HomeMy WebLinkAboutContract 45893-CO3 (2)Project City of Fort Worth Change Order Request Project Name: Water and Sanitary Sewer Relocations for SH121T, Part 25 City Sec No.: 45893 Project No.(s): P265-606170089983 and P275-706170089983 DOE No. 7183 City Proj. No.: 00899 FORT «(�RTH Water and Sanitary Sewer Main Relocations for SH121T, Part 25 from Dirks Road to FM 1187 Contractor: Jackson Construction, Ltd City Project Mgr. Liam Conlon Phone Number: 817-392-6824 Dept. � Water Original Contract Amount Extras to Date Cretlits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) 501 $367,013.00 CHANGE ORDERS to DATE (lNCLUDING THIS ONE) AS % OF ORIGINAL CONTR,4CT MAX ALLOWABLE CONTRACT AMOUNT (OR/GINAL CONTRACT COST + 25%) - :c � ,� },j, I � Totals 7.50% $2,390,394.38 JUSTI � The change order will provide for the installation of 71 linear feet of 48-inch tunnel liner plate by other than open cut (instead of by open cut) at the east end of Big Spruce Lane. The original plans provided for open cut installation at the identified location, which would have necessitated closure of the Big Spruce / Seawood intersection . By other than open cut installation will allow uninterrupted ,rgency vehicles, thrash trucks, school buses and residents across the intersection. ��� �' '��� ��,' _����° �°�e,. ��� Staff recommends the approval of 20 additional calander days for the change �,,�P - 4 2015 �� `; s —:.��;;��a '�1i�;�r_1 - , .., � , i ! �' f � �. � � i �. �9 • � � Contract Time ��: a � �►,. � � �, It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time antl money) for all costs arising out of, or incitlental to, the above Change Ordgr. Contractor's Company Name Jackson Construction, Ltd Contractor Name � Steve Harberstoh ,� Change Order # �3 Date: 8/24/2015 City Inspector: Luisa Allbright Phone Number: 817-223-2259 Sewer I Screen Wall � "L � (.�' 'S � i 1 � � c}r3- I �i'(; i �} �C�RT WC�RTH City of Fort Worth Change Order Additions Project Name SH121T Part 25 Relocations Project No.(s): P265-606170089983 - P275-706170089983 DOE No. 7183 Project Description Contractor City Project Mgr City Sec No City Proj. No. 45893 899 SH 121 Southwest Parkway Water and Sewer Main Relocations part 25 from Dirks Road to FM 1187 Jackson Construction Change Order: �3 Date: 8/18/2015 Liam Conlon City Inspector Luisa Allbright ADDITIONS Total � r Water Sewer Wall �s Sub Total Page 2 of 4 F�� R T WC7 RT H Project Name Project No.(s): Project Description Contractor City Project Mgr City of Fort Worth Change Order Deletions Water and Sanitary Sewer Relocations for SH121T, Part 25 P265-606170089983 and P275-706170089983 DOE No. 7183 City Sec No. City Proj. No. 45893 00899 Water and Sanitary Sewer Main Relocations for SH121T, Part 25 from Dirks Roatl to FM 1187 Jackson Construction, Ltd Liam Conlon Change Order: �3 Date 8/24/2015 City Inspector: Luisa Allbright DELETIONS ITEM IDESCRIPTION DEPT Qty �Unit Sewer Unit Cost ITotal Screen Wall Page 3 of 4 �Deletions Sub Total Page 4 of 4