Loading...
HomeMy WebLinkAboutContract 42544-CO1 (2) C10TY 1 0 F z FORT WORTH City of Fort Worth CITY SECRETARY Change Order Request CQI� ACTNO. Project Name HMAC Surface Overlay At Various Locations(2011-19) City Sec# 1 42544 Client Project#(s)l C293-541200-203620178883 City Project No.:01788 DOE:6722 Project Descriptio HMAC Surface Overlay At Various Locations throughout the city.. ContractorF JLB Contracting LLC Change Order# Date 1 6/17/2012 City Project Mgr.1 Kristian Sugrim (817)392-8902 City Inspector FMike Glover (817)944-0914 Dept. TPW Water Sewer Totals Contract Time (CD) Original Contract Amount $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 110 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 110 Go to ADD&DEL Tabs to Enter CO Backup fo.00 0.00 $0.00 110 Revised Contract Amount $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 220 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) I I d CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.000/0 MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25916) $1,281,202.50 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order is being submitted to request that an additional 110 calendar days(CD)be added to this contract.The added time will allow for the construction of two added projects,Bonnie Dr.and Pennsylvania Ave.The pulverization and overlay of Bonnie Dr.(Ewing Ave- Southwest Dead End),38 CD and the full mill and overlay of Pennsylvania Ave.(6th Ave-8th Ave),72 CD. The extended time on Pennsylvania is necessary to mitigate the noise,time and traffic restrictions stipulated on the street work permit. °�®����� 1� my's o o + OFFICIAL RECORD %l d d IKa►''l'��', �It�� � ° °°0p0000°° CITY SECRETARY FT.WORTH TX It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Ccntrac&s CwVany Name Contractor Nam Contract SJ nature Dale JLB Contrading LLC Inspector/Inspection Su rviso Date ProjV Ma eriProgram Manager Date z �.. Ass' t Date r,2W ng De artrnent(Dept) Date A i tto a Date Aggictaid i Mana ate `y U z Council Action if required) M&C Number M&C Date Approved 10 FORT WORTH. City of Fort Worth , I Change Order Request Project Namel HMAC Surface Overlay At Various Locations(2011-19) City Sec# 42544 Client Project#(s)l C293-541200-203620178883 City Project No.:01788 DOE:6722 Project Descxiptio HMAC Surface OverLay At Various Locations throughout the city. Contractorl JLB Contracting LLC Change Order# Date 6/17/2012 City Project Mgr.1 Kristian Sugrim (817)392-8902 City Inspector FMike Glover (817)944-0914 Dept. TPW Water Sewer Totals Contract Time CD) Original Contract Amount $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 110 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Copi#ract Cost toDate $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 110 Go to ADD&DEL Tabs to Enter CO Backup O 00 0.00 $0.00 110 Revised Contract Amount $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 220 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2591.) $1,281,202.50 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order is being submitted to request that an additional 110 calendar days(CD)be added to this contract.The added time will allow for the construction of two added projects, Bonnie Dr.and Pennsylvania Ave.The pulverization and overlay of Bonnie Dr.(Ewing Ave- Southwest Dead End),38 CD and the full mill and overlay of Pennsylvania Ave.(6th Ave-8th Ave),72 CD. The extended time on Pennsylvania is necessary to mitigate the noise,time and traffic restrictions stipulated on the street work permit. t It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's CorTany fume Contractor(Name) Cq*ad Signature Dale JLB Gontmctang LLC 51 f -- I Inspector/Inspecfion Supervisor Date Pro' t Manager/Program Manager Date Assist or t Date Dig ,CpWAng Pepartrrleent(Dept) Date r As tto Date i Mana a ate Council Action i€required) M&C Number ., M&C Date Approved +. 6 6 b r FORT WORTH® City of Fort Worth Change Order Request + Project Namel HMAC Surface Overlay At Various Locations(2011-19) City Sec# 42544 Client Project#(s)l C293-541200-203620178883 City Project No.:01788 DOE:6722 Project Descrilptiori HMAC Surface Overlay At Various Locations throughout the city. Contractorl JLB Contracting LLC Change Order# Date 6/17/2012 City Project Mgr.1 Kristian Sugrim (817)392-8902 City Inspector FMike Glover (817)944-0914 Dept. TPW Water Sewer Totals Contract Time (CD) Original Contract Amount $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 110 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 110 Go tc -'D5&D L—abs.r)E-i!,;;. 0 B:;.,k!.p $0.00 $0.00 $0.00 110 Revised Contract Amount $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 220 Original Funds Available for Change Orders 1 $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,281,202.50 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order is being submitted to request that an additional 110 calendar days(CD)be added to this contract.The added time will allow for the construction of two added projects,Bonnie Dr.and Pennsylvania Ave.The pulverization and overlay of Bonnie Dr.(Ewing Ave- Southwest Dead End),38 CD and the full mill and overlay of Pennsylvania Ave.(6th Ave-8th Ave),72 CD. The extended time on Pennsylvania is necessary to mitigate the noise,time and traffic restrictions stipulated on the street work permit. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. JLB Contracting LLC Inspector/Inspection Supervis94 Date Pro ct Marvager/Program Manager Date Assistant Director Dept) Date Director,Contra in De artment(Dept) Date AssisjpLCity Attompy Date Assata"ity manager Date Council Action if required) M&C Number M&C Date Approved FORT WORTH® City of Fort Worth Change Order Request ` Project Namel HMAC Surface Overlay At Various Locations(2011-19) City Sec# 42544 Client Project#(s)l C293-541200-203620178883 City Project No.:01788 DOE:6722 Project Description HMAC Surface Overlay At Various Locations throughout the city. Contractorl JLB Contracting LLC Change Order# 0 Date 1 6/1 712 0 1 2 City Project Mgr,I Kristian Sugrim (817)392-8902 1 City Inspector FMike Glover (817)944-0914 Dept. TPW Water Sewer Totals Contract Time k — (CD) Original Contract Amount $614,977.20 $N5,990.88 $163,993.92 $1,024,962.00 110 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 110 D :D! ; Td::- 1'e, rs.� ^ackap 0.00 $0.00 $0.00 110 Revised Contract Amount $614,977.20 $245,990.88 $163,993.92 $1,024,962.00 220 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,281,202.50 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order is being submitted to request that an additional 110 calendar days(CD)be added to this contract.The added time will allow for the construction of two added projects,Bonnie Dr.and Pennsylvania Ave.The pulverization and overlay of Bonnie Dr.(Ewing Ave- Southwest Dead End),38 CD and the full mill and overlay of Pennsylvania Ave.(6th Ave-8th Ave),72 CD. The extended time on Pennsylvania is necessary to mitigate the noise,time and traffic restrictions stipulated on the street work permit. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. 1pt�t1C #utttt JLB Contracting LLC A 9— Inspector/inspection Su ervi Date Project Manager/Program Manager Date Assistant Director Dept Date Director,Contracting Department(Dept) Date Assistant City Attorney Date Assigtent-Ci1y Manager Date Council Action if required M&C Number M&C Date Approved m 0 v _N O � N � O � O C � O U cc N r— t0 C W O � m •' o C7 a� m v O N o �+- rn U O C y 00 U C tko O 42:1 d O U N t+ 5 n O 0,0 o 3a a (D Q 0 0 o �, �' 9 Q op 0 o 04N C14 to ♦� c 0 U V O S CV Vcc UO Ch J N ti N � O � 2O > �co cc Q 000 Q a r— T cc N O J y 04 y U cmo J O O O J c� o c°; E Cl 7 U L? U o cued cn U m 04 = U = � X I �^ m 3 Z a N o a o o U o p c d a v a � 'o U a` O O O C) O O fA di O d aCc c9m 0 N O N G1 OD f0 a c 0 Q v O v on c ro t U ca 3 ° \ _C%j _ � 10 / izz 75 q G a § 0 0 J # I k 6 � ® co cu \ r 6 / & 0 zAl cu ® k p 2 . ° L 22 « � 0 4- 0 § @ � a � no U § \ OP % U i § § 2 > k / :., co 3 2 / CV ƒ cm \ Cl 4 f f 3 r 3 — 3 / 7 / I m I m m I Q I R 2 \ k : \ U t 2 t \ ƒ 2 D CL SSS 000 0 La a � � � 0 N O N d OO m 0. C O r d d v 0 v 00 C m t U MMBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 N N N G� O) M M M LI IM Im Im N M CM CM co co co oq co co 1 0 0 0 MI N Lo d N N N 61) to) to fR to fR fR fR 6% i N i Q N ' rn 13 rn CN N m m co co LO W fR fR to to), EA fR fR fR EA p = C U O O O 2 m O II } �• t cm CM O U J w WZw U N N W N d R C m V O O cu Cl) v;r v;r v;r tR tR tR tR tR c m F R N `t W U as a U co � O 0 L m O O a N 9N � -m0 V N N Q CM M m 0 'O cc � 2 CL Z o U co t° ;✓ c ` 0- -2 U Z O Q L Cc L m L O � O C m m m m c N N m � � m m U o Cc> c � m rn ° � � � a E Q > �' c E O 0 O m Q cA Q O W L 0- ccQ cc rn h . p Q o o m c n �, c UU ° = ° ` LL � cZ w m o Z Z Z C W U E a U- mE ZN O cc � Q U cU a) m Z m O m cm W v C U) c0 O a m m m p m c m E a o0 0 6 < — 0 U Q Ix U Ix ¢ 'O Q