 . ~·