HomeMy WebLinkAboutContract 42720INFRASTRUCTURE CONSTRUCTION AGREEMENT THE STATE OF TEXAS § COUNTY OF TARRANT § City Secretary Contract No. WHEREAS, on November 25, 1997 the City Council of the City of Fort Worth , Texas adopted Ordinance No. 13259, establishing Tax Increment Financing Reinvestment Zone Number Four, City of Fort Worth, Texas (the "TIF District "), and establishing the tax increment fund of the TIF District ; and WHEREAS, on August 30, 1999 the Board of Directors of the TIF District adopted a project and financing plan for the revitalization of Fort Worth's Near Southside , which was approved by the City Council on August 31, 1999 pursuant to Ordinance No. 13919; and WHEREAS, Fort Worth Southside Development District. Inc. is a Texas non - profit corporation working to sustain the momentum of the revitalization of Fort Worth's Near Southside and is doing business as Fort Worth South, Inc.; and WHEREAS, Fort Worth South, Inc. ( "Developer ") desires to oversee the preparation of final engineering plans and construction of streetscape improvements on Park Place Avenue ( "Streetscape Improvements "); and WHEREAS, the Board of Directors of the TIF District has approved a Tax Increment Financing Development Agreement with Fort Worth South, Inc. (the "TIF Agreement ") and agreed to dedicate revenue from the tax increment fund of the TIF District (the "TIF Funds ") for streetscape and public right -of -way improvements on Park Place Avenue; and WHEREAS, the City of Fort Worth has requested that Fort Worth South, Inc. also construct related infrastructure improvements, including water, sewer, storm drain, paving, and sidewalks ( "Related Infrastructure ") on Park Place Avenue and Enderly Place and agrees to participate in the costs of the related infrastructure; and Park Place ICA Page I of 10 ■;. ..fir k '!'� WHEREAS, Fort Worth South, Inc. will retain a contractor ( "Contractor ") to construct the Streetscape Improvements and Related Infrastructure, collectively known as the "Community Facilities" as further depicted on the attached exhibits hereto ( "Exhibits "); NOW, THEREFORE, KNOW ALL BY THESE PRESENTS: For and in consideration of the covenants and conditions contained herein, the City and Fort Worth South, Inc. do hereby agree as follows: General Requirements A. The Policy for the Installation of Community Facilities ( "Policy ") dated March 2001, approved by the City Council of the City of Fort Worth and subsequently amended from time to time via a Mayor and Council Communication adopted by the City Council of the City of Fort Worth, is hereby incorporated into this Infrastructure Construction Agreement as if copied herein verbatim. Developer agrees to comply with all provisions of said Policy, except those provisions expressly waived in this agreement, in the performance of its duties and obligations hereunder and to cause all contractors hired by Developer to comply with the Policy in connection with the work performed by said contractors. B. The project that is the subject of this Infrastructure Construction Agreement consists of (1) the preparation of final engineering plans and construction of the streetscape improvements on Park Place Avenue and (2) construction of related infrastructure on Park Place Avenue and Enderly Place (the "Project"). The Developer shall not be required to provide financial security in conformance with paragraph 6, Section II, of the Policy. Instead, the funding and payments are set forth as follows: i. The TIF Agreement between the Board of Directors of the TIF District and the Developer has provided TIF Funds for the preparation of final engineering plans and construction of streetscape improvements on Park Place Avenue. The Developer shall be entitled to Project Payments for the preparation of final engineering plans and for the construction of streetscape improvements from the TIF Funds by reimbursement or by draw as set forth Park Place ICA Page 2 of 10 in the TIF Agreement. ii. Additionally, the City of Fort Worth has requested that Developer construct certain related infrastructure on Park Place Avenue and Enderly Place, and agrees to participate in the costs of the related infrastructure (the "City Funds "). Payment will be made by the City directly to the Contractor, and the Developer will provide consent to assignment of partial payments as part of the language in his Contract with the Contractor. On or before the fifth (5`h) day of each calendar month during the term hereof, the Contractor shall submit to the Project Manager on this Project (i) an Application for Payment (herein so- called) describing the work completed through the last day of the previous month, (ii) invoices relating to such work previously performed and/or materials installed that are the subject of the Application for Payment, (iii) and the Project Engineer's estimate of work completed on the portion of the Project that is to be funded by City Funds. No later than the tenth (10`h) day of the month (the "Review Period ") the City shall review and approve the application for Payment, and the City shall pay the authorized recipient the amount requested in the Application for Payment (less applicable retainage per construction contract documents) and approved by the City within twenty-five days after the earlier of (1) the expiration of the Review Period or (2) approval or deemed approval of the Application for Payment. If any portion of the application for Payment is disputed by the City, then the disputing party shall deliver to the Contractor a written objection notice during the Review Period setting forth such objections in reasonable detail. The undisputed portion of the Application for Payment shall be timely paid to the authorized recipient as provided above. If the City timely and reasonably objects to the Application for Payment, the Contractor shall exercise good faith efforts to cure the objectionable items to the city's reasonable satisfaction , and the process set forth above shall be repeated until the application for payment is completely approved and fully paid. After the City has paid the funds requested in an Application for Payment, the Contractor will obtain a release and /or waiver of liens, claims, security interests and encumbrances arising out of the work paid for by the City and provide copies thereof to the City with each following application for Payment.. Developer acknowledges that, upon completion of the Park Place ICA Page 3 of 10 Project, it will submit an Affidavit of Bills paid signed by its contractor and Consent of Surety signed by its surety to ensure the contractor has paid the sub - contractor and suppliers in full. Additionally, the contractor will provide in writing that the contractor has been paid in full for all the services provided under this contract. C. Developer agrees to cause the construction of the improvements in the Project contemplated by this Agreement and that said construction shall be completed in a good and workmanlike manner and in accordance with all City standards and the City- approved construction plans, specifications and cost estimates provided for the Project and the exhibits attached hereto. D. The following checked exhibits are made a part hereof: Water (A) , Sewer (A -1) ; Paving (B) ; Storm Drain (B -1) ; Street Lights & Signs (C) . Streetscape (D) E. The Developer shall award all contracts for the construction of community facilities in accordance with Section II, paragraph 7 of the Policy and the contracts for the construction of the public infrastructure shall be administered in conformance with paragraph 8, Section II, of the Policy. F. For all infrastructure included in this Agreement for which the Developer awards construction contract(s), Developer agrees to the following: i. To employ a construction contractor who is approved by the director of the department having jurisdiction over the infrastructure to be constructed, said contractor to meet City's requirements for being insured, licensed and bonded to do work in public streets and/or prequalified to perform water /waste water construction as the case may be. ii. To require its contractor to furnish to the City a payment and performance bond in the names of the City and the Developer for one hundred percent (100 %) of the contract price of the infrastructure, and a maintenance bond in the name of the City for one hundred percent (100 %) of the contract price of the infrastructure for a period of two (2) years insuring the maintenance and repair of the constructed infrastructure during the term of the maintenance bond. All bonds to be furnished before work is commenced and to meet the requirements of Chapter 2253, Texas Government Code. iii. To require the contractor(s) it hires to perform the construction work Park Place 1CA Page 4 of 10 contemplated herein to provide insurance equal to or in excess of the amounts required by the City's standard specifications and contract documents for developer - awarded infrastructure construction contracts. The City shall be named as additional insured on all insurance required by said documents and same will be evidenced on the ACORD Certificate of Insurance supplied by the contractor's insurance provider and bound in the construction contract book. iv. To require its contractor to give 48 hours notice to the City's Construction Services Division of intent to commence construction so that City inspection personnel will be available; and to require the contractor to allow the construction to be subject to inspection at any and all times by City inspection forces, and not to install or relocate any sanitary sewer, storm drain, or water pipe unless a responsible City inspector is present and gives his consent to proceed, and to make such laboratory tests of materials being used as may be required by the City. v. To require its contractor(s) to have fully executed contract documents submitted to the City to schedule a Pre - Construction Meeting. The submittal should occur no less than 10 working days prior to the desired date of the meeting. No construction will commence without a City- issued Notice to Proceed to the Developer's contractor. vi. To require its contractor(s) to delay connections of buildings to service lines of sewer and water mains constructed under this Agreement until said sewer and water mains and service lines have been completed to the satisfaction of the Water Department. G. Developer agrees to require its Engineer to provide to City staff copies of all engineering drawings and documents necessary to construct the improvements required by this Agreement. H. Developer shall require its contractor(s) to cause the installation or adjustment of the required utilities to serve the development or to construct the improvements required herein. I. City shall be responsible for costs incurred by Contractor in the relocation of utilities that are or may reasonably be in conflict with any of the Related Infrastructure to be installed hereunder as finiher depicted on the Exhibits. J. Developer's Engineer preparing the preliminary plans, specifications and cost Park Place 1CA Page 5 of 10 estimates carries insurance to cover any negligent errors in the preliminary plans, specifications and cost estimates prepared by the Engineer for this Agreement. K. Developer and its Engineer will assist the City in obtaining all necessary rights of way and easements across property required for the construction of the current and future improvements provided for by this Agreement. L. Developer will further require its contractors to indemnify, defend and hold harmless the City, its officers, agents and employees from and against any and all claims, suits or causes of action of any nature whatsoever, whether real or asserted, brought for or on account of any injuries or damages to persons or property, including death, resulting from, or in any way connected with, the construction of the infrastructure contemplated herein, whether or not such iniuries, death or damazes are caused, in whole or in part, by the allezed neelizence of the City of Fort Worth, its officers, servants, or employees. Further, Developer will require its contractors to indemnify, and hold harmless the City for any losses, damages, costs or expenses suffered by the City or caused as a result of said contractor's failure to complete the work and construct the improvements in a good and workmanlike manner, free from defects, in conformance with the Policy, and in accordance with all plans and specifications and shall cause to be executed and delivered to the City an indemnity agreement from such contractors on a form to be promulgated by the City. Such indemnity agreement may be contained in and made a part of the construction agreements between developer and its contractors. M. Developer agrees that all contracts with any contractor shall include provisions granting to the City the right to enforce such contracts as an express intended third party beneficiary of such contracts. Further, upon completion of all work associated with the construction of the infrastructure and improvements, Developer will assign to the City a non - exclusive right to enforce the contracts entered into by the Developer and its contractor along with an assignment of all warranties given by the contractor, whether express or implied. N. Developer shall be responsible for payment or reimbursement to the City of Developer's costs of construction inspection and/ or material testing. Park Place ICA Page 6 of 10 O. COMPLETION WITHIN 2 YEARS i. In the TIF Agreement, the Developer agreed to have engineering plans prepared and construct streetscape improvements no later than August 31, 2012. With regard to the related infrastructure, if the Developer has not scheduled a pre - construction meeting within nine months of the execution of this Agreement, or if construction of the related infrastructure has not been substantially completed within two years from scheduling the pre - construction meeting, the City shall have the right to terminate the contract, and shall have the right to complete the construction of the related infrastructure and to use the City Funds to complete it. ii. The City may also utilize the City Funds to cause the completion of the construction of the related infrastructure or to cause the payment of costs for construction of same before the expiration of two (2) years if the Developer breaches this Agreement, becomes insolvent or fails to pay costs of construction. (Remainder of Page Intentionally Left Blank) Park Place ICA Page 7 of 10 Cost Summary Table Item TIF Cost' Water Dept. Cost" TPW Cost" Total Cost A. Water Dept. Construction in Park PI 1. Water N/A $ 438,100.00 N/A $ 438,100.00 2. Sewer N/A $ 6,160.00 N/A $ 6,160.00 B. Water Dept. Construction in Enderly PI 1. Water N/A $ 46,002.55 N/A $ 46,002.55 2. Sewer N/A $ - N/A $ - Water Dept. Contingency 10% N/A $ 49,026.26 N/A $ 49,026.26 Total Water Dept. Constr. with Contingency N/A $ 539,288.81 N/A $ 539,288.81 C. Water Dept. Construction Fees 1. Water Inspection 2% N/A $ 10,650.26 N/A $ 10,650.26 2. Water Mat. Testing 2% N/A $ 10,650.26 N/A $ 10,650.26 3. Sewer Inspection 2% N/A $ 135.52 N/A $ 135.52 4. Sewer Mat. Testing 2% N/A $ 135.52 N/A $ 135.52 Total Water Dept. Construction Fees N/A $ 21,571.56 N/A $ 21,571.56 Total Water Dept. N/A $ 560,860.37 N/A $ 560,860.37 D. TPW Construction in Park PI 1. Paving $ 479,325.00 N/A N/A $ 479,325.00 2. Drainage $ 10,000.00 N/A $ 72,970.00 $ 82,970.00 3. Street Lights and Signage $ 177,000.00 N/A N/A $ 177,000.00 4. Streetscapes $ 73,564.00 N/A N/A $ 73,564.00 E. TPW Construction in Enderly PI 1. Paving N/A $ 41,285.15 $ 41,285.15 $ 82,570.30 2. Drainage N/A N/A $ 132,045.00 $ 132,045.00 3. Street Lights and Signage N/A N/A N/A N/A 4. Streetscapes N/A N/A N/A N/A Total TPW Dept. Constr. $ 739,889.00 $ 41,285.15 $ 246,300.15 $ 1,027,474.30 TPW Contingency 10% $ 73,988.90 $ 4,128.52 $ 24,630.02 $ 102,747.44 TPW Constr. With Contingency $ 813,877.90 $ 45,413.67 270 930.17 $ 1,130,221.74 F. TPW Construction Fees 1. Paving and Streetscapes Inspection 4% $ 24,327.12 $ 1,816.55 $ 1,816.55 $ 27,960.22 2. Paving and Streetscapes Mat. Testing 2% $ 12,163.56 $ 908.27 $ 908.27 $ 13,980.10 3. Drainage Inspection 4% $ 440.00 N/A $ 9,020.66 $ 9,460.66 4. Drainage Mat. Testing 2% $ 220.00 N/A $ 4,510.33 $ 4,730.33 5. Street Light Inspection 4% $ 7,788.00 N/A N/A $ 7,788.00 Total TPW Construction Fees $ 44,938.68 $ 2,724.82 $ 16,255.81 $ 63,919.31 Total TPW $ 858,816.58 $ 48,138.49 $ 287 185.98 $ 1,194,141.05 Grand Total $ 858,816.58 $ 608,998.86 $ 287,185.98 $ 1,755,001.42 Park Place ICA Page 8 of 10 "Requested City Cost Participation per this agreement. Please see attached exhibits and estimates for the detail cost breakdown. * The Board of Directors of the Tax Increment Financing Reinvestment Zone Number Four, the City of Fort Worth, Texas, entered a Tax Increment Financing Development Agreement with Fort Worth South, Inc. agreeing to dedicate revenue from the TIF Funds for the engineering plans and the construction of the streetscape on Park Place Avenue. Those amounts are labeled as "TIF Cost" on this table. The Checked Must be Included as Attachments to this Agreement Included Attachment ® Location Map ® Exhibit A: Water Improvements ® Water Estimate ® Exhibit A -1: Sewer Improvements ® Sewer Estimate ® Exhibit B: Paving Improvements ® Paving Estimate ® Exhibit B -1: Storm Drain Improvements ® Storm Drain Estimate ® Exhibit C: Street Lights and Signs Improvements ® Street Lights and Signs Estimate ® Exhibit D: Streetscape and Irrigation Improvements ® Streetscape and Irrigation Estimate Park Place ICA Page 9 of 10 THE CITY OF FORT WORTH, TEXAS COST EXHIBITS PARK PLACE AVENUE IMPROVEMENTS FROM WARNER ROAD TO 8TH AVENUE & ENDERLY PLACE IMPROVEMENTS FROM ALLEN AVENUE TO PARK PLACE AVENUE LOCATION MAP N.T.S FORTWORTH C � � Kimley -Horn and Associates, Inc. ZrZ W ZN N�L�iJ U O ,Qa a. 3 -1 Wi mi zi Q I I Q I 30V-Id 'I- 30N3 ' c ' I / 4 V Hlg OV08 83NHVM 0 u ui J Q U U w Od D z z Q w Q U 00 a Y O< O0 �W o! D U) Wz Z Q Q 23:z 00-J W Q LL �w0 W z U- www aQgW J ~ a � m Y W 2 cl xaz waw EE Park Place Avenue Infrastructure Improvements Water Cost Estimate Water Improvements in Park Place (City Cost) Line No. Description Quantity Unit Unit Price Cost 1 Mobilization - Services 1 LS $15.000.00 $15,000.00 2 Preparating Right -of -Way 1 LS $12,000.00 $12,000.00 3 SWPPP>1 Ac SWPPP - Install 1 LS $5,000.00 $5,000.00 4 Pipe - Casing - 24 -Inch - (Steel Casing Pipe with 12 -Inch Pressure Class 350 DI Water Pipe by Other Than Open Cut (All Depths) (Restrained) with Stainless Steel Spacers per Technical 150 LF $600.00 $90,000.00 5 Pipe - Pressure - 12 -Inch (PVC C -900 DR -14 Water Pipe by Open Cut (All Depths) with 780 LF $150.00 $117,000.00 6 Pipe - Pressure - 12 -Inch (Pressure Class 350 DI Water Pipe by Open Cut (All Depths) with 160 LF $170.00 $27,200.00 7 Pipe - Pressure - 6 -Inch (PVC C -900 DR -14 Water Pipe by Open Cut (All Depths) with 60 LF $70.00 $4,200.00 8 Water Service - 2 inch (Type K Copper Water Service Line to Meter Per Item D -51.7) - Install 20 LF $45.00 $900.00 9 Water Service - 1 Inch (Type K Copper Water Service Line to Meter Per Item D -51.7) - Install 320 LF $35.00 $11,200.00 10 Valve - 12 -Inch - (Resilient Seated) Gate Valve with Box (Per Detail WTR -002M) - Install 10 EA $2,400.00 $24,000.00 11 Valve - 6 -Inch - (Resilient Seated) Gate Valve with Box (Per Detail WTR -002M) - Install 1 EA j $1,000.00 $1,000.00 12 Valve - 6 -Inch - Blow Off - with Sump Manhole (Per Detail WTR -015A) - Install 1 EA $8,000.00 $8,000.00 13 Fire Hydrant (Per Detail WTR -006) - Install 2 EA $3,500.00 $7,000.00 14 Fire Hydrant - Barrel & Stem Extension - Install 6 VF $300.00 $1,800.00 15 Pipe Fittings - Ductile Iron - 16 -Inch and greater Ductile Iron Pipe - Install 0.1 TON $4,000.00 $400.00 16 Pipe Fittings - Ductile Iron - Less Than 16 -Inch Ductile Iron Pipe - Install 4.0 TON $4,000.00 $16,000.00 17 Water Service - 1 Inch -Tap to Main (Per Item D -51.7) - Install 13 EA $1,000.00 $13,000.00 18 Water Service -2 Inch - Temporary (Per Item D -51.8) - Install 1 LS $8,000.00 $8,000.00 19 Meter Box -Class B - Install 1 EA $300.00 $300.00 20 Meter Box -Class A - Install 13 EA $200.00 $2,600.00 21 Meter Box - Remove 14 EA $500.00 $7,000.00 22 Trench Safety System for Depths Exceeding 5 -foot (Per Item D -26) - Install 1,600 LF $5.00 $8,000.00 23 Dehole Exploratory Excavation (Per Item D -51) - Study 1 EA $2,000.00 $2,000.00 24 Valve -Gate (Remove and Salvage Existing Gate Valve 12 -Inch and Smaller per Item D -29) - Remove 4 EA $500.00 $2,000.00 25 Valve -Gate (Remove and Salvage Existing Gate Valve 16 -Inch and Larger per Item D -29) - Remove 4 EA $750.00 $3,000.00 26 Fire Hydrant (Remove and Salvage Existing Fire Hydrant Per Item D -28) - Remove 1 EA $500.00 $500.00 27 Water - Cut and Plug Existing Water Line (At Different Locations Other Than Proposed Water Improvements) - Abandon 1 EA 1 $2,500.00 $2,500.00 28 Pavement - Permanent HMAC Pavement Repair (Per Detail STR -028M) - Install 100 LF $60.00 $6,000.00 29 Pavement - 2 -inch HMAC - Temporary (Pavement Repair Per Figure STR -030) - Install 500 LF $35.00 $17,500.00 30 Traffic Control (Per Item DA -117)- Install 1 LS $20,000.00 $20,000.00 31 Pipe - Pressure - Extra Depth Greater Than 1 -foot (Depth Greater Than That Shown in the Construct on Plans) - Install 100 LF $50.00 $5,000.00 Subtotal: $438,100.00 ater Improvements in Enderly Place (City Cost) Line No. Description Quantity Unit Unit Price Cost 1 Pavement -2 Inch HMAC on 6 Inch Flex Base - Temporary - Install 1,113 SF $ 3.35 $3,728.55 2 Fire Hydrant - Install 1 EA $ 1,950.00 $1,950.00 3 Fire Hydrant - Remove 1 EA $ 295.00 $295.00 4 Meter Box -Class A - Install 11 EA $ 105.00 $1,155.00 5 Pipe - Remove 307 LF $ 4.00 $1,228.00 6 Pipe Fittings- <Than 16 Inch DI Pipe - Install 1 TONS $ 4,750.00 $4,940.00 7 Pipe - Pressure -12 Inch - Install 300 LF $ 65.00 $19,500.00 8 Pipe - Pressure -4 Inch - Install 3 LF $ 22.00 $66.00 9 Pipe - Pressure -6 Inch - Install 18 LF $ 28.00 $504.00 10 Valve -12 Inch -Gate Valve w/ Box - Install 2 EA $ 1,200.00 $2,400.00 11 Valve -6 Inch -Gate Valve w/ Box - Install 1 EA $ 820.00 $820.00 12 Valve -Gate - Remove 1 EA $ 155.00 $155.00 13 Water Service -1 Inch - Install 191 LF $ 21.00 $4,011.00 14 Water Service -1 Inch -Tap to Main - Install 11 EA $ 300.00 $3,300.00 15 lWater Service -2 Inch - Temporary - Install 300 LF $ 6.50 $1,950.00 Subtotal: $46,002.55 otal Water $484,102.55 '3AV H18 I I I i I I II I I W Q I ' Q , I - - N La 0 �Vld Jl_ 1839N3- _ { / v� V Q0U � a v N / La , , a a , I ' J , a , , , , ovoa 83NaVM of u a J Q U N Z 2 w � Z Q � 2 W 00 uj1Z0 v/ QQ0 t:CL w CO Y Z a- Q W Total Sanitary Sewer $6,160.00 Park Place Avenue Infrastructure Improvements Sanitary Sewer Cost Estimate Sanitary Sewer Improvements in Park Place (City Cost) Line No. Description Quantity Unit Unit Price Cost 1 Pipe - Sewer - 8 -Inch SDR -26 PVC (by Open Cut with Concrete Stabilized Backfill Per WTR -029M) - Install 20 LF $90.00 $1,800.00 2 Pipe - Sewer- 6 -Inch SDR -26 PVC (by Open Cut with Concrete Stabilized Backfill Per WTR -029M) - Install 20 LF $70.00 $1,400.00 3 Sewer- Plug Existing All Sizes All Depths - Abandon 2 EA $1,000.00 $2,000.00 4 Inspection - Pre - Construction Cleaning & TV (Per Item D -34) - Stud 240 LF $4.00 $960.00 Subtotal: 6,160.00 Total Sanitary Sewer $6,160.00 012 Z Z p W N aa. o v O aa.. 30VId A1830N3 mil® Ck. , , ce , , , , , , , 4� N , / Z CL ' CL0F CL IL _ mil® Ck. , , ce , , , , , , , W 06 Z) W LZU Z) > Z Q w w a� 00 O� F- QW OFO �w �Q F-- � > w Q Q w w >2J J CL LLQ 2 w Q C� Z LL Z W w aQg awa m J J ~ a m Y w 2 � � X Q Z w (I. w , , , , "J Q I1� \ OV08 83N8VM W 06 Z) W LZU Z) > Z Q w w a� 00 O� F- QW OFO �w �Q F-- � > w Q Q w w >2J J CL LLQ 2 w Q C� Z LL Z W w aQg awa m J J ~ a m Y w 2 � � X Q Z w (I. w n w "J Q U U) W 06 Z) W LZU Z) > Z Q w w a� 00 O� F- QW OFO �w �Q F-- � > w Q Q w w >2J J CL LLQ 2 w Q C� Z LL Z W w aQg awa m J J ~ a m Y w 2 � � X Q Z w (I. w Park Place Avenue Infrastructure Improvements Paving Cost Estimate Paving Improvements in Enderly Place (City Cost) Line No. Description Quantity Unit Unit Price Cost 1 Driveway – Remove 950 SF 0 $1,900.00 2 Driveway -6 Inch – Install 950 SF 0 $6,650.00 3 Utility Adjustment – Repair 1 LS 0 $5,000.00 4 Curb & Gutter – Remove 572 LF 0 $1,716.00 5 Curb & Gutter -7 Inch w/18 Inch Gutter – Install 572 LF 0 $17,160.00 6 Pavement Asphalt – Install 887 SY 0 $7,983.00 7 Pavement -2 Inch HMAC On 6 Inch Flex Base - Temporary – Install 2,930 SF 40 A$$14244.001001 $9,962.00 8 Pavement -2" (Min) HMAC on 2/27 Concrete Base 244 SF 45 $1,085.80 9 Pavement -8 Inch - Pulverization – Rehab 887 SY 50 $3,991.50 10 Pavement - Unclassified Street Excavation – Remove 369 CY 00 $1,845.00 11 Sign- Project Designation – Install 1 EA 00 $500.00 12 Grass Sod – Install 1,920 SY 00 $9,600.00 13 Topsoil – Install 214 CY .00 $2,996.00 14 Walk – Install 2,112 SF $4.00 $8,448.00 15 lWalk – Remove 918 SF $1.00 $918.00 16 Walk -ADA Wheelchair Ramp – Remove 50 SF $1.00 $50.00 17 Pavement - Cement Modification -26 Lbs /sy – Install 11.5 TON $110.00 $1,265.00 18 Walk -ADA Wheelchair Ramp – Install 3 EA $500.00 $1,500.00 11Subtotal: —1 $82,570.30 Paving Improvements in Park Place (TIF Cost) Line No, Description Quantity Unit Unit Price Cost 1 Mobilization – Services 1 LS $15,000.00 $15,000.00 2 Preparing Right -of -Way 1 LS $15,000.00 $15,000.00 3 SWPPP>1 Ac SWPPP – Install 1 LS $5,000.00 $5,000.00 4 Traffic Control – Install 1 LS $20,000.00 $20,000.00 5 Pavement - Unclassified Street Excavation – Remove 2,000 CY $12.00 $24,000.00 6 Pavement -8 -Inch Concrete Pavement w/ Integral Curb and Gutter – Install 5,600 SY $50.001 $280,000.00 7 Subgrade -8 -Inch Lime Stabilized Subgrade (40 Ibs /sy) – Install 6,225 SY $2.00 $12,450.00 8 ISubgrade - Lime for Stabilization – Install 125 TON $135.00 $16,875.00 9 Pavement - Header – Install 105 LF $10.00 $1,050.00 10 Pavement -Paver on Concrete Base – Install 585 SF $10.00 $5,850.00 11 Median -Type 1 Median Nose – Install 2 EA $2,000.00 $4,000.00 12 jPavement Markings – Install 1 LS $10,000.00 $10,000.00 13 Walk -4 Inch – Install 1,300 SY $30.00 $39,000.00 14 Walk -ADA Wheelchair Ramp – Install 20 EA $1,000.00 $20,000.00 15 Wheel Stops – Install 15 EA $100.00 $1,500.00 16 Manhole- Sanitary- Adjustment – Services 6 EA $1,200.001 $7,200.00 17 Manhole- Telephone - Adjustment – Services 2 EA 1 $1,200.001 $2,400.00 Subtotal: - -I $479,325.00 otal Paving $561,895.30 W U Z a R E Cr r I D WLLJa DI O z N z .0�68 d Q cr 0- ?Qvi 30Vld Jkl83aN3 '3AV H18 :r6 N cl: Wgo , am CL v~ia- a� , � r �z �a O� � W T 1 cno �Ot LL. �a CE a , z ' Cr Wa� Cc 0 Oa z 0 M 4, �,( �- - aV08 83N8VM 0 E D w Q U w 06 0 z Z) wa >w U 2 I- 0- O w H Q (n 0 a- w 00 �w � wz Q Q z LLJ Z J ��Q LL �?O Z LL w w Q w I_- a m Y w 2 w 0 xaz waw Park Place Avenue Infrastructure Improvements Storm Drain Cost Estimate Storm Drain Improvements in Enderly (City Cost) Line No. Description Quantity Unit Unit Price Cost 1 Mobilization- Services 1 LS 10,000.00 10,000.00 2 Preparing Right -of -Way 1 LS $8,000.001 $8,000.00 3 SWPPP>1 Ac SWPPP — Install 1 LS $4,500.00 $4,500.00 4 Traffic Control — Install 1 LS $10,000.00 $10,000.00 5 Pipe -21 Inch -CL III — Install 64 LF $63.00 $4,032.00 6 Pipe -24 Inch -CL III — Install 34 LF $74.00 $2,516.00 7 Pipe -30 Inch -CL III — Install 40 LF $87.00 $3,480.00 8 Pipe -36 Inch -CL III — Install 122 LF $115.001 $14,030.00 9 Box Culvert-5 ft x 3 ft — Install 120 LF $400.00 $48,000.00 10 Inlet - Inline -10 ft — Install 2 EA $2,350.00 $4,700.00 11 Inlet - Inline -20 ft — Install 2 EA $4,700.00 $9,400.00 12 Manhole -4 ft — Install 1 EA $2,500.00 $2,500.00 13 Fence — Remove 98 LF $2.50 $245.00 14 Fence -Chain Link — Install 98 LF $9.001 $882.00 15 Junction Box (11 ft x 7ft) — Install 1 EA $8,500.001 $8,500.00 16 jTren ch Safety System 5' Depth —Install 380 LF $2.00 $760.00 17 Sign- Project Designation — Install 1 EA $500.00 $500.00 Subtotal: 132,045.00 Storm Drain Improvements in Park Place (City Cost) Line No. I Description Quantity Unit Unit Price Cost 1 Channel- Earthen — Install 440 CY $14.00 $6,160.00 2 Headwall — Install 6 CY $225.00 $1,350.00 3 Pipe — Remove 150 LF $8.00 $1,200.00 4 Pipe -30 Inch -CL III — Install 34 LF $87.00 $2,958.00 5 Pipe -42 Inch -CL III — Install 158 LF $125.00 $19,750.00 6 Pipe -48 Inch -CL III — Install 79 LF $190.00 $15,010.00 7 Riprap- Grouted- < Than 18" Rock — Install 62 CY $75.00 $4,650.00 8 Inlet — Remove 5 EA $500.00 $2,500.00 9 Inlet- Drop -4 ft — Install 1 EA $2,500.00 $2,500.00 10 Inlet - Inline -10 ft — Install 1 EA $2,350.00 $2,350.00 11 Inlet - Inline -5 ft — Install 1 EA $2,000.00 $2,000.00 12 Manhole- > Than 4 ft — Install 1 EA $3,500.00 $3,500.00 13 Junction Box (11 ft x 7ft) — Install 1 EA $8,500.00 $8,500.00 14 Trench Safety System 5' Depth — Install 271 LF $2.00 $542.00 11Subtotal: 72,970.00 IStorm Drain Improvements in Park Place (TIF Cost) Line No. Description Quantity I Unit I Unit Price Cost 1 Inlet -In Line5 Ft— Install 1 EA $3,000.00 $3,000.00 2 Inlet -Top of 10' Inlet- Replace 2 LF $2,000.00 $4,000.00 3 Pipe -21 Inch -CI III—Install 40 LF $70.00 $2,800.00 4 Trench Safety System 5 Foot Depth — Install 40 LF $5.00 $200.00 Subtotal: $10,000.M Total Storm Drain $215,015.00 '3AV Hig V) II 0 C O L. OL L w 0. F= WI wz� 30VId AIMMN3 CD 0 0 F= a. 0 w :3 0 X 0 I.- LL. W 5 F= N z (n 0 a. 0 z OVOIJ 83NNYM b LO 6i L) U) F-- z w 2 W 0 CL 2 w Z (D U) w 0 Q Z z W T (D Q T- LU �-- 00 w Z W U) w 0 .. () w C) < w F-- w op Y Z X < W CL Park Place Avenue Infrastructure Improvements Street Light and Signage Cost Estimate Street Light and Signage Improvements in Park Place (TIF Cost) Line No. Description Quantity Unit Unit Price Cost 1 Light Concrete Foundation -Type 7— Install 29 EA $3,000.00 $87,000.00 2 Light- Purchase from City — Install 29 EA $3,000.00 $87,000.00 3 ISignage 1 LS $3,000.00 $3,000.00 Subtotal: $177,000.00 Total Street Light and Signage 11 $177,000.00 '3A H.L6 I I I II I I I II I I I WI Q ( � i I / i 30VId AIU3aN3 aFV, �a6 v / f w w o V wil ir 0VON a3NNVM o u a w J Q U F- Cw G\ w O 0 W Z D Q w w Q Q = C)W00 WWF- wQ0 cnw0 �Q� F- OJ. w 00 Y Z Q W a Park Place Avenue Infrastructure Improvements Streetscape and Irrigation Cost Estimate Streetscape and Irrigation Improvements in Park Place (TIF Cost) Line No. Description Quantity I Unit Unit Price Cost 1 Landscape -Per Plans - Install 1 LS $40,000.00 $40,000.00 2 Irrigation System w /Control and Electrical System - Install 1 LS $30,000.00 $30,000.00 3 Grass Sod - Install 542 SY $5.00 $2,710.00 4 Topsoil - Install 61 CY $14.00 $854.00 Subtotal: 73,564.00 Total Streetscape and Irrigation 11 $73,564.00 IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed in quadruplicate in its name and on its behalf by its Assistant City Manager, attested by its City Secretary, with the corporate seal of the City affixed, and said Deyeloper has executed this instrument in quadruplicate, at Fort Worth, Texas this )3 day oft X 201Q. CITY OF FORT WORTH Fernando Costa Assistant City Manager Recommended by: Transportation & Public Works Department W.� Douglakk Wiersig, P.E. Director Water Department �)4e,_ZLC Wendy Chi-B A ulal, EMBA, P.E. Water Development Engineering Manager Approved as to Form & Legality: g s lack Assistant City Attorney ATTEST: `Jv�'v� '1►48��1 City Secretary Park Place ICA DEVELOPER Fort Worth South, Inc. Paul F.Paine President, Fort Worth South, Inc. S Frank Crumb, P.E. Director, Water Department M &C: C - 2 5 2 3 3 Date: to I3 /1 ��. (�0000 G °o , L o %� o o �1,00 Gi ICY -di Page 10 of 10 CITY FT. ;, IVIM%_, neView Page 1 of 3 Official site of the City of Fort Worth, Texas CITY COUNCIL AGENDA FORTWORT>r Ir RECOMMENDATION: It is recommended that the City Council: 1. Authorize the execution of an Infrastructure Construction Agreement with Fort Worth South, Inc., with city participation in the amount of $896,184.84 for the construction of public improvements on Park Place Avenue from Warner Road to Eighth Avenue and Enderly Place from Allen Avenue to Park Place Avenue and; 2. Authorize the acceptance of funds in the amount of $858,816.58 from the Special Assessment District Fund for the construction of this project and adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in the amount of $858,816.58 in the Specially Funded Capital Projects Fund. DISCUSSION: Fort Worth South, Inc., desires to oversee the preparation of final engineering plans and construction of streetscape and public right -of -way improvements associated with redevelopment along Park Place Avenue including on- street parking, sidewalks, paving, drainage and streetlights using revenue from the Southside Tax Increment Financing District (TIF). In conjunction with these improvements, the City of Fort Worth has requested that Fort Worth South, Inc., also construct water and sewer improvements along Park Place from City Project No. 01687 Medical District Part 8 Water Distribution System Improvements and construct water, paving and drainage improvements on Enderly Place from City Project No. 00094 Miscellaneous Storm Drain Improvements contract B, Phase IV, Fort Worth South, Inc., agrees to participate in these costs as requested. Consideration for the construction of water and sewer improvements along Park Place will be payable by the City from the current Water and Sewer Capital Projects Fund. Consideration for the construction of water, paving and drainage improvements on Enderly Place will be payable by the City from proceeds from Water Capital Projects Funds and Storm Water Capital Projects Funds. Based on engineer estimates in the Infrastructure Construction Agreement, funding in the amount of $896,184.84 is requested for the City's portion of the construction cost, construction inspection, material /soil testing and construction contingencies for potential change orders. ivi&t: xeview The funding breakdown for this project is: rase 6 01 .3 5 DESCRIPTION DEVELOPER COST (TIF) CITY COST WATER CITY COST (TPW DEPT.) TOTAL ESTIMATED C291 531200 209760177184 $12,383.56 ' DEPT. 531350 209760177185 COST Construction $739,889.00 $531,547.70 $246,300.15 $1,517,736.85 Cost 11 C291 488100 2097601771XX $656.328.58 2 C291 10 Percent $ 73,988.90 $ 53,154.78 $ 24,630.02 $ 151,773.70 Contingency $96.016.48 1.1 P253 531200 601170009484 Material $ 12,383.56 $ 11,694.05 $ 5,418.60 $ 29,496.21 Testing 531350 601170009484 $480.08, 1 P253 Inspection $ 32,555.12 1 $ 12,602.3-3--F$ 10,837.21 $ 55,994.66 TOTAL $858,816.5 $608,998.86 1 $287,185.98 $1,755,001.42 This project is located in COUNCIL DISTRICT 9, Mapsco 750. FISCAL INFORMATIOWCERTIFICATION: The Financial Management Services Director certifies that upon approval of the above recommendations and adoption of the attached appropriations ordinance, funds are available in the current capital budget, as appropriated, of the Storm Water Capital Projects Bond 2009 Fund, Water Capital Projects Funds and Sewer Capital Projects Fund. TO Fund/AccountMenters Fund/Account/Centers 11 C291 541200 209760177183 $619.177.90 C291 531200 209760177184 $12,383.56 C291 531350 209760177185 4 767.1 2 C291 541200 209320177183 $194.700.00 u C291 511010 209320177180 $7.788.001 11 C291 488100 2097601771XX $656.328.58 2 C291 488100 2093201771XX $202.488.00 FROM Fund/Account/Centers 0 GS87 539120 020704097000 $858.816.58 111 P227 541200 201270009487 $270.930.17 P227 531200 201270009484 063. W P227 531350--201270009484 $1,354.65 Lu P227 531350 201270009485 1 7. W P253 541200 601170009487 $96.016.48 1.1 P253 531200 601170009484 $1.440.25 P253 531350 601170009484 $480.08, 1 P253 531350 601170009485 $2.828.61 111 P265 541200 609170168783 $481.910.00 W P265 531200 609170168784 $9.638.20 111 P265 531350 609170168785 $9.638.20 111 P275 541200 709170168783 $6,770.00 1VImk- 1CCVICW Submitted for City Manager's Office by: Originating Department Head: Additional Information Contact: Fage 3 of 3 P275 531200 709170168784 135.52 P275 531350 709170168785 135.52 Fernando Costa (6122) Randle Harwood (6101) David Schroeder (2239) ATTACHMENTS 06PARK PLACEENDERLY PLACE WATERTPW CFA A012.doc Park Place CFA ExhibitA.pdf REVISED 09 -13 -11 Park PI and Enderly PI Cost Summary Table pdf