HomeMy WebLinkAboutContract 43124-CO1 (2)FO RT WO �'l' ff-�
f 3 y� ,
Project Name� West
Client Project
Project
Contractor
City Project Mgr.
City of Fort Worth
Change Order Request
Improvements
GR76-541200-006203110800
West Berry improvements of paving, lantlscape & hardscape
McClendon
Dept.
Original Contract Amount
E�ras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
TPW
Water
- ,�. .
� � ,..� �
City Sec # 43124
Change Order # � Date 3/3/2014
City Inspector Mike Myers
Sewer Totals 5elect Day Type
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORlGINAL CONTRACT
MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
TION
See attachetl sheet.
1.24%
$2,475,467.31
�FFICIAL RECOR�
�li'Y SECRETAR�
�T. W�RT4i, iX
300
It is understood and agreed that the acceptance of this Change Ortler by the contractor constitutes an accord and satisfaction and represents payment
in full (both time antl money) for all costs arising out of, or incidental to, the above Change Order. ���
Contractor's Company Name
McClendon
Assistant Directo�i
Contractor
Date
���i
Date
r
Council
FOR CHANGE ORDER
,er; � ��- _
��,/'I
�r
�
�
�
�
�
��
M&C Number ��`; M&C Date Approved �
. . � •: :: � i
�. � . ■ ��
■
�
•
.
� � �
.� ..
.
..
.
� �
.
.
.
.
•
�
•
�.
�
•
.
:
� �
..�.....
. .�� -=
.
�.
.
,
.
.
�
-
_ �
D
a
v
a
z
�
n
'-c
�
0
m'
�.
�
cfl
�
�
a�i
0
�
�
0
Q
�
��
_
�
-�
�
�
a
�
�
�
0
�
w
0
0
�
c�
C7
�
0
�
�
�
�
_
�
�
0
a
�
,
�
,
0
�
�
w
w
N
O
�
'O
O
CD�
�
�
m
�
�'
o'
�
m
N.
W
m
�
�
�
0
m
�
m
�
�
0
�
�
m
<
�'
cfl
v
�
o..
�
a�i
�
m
�
�
�
n
�
�
�
�
C7
m�
�
�
0
m'
�
�
G�
�
�
rn
�
�
0
�
z
�
�
m
�
��
�
�
�
�
?
W
N
�
�
.�
�
-�
�
77
Z
n
�
tU �
7
� r�"
<D
Q �
Q. �
�p O
��
a�
Qo
o �
�
�
N
i
��
o �—�,
��
o�
�.�.. �
� O
� �
V
�
�
V
x
�
3
Fr
�
n
�.:.i
N
.---
M
d'
�k
U
N
�
T
U
�
�
�
�
Z
U
N
�o
�
�
'::'
�
�
U
N
O
d
c
�
U
a�
�
N
'D
N
L
�
�..
N
U
�
�
C
(V
�
C
.�
N
a
4--
O
�
C
�
�
�
>
`O
Q
�
.�
N
m
�
�
�
0
.Q
U
�
N
�
U
�
�o
�
�
�
O
N
M
M
a�
�
�
�
�
N
�
0
�
�
C
f6
L
U
0
N
C
O
U
a>
Y
�
L
�
U
N
Q
N
C
T
U
'D
0...'
�
C
O
(O
N
t
�
�
�
N
�O
d
T
U
�
z
D
�
w
�
w
❑
�
�
i
�
�
�
■
-
_ �
:
:
,
�
i
•
•
�
�
�
.
�
► �
�
c
0
�
w
a�
0
L
�
�
L
�
�
�
�
�
�
U
Previous Change Orders
Co# DATE AMOUNT
Total �����
JU5TIFICATION (REASONS) FOR CHANGE ORDER
Item 88 - A fire hydrant was required to be relocated to the standard distance behind the curb after the
curb was reconstructed closer to the street centerline. ($2,690)
Item 89- An unforeseen and buried concrete cap had to be carefully removed from an existing water
main to prepare paving subgrade. ($3,321)
Item 90 - Unforeseen and buried railroad ties had to be removed and select fill material placed to
prepare the subgrade in preparation for paving at the University and Berry intersection. ($4,800, 4 days)
Item 91- Additional barricades and pavement markings had to be placed to accommodate high traffic
volumes in the TCU area during the football season. ($2,750, 4 days)
Items 79 and 92 - Two of the specified Desert Willow trees are being replaced by Texas Mountain Laurel
trees as a memorial to a community leader involved with this project. A warranty stipulation is included
to point out the Texas Mountain Laurels will not be warranted due to damage sustained by freezing
temperatures and that the City will inspect the trees in the Spring to ascertain damage from freezing
temperatures. ($410)
Items 79 and 93 — Due to a shortage of the speci�ed 2%-inch caliper Desert Willow trees, twelve 2-inch
caliper Desert Willow trees were furnished for a credit. (-$1,200}
Item 94 Long vehicles making right turns from narthbound University Drive onto eastbound Berry Street
occasionally roll up onto the median nose damaging a portion of the newly installed (andscaping and
sprinkler system. A concrete cap on the median nose replacing some of the landscaping is proposed to
eliminate the damage. ($11,725, 14 days)
Other Time Extensions:
1. The contractor closed dawn for the Christmas holidays. (10 days)
2. An unidentified 12" pipeline had to be inspected by various utility companies before paving
subgrade operations could resume. (10 days)
3. An adjacent property owner's improvement project interfered with the contractor's progress.
(10 days)
4. A decorative hardscape area connecting to the project's sidewalk was required to be
reconstructed to comply with state and federal ADA regulations. (10 days)