AMENDMENT No.2 N� q-j J q1COMCT
TO CITY SECRETARY CONTRACT No. 42547
WHEREAS, the City of Fort Worth (CITY) and TranSystems Corporation,
DBA TranSystems Corporation Consultants, (ENGINEER) made and entered into
City Secretary Contract No. 42547, (the CONTRACT) which was authorized by
the City Council by M&C C-25255 on the 01 day of November, 2011 in the
amount of $243, 322 . 00 and Amendment #1 administratively approved on
October 26, 2012 in the amount of $13, 010 . 00 for a revised contract
amount of $256, 332 . 00; and
WHEREAS, the CONTRACT involves engineering services for the
following project :
North Fort Worth Intersections; and
WHEREAS, it has become necessary to execute Amendment No. 2 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified on Attachment "A" June 27, 2013, a copy of
which is attached hereto and incorporated herein. The cost to the City
for the additional design services to be performed by Engineer totals
$39, 791 . 50 (See Attached Funding Breakdown Sheet, Page 3) .
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $296, 123. 50.
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8 f 1 f 2012
Page 1 of 3
OFFICIAL RECORD
RECEIVED JUL 10 2013 CITY SECRETARY
FT.WORTH,TX
i
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth TranSystems Corporation DBA
TranSystems Corporation
Consultants
c�44 4 D
Fernando Costa Raul Pena f1l, P.E.
Assistant City Manager Senior Vice President
DATE: DATE:
APPROVAL RrEC�OM'MEpNDED:
:a 4 w, W
Doug1a W. Wiersig, V.E.
Director, Department&f Transpollation
And Public Works
APPROV AS TO FORM AND LEGALITY: M&C: M
4i� - -
Date:
Doul glas W. Black
Assistant City Attorney
ATTEST: ___— .� p� °po000, F�
o°
at
Maryk./K-Y,6er�/ °�
0
City Se retary �oo60
0000° ICY
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012
Page 2of3 p
OFFICIAL RICORD
CITY SECRETARY
FT,WORTHo TX
FUNDING BREAKDOWN SHEET
City Secretary No.
Amendment No. 2
Department Fund-Account-Center Amount
C200 531200 202390165230 $39, 791 . 50
Total: $39, 791 . 50
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012
Page 3 of 3
ATTACHMENT"A"
The scope set forth herein defines the work to be performed by the ENGINEER in completing the
project. Both the CITY and ENGINEER have attempted to clearly define the work to be performed and
address the needs of the Project.
OBJECTIVE
Prepare Design of Roundabout at Intersection of Mark IV Parkway and Cantrell Samson.
WORK TO BE PERFORMED
Task 1. Project Management
Task 2. Design of Roundabout
Task 3. Survey and Right-of-Way Documentation
Task 4. Opinion of Probable Cost
TASK 1. PROJECT MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use of
ENGINEER's and CITY's time and resources. ENGINEER will manage change, communicate
effectively, coordinate internally and externally as needed, and proactively address issues with the
CITY's Project Manager and others as necessary to make progress on the work.
• Managing the Team
o Lead, manage and direct design team activities
o Ensure quality control is practiced in performance of the work
o Communicate internally among team members
o Task and allocate team resources
TASK 2. DESIGN OF ROUNDABOUT
The ENGINEER shall provide exhibit layout for a roundabout at Intersection of Mark IV Parkway and
Cantrell Samson.
• Horizontal Geometry
o Select overall size of roundabout
o Select lane widths and configuration
o Develop splitter island configurations
o Develop cross-walk locations
o Establish the truck apron location
o Check for entry and exit path overlap
o Check 0 angle between each entry and exit leg
o Check lookback angle at each yield line
o Check turning movements of design vehicle and busses(emulate emergency vehicle)
o Perform sight distance analyses per NCHRP 672
• Verify Compliance with Fastest Path Analysis per NCHRP672:
o Entry Path R,
o Circulatory Path R2
ATTACHMENT"A"TO STANDARD AGREEMENT FOR ENGINEERING RELATED DESIGN SERVICES(REV 7/27/2009)
PAGE 1 OF 2
o Exit Path R3
o Circulatory Path for Left Turns R4
o Right Turn Path R5
o Summary table of Fastest Path for all approaches
• Verify Turning movement of design vehicle using AutoTURN:
o Left turn movement for each approach
o Right turn movement for each approach
o Through movement for each approach
• Verify Turning movement of city bus using AutoTURN to approximate fire vehicles and school
busses ensuring no encroachment on the truck apron for these common vehicle:
o Left turn movement—this is the most critical and has the largest swept path within the
circulatory roadway
• Sidra Capacity Analysis to confirm geometrics.
• Establish grading for the roundabout to establish general construction limits.
• Sight Distance Analysis will be performed to confirm the intersection can function properly.
• Provide Plan and Profile sheets.
• Develop Typical sections.
• Determine all ADA and Bicycle requirements.
• Provide cross sections.
TASK 3. SURVEY AND RIGHT-OF-WAY DOCUMENTATION
• Provide topographic survey to complement the existing survey.
• Prepare Right-of-Way documentation to acquire property.
TASK 4. OPINION OF PROBABLE COSTS.
ENGINEER will provide the CITY an opinion of probable costs for project items.
ASSUMPTIONS
• The ENGINEER will prepare for and attend three (3) review meetings with the CITY.
• Evaluation of pavement markings and signing is included.
• Evaluation of lighting system included.
• Design vehicle to establish the geometry of the intersection will be a WB-67 truck due to the
proximity of Fed Ex Center.
DELIVERABLES
A. Exhibit
B. Plans and Specification
Opinion of Probable costs for project items and ROW needs
ATTACHMENT"A"TO STANDARD AGREEMENT FOR ENGINEERING RELATED DESIGN SERVICES(REV 7/27/2009)
PAGE 2 OF 2
Intersection Improvement Projects
Mark IV at Cantrell Samson
TranSystems Corporation Consultants
06/27f2013
Design Services HOURLY RATE WORK Total
Estimated Mardaurs Cost
Project Senior Design RPLS Survey Tech Clerical Esbmam
WORK TASK DESCRIPTION Manager Erginer Engineer Crew (S)
195.00 150.00 130.00 125.00 130.00 95.00 50.00 M/WBE
1, Project Managernert
PmIW M 4 taurshr onth 6 $N$ 260.00
kV"Reports 3 3 $
Buzz Saw maintenance 2 sub-total 2. Plan and S tlatlons
SidraA 2 8
GeomeMcs 2 32 8 12 S 7,370.00
Plan and Profile Sheets 4 40 $ 4,400.00
Typical Sections 2 4 4 $ 1,370.00
GrdM Plan 4 32 $ 4,760,00
Sidewalks/ADA 2 2 i 690.00
X-Sections 4 32 $ 3 820.00
sub-total i 24000.00
Alm Su MWBE of Amendment
To $5815.00 $ 5815,00
Rigm of W S 3,250.00 S 3250.00
sub-total $ 9065.00
City Review and Meetln
Review ard Comments f3l 4 6 12
Meet 3 3 3 $ 975.00
sub-total $ 3675.00
Expenses
Co couMouse 'es surveys) i 130.00
Plan and Speakabon Copies 20 sets
travel
subtotal S 130.00
MNYBE Markup
subtotal 90&50
Total $9 06&00 i 39 791.50