HomeMy WebLinkAboutContract 44155-CO8 (2)FORT WQ�'�'� City of Fort Worth �"' ��� Change Order Request Project Name North Beach Street from Vista Meadows to south of Shiver Client Project #(s)� 01292 Project Description� 4-lane divided arterial street from Vista Meadows Drive to south of Shiver Road - ;:r �A �J ��i City Sec # 44155 Contractor Mario Sinacola & Sons Excavating, Inc. Change Order #� Date 9/24/2015 City Project Mgr. Michael Weiss, P.E. City Inspector Tom Miller Dept. Original Contract Amounf Extras to Date Credifs to Date Pending Change Orders (in M&C Process) Contract Cost to Date (;i� i�> >,I)I i c: I)� I I�<ti)'. [�'�-:iiiLl ( C� I�;;1C„U� Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) TPW `— 1,738,543.04 $577,554.87 i,316,097.91 $28,887.83 i,3G4,985.74 $189,456.96 �0.00 $28.887.83 Water S,� �� Sewer Totals $4,738,543.04 $1,101,954.87 $5,840,497,91 $28,887.83 $5,869,385.74 $189,456.96 $28.887.83 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 23.86% MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) �$5,923,178.80 Contract Time 730 105 -330 m JUSTIFICATIAN (REASONS) FQR CHANGE ORDER Provide pay items and quantities for the removai of existing pavement markings and signs, atlditional pavement markings, curb repairs, bicycle and metro signs, and relocate Shiver Road traffic signal radar equipment from the temporary signal to the pe .,, ,.,.,, ,signal. 85 days are added to the contract time for this additional work. . t_ � r� _�:;� . �p�►t�-��.�F�� DEC 1 1 1015 �r (i� I O:';�f�l���(;n;�'�, , ,,; t, ��.._ �: � .� . �� It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accortl payment in full (both time and money) for all costs arising out of, or incidental to, the above Change �)rde�. Contractor's Company Name io Sinacola & Sons Excavatin Assistant � i, Contractor (Nai ,�I �IN i ;; � Date 1L •��� i Date � c�i�,p;, �� — -- _ Council Action M&C Number " a�C�'�J �:,,� s��'���i�� M&C Date Approved � ,�i�.�„�, �P�����"��� �� `�H', � i ��, - � ;+,il`'i'�l "' " `���'� � � �����: � � � a:�, i! ff;,�� J ,-i..� � �tisFactior� and-represents_.— � ir Date ,- ;1,r�r �r Date '� ,r %,r Dept) Date �.Z%� / >`� Date Y•o; � I - r� ,.'J :i _. � r � 1 O � � ("E' � s 3 N O n m D n 0 J V w N O F+ U�A J A A A u A C7 :O � (n tn ZJ :il Tl :U :T/ � �1 A � � z � o o�� 3� 3� 3 m �� ' N� 3 � - � � � _ `D � � - m� �? � m m� m_ m n� a o 0 3 - a`� � D m(n ry r�- y 'o v� � � � � � � N c_ � cn a � 3 3 � � � r '� � � � � `� v o', v� m`" � a m���_ � 3 N - D �; � a'm - � � a� �� _' u'� �_ °1 m � � � � ` � - � � � -1 � --i -i -i -1 -i -1 -1 -V � 1 1 1 1 V 'D � � � � V � � V V � � � � � � � � � � � � � � � � � � � � � � l�i� A N tD A�O A--� �in��"��"nnn��� ;��' _ � � � � � D � � � N A � � o A o O A O O A A o 0 0 � � � O �% a � n � � n � O �� # � O � C7 _ � O � N � - � z � R � � � m # A A � n � 3 �! �� N � �. Q � �p O .7, D a� 0 � 7 N f7 � � � ov m O Q � � 0 � � � o' � � � a, oa � N O � N � � � � • � . . ! � � • 7 � � � 5 z � n `G � 0 `m� � � cQ � C'> � CD � N �� cn � rll c� �� � � -a cn c� 0 O � � CD c� 0 � v � 0 � � O C/� � N n O v Qo � O � � � c� n � v � cQ m � Q N � � v N � N � N O � � O CD� � � m � � �� o' � � n� � CD Q <� Q CD Q N (D N � (D m � 0 � G �' v � m n� � 0 � 0 <' m 0 0 _ � 0 � � � < c� � 0 � Q n (D � � 0 m' � �* 0 N CO N � 0 io" � z v 3 m Z O � W cD N n � C/� cD CD --n O � < �' v � m v n 0 � � 0 � 0 � 0 � � m n `G N (D n �# ? � C.II CJl "'n T C T n � S1 � 3 � (Q �' fD � �+ Q � �p O � rt v� �D o o � � N � � v � aa m O � � m � 0 m m '+ o� � � -o v v4 m N O � N M/WBE Breakdown for this Change Order