Change Order Request
Project Name Village Creek WRF Deep Filters 1-20 Modifications City Sec # 43754
Client Project #(s) Fort Worth (01628); F&N (FTW11104A); Pepper-Laswon (21813)
'""''"'"` Rehabilitation of 20 filters at Village Creek WRF, Design M&C C-24703; Construction M&C C-25887
Description
Contractor Pepper-Lawson Waterworks LLC Change Order #�1 Date 10/3/2013
City Project Mgr. Farida S Goderya, PhD, PE City Inspector Robert Walker and Ted Gay (F&N)
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
of Proposed Change Order
Revised ContractAmount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Adtlitional Funtling (if necessary)
Water
$16,268,000.00
$0.00
$16,268,000.00
$75,977.00
$16,343,977.00
$0.00
1
Totals
0.00
7.00
Select Day
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord antl satisfaction antl represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. n ;
I�ECEIVED
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.47%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $20,335,000.00
N
i
� O
�i' =
O �
�a
� L
Q �
��
�o
0
� �'
� �
U�
�
U
x
F
Q�i
3
F
�
�
Lz.
�
�
�
M
V
�
U
N
�
T
U
� ,
� �,
o Q
'� Q
a�
w a
a
� Q
o '�
N �
N �
L.L ��---
Q Z
d �
N �
L.L �
� N
�
Y O
N
� L
U �
a�
�
rn
� �
> �i
a� *k
� U
z .�
O
N �
"o c
� �
U
ti
�
�
�
N
U
U
�
�
0
U
�_..
c
0
U
cYS
0
ti
v
N
U
U
�
�
m
.N
�
0
�
�
�
Y
d
U
N
N
�
(U
N
�
�
O
N
O
O
.�
:.fl
m
�
0
.Q
U
N
�
U
a�
'o
a.
M
O
N
�
� Z
�
L.L
>
�
N U
m -a
0 �
a
c
co
a`�
Y
(6
� �
�
�
�
� �
�
�
O
� o
� U
C �
(6 Q
L
U c
.�
U
J
J
Y a
O
� 0
fa �
� �
�
m
�
�
�
o �
U �
�
� U
O �
U �
O..
�
U
N
Z
�
0
0
a
�
0
�
v
�
to
a
c
0
'a
�
Q
N
�
�
�
�
�
�
s
U
c
;
D�PARTMENT NAME:
��`-�j . 6 a o q lr 13 ,
ESTIMATED COST / PROF SA DATE
v' C �i �T �' '� �-� �3 �. t-� �.. � � 1 ��-� Y��.�
NAME OF PROJECT/BID:
SIGNATURE O�
MANAGER
� 2 1�
EXTENSION
�1�2.�
DOE/PROJECT NO.
� l3 l 3
DA E
NIGP CODE
Prior to advertisement, the contracting/managing department shall determine whether the bid/proposal is one whzch MBE/WBE
requirements should not be applied. MBE/WBE requirements may be waived upon written approval of the M/WBE Managex. If one
of the conditions listed below exists, the contracting/managirig department shall notify the•Manager via this form, stating the specific
reason (s) for reauestine a waiver. '
If the contracting/managing department and the Manager are in conflict over the granting of a wazver, either
may appeal to the City Manager, or designee, and his/her decision is final.
Please Check Applicable Reason:
A. A public or administrative emergency exists which requires the goods oz' services to be
provided with unusual immediacy; or
►/ B. Purchase of goods or services from source(s) whexe subcontracting or supplier opporiunities
axe negligible; or
C. The application oi the provisions of this ordinance will i.znpose an economic risk on the City or
unduly deJ.ay acquisition of the goods or services; or
'� D. Other (explain)
Justifp Commodity or Service Waive�r Request:
_ � ��.� ,� F..� J �� n � ; <�- »�
N r � - Y� c�z ti `� c.Q --� � W ��'�r� � L� �ld..�ora�,� -� ^�? ^� �t- i i "�/'e�- 1
S� �:..� cr�� � Q C �-. � tJt� +t��� �oi[ �..� v ..i� , t- �..v C�. _
CY t- �- v� ��- �. �'�'�� Zij q�� 1� �.�i. r-�. J� �.-� J�.
��. k\�.5� � � C, t--�-+1�� e� `�► C,� "'-e-'�� UY �.-r J� �i C�.2-Y
�,��, � �
Please use additional sheets, if needed
M/ E OFFICE USE ONLY:
� � � � - ���i���� ���o I�
�. °�,�, i.� �.
Approved Not Approved , Signa�ure of M/WBE Authorized e-� ������ ate
' Rev. 212aroa
�
City of Fort Wortih
Departmerital Request for Waiver
Of MBE/ WBE Subcontracting/ Supplier Goal
�C__,Y
_ Bailes, Norma
To:
Subject:
ajames@pepperlawson.coi�
FW: VC Deep Filters CMR002B REVIEW RECOMMEND
From: Goderya, Farida
S�nt: Monday, September 16, 2013 1:55 PM
To: Gay, Ted; matt jal .bert@fr_eese.com; Bailes, Norma
Cc: ajarr�e_s_ a>�e�per_lawson,co__m; 'Gorell, Dean T.'; 'Robinson, John M. (Dallas)'; Walker,
Lance Price; 'Wendy Nilsson'; Matus, Luke; Pena, )acob
Subject: RE: VC Deep Filters CMR002B REVIEW RECOMMEND
Hi Ted and All,
Robert; Ana Julia Pena-Tijerina;
I have reviewed this CMR 002B (Additional Controller for the DCS system) and its previous versions (CMR 002 and CMR
002A). We realize that the need for this work was discovered during early construction (October 2012), after bidding
process. Therefore, consideration of procuring this work by any means other than by Contract Modification was neither
practical nor desirable.
The City Staff has also reviewed this CMR and related aspects and considers this fee to be within acceptable limits for
the scope of services proposed. Please proceed and incorporate it into the official Change Order.
Thank you all for your efforts and coordination. Regards. Farida
♦Fm•rdn S. Goderyo, Ph.D., P.E ♦ Facilities Pro�ert Ma!tager 1F,ngineering K F'iscal S.rvices 1H'oe•! �i"orth �1'ater Dep:irtment
♦if00 Th��od<.r,�ort�n 5�. Fo�t ��Vor�:h, TX 751Q2 ♦%�U39?.s32�Ld oFfire ♦-� 17 351.�91[) Culi �Farida.r,��ler�7forbr�oi thtexas.gov
From: Bailes, Norma
Sent: Thursday, September 12, 2013 3:24 PM
To: Goderya, Farida
Cc: Pena, Ana; ir�att�alb_ert�freEse.com; Walker, Robert
Subject: VC Deep Filters CMR002B REVIEW RECOMMEND
Farida,
Attached please find our CMR002B Additional Controller for DCS recommend letter. Thanks.
Norma
�: �, `� �•�
�
,,
�
1
September 12, 2013
City of Fort Worth
Water Engineering Department
1000 Throckmorton 5treet
Fort Worth, TX 76101
Attn: Ms. Farida Goderya, P.E.
RE: Village Creek Deep Filters 1-20 Modifications
Capital Pr�ject No. 0162� F&N No. FTW11104A
CMR-002B Additional Controlier for DCS
Dear Ms. Goderya:
Transmitted herewith please find a copy of Pepper-Lawson's September 11, 2013 price proposal for the
referenced work. The cost for this work is $75,997.00. No additional Contract Time has been requested.
The Contract Drawings required a new DCS Controller 6/56 iri the new Filter Control Building #i2 for
process cantrol of the new filter equipment and wiring terrninatior� of some of the new equipment and a
remote Terminal Cabinet in the new Electric Building for terrnination of the remaining new equipment.
The design of the project and the preselected Application Engineering Services provider's (CDM/Smith)
scope of services were both prepared on the assumption that the 32,000 database points provided in
new DC5 Controller 6/56 w�re sufficient. The preselection price proposai was submitted by CDM/Srnith
July 26, 20�2 and the construction contract bid August 23, 2012.
CDM/Smith was the Application Engineering Services pr�vider for the main plant computer replacement
project at VCWRF under another corrtract. It v�as deterrnined in October 2012 that the required
programming and graphic plant standards adopted needed more database points than had been
expected. This issue also manifested itself in the Deep Filters Renovation project. A second new DCS
controlier is requieed to provide sufficient database points for programn�ing the new filter controls. The
new DC5 cont�-oller will replace the remote Terminal Cabinet.
We have revie�Ned this price proposal and are of the opinion that it is a fair and equitable price. We
recommend the City accept this cost and issue a Change Order in the amount of $i5,977.00. Please
advise if the Water Department desires this CN1R be incorporated in a Change Order,
Sincerely,
FREESE AND NI%NOLS, 1NC,
���o ,/
� y'�,.,
s� '
G, E. Gay, P.E.
Xc: Matt Jalbert-FNI
file FTW1110�A.4.4Z.002B
L:\VC Deep Filters\CHANGES\CMR\CMR0026 Addition2l Contr�oller For DCS RCMD 91213
;� '�: i�� � �
1
i �"
- 4055 Internatlonal Plaza, Sufte 200 • Fort Worth, Texas 76109 • 817 735-7900 • fax 817-735-7A91 �nrww.frnrtie.cnnt
�
CONTRACTOR'S MODIFICATION REQUEST
(4.42 /002B)
PROJECT:
OWNER:
CONTRACTOR:
ENGINEER:
CONST. MGR.:
VILLAGE CREEK WRF DEEP FILTERS 1-20 MODIFICATIONS
CITY OF FORT WORTH WATER DEPARTMENT
PEPPER-LAWSON
FREESE & NICHOLS, INC.
FREESE & NICHOLS, INC.
DESCRIPTION: Additional Controller for DCS NO. CMR002B
NOTIFICATION BY CONTRACTOR
The Contractor proposes to make the additions, modifications, or deletions to the Work described in the
Contract Documents, as shown in Attachment "A" and requests that you take the following action:
❑ Notify us that you concur that this change does not require a change in Contract time or amount
and issue a Field Order.
X Issue a Change Order for perForming the described change. Change in Contract amount is
indicated in the attached detailed cost breakdown of labor, materials, equipment and all other
costs associated with this change. Impacts on Contract Time are shown in the attached revised
schedule.
L
❑�
Authorize the Contractor to proceed with the described change. Payment will be requested at the
unit price bid.
Authorize the Contractor to proceed with the change under the time and materials provisions of
the Contract.
PROJECT NUMBER:
01628
21813
FTW 11104
By: Aaron James
CONSTRUCTION MANAGER'S RESPONSE
We respond to your request as follows:
❑
❑
❑
❑
❑
❑
By:
Date: 9/11 /13
We concur that this is a no cost or time change. See attached/forthcoming Field Order No.
_/ comments.
Your proposal is recommended to the Owner. See attached/forthcoming proposed Change
Order.
Proceed with the change at the unit price bid.
Proceed with the change under the time and materials provisions of the Contract.
Additional information is required to evaluate this request. Provide information as described
in the attached comments and resubmit.
Contractor's Modification Request is not accepted.
W:11 - Active Projects121813 - Village Creek Filters\31.2 - Spec No - SubmittallPEPPER LAWSON (CMR)
ED.doc
:� ,ie
:;��;
��f
PEPPER-LAWSON
W��l i_i;W�F�KS
September 11, 2013
Mr. Ted Gay
Freese and Tlichols
4055 International Plaza
Suite 200
Fort Worih, Texas 76109
Re: City of Fot�t Worth
Vilinge Creek Deep Filte��s i-2o mo�i�r�ar�o��s
CMR002 Rev. 2
Dear Mr. Gay:
Additiona( Controller lor DCS
Per the Engineer's request in RFI029, Pepper-Lawson Waterworks offer a proposal to purchase and install one (1)
additional controller for the filter DCS. A copy of CDM Smith's proposal, cost breakdo�vn, and memv detailing the history and
issues requiring the addition of a second redundant controller. "1'his revision has breaf.down as requestcd and a scrvices price
reduction.
This chrnage ivil! resa�lt i�a a ndcl to tlae Conh•act of $75,997 arxl an i�zcrense in coi�N�nc[
duratron of D enlendnr cicrys�i•om �he clate of npproval /o deliver /he nrcrle��rnls lo /he sile a�zcf
pe�fa��n tlze ivorlc.
Upon receipt of approval from the City of Fort Worth and Freese and Nichols as to the acceptability of our proposal,
Pepper-Lawson avill proceed �vith prociiring the materials to be installed. Should you or [he owner have any queslio�s
you are welcame to contact me at any time. Thank You.
Sincerely,
PEPPER-LAWSON WATERWORKS. LLC
Aaron James
Project Manager
�i3U� c �� rl��vy i 1�3I, Suii� i%0 ��url�s�n, IX 7S0`ti3
� ("060) 530-%98' �_ (856) 2o5-E220
www. plwaterworks. com
� s ! ,�, :• � r
i �.
y_....
`,`_t' . ! �f. ,,, ! ! ' �
- �� ;�
PEPPER-LAWSON
�''.' 'I ,;'�;'�;�i�� �.
�.
City of Fort Worth - Village Creek Deep Filter 1-20 Modifications
Pepper Lawson Job # 21813
CMR002 Rev. 2
ITEM
NO.
1
DESCRIPTION
Quote
iA�IJilion,il ('uid�ullci liir I )C'ti
NON-TAXED TAXED
LABOR MATERIAL MAiERIAL EUUIPM
UNIT TOTAL UNIT TOTAL UNIi TOTAL UNIT
QT`( UNIT COST __ COST COSi_ COST COSi COST COS7
0.00 0.00 0 00
1 LS 0 00 0 00 0 00
0 00 0 00 0 00
o.00 0 00 o ao
000 000 000
0 00 0 00 0.00
o.00 0 00 0 00
0 oa o ao 0 00
0 00 0 00 0.00
SUMMARY
DIRECT COST SUBTOTAL
A LABOR BURDEN
B TAX @ 8.25%
C SUBTOTAL2(A+g+C)
D SMALL TOOLS
E SUBTOTAL(D+E)
F EQUIPMENT BURDEN
G SUBTOTAL(F+G)
H OH&P SUBS @ 5% (0 ixH)
I SUBTOTAL 3 (H+I)
J OH&P SELF PERFORMED @ 15°/ (0.15xJ)
K SUaTOTAL 4 (J+I<)
L BONDS & INSURANCE @ 1.59% (0.0159xL)
M SUBTOTAL(L+M)
N TOTAL BASE BID (J1+J2+J3+�4+J5)
TOTFlL BASE BID (J�+J2+J3+J4+J5)
OTHER
TOTALCOST
2
0
N/A
N/A
0
N/A
0
N/A
0
N/A
0 00
0.00
0 00
0 00
0.00
0 00
3
0
N!A
0
0
N/A
�
N/A
0
N/A
0.00
0.00
0 00
0.00
0 00
LNT SUBCOP
TOTAL UNIT
COST COST _
OAO
0 00 71245.00
a o0
0 00
a o0
0 00
0 00
0 00
4
0
N/A
0
0
N/A
0
0.00
0 00
N/A
OAD
0.00
0 00
0.00
0.00
� 5 �`; � ' 1
r
� i - v�' .: s- -r
o.00
1
0
0 00
N1A
0
0 00
0.00
N/A
0
N/A
0 00
0.00
0.00
0.00
0.00
75996.69
N/A
$ 75,997
9 /1 112 01 3
+CTOR
fOTAL
COST
0
�izns
0 00
o.oa
o.00
0 00
o.ao
0 00
5
71245
71245
�I/A
71245
N/A
71245
3562 25
74a�% ZrJ
M!A
74807 25
1189.44
75996.69
! i
w �w-
� ' �
June 28, 20�.3
Pepper-Lawson Construction
P.O. Box 120338
Arlington, TX 76012
Attn: Aaron James
RE: Change Request 1—Add an additional controller to the Ffiter DC5
Village Creek Waste Water Reclamation Facility Deep Filters 1— 20 Modificatfons
City of Fart Worth
CDM Constructors Inc, shall furnish, instail and program ali required Hardware modificatlons for
the above referenced Change Order as follows:
• Hardware
o Replace the Remote I/O Node kit and 24V power supply in the Remote I/O
cabinet with 1 Ovation Redundant OCR400 Controller Kit, including one (1)
additional 24V power supply, one (1) set of power supply feeds, and 2 Media
Converters.
o Hardware Submittals will be modified to show the changes
• Subm(ttals
o I/O List
■ Revise and resubmit I/O list for both contrallers
o Control Narratives
■ Revise and resubmit control narrat(ves for both controllers
• Programming
o Contraller Configuratian
■ Setup and configure new controller with new I/O list
■ Remove deleted I/O points from the existing contraller
o Control Loglc
■ For equipment wired to the remote I/O cabinet, remove blocks and logic
from the existing controiler to the new controller
■ To free the existing controller memory, remove ail backwash sequence
logic to the new controller.
■ Develop memory mapping for data sharing between both controllers.
Fi{ters status, backwash data and interlocks will need to be transferred
between both controllers due to relocating the backwash sequence logic.
o Graphics
■ Modify graphics/database of all equipment wired to the remote I/0
cabinet
.�'' ` r t , : �" �f
- -,�
r
( t � i�' •
���
�1''1�flri'�
graphics
■ Modify parts of fllters 1-20 graphlcs/database as It relates to points
relocated to the new controller
• Testing
o Unwitnessed Factory Test
■ Repeat Unwitnessed Testing using two virtual controllers after all logic
and I/O modification is implemented
o Wltnessed Factory Test
■ Perform Witnessed Testing using two virtual controliers
o Operational Readiness Test (I/O Checks�
■ No additional effort needed
• Commissioning
o Functional Demonstration Test
■ Demonstrate and test backwash sequence interlocks and permissives
communfcation and exchange between both controllers.
� O&M
o O&M manuals will reflect the revised hardware configuration
Exclusions
• Configuration of any communications switches, routers, etc.
Assumptions
• COFW has communicated via the submittai process al) critiques of the proposed logic
and graphics.
• Scope and cost are based on technlcal requirements of adding a second controller plus
COFW comments provided in submittals prior to lune 21, 2013
• COFW and engineer will review updated I/O list and Control Narrative submittals in a
timely fashion,
Total Fee far this change Request: $76,850.00.
,� - .j � �,. � _ �
- - ;.
t
J } �; .
. CDM
Sm�th
September 10, 2013
Pepper-Lawson Construction
P.O. Box 120338
Arlington, TX 76012
Attn: Aaron lames
RE: Change Request 1— Add an additional controller to the Filter DCS
Village Creek Waste Water Reclamation Facility Deep Filters 1. — 20 Modifications
City of Fort Worth
Subject: Revised Pricing for CMR 1
Dear Mr. James,
CDM Smith Constructors Inc has received review comments dated September S, 2013 and
consulted with individuals in the respective Engineering organizations relating to their
concerns. CDM Smith understands the concerns raised and values the opportunity to work for
the City of Fort Worth, Texas. Accordingly, we offer a reduction in the pricing of all services
quo#ed with the ove�all pricing of CMR 1 being revised as noted below:
Equipment
1. Emerson Hardware & Software
Services
2. Configuration update (Coordination with Emerson,
I/0, additional Virtual Controller, Narrative changes)
3. Application Engineering (Data base, Graphics,
Programming, O&M update)
r�i
Testing & Startup (Unwitnessed, Witnessed, Field checkout)
$ 26,567.00
$ 6,132.00
$20,016.00
$11,028.00
5. CCI Project Management & Administration $ 6,236.00
,� � . .� ; ,x . . � , �
�
� �
CDM
Smith
Services Subtotal
Services price reduction at 12% of Subtotal
Subtotal Equipment, Services, and reduction
OH & Profit @ 10%
Total
Please let me know if you have any questions.
Rega rds,
Dean T. Gorell
Project Manager
$ 43,412.00
$ (5,210.00)
$ 64,769.00
$ 6,476.00
$ 71,245.00
;� � . �,, . .. � "• �
CITV SECRE'�iARY