HomeMy WebLinkAboutOrdinance 24879-06-2021 ORDINANCE NO. 24879-06-2021
AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE 2014 BOND
PROGRAM FUND IN THE AMOUNT OF $100,000.00 BY INCREASING
APPROPRIATIONS IN THE WJ BOAZ AND BOWMAN ROBERTS
ROUNDABOUT PROJECT (CITY PROJECT NO. 101867), AND DECREASING
APPROPRIATIONS IN THE 34014 APPROPRIATION ONLY PROJECT (CITY
PROJECT NO. U34014) BY THE SAME AMOUNT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-2021 in the
Budget of the City Manager, there shall also be adjusted appropriations in the 2014 Bond Program Fund in
the amount of$100,000.00 by increasing appropriations in the WJ Boaz and Bowman Roberts Roundabout
project (City Project No. 101867), and decreasing appropriations in the 34014 Appropriation Only project
(City Project No.U34014)by the same amount.
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
A MtP�
Mack(Jun 25,202110:36 CDT)
Douglas W Black Mary J.Kayser
Sr.Assistant City Attorney
o�.FORT�o
2021
ADOPTED AND EFFECTIVE: June 22,
U=.
TEXAS
MAYOR & COUNCIL COMMUNICATION MAP
i
� , r Project L�catic
�'t r �t � � -•
�•.
y ,
-� W J B OAZ RD
_ 0 k
k.
N.
. [
CPN 101867 FORT WORT14
WJ Boaz Rd at Bowman Roberts Rd � E
o-�- rr+
s
6/7/21 10:22 AM 1: 1,208
An intersection improvement project This product is for informational purposes and may not have been prepared for or be
suitable for legal,engineering,or surveying purposes.The City of Fort Worth assumes no
responsibility for the accuracy of said data.
NCTCOG ORTHOPHOTOGRAPHY
0 0.0 Miles
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/22/21 MSC FILE NUMBER: M&C 21-0414
LOG NAME: 20WJ BOAZ ROAD&BOWMAN ROBERTS ROAD
SUBJECT
(CD 2 and CD 7)Adopt Attached Appropriation Ordinance in the Amount of$100,000.00 to Provide Additional Funding for the WJ Boaz and
Bowman Roberts Project and Amend the Fiscal Years 2021-FY2025 Capital Improvement Program(2014 Bond Program)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance adjusting estimated appropriations in the 2014 Bond Program Fund in the amount of
$100,000.00, by increasing estimated appropriations in the WJ Boaz and Bowman Roberts Roundabout project(City Project No. 101867)
and by decreasing estimated appropriations in the 34014 Appropriation Only project(City Project No. U34014)by the same amount;and
2. Amend the Fiscal Years 2021-2025 Capital Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication is to provide for additional funding for the WJ Boaz and Bowman Roberts project(City
Project No. 101867). On March 25,2021,a community meeting was held for the project. In the meeting,staff received public input regarding
concerns for the lack of pedestrian improvements in the vicinity of the WJ Boaz and Bowman Roberts Road project. As a result of this input,staff
agreed to revise the design to incorporate pedestrian improvements to improve safety within the limits of the project. Coordination efforts are
ongoing to improve pedestrian safety in the area at the program level.To implement the pedestrian improvements for this project,additional funds
are required to construct crosswalks,sidewalks, and ADA ramps in addition to drainage improvements.
Funding History
Fund Existing Appropriation Additional Project Total
Appropriation
34014 $261,099.05 $100,000.00 $361,099.05
39001 -J $630,638.06 $630,638.06
Project $891,737.11 $100,000.00 $991,737.11
Total
Funding was not included in the FY2021-2025 Capital Improvement Program for the WJ Boaz and Bowman Roberts Roundabout project. The
additional safety improvements were identified and approved after the FY2021 budget was approved. This action will amend the FY2021-2025
Capital improvement Program as approved in connection with Ordinance 24446-09-2020. Construction is anticipated to start in June 2021 and
finish October 2021.
This project is located in COUNCIL DISTRICTS 2 and 7.
A Form 1295 is not required because:This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Fund 34014 Appropriations Only project within the 2014 Bond Program
Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the 2014
Bond Program Fund for the WJ Boaz and Bowman Roberts RAB project to support the approval of the above recommendations and execution of
the agreement. Prior to an expenditure being incurred,the Transportation and Public Works Department has the responsibility of verifying the
availability of funds.
Submitted for Cily Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Monty Hall 8662
Lissette Acevedo 2722
Expedited