Loading...
HomeMy WebLinkAboutContract 42543-CO1 (2) i 0 TRRACT NO 1la 5 L-13-c o - amm FORT WORTH. city of Fort worth � Change Order Request Project Name I Butler&McClure Culvert Improvements City Sec# 1 42543 Client Project#(s)l P227-541200-209280047583 (DOE 5415) Project Descriptio Paving,Drainage,Water,Sanitary Sewer Contractorl Conatser Construction TX.L.P. Change Order# 0 Date 2/10/2012 City Project Mgr.1 Michael Owen City Inspector I Michael Collier Dept. TPW Water Sewer Totals Select Day Type Original Contract Amount $1,618,576.50 1,618,576.50 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,618,576.50 $1,618,576.50 Amount of Proposed Change Order $7,910.00 $0.00 $0.00 $7,910.00 Revised Contract Amount $1,626,486.50 $1,626,486.50 Original Funds Available for Change Orders $48,577.30 $48,577.30 Remaining Funds Available for this CO $48,577.30 $48,577.30 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.49% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,023,220.63 JUSTIFICATION(REASONS)FOR CHANGE ORDER The Water Department requested a different pipe material due to the sewer being located under the box culverts. Note-All improvements are funded by Stormwater,including water and sewer,because the water and sewer work is required because of the drainage work. IF Pr aob�u�g a 47 *� o 00 °°°00°®a °° �M J. Kayser City Pp � anIf ItXA oq It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's Company Name Contractor Name ContracL&MnaWre Date Conatser Construction TX. L.P. - /- ,Z Inspector/Inspection Su i Date ProjeceMonager/Program Minager Date Assis Date D*V,(�qntktingDepartment(Dept) Date 7 y 1--' I//z &,z Assis nt City Attorney Date Assi ity_KanaAr 4 64 Date 3-i3-� r Council Action if required) M&C Number M&C Date Approv d FT:WORTH,TX n ° 3 q DO / # % a 0 E- m G I LL 75 75 CD $ # / � k 6 & k ? ƒ E / � � a 2 n § o � o « \ LL D � c ® 2 ® u U \ A f \ /E U/ Q Q / / m k / g & E / C k 0 / / k cu m OL a_ k d m _ ® w (D # § & O u : cm k 0 \ o ■ % 2 2 0 3 a 0 0 0 0 0 0 te, 6-> o CV C O 0 3 a co � m 0 N O N OD fp a c O v v Q v v O a on c m t u 0 \ » � a a . # \ 8 - m 3 3 i c a) :D :? # / � k d � � & \ 0 CL C t v 12. � 2 � § o � q 1. \ w 2 � Ji k O �g / c ® 2 u U 7 b a) CD g ƒ 00 / £ R 3 / / / / co \ e o CD 7 « C k \ / / k d m CL L 3 dco o \ \ M 2 & k k ) ¥ a) ° 0 2 % ■ $ 2 o g CL O O O O O O N t� �3 N N C O N � 3 0 a D CO 0 CD 4- 0 N O1 OD m a N C O Aj 0 ai to C m L U MIWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders Co# DATE AMOUNT Total $0.00 N O O O O O O O c0 (O (O O_ (O 1� 1� 1� L CO CO r (O co co O > O — — N c "� (O (O (O co C � X H Q W Ei3 ER ER ER ER ER fA ER Z Q W) Of qT W) W) co C 0 ~ 00 00 14, N qT qT Oq > J co co co U V v T E 06 v� Q E a m Y > U C U � � N a W � L � U t N -2 m � f ca O U f � M W} a m W V L C Q) cu z -2 � Q) O Q o cB a a) L .� uA C �O a) N cu U C 4+ C j cu a) cm 0 f) Q N U 0 > c C co C E O � E Q > W to +' to V V to .r p V C C ~ z W ° � z r Q _c WUcLEBao Li UO UCM z NU O a) c m 16 e c °- coca c o) oW cn cc S o d o �' o E a) o m v aWUo a 0Q (If U (If Q ' FORT WORTH. City of Fort Worth f Change Order Request Project Namel Butler&McClure Culvert Improvements City Sec# 42543 Client Project#(s)l P227-541200-209280047583 (DOE 5415) Project Description Paving,Drainage,Water,Sanitary Sewer Conh-acbrl Conatser Construction TX.L.P. Change Order# Date 1 2/10/2012 City Project Mgr.1 Michael Owen City Inspector Michael Collier Dept. TPW Water Sewer Totals Select Day Type Original Contract Amount $1,618,576.50 $1,618,576.50 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,618,576.50 $1,618,576.50 Amount of Proposed Change Order $7,910.00 $0.00 0.00 $7,910.00 Revised Contract Amount 1,626,486.50 $1,626,486.50 Original Funds Available for Change Orders $48,577.30 $48,577.30 Remaining Funds Available for this CO $48,577.30 $48,577.30 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.490/0 MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2551o) $2,023,220.63 JUSTIFICATION(REASONS)FOR CHANGE ORDER The Water Department requested a different pipe material due to the sewer being located under the box culverts. Note-All improvements are funded by Stormwater,including water and sewer,because the water and sewer work is required because of the drainage work. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's Company Name Contractor Name Contr na4ve Date Conatser Construction TX.L.P. Inspector/Inspection Supprvisgr Date Project Manager/Program dnager Date Assists -tot p Date DhIntor,Contr&*2 D2partment(Dept) Date ,. Assistant City Attorney Date Assi ity Mana Date i Council Action if required M&C Number w, M&C Date Approved lr—J FORT WORTH® City of Fort Worth f Change Order Request Project Namer Butler&McClure Culvert Improvements City Sec# 1 42543 Client Project#(sJ P227-541200-209280047583 (DOE 5415) Project Desaip' Paving,Drainage,Water,Sanitary Sewer Contradorl Conatser Construction TX.L.P. Change Order# L'J Date 2/10/2012 City Project Mgr.1 Michael Owen City Inspector r Michael Collier Dept. TPW Water Sewer Totals Select Day Type Original Contract Amount $1,618,576.50 $1,618,576.50 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,618,576.50 $1,618,576.50 Amount of Proposed Change Order 7,910.00 0.00 0.00 $7,910.00 Revised Contract Amount $1,626,486.50 $1,626,486.50 Original Funds Available for Change Orders $48,577.30 $48,577.30 Remaining Funds Available for this CO $48,577.30 $48,577.30 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.49% MAXALLOWABLECONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $2,023,220.63 JUSTIFICATION(REASONS)FOR CHANGE ORDER The Water Department requested a different pipe material due to the sewer being located under the box culverts. Note-All improvements are funded by Stormwater,including water and sewer,because the water and sewer work is required because of the drainage work. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's Company Name Contractor Name Contract Si natpre Date Conatser Construction TX.L.P. Inspector/Inspection Supervisor Date Project Manager/Program M na er Date i Assistant Director(Dept) Date Director,Contricting Department Dept Date Assistant City Attorney Date Assis ity Maria r f 1 Date Council Action if required M&C Number M&C Date Approved 1! FORT WORTH City of Fort Worth Change Order Request Project Namel Butler&McClure Culvert Improvements City Sec# 1 42543 Client Project#(s)l P227-541200-209280047583 (DOE 5415) Project Description Paving,Drainage,Water,Sanitary Sewer Contractorl Conatser Construction TX.L.P. Change Order# Date 2/10/2012 City Project Mgr.1 Michael Owen City Inspector Michael Collier Dept. TPW Water Sewer Totals Select Day Type Original Contract Amount $1,618,576.50 $1,618,576.50 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,618,576.50 k$11;,626,486.50 8,576.50 Amount of Proposed Change Order 7,910.00 0.00 0.00 7,910.00 Revised Contract Amount $1,626,486.50 Original Funds Available for Change Orders $48,577.30 $48,577.30 Remaining Funds Available for this CO $48,577.30 $48,577.30 M Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.49% P MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,023,220.63 JUSTIFICATION(REASONS)FOR CHANGE ORDER The Water Department requested a different pipe material due to the sewer being located under the box culverts. Note-All improvements are funded by Stormwater,including water and sewer,because the water and sewer work is required because of the drainage work. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's Company Name Contractor Name Contract Signature Date Conatser Construction TX.L.P. Inspector/Inspection Supervisor Date Project Manager/Program Manager Date Assistant Director De t Date Director,Contracting Department Dept Date Assistant City Attorney Date Assistant City Manager Date Council Action if required M&C Number M&C Date Approved