AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE SEWER CAPITAL PROJECTS FUND IN THE
AMOUNT OF $329,406 FROM AVAILABLE FUNDS, FOR THE PURPOSE OF
EXECUTING AMENDMENT NO. 2 TO AN ENGINEERING AGREEMENT WITH
DANNENBAUM ENGINEERING CORPORATION FOR SANITARY SEWER
MAIN 257 AND 325 (MIDDLE AND UPPER VILLAGE CREEK) PARALLEL
RELIEF ALIGNMENT AND DESIGN; PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES
IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2007-
2008 in the Budget of the City Manager, there shall also be increased estimated receipts and
appropriations in the Sewer Capital Projects Fund in the amount of $329,406 from available funds,
for the purpose of executing Amendment No. 2 to an Engineering Agreement with Dannenbaum
Engineering Corporation for Sanitary Sewer Main 257 and 325 (Middle and Upper Village Creek)
Parallel Relief Alignment and Design.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid,
inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or
judgment shall in no way impair the remaining portions, sections, or parts of sections of this
ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance No. 17749 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance
are in direct conflict with such other ordinances and appropriations, in which instance said
conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
ADOPTED AND EFFECTIVE: November 27, 2007
This ordinance shall take effect upon adoption.
Cif ®f F®rf ~/®h, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 11/27/2007 -Ordinance No. # 17880-11-2007
DATE: Tuesday, November 27, 2007
LOG NAME: 30SSMAIN257-325
SUBJECT:
Authorize Execution of Amendment No. 2 to City Secretary
Agreement with Dannenbaum Engineering Corporation, fo
(Middle and Upper Village Creek) Parallel Relief Alignment
Ordinance
REFERENCE NO.: *~C-22535
Contract No. 28006, an Engineering
r Sanitary Sewer Main 257 and 325
and Design, and Adopt Appropriation
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the City Manager to execute Amendment No. 2 to City Secretary Contract No. 28006 with
Dannenbaum Engineering Corporation for Sanitary Sewer Main 257 and 325 Middle and Upper Village
Creek Parallel Relief Alignment and Design;
2. Authorize the transfer of $329,406, for the Water and Sewer Operating Fund to the Sewer Capital
Projects Fund; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Projects Fund in the Amount of $329,406 from available funds.
DISCUSSION:
On July 30, 2002, (M&C C-19172) the City Council authorized the City Manager to execute an engineering
agreement with Dannenbaum Engineering Corporation in the amount of $721,899.76, to prepare plans and
specifications for Sanitary Sewer Main 257 and 325 Middle and Upper Village Creek Parallel Relief
Alignment Study and Design.
The City Council approved amendment No. 1 for $111,800.50, (M&C C-19936) on January 20, 2004, for
additional engineering services for approximately 3,000 linear foot extension of Sanitary Sewer Main 257
alignment study and design of Sanitary sewer laterals 2389, 2484, 3694, Main 238 and Lateral 9920.
This proposed amendment will allow Dannenbaum Engineering Corporation to provide additional
engineering services for approximately 23,076 linear feet of 42-inch Sanitary Sewer Main 325, 47
manholes, five junction boxes, concrete pavement repairs and other pertinent items. This amendment also
includes special services for geotechnical studies, easement documents preparations, plans for Storm
Water Pollution Prevention, Traffic Control Plans, Engineering Feasibility Report and coordination with
railroad companies, TX DOT and local utilities companies. Dannenbaum will also provide limited assistance
during construction services and prepare As-Built drawings.
Dannenbaum Engineering Corporation proposes to provide these additional services for a lump sum fee of
$329,406. This fee includes credits for the design of Sanitary Sewer Main 257 included in the original
contract. The Water Department decided to remove this portion of design work from the contract. City staff
Logname: 30SSMAIN257-325 Page 1 of 2
considers this fee to be fair and reasonable for the scope of services proposed.
Dannenbaum Engineering Corporation is in compliance with the City's M/WBE Ordinance by committing an
additional 40 percent M/WBE participation on this Amendment No. 2. The City's Goal on this amendment is
40 percent.
This project is located in COUNCIL DISTRICT 8, Mapsco 106V, and Z, 107F, K, J, N, S.
FISCAL. INFORMATION/CERTIFICATION:
The Finance Director certifies that upon approval and completion of recommendation No. 1 and the
adoption of the attached appropriation ordinance, funds will be available in the current capital budget, as
appropriated of the Sewer Capital Projects Fund.
TO Fund/AccountlCenters FROM Fund/Account/Centers
1&2)P172 472045 070172141030 $329,406.00 1)PE45 538070 0709020 $329.406.00
2)P172 531200 070172141030 $329,406.00 3)P172 531200 070172141030 $329.406.00
Submitted for Char Manager's Office b}r_ Marc A. Ott (8476)
Originating Department Head: A. Douglas Rademaker (6157)
Additional Information Contact: Gopal Sahu (7949)
Logname: 30SSMAIN257-325 Page 2 of 2