HomeMy WebLinkAboutOrdinance 24872-06-2021 ORDINANCE NO. 24872-06-2021
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF$250,000.00, TRANSFERRED FROM AVAILABLE FUNDS
IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING THE
2020 MISCELLANEOUS SANITARY SEWER MANHOLE REPAIR PROJECT
(CITY PROJECT NO. 1026391; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;AND PROVIDING
AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-2021 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of$250,000.00,transferred from available funds in the Water
and Sewer Fund,for the purpose of funding the 2020 Miscellaneous Sanitary Sewer Manhole Repair Project
(City Project No. 102639).
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
akVDelack(Jun 14,2u., 1,21 CDT)
Douglas W Black Mary J.Kayser
Sr.Assistant City Attorney � FORT
0:
ADOPTED AND EFFECTIVE:June 8,2021
_
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 06/08/21 M&C FILE NUMBER: M&C 21-0386
LOG NAME: 602020SSHMRR1-ACEPC
SUBJECT
(ALL)Authorize Up to Four Renewals of the 2020 Miscellaneous Sanitary Sewer Manhole Repair for Various Locations throughout the City
Contract with Ace Pipe Cleaning,Inc.,Authorize Execution of the First Renewal and Adopt Attached Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize up to four renewals of the 2020 Miscellaneous Sanitary Sewer Manhole Repair contract(City Project No. 102639)with Ace Pipe
Cleaning,Inc.;
2. Authorize execution of the first renewal of the 2020 Miscellaneous Sanitary Sewer Manhole Repair contract in the amount of$225,000
with Ace Pipe Cleaning, Inc.;and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of$250,000.00 transferred from available funds within the Water and Sewer Fund.
DISCUSSION:
On June 23,2020,Mayor and Council Communication(M&C)20-0458,the City Council authorized the execution of a contract in the amount of
$225,000.00,for the 2020 Miscellaneous Sanitary Sewer Manhole Repair project(City Secretary Contract No.54211). The M&C referenced four
renewals but did not specifically authorize same.
The City and the contractor desires to exercise the first renewal of the contract in the amount of$225,000.00. This M&C is also to appropriate
funds in the Water and Sewer Capital Projects Fund for the 2020 Miscellaneous Sanitary Sewer Manhole Repair project The work to be
performed under this contract consists of sanitary sewer manhole repairs and the installation of interior epoxy manhole coatings as identified by
the Water Department's Wastewater Field Operations staff.The Water Department is neither staffed nor equipped to perform sanitary sewer
manhole interior epoxy coating.This contract is necessary to extend the useful life of deteriorated sanitary sewer manholes in the wastewater
system in lieu of replacing them with brand new manholes. In addition to the contract amount,$25,000.00 is required for project management and
inspection. This project will have no impact on the Water Department's operating budget when completed.
Appropriations for the 2020 Miscellaneous Sanitary Sewer Manhole Repair project are depicted below:
Fund Existing Additional Project
Appropriations Appropriations Total*
W&S Capital $250,000.00�F $250,000.00$500,000.00
Projects-Fund 56002
Project Total $250,000.0011 $250,000.0 $500,000.00
*Numbers rounded for presentation
M/ BE OFFICE: Ace Pipe Cleaning, Inc is in compliance with the City's BDE Ordinance by committing to seven percent MBE participation on
this project.The City's MBE goal on this project is seven percent.
This project is located in ALL COUNCIL DISTRICTS.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water&Sewer Fund and upon approval of the above
recommendation and adoption of the attached appropriation ordinance,funds will be available in the W&S Capital Projects Fund for the MISC
Manhole Repair Contract project to support the renewal of the contract.Prior to any expenditure being incurred,the Water Department has the
responsibility to validate the availability of funds.
Submitted for City Manager's Office W. Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: J. Chris Underwood 2629