HomeMy WebLinkAboutContract 38672-CO5FORT WORTH . City of Fort Worth Change Order Request CllY SECRETARY CONTRACT NO. 2,j<o1+ -t;r;,:5 ~ Project Name! Edwards Ranch Rd . Ph .II City Sec # 38672 Client Project #(s)j C221-541200-303230010783 DOE 5994 Project Description' Paving and Drainage Contractor! L.H. Lacy Change Order # 5 Date City Project Mgr.l_Leon __ Wi_11so_n __________ ...., City Inspector Martina Salinas Dept TPW Original Contract Amount $3,931,769.09 Extras to Date $277,117.88 Credits to Date $9,973 .64 Pending Change Orders (in M&C Process) Contract Cost to Date $4, 198,913.Jl .. · IAmount of Proposed Change Order ~.we.JU ~ "!' . ,., ;;· ,,1:t ,, >'. ,,;:. . Revised Contract Amount .J4,,ll"JI 1•N.t,J. !' 'ii'·.'·~ . r• .·. ,. . Original Funds Available for Change Orders $118,000.00 Remaining Funds Available for this CO · · $0.00 ·, ' :, .. Additional Funding (if necessary) $3,096.30 ,, .. ,_ .. ' CHANGE ORDERS to DATE (INCLUDING THIS ONE} AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%} 1i. ' ·> r . , .. Installation of 2· bore and riser necessary to provide electrical service to the street lights. Totals $3,931,769.09 $277,117.88 $9 ,973 .64 $4,198,913.33 ~.09ti.3U $4,202 ,009.63 $118,000.00 $3,096.30 6.87'6 $4,91~,7,11:3& 4/22/2011 Contract Time (CD) 240 240 10 250 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. ,v, I..(\ I ,o I l(\ 0 I \ ) 1 1 J L---~=======---l,...JJUJ...M.&~IJJJJ..HJil.L.,J....----=====-------'-l-~ City of Fort Worth Change Order Additions Project Name Edwards Ranch Rd . Ph .II City Sec# 38672 :::::============================================:..._-=----===::; Client Project# ::::C=22=1:::-54=1=200-=:3=03=2=30:=01=0=78:=3:::D:::O:=E:=59:::94=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:=:~ Project Description Paving and Drainage Contractor '--L_.H_. L...;a ..... cy'--------------------' Change Order# 5 Date 4/22/2011 City Project Mgr . Leon Wilson ~..;..;_------------------' City Inspector Martina Salinas ADDITIONS 111:M Ut::St,;Klt-' I IUN Utt-'I CJty Unit unit c.;ost f Otal "/. J M, 1 ms in 7 scneaul8 '+U t-'Vc.; TPW ou .uu ~r-$1"/..tl ~/Ol.Ul 6 Pull~x 11-'W 2.UU l:A $504 .l:ll $1,UUl:I.Ol 7-NEW 1, Conduit Bore fPW 1.UU L~ ~012.0l $H12 .0U 8-NEW 1, RMC Riser fPW lU.00 LF ~lO.bl $~12.UU Tl W $J,U!:lo.Jl ~UD I Otal ACIC11tions $J , Ul:lb . JU Change Order Additions Page 1 of 1 Project Name Cl ient Project # Edwards Ranch Rd. Ph.II City of Fort Worth Change Order Deletions C221-541200-303230010783 DOE 5994 City Sec# Project Description Paving and Drainage Contractor ......_L_.H_. L_ac_,y...__ _____________ __. Change Order # 5 Date 4/22/2011 City Project Mgr. Leon Wilson ......_ _____________ ____. City Inspector Martina Salinas DELETIONS llt:M Ut:;:,l.,~lt' I IUN Ut:t' I 1 .. ny Unit unit c.;ost TIW Sub Total Deletions Change Order Deletions Page 1 of 1 38672 IOtal $0.UCJ l M/WBE Breakdown for this Change Order MWBESub : ,., ... . Type of Service. . ,., I • Amount for this CO ,, Total :"Y''. V. ..: .. , . , , so 00 lo' • ,a_ "" ~!<: ' ' :/;!t"-' ,, ,,. ' .. ,,,. ,, , ~· Previous Change Orders CO#' .~ ' DATE ' , ... . ·, ., ,· AMOUN T', . ci,;.· -ti,fr}", ,.,;, " • 'j, ... , ,.·· ····~, '· ).:, I ,.,~ •• ' .• \:;( 1._J-I ' SO~OQ t' Total ... . :; \, \ .y , .• PROJECT SUMMARY SHEET · (Change Order Attachment) PROJECT NAME : BuySpeed No: Edwards Ranch Road, Phase II, Unit 2 CSC0-09-00054509 City Project No : 00107 Contract No : CS38672 D.O .E . No : 5994 Attachment to Change Order No : 5 Today's Date : 4/26/11 Original Contract Amount: Extras to Date: Credits to Date: Contract Amount to Date: Amount of Proposed Change Order: Revised Contract Amount: Contingency Funds Avail. for Admin. Change Orders : Remaining Funds Available for Change Orders: Additional Funding (if necessary): TOTAL $ 3,931,769.09 $ 277,117.88 $ $ (9,973.64) $ $ 4,198,913.33 $ 3,096.30 $ 4,202,009.63 $ 118,000.00 $ $ (3,096.30) Prepared By: Christy Ezernack T/PW Construction Services C221 /TPW 3,931,769.09 277,117 .88 (9,973.64) 4,198,913.33 3,096 .30 4 ,202,009.63 118,000.00 (3,096.30) PROJECT SUMMARY SHEET (Change Order Attachment) PROJECT NAME: Edwards Ranch Road, Phase II, Unit 2 BuySpeed No: Contract No: D.O.E. No : Attachment to Change Order No: Today's Date: Original Contract Amount Extras to Date: Credits to Date: Contract Amount to Date: CSCQ-09-00054509 CS38672 5994 5 5/12/11 Amount of Proposed Change Order. Revised Contract Amount: Contingency Funds Avail. for Admin . Change Orders: Remaining Funds Available for Change Orders: Additional Funding (if necessary): TOTAL/C221 $ 3,931,769.09 $ 277,117.88 $ 9,973.64 $ 4,198,913.33 $ 3,096.30 $ 4,202,009.63 $ 118,000.00 $ $ 3,096.30 Prepared By: Karen Striker -T/PW Business Support