AMENDMENT No.3 CONTRACT NO.
TO CITY SECRETARY CONTRACT No. 42547
WHEREAS, the City of Fort Worth (CITY) and TranSystems Corporation,
DBA TranSystems Corporation Consultants, (ENGINEER) made and entered into
City Secretary Contract No. 42547, (the CONTRACT) which was authorized by
City Council by M&C C-25255 on the 01 day of November, 2011 in the amount
of $ 243, 322; and amended by amendment #1 administratively approved on
October 26, 2012 in the amount of $13, 010 . 00; and amended by amendment #2
administratively approved on July 9, 2013 in the amount of $39, 791 . 50 for
a revised contract amount of $296, 123 . 50 .
WHEREAS, the CONTRACT involves engineering services for the
following project:
North Fort Worth Intersections; and
WHEREAS, it has become necessary to execute Amendment No. 3 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated August 5, 2013, a copy
of which is attached hereto and incorporated herein. The cost to City
for the additional design services to be performed by Engineer totals
$48,035. 00. (See Attached Funding Breakdown Sheet, Page -3-)
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $344,158. 50.
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012 E/�ORD
R Page 1 of 3 OFFICIAL C
CI r'Y SECRETARY
f,ECFIV` �',WORTVIS11
r
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth TranSystems Corporation DBA
TranSystems Corporation
Consultants
4��� ZLw-
�
Fernando Costa Raul Pena III, P.E.
Assistant City Manager Senior Vice President
DATE: Z / DATE: f 9
APP AL RE/CO�MME/N'DED:
Dougla W. Wiersig, P .
Director, Department of Transporation
And Public Works
APPROVED AS TO FORM AND LEGALITY: M&C: C
Date: Ib�l5� ao13
Douglas W B1ark c (A e }�-
Assistant City Attorney
ATTEST:
\ 0�-.0 000 010�%
� ems $• �� C
8
ady J. Kayser C)gy
City SecretaryL$o
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012
Page 2 of 3 OFFICIAL
RECORD
CITY SECRETARY
FT. WORTH, TX
r
FUNDING BREAKDOWN SHEET
City Secretary No.
Amendment No. 3
Department Fund-Account-Center Amount
C204 531200 202390165230 $48, 035
Total: $48, 035
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012
Page 3 of 3
TranSystems
® , SKIS y 500 W.7th St
Suite 110
Fort Worth,TX 76012
Tel 817.339.8950
Fax 817.336.2247
www.transystems.com
August 5,2013
Lissette Acevedo,P.E.
Project Manager/Sr.Prof Engineer
City of Fort Worth Infrastructure Design and Construction
1000 Throckmorton St.,RM 266
Fort Worth,TX 76102
RE:Amendment#3 Request
Lissette,
TranSystems Corporation Consultants(TSC)would like to submit to complete the following additional
services on the City of Fort Worth North Intersection Improvements at the intersection or Mark IV and
Cantrell Samson.
The additional services TSC will provide at the intersection of Mark IV and Cantrell Samson are
updating/revising signing and striping placement,updating/revising SWPPP layouts, updating drainage area
map and drainage plan,determine light pole placement and coordination wit h the power company,revise
traffic control plans and submit all monthly reports and invoicing as per the contract.
We look forward to working with you on this project.
Sincerely,
ny L. ms, E.
Project ger
Intersection Improvement Projects
Mark IV at Cantrell Samson
TranSystems Corporation Consultants
8/5/2013
Design Services HOURLY RATE WORK Total
Estimated Manhours Cost
Project Senior Design RPLS Survey Tech Clerical Estimate
WORK TASK DESCRIPTION Manager Enginer Engineer Crew ($)
195.00 150.00 1 130.00 125.00 130.00 95.00 50.00 I M/WBE
1. Project Management
Project Management 4 hours/month 6 $ 1,170.00
Monthly Reports 3 3 $ 585.00
Buzz Saw maintenance 2 $ 260.00
sub-total $ 2,015.00
2. Plans and Specifications
Signing and Stri in 4 32 $ 3,640.00
SWPPP 2 8 24 $ 3,710.00
Specifications 8 8 $ 2,760.00
sub-total $ 10110.00
3. Drainage Anal is
DA Map 4 4 $ 1,160.00
Drainage Plan 40 32 $ 9,040.00
iSWM-Checklist 20 8 1$ 3,760.00
sub-total $ 13,960.00
Li-qhtina Design
Determine Pole location 1 4 16 16 $ 4,395.00
Coordinate with Power Company 1 3 $ 645.00
sub-total $ 5040.00
Traffic Control Plan
Phased Plans 2 4 32 40 $ 8,950.00
Prepare traffic sequence 2 8 $ 1,590.00
sub-total $ 10 540.00
City Review and Meetings
Review and Comments 3 5 6 1 1 12 $ 2,895.00
Meetings 3 3 3 $ 975.00
sub-total $ 3,870.00
Reimbursalbles-Printin $ 2500.00
Total 1$ 48 035.00
P-.I
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 10/15/2013
DATE: Tuesday, October 15, 2013 REFERENCE NO.: **C-26496
LOG NAME: 202011 INTERSECTION IMPROVEMENTS-MARK IV
SUBJECT:
Authorize Execution of Amendment No. 3 to City Secretary Contract Number 42547, the Engineering
Services Agreement, with TranSystems Corporation Consultants in the Amount of$48,035.00 for the
Preparation of Plans and Specifications for the Design of a Roundabout at the Intersection of Mark IV
Parkway and Cantrell Samson Road for a Revised Total Contract in the Amount of$344,159.00 (COUNCIL
DISTRICT 2)
RECOMMENDATION:
It is recommended that the City Council authorize execution of Amendment No. 3 to City Secretary
Number 42547, an Engineering Services Agreement with TranSystems Corporation Consultants in the
amount of$48,035.00, for the preparation of plans, specifications and construction estimates for the
design of a roundabout at the intersection of Mark IV Parkway and Cantrell Samson Road for a revised
total contract in the amount of$344,159.00.
DISCUSSION:
The 2008 Bond Program allocated funds for intersection improvements that would promote efficient traffic
flow. TranSystems Corporation Consultants was selected to prepare plans, specifications and cost
estimates at Mark IV Parkway/Cantrell Samson Road, and three other locations. Originally, a traffic signal
with roadway improvements was proposed for the intersection. However, it has been determined that
traffic will be better served by the construction of a roundabout at this intersection.
Amendment No. 2, in the amount of$39,792.50, was executed administratively to perform a feasibility
study and preliminary design to determine right-of-way needs in order to accommodate the
roundabout. This proposed Amendment No. 3 is for the preparation of construction plans for the actual
construction of the roundabout. The following table summarizes previous contract action and
Amendments:
City Project
No.01652 Amount Proiect Description M&C No. ;Approved
Design services for the preparation of plans and s
Initial specifications for intersection improvements at
;Contract 4243,322.00 four locations in North Fort Worth including C-25255 11/1/2011
adding left and right turn lanes with signal
modifications
_..... ......... _ _ ._.._ -......-.._..._
Amendment for additional surveys to acquire
Amendment $13,010.00 ROW to build permanent traffic signal and full ;Approved 1026/2012
`No. 1 pavement section at the intersection of Mark IV Administratively
at Cantrell Samson Road
!Amendment Amendment to perform feasibility study and Approved
No 2 $39,791.50 determine right-of-way requirements to build a Administratively 7/10/2013
( roundabout instead of traffic signal at Mark IV at
Logname:202011 INTERSECTION IMPROVEMENTS-MARK IV Page 1 of 2
. 'Cantrell Samson Road
Amendment Amendment to acquire right-of-way to proceed
3 {$48,035 00`with development of final plans for a roundabout Pending Pending
Me. 3 ion Mark IV at Cantrell Samson Road
�T�1____� _...-5344,159.00� .._.�..� �___.,_.____..�� __.. *i_._..._.. •� __.*!
This project is located in COUNCIL DISTRICT 2, Mapsco 49F.
FISCAL INFORMATION /CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Street Improvements 2008 Fund.
FUND CENTERS:
TO Fun d/Account/C enters FROM Fund/Account/Centers
C204 531200 202390165230 $48,035.00
CERTIFICATIONS:
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Douglas W. Wiersig (7801)
Additional Information Contact: Lissette Acevedo (2722)
ATTACHMENTS
1. 01652.pdf (CFW Internal)
2. C204 99901.docx (CFW Internal)
3. CANTRELL SAN MARK IV INT IMP 01652 7003.0 (Public)
4. Overall MWBE Percentage.pdf (CFW Internal)
Logname:202011 INTERSECTION IMPROVEMENTS-MARK IV Page 2 of 2