HomeMy WebLinkAboutContract 388577
CITY OF FORT WORTH, TEXAS
2009
SPECIFICATIONS AND CONTRACT DOCUMENTS
FOR
LAKE WORTH RESTORATION AND MAINTENANCE
PROJECT NUMBER : WTR-2009-560001
UNIT I -BOAT RAMP REPLACEMENT AT ARROW "S" PARK
UNIT II -MARKER BUOY/ FLOAT LINE REPLACEMENT
UNIT III -REMOVAL OF BRUSH AND TREES AT THE DAM
PROJECT NUMBER: WTR-2009-560001
MIKE MONCRIEF
MAYOR
DALE FISSELER, P.E.
CITY MANAGER
FRANK CRUMB, P.E.
DIRECTOR, WATER DEPARTMENT
PFI I l ECORD
ITV SECRETARY
.WORTH,TX
M&C Review ,I
Page 1 of 2
Official site of the City of Fort Worth, Texas
CITY COUNCIL AGENDA FORT WORTH
~
COUNCIL ACTION: Approved on 6/2/2009 -Ord. No. 18647-06-2009 & 18648-06-2009
DATE: 61212009 REFERENCE
NO.:
CODE: C TYPE:
C-23567
NON-
CONSENT
LOG NAME:
PUBLIC
HEARING:
60LAKE WORTH
RESTORATION
NO
SUBJECT: Authorize a Contract in the Amount of $359 ,732.00 with Lehne Construction , Inc., for
Certain Boat Ramp and Dam Improvements Associated with the Lake Worth Restoration
and Maintenance Project and Adopt Appropriation Ordinances
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in th
Lake Worth Trust Fund by $374 ,732.00 from Gas Well Revenues ;
2. Authorize the transfer of $300 ,000 .00 from the Lake Worth Trust Fund to the Water Capital
Projects Fund ;
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in th
Water Capital Projects Fund in the amount of $300 ,000 .00 ; and
4 . Authorize the City Manager to execute a contract with Lehne Construction, Inc., for certain boat
ramp and dam improvements associated with the Lake Worth Restoration and Maintenance Project
in the amount of $359 ,732.00.
DISCUSSION:
On January 8, 2008 , the City Council amended the Gas Well Revenue Distribution Policy to allow for
revenues derived from lease bonuses and royalties from properties in and around Lake Worth to be
used for the execution of the 2007 Lake Worth Capital Improvements Implementation Plan . One of
the projects designated in this Plan is the improvements to the existing boat Ramp at Arrow S Park.
The existing ramp has experienced significant under cutting over the years due to prop wash ; this he
been determined to be hazardous and is currently out of service. This project will be funded with Ga~
Lease Revenue Funds in an amount not to exceed $229 ,332.00 .
Dam safety and security inspections of the Lake Worth Dam by the Texas Commission on
Environmental Quality and the City's security consultant recommended a number of improvements t<
enhance safety and security at the dam . To date new fencing , access control, lighting and a camera
system have been installed . The only remaining recommendations to be completed are the
replacement of the existing buoy line in front of the dam in an amount not to exceed $58 ,400.00 and
removal of brush and trees from the dam area in an amount not to exceed $72 ,000.00 .
The proposed contract with Lehne Construction , Inc., will include the demolition of the existing boat
ramp and the installation of a new concrete boat ramp at Arrow S Park , the removal of the existing
buoy line and the installation of a new lighted buoy line at the Lake Worth Dam , and removal of trees
and brush on the Lake Worth Dam .
-1 -
http://apps.cfwnet.org/council_packet/mc _review.asp?ID=l l 61 O&councildate=6/2/2009 06/25 /2009
M&C Review Page 2 of2
The project was advertised for bid on December 11 , 2008, and December 18, 2008 . On January 22 ,
2009 , the following bids were received :
BIDDERS
Lehne Construction , Inc.
Patco Utilities, Inc.
Northstar Construction, Inc.
Orval Hall Excavating, Ltd.
Boyer, Inc .
BID
$359 ,732 .0(
$382,884.31
$398,900.0(
$410,400 .0(
$563,825.0(
In addition to the contract price $15,000 .00 is needed for project management and inspection.
Lehne Construction , Inc ., is in compliance with the City's M/WBE Ordinance by committing to eight
percent M/WBE participation. The City's goal on this project is six percent.
FISCAL IN FORMATION/CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above
recommendations and adoption of the attached appropriation ordinance funds will be available in the
current capital budget, as appropriated , of the Lake Worth Trust Fund.
TO Fund/Account/Centers
1) FE70 446100 030001902000 $374,732 .00
1) FE70 539120 030001902000 $74 ,732 .00
1) FE70 538070 030001902000 $300 ,000 .00
2&3)
P253 472070 6075601310ZZ $300 ,000 .00
3)P253 511010 607560131085 15 000 .00
3) P253 541200 607560131080 $285,000 .00
Submitted for City Manager's Office by:
Originating Department Head:
Additional Information Contact:
ATTACHMENTS
60LAKE WORTH RESTORATION REC1.doc
60LAKE WORTH RESTORATION REC3.doc
Lake Worth Restoration map.ppt
FROM Fund/Account/Centers
2) FE70 538070 030001902000 $300 ,000 .0
4) FE70 539120 030001902000 $74,732.0
4) P253 541200 607560131080 $285,000 .0
Fernando Costa (6122)
S. Frank Crumb (8207)
Paul Bounds (8567)
http://apps.cfwnet.org/council_packet/mc _review.asp?ID= 1161 O&councildate=6/2/2009 06 /25 /2009
LAKE WORTH RESTORATION AND MAINTENANCE
PROJECT NUMBER : WTR-2009-560001
UNIT I -BOAT RAMP REPLACEMENT
UNIT II -MARKER BUOY/ FLOAT LINE REPLACEMENT
UNIT III -REMOVAL OF BRUSH AND TREES AT THE DAM
2009
DALE FISSELER, P .E.
CITY MANAGER
FRANK CRUMB, P.E.
DIRECTOR, WATER DEPARTMENT
RECOMMENDED ------------------
ANDY CRONBERG, P.E. -ASSISTANT DIRECTOR, WATER DEPARTMENT
APPROVED ---------------------
S. FRANK CRUMB, P.E.-DIRECTOR WATER DEPARTMENT
SPECIAL CONTRACT DOCUMENTS FOR
LAKE WORTH RESTORATION AND MAINTENANCE
PROJECT NUMBER : WTR-2009-560001
UNIT I -BOAT RAMP REPLACEMENT
UNIT II -MARKER BUOY/ FLOAT LINE REPLACEMENT
UNIT III -REMOVAL OF BRUSH AND TREES AT THE DAM
DALE FISSELER, P.E.
CITY MANAGER
FRANK CRUMB, P.E.
DIRECTOR, WATER DEPARTMENT
ANDY CRONBERG, P.E.
ASSISTANT DIRECTOR, WATER DEPARTMENT
CITY OF FORT WORTH, TEXAS
SECIFICA TIONS AND CONTRACT DOCUMENTS
FOR
LAKE WORTH RESTORATION AND MAINTENANCE
PROJECT NUMBER: WTR-2009-560001
TABLE OF CONTENTS
PART "A" Notice to Bidders
Special Instructions to Bidders
PART "B" Proposal (Bid)
MWBE Bid Specifications
PART "C" General Conditions
PART "CS" Supplementary Conditions
PART "D" Special Conditions
PART "E" Technical Specifications
PART "F" Bonds and Insurance
PART "G" Contract
PART "H" Area locations ( Units I, II, III )
Project Sign Detail
PART "A"
NOTICE TO BIDDERS
NOTICE TO BIDDERS
Sealed Proposals for the furnishing of all labor, materials, and equipment for
Construction of the Lake Worth Restoration and Maintenance (Units I, II, III)
Water Department Project Number WTR-2009-560001 addressed to Purchasing
Manager of the City of Fort Worth, will be received until 01:30 p.m. on the date of
The bid opening, at the Office of the Purchasing Division, located on the lower level
of the Municipal Building, 1000 Throckmorton Street, Fort Worth, Texas 76102.
The Bids will be publicly opened and read aloud in the City Council Chambers at:
2:00 p.m., January 22nd, 2009
Special Contract Documents, including plans and detailed specifications, have been
Prepared for the project and may be obtained from the City of Fort Worth Water
Department Engineering Office at no cost located, 2nd floor -1000 Throckmorton Street,
Fort Worth, Texas 76102 .
A pre-bid conference will be held at 10:30am Wednesday, January i\ 2009 at the
Arrow S Park Boat Ramp (under the HWY 820 Bridge over Lake Worth-Mapsco 59G).
Engineer will transmit to all prospective bidders of record such Addenda, as Engineer
considers necessary in response to questions arising at the conference.
Prequalification according to the Fort Worth Water Department Contract Specifications
(as listed in Special Instructions to Bidders) is required. All Bidders must submit
prequalification documents with the City of Fort Worth Water Department a
minimum of seven (7) days prior to the bid opening. The City reserves the right to
Reject any or all bids and waive any or all irregularities. No Bid may be withdrawn
until the expiration of ninety (90) days from the date the Bids are opened.
For additional information, please contact Walter W. Hardin, Jr., P.E. at (817) 392-8698
or (682) 432-4075 -email walter.hardin(@fortworthgov.org
Publication Dates: December 11, 2009
December 18, 2009
Dale Fisseler
City Manager
Marty Hendrix
City Secretary
SPECIAL INSTRUCTIONS TO BIDDERS
(February 15, 2006)
1. PREQUALIFICATION REQUIREMENTS. All contractors submitting bids, are
required to be pre-qualified by the Fort Worth Water Department prior to submitting
bids. This pre-qualification process will establish a bid limit based on technical
evaluation and financial analysis of the contractor. It is the bidder's responsibility to
submit the following documentation: a current financial statement, an acceptable
equipment schedule, names and addresses of each individual or business entity
owning 10% or more of the bidding entity, and any other documents the Department
may deem necessary, to the Director of the Water Department or his designated
representative, at least seven (7) calendar days prior to the date of the opening of bids.
a) COVER LETTER. The cover letter provided by the prospective bidder
with the pre-qualification information must include the following
information:
• Contact person (for additional information) if other than individual
who signed the cover letter
• If the bidder intends to submit a bid within thirty (30) days from the
date that the pre-qualification request is submitted to the City, a
statement as to the project to be bid and the date that the bids are
scheduled to be opened.
b) FINANCIAL STATEMENT. The financial statement required shall have
been prepared by an independent certified public accountant or
independent public accountant holding a valid permit issued by an
appropriate State licensing agency and shall have been so prepared as to
reflect the financial status of the submitting company. This statement must
be current and not more than one (1) year old. In the case that a bidding
date falls within the time a new statement is being prepared, the previous
statement shall be updated by proper verification.
c) EXPERIENCE RECORD. For an experience record to be considered to be
acceptable for a given project, it must reflect the experience of the firm
seeking qualification in the work of both the same nature and technical
level as that of the project for which bids are to be received . Experience
must be on projects that were completed no more than 5 years prior to the
date on which bids will be received . A minimum of three references must
be included. References must include a contact person name, telephone
number, project name and total cost, and type of work done (Utility
contractor shall list pipe size and pipe linear footage).
d) EQUIPMENT SCHEDULE. The prospective bidder shall list the
equipment that the Contractor has available for the project and list the
equipment that Contractor will rent as may be required to complete the
project on which the Contractor submits a bid.
A-2
The Water Department will review each pre-qualification submittal. From the financial
statement, the maximum bid limit will be based on amount of liquid assets times 10. The
expiration date for pre-qualification will be established as 15 months after the date of the
financial statement. The experience record will be reviewed and verified at the same time.
The following condition§ will apply:
a) The Director of the Water Department shall be the sole judge as to the
acceptability for financial and experience qualification to bid on any Fort
Worth Water Department project.
b) Bids received in excess of the bid limit shall be considered non-responsive
and will be rejected as such.
c) The City, in its sole discretion, may reject a bid for failure to demonstrate
experience and/or expertise.
d) Any proposals submitted by a non pre-qualified bidder shall be returned
unopened, and if inadvertently opened, shall not be considered.
e) The City will attempt to notify prospective bidders whose qualifications
(financial or experience) are not deemed to be appropriate to the nature
and/or magnitude of the project on which bids are to be received. Failure
to notify shall not be a wavier of any necessary pre-qualification.
For additional information contact John Kasavich, Fort Worth Water Department at (817)
392-8480 (FAX 817-392-8195). Pre-qualification submittal should be sent to:
John Kasavich
Fort Worth Water Department
1000 Throckmorton
Fort Worth, TX 76102-6212
2. BID SECURITY. A cashier's check, or an acceptable bidder's bond, payable to the
City of Fort Worth, in the amount of not less than five (5%) percent of the largest
possible total of the bid submitted must accompany the bid, and is subject to
forfeiture in the event the successful bidder fails to execute the Contract Documents
within ten (10) days after the contract has been awarded. To be an acceptable surety
on the bid bond, the surety must be licensed to do business in the State of Texas. In
addition, the surety must (1) hold a certificate of authority from the United States
Secretary of the Treasury to qualify as a surety on obligations permitted or required
under federal law; or (2) have obtained reinsurance for any liability in excess of
$100,000 from a reinsurer that is authorized and admitted as a reinsurer in the State of
Texas and is the holder of a certificate of authority from the Untied States Secretary
of the Treasury to qualify as a surety on obligations permitted or required under
federal law. Satisfactory proof of any such reinsurance shall be provided to the City
upon request. The City, in its sole discretion, will determine the adequacy of the proof
required herein.
A-6
3. CONFLICT OF INTEREST DISCLOSURE REQUIREMENT. Pursuant to Chapter
176 of the Local Government Code, any person or agent of a person who contracts or
seeks to contract for the sale or purchase of property, goods, or services with a local
governmental entity (i.e. The City of Fort Worth) must disclose in the Questionnaire
Form CIQ ("Questionnaire") the person's affiliation or business relationship that
might cause a conflict of interest with the local governmental entity. By law, the
Questionnaire must be filed with the Fort Worth City Secretary no later than seven
days after the date the person begins contract discussions or negotiations with the
City, or submits an application or response to a request for proposals or bids,
correspondence, or another writing related to a potential agreement with the City.
Updated Questionnaires must be filed in conformance with Chapter 176 .
A copy of the Questionnaire Form CIQ can be found in the contract documents. The
form is also available at http://www.ethics.state.tx.us/forms/CIO.pdf.
If you have any questions about compliance, please consult your own legal counsel.
Compliance is the individual responsibility of each person or agent of a person who is
subject to the filing requirement. An offense under Chapter 176 is a Class C
misdemeanor.
4. BONDS. A performance bond, a payment bond, and a maintenance bond each for one
hundred (100%) percent of the contract price will be required. Reference C3-3.7.
5. WAGE RATES. Not less that the prevailing wage rates established by the City of Fort
Worth, Texas, and as set forth in the Contract Documents. must be paid on this
project.
6. AMBIGUITY: In the case of ambiguity or lack of clearness in stating prices in the
Proposal, the City reserves the right to adopt the most advantageous construction
thereof to the City or to reject the Proposal.
7. BIDDER LICENSE: Prior to the award of contract to an out-of-state bidder, the
bidder shall be licensed to do business in the State of Texas . For licensing procedures,
contact the Texas Secretary of State Offices (Telephone Number 1-512-463-5555 or
1-900-263-0060)
8. NONRESIDENT BIDDERS: Pursuant to Article 601g, Texas Revised Civil Statues,
the City of Fort Worth will not award this contract to a nonresident bidder unless the
nonresident's bid is lower that the lowest bid submitted by a Texas resident bidder by
the same amount that a Texas resident would be required to underbid a nonresident
bidder to obtain a comparable contract in the state in which the nonresident's
principal place of business is located.
"Nonresident bidder" means a bidder whose principal place of business is not in this
state, but excludes a contractor whose ultimate parent company or majority owner has
a place of business in the State of Texas.
This provision does not apply if this contract involves federal funds.
A-6
The appropriate blanks of the Proposal must be filled out by all nonresident bidders in
order for the bid to meet specifications. The failure of a nonresident contractor to do
so will automatically disqualify that bidder.
8. PAYMENT: If the contract amount is $25,000 or less, the contract amount shall be
paid within forty-five (45) days after the completion and acceptance by the City.
9. AGE: In accordance with the policy ("Policy") of the Executive Branch of the Federal
Government, Contractor covenants that neither it nor any of its officers, members,
agents, employees, program participants or subcontractors, while engaged in
performing this contract, shall, in connection with the employment, advancement or
discharge of employees or in connection with the terms, conditions or privileges of
their employment, discriminate against persons because of their age except on the
basis of a bona fide occupational qualification, retirement plan or statutory
requirement.
Contractor further covenants that neither it nor its officers, members, agents,
employees, subcontractors, program participants, or persons acting on their behalf,
shall specify, in solicitations or advertisements for employees to work on this
contract, a maximum age limit for such employment unless the specified maximum
age limit is based upon a bona fide occupational qualification, retirement plan or
statutory requirements.
Contractor warrants it will fully comply with the policy and will defend, indemnify
and hold City harmless against any claims or allegations asserted by third parties or
subcontractors against the City arising out of the Contractor's and/or its
subcontractors' alleged failure to comply with the above referenced Policy concerning
age discrimination in the performance of the contract.
10. DISABILITY: In accordance with provisions of the Americans with Disabilities Act
of 1990 ("ADA"), Contractor warrants that it and any and all of its subcontractors will
not unlawfully discriminate on; the basis of disability in the provision of services to
the general public, nor in the availability, terms and/or conditions of employment for
applicants for employment with, or employees of the Contractor or any of its
subcontractors . Contract warrants it will fully comply with ADA's provision and any
other applicable Federal, State, and local laws concerning disability and will defend,
indemnify and hold harmless against any claims or allegations asserted by third
parties or subcontractors against the City arising out of the Contractor's and/or its
subcontractors' alleged failure to comply with the above referenced Policy concerning
disability discrimination in the performance of this contract.
11. MINORJTY AND WOMEN BUSINESS ENTERPRJSES: In a accord with City of
Fort Worth Ordinance No. 15530, the City of Fort Worth has goals for the
participation of minority business enterprises and women business enterprises in City
contracts. A copy of the Ordinance can be obtained from the Office of the City
Secretary. The bidder shall submit the MBE/WBE SUBCONTRACTOR/SUPPLIER
UTILIZATION FORM, PRJME CONTRACTOR WAIVER FORM, and/or the
A-6
GOOD FAITH EFFORT FORM ("with Documentation") and/or the JOINT
VENTURE FORM as appropriate. The Documentation must be received by the
managing department no later than 5:00 p.m, five (5) City business days after the bid
opening date. The bidder shall obtain a receipt from the appropriate employee of the
managing department to whom delivery was made. Such receipt shall be evidence
that the documentation was received by the City. Failure to comply shall render the
bid non-responsive .
Upon request, Contractor agrees to provide the Owner complete and accurate
information regarding actual work performed by a minority business enterprise
(MBE) and/or women business enterprise (WBE) on the contract and payment
thereof. Contractor further agrees to permit any audit and/or examination of any .
books, records or files in its possession that will substantiate the actual work
performed by an MBE and/or WBE. The misrepresentation of facts ( other than a
negligent misrepresentation) and/or commission of fraud by the Contractor will be
grounds for termination of the contract and/or initiating action under appropriate
Federal, State or local laws or ordinances relating to false statements . Further, any
such misrepresentation facts (other than a negligent misrepresentation) and/or
commission of fraud will result in the Contractor being determined to be irresponsible
and barred from participating in City work for a period of time of not less that three
(3) years.
12. ADDENDA: Bidders wanting further information, interpretation or clarification of
the contract documents must make their request in writing to the Fort Worth Water
Department Engineering Services, at least 96 hours prior to bid opening . Answers to
all such requests will be bound and made a part of the Contract Documents. No other
explanation or interpretation will be considered official or binding. Should a bidder
find discrepancies in , or omissions from, the Contract Documents, or should the
bidder be in doubt as to their meaning, the bidder should at once notify the Fort
Worth Water Department Engineering Services, in order that a written addendum may
be sent to all bidders. Any addenda issued will be mailed or be delivered to each
prospective bidder. The bid proposal as submitted by the bidder must be so
constructed as to include any addenda issued by the Fort Worth Water Department,
prior to 24 hours of the opening of bids with appropriate recognition of addenda so
noted in the bid proposal.
A-6
PART "B"
PROPOSAL
TO: Mr. Dale Fisseler
City Manager
Fort Worth, Texas
PART "B" -PROPOSAL
PROPOSAL FOR: furnishing of all material and equipment and labor and all
necessary appurtenances and incidental work to provide an operable project
designated as:
LAKE WORTH RESTORATION AND MAINTENANCE
PROJECT NUMBER: WTR-2009-560001
UNIT 1 -BOAT RAMP REPLACEMENT
UNIT II -MARKER BUOY/ FLOAT LINE REPLACEMENT
UNIT III -REMOVAL OF BRUSH AND TREES AT THE DAM
Pursuant to the foregoing Notice to Bidders, the undersigned Bidder having thoroughly
Examined the Contract Documents, including plans, special contract documents and the
General Specifications for Water Department Projects, the site of the project and
understanding the amount of work to be done, and the prevailing conditions hereby
proposes to do all the work, furnish all the labor, equipment and material , except as
specified to be furnished by the City, which is necessary to fully complete the work as
provided in the plans and contract Documents and subject to the inspection and approval
of the Director of the City Water Department of the City of Fort Worth, Texas; and binds
himself upon acceptance of this proposal to execute a contract and furnish an approved
Performance Bond, Payment Bond, Maintenance Bond, and such other bonds, if any, as
may be required by the Contract Documents for the performing and completing of the
said work. Contractor proposes to do the work within the time stated and for the
following sums:
B-1
•
...
• >
ITEM APPROX . DESCRIPTION OF ITEM UNIT
PRICE
TOTAL
AMOUNT BID NO . QUANTITY WITH BID PRICES
WRITTEN IN WORDS
UNIT I -BOAT RAMP REPLACEMENT (INCLUDING PROJECT SIGN)
1. LS
2. LS
3. LS
INST ALL /MAINTAIN COFFERDAM AND
DEWATER AS REQUIRED TO CONSTRUCT
A NEW BOAT RAMP -REMOVE UPON COMPLETION
No CENTS
C>C eG
$1S'i'1ooo -LS $ 3'8'1 ooo -
PREPARE LAKE BOTTOM INCLUDING A LL EXCAVATION
AS NECESSARY TO CONSTRUCT THE NEW BOAT RAMP
No ----------t-±:NTS
oG
$ J'-f oo o -LS
SA WCUT THE EXISTING ASPHALT PAVEMENT NEXT TO
THE EXISTING CONCRETE HEAD WALK AT THE EAST
END OF THE EXISTING BOAT RAMP AND REMOVE THE
ENTIRE EXISTING BOAT RAMP & HEAD WALK
ttUo t-ffa"s 1t1·h:1 f'tv£ l-/<J 1-fon..c,tJ DOLLARS
fl, CE~ffS
$ zs 0 ,o LS
B-2
' '
4. LS
5. LS
6. LS
HAUL FROM SITE ALL THE EXCAVATED/ REMOVED
MATERIALS AS REQUIRED FOR THE NEW BOAT RAMP
CONSTUCTION
No ---------p;ENTS
~ ..c,
$ -5 ") I L LS $ 5 1 I L -
PROVIDE NECESSARY SECURITY & OPERATIONAL CREW
TO INSURE THAT THE COFFERDAM REMAINS
FUNCTIONAL DURING THE CONSTRUCTION PROCESS
.,--.
h FrJ££J../ T l-lov5J1HJ::J -=--DOLLARS
N-,o CENTS --~----------
~ tll(
$_L~~-OCJ_u ___ LS $ Is .,o o ~
CONT RACTOR JOB SET-UP AND MOBILIZATION
,,.......
/-o ¥Lr'( S,c; v c N 1J-/a-., s '4 11..LJ DOLLARS --'-------------
_ __._N ....... o"--________ cENTs
a<. d"CI
$ 4 ,1 (JOO -LS $ L/ 7 CJ O <J-
B-3
7 . LS
8. LS
CONSTRUCT NEW 8 INCHES THICK CAST IN PLACE
REINFORCED CONCRETE BOAT RAMP HEAD WALK
SECTION WITH THICKEN EDGES . 4000 PSI CONCRETE
DESIGN WITH 7 % ENTRAINED AIR WITH 1.5 LBS .
PER CUBIC YARD OF SYNTHETIC NON-MET ALIC FIBERS .
THE REINFORCEMENT BARS TO BE #4 GFRP PLACED ON
12 INCH CENTERS BOTH WAYS .
THIS HEAD WALK SECTION TO BE 40 FEET BY 12 FEET
WITH A SMOOTH BROOM FINISH.
No cENTs
OG a v
$ 4,3ZD -LS $ L/1 3Zo -
CONSTRUCT NEW 8 INCHES THICK CAST IN PLACE
REINFORCED CONCRETE BOAT RAMP (NOT INCLUDING
THE HEAD WALK TRANSITION SECTION).
4000 PSI CONCRETE DESIGN WITH 7 % ENTRAINED AIR
WITH 1.5 LBS . PER CUBIC YARD SYNTHETIC
NON-METALIC FIBERS. THIS RAMP IS
TO HA VE A PERIMETER GRADE BEAM 12 INCHES WIDE
AND 24 INCHES DEEP WITH FOUR # 6 GFRP REBARS
PLACED TWO ABOVE AND TWO BELOW WITHIN THE
CROSS-SECTION OF THE BEAM. THE REMAINDER OF THE
BOAT RAMP WILL HA VE #4 GFRP REBARS PLACED ON
18 INCH CENTERS BOTH WAYS. THE DIMENSIONS OF
THIS BOAT RAMP WILL BE TRAPEZOIDAL IN SHAPE
WITH THE RAMP'S BEGINNING TO BE 40 FEET WIDE AND
THE DEEPEST END'S WIDTH TO BE 60 FEET WIDE. THE
OVERALL LENGTH (NOT INCLUDING THE HEAD WALK
SECTION) WILL BE 88 FEET LONG. Continued next page
B-4
THE SLOPE OF THE RAMP TO BE APPROX. 12 .5 %
AND THE ELEVATION OF THE DEEPEST END TO BE
584 FT. ABOVE SEA LEVEL (I.E . NORMAL FULL LAKE
LEVEL IS 594 FEET ABOVE SEA LEVEL).
THE SURF ACE OF THE BOAT RAMP TO HA VE A
ROUGH-BROOMED FINISH WITH Yi INCH DEEP TOOLED
OR SAW CUT GROVES ON THE DIAGONAL FROM THE
CENTER LINE OF THE BOAT RAMP TOWARDS THE DEEP
END OF THE RAMP AT A 60 DEGREE ANGLE DIRECTION
PLACED EVERY SIX INCHES (TO ALLOW THE WATER TO
SHED).
U,;t-/41t-efl G ,=I'( t:i.uv t:ll&./st4-l'/I(} £,u!IT rr DOLLARS
No CENTS
TOTAL BID FOR UNIT I
B-5
<JG, ....
$ 52 ~()cJ -LS $ S-c, o'OC -
~
$ 2'2 °/, 332-
PART"B"-PROPOSAL
ITEM APPROX. DESCRIPTION OF ITEM UNIT
PRICE
TOTAL
AMOUNT BID NO. QUANTITY WITH BID PRICES
WRITTEN IN WORDS
UNIT II -MARKER BUOY/ FLOAT LINE REPLACEMENT
1. LS
2. LS
REMOVE THE EXISTING MARKER BUOY/FLOAT LINE
_ ___,_"1.=.o""--_______ CENTS
CONSTRUCT (WELD) TWO (2) NEW LINE-END
ANCHORAGE SUPPORTING STRUCTURES NEAR THE
SHORE LINE. EACH STRUCTURE TO BE MADE OF 4
INCH SCHEDULE 40 STEEL PIPE SET/PLACED INTO THE
EARTH THREE (3) FEET DEEP ENCASED WITH
CONCRETE INTO 12 INCH MIN. DIAMETER HOLES.
THE SHAPE OF THE STRUCTURES TO BE
FIVE (5) FOOT WIDE "H'' PATTERN WTH BRACE ABOVE
THE NORMAL LAKE LEVEL OF 594 FT. WITH FIVE (5)
FEET PROJECTION ABOVE THIS NORMAL LEVEL.
EACH STRUCTURE TO BE PRIMED AND PAINTED WITH
TWO COATS OF WHITE EPOXY PAINT. TOPS OF PIPES
TO BE WELDED CLOSED WITH STEEL CAPS .
• o oc-
$ 4,.36"...--LS $ i 3 <!.0 -
B-6
3. LS FURNISH AND INSTALL THE NEW MARKER BUOY/
FLOAT LINE APPROX. 2400 FEET LONG NEAR THE DAM
USING "ROLY AN MANUFACTURED PRODUCTS" OR
APPROVED EQUAL :
23 -B961R BUOYS WITH LIGHT MOUNTS (two spares)
23 -T81 LIGHTS WITH BATTERYS (two spares)
21 -B2152 (300 LB .) CONCRETE ANCHORS
IOO-B1400A FLOATS (five spares)
6 -B 1933 CABLE (500 FT. SPOOLS EACH)
1 -B1931 CABLE (500 FT . SPOOLS EACH)
310 -B2335 CABLE CLAMPS
20-B2333 CABLE CLAMPS
123 -B1902 ANCHOR SHACKLES
46 -B2323 CABLE THIMBLES
10 -B2321 CABLE THIMBLES
23 - B 1923 SWIVELS
No
B-7
CENTS
~ ~
LS $ q g-Sao
. ~.
4 . LS CONTRACTOR JOB SET-UP AND MOBILIZATION
tw~ f-Jfo,,s;ftfl:J Ft vc__ f/-c,t-fIJl)!.LJ DOLLARS
No CENTS
~ ~ $ 25 a O LS $ -z._s de..>
cc.
TOT AL BID FOR UNIT II $ 5'€ 'I O 0
B-8
PART "B" -PROPOSAL
ITEM APPROX. DESCRIPTION OF ITEM UNIT
PRICE
TOTAL
AMOUNT BID NO. QUANTITY WITH BID PRICES
WRJITEN IN WORDS
UNIT III -REMOVAL OF BRUSH AND TREES AT THE DAM
I. LS
2. LS
CONTRACTOR JOB SET-UP AND MOBILIZATION
_;_[frl\J T ~~U_S--"O'--kJ_-d,._· ___ DOLLARS
~~--N~o~~~~~~_CENTS
CUT I SHRED / REMOVE FROM SITE THE BRUSH AND
DESIGNATED TREES FROM THE NORTHWEST SECTION
OF THE DAM (i.e. NORTH OF THE SPILLWAY)
INCLUDING GROWTH IN THE WATER NEXT TO DAM .
ACCESSABLE ONLY VIA THE NATURAL SPILLWAY
DISCHARGE ZONE JUST EAST OF THE SPILLWAY.
THE APPROX. SIZE OF THIS AREA IS 800 FEET LONG
BY 60 FEET WIDE.
, 9,t!:'{
SeveiV}f,eµT~~?~ c 5~i..uudred DOLLARS
---o-\'l_· o _______ CENTS
7 7So Du ;n r, <'Q oO $ / 1 • LS $ ~ I, . t _<J ·
. T 7
B-9
3. LS
4 . LS
CUT/ SHRED / REMOVE FROM SITE THE BRUSH AND
DESIGNATED TREES FROM THE SOUTHWEST SECTION
OF THE DAM (i.e . SOUTH OF THE SPILLWAY)
INCLUDING GROWTH IN THE WATER NEXT TO DAM
AND ALL GROWTH IN THE RIP-RAP AREA THE APPROX.
SIZE OF THIS AREA IS 800 FEET LONG BY 80 FEET WIDE.
('0 I ~-~\~
[if?'(,<ljJ ThoLtsai0d f .)eyel\J M,vdrtd DOLLARS
N.o CENTS --~~--------
$4 _-7qa . o\s $ -/ ~ -r;s-o . oo
CUT/ SHRED / REMOVE FROM SITE THE BRUSH AND
DESIGNATED TREES FROM THE SOUTHWEST SECTION
OF THE DAM (i.e. SOUTH OF THE SPILLWAY) AN AREA
(APPROXIMATELY 60 FEET WIDE BY 550 FEET
LONG) FROM THE TOE OF SLOPE ON THE
WEST SIDE OF THE DAM NOT IN THE RIP-RAP AREA.
"TC_.__~~-~d-·-'-'~=--·-'--~_,_,~::[Yo~------~--~-c,,.,J~d~~DOLLARS
H-o ~~~~~~~-· CENTS
$ .~ oOO, rs ·$ , t ~ 0 00. vO
B-10
I
I :
5. LS CUT I SHRED I REMOVE FROM THE SITE BRUSH AND
DESIGNATED TREES FROM THE SOUTHEAST SECTION
OF THE DAM (i.e. SOUTH OF THE SPILLWAY) AN AREA
IN THE RIP-RAP APPROX. 200 FEET BY 80 FEET ON THE
SLOPE OF THE DAM. L 0 , 0 kWJd.K-<l
f(X..t<2.. Tko1.t9Jcd fi Nve DOLLARS
__ ____.IL....:.~-=o ________ CENTS
$_ ~I S'DU, "OLS $ li soa, uO
7
TOT AL BID FOR UNIT III $-7~Z-}_(}_0_0_· _· -----
t Z . Cl'J I eµd~ J~i-s
B-11
PART "B" -PROPOSAL
ITEM APPROX. DESCRIPTION OF ITEM UNIT
PRICE
TOTAL
AMOUNT BID NO . QUANTITY WITH BID PRICES
WRITTEN IN WORDS
UNIT III -REMOVAL OF BRUSH AND TREES AT THE DAM
I. LS
2 . LS
CONTRACTOR JOB SET-UP AND MOBILIZATION
-'-Lb1v T~_ou·_ s_o_u_d_· ___ DOLLARS
~~----l'J..._o=--~~~~~-CENTS
CUT/ SHRED / REMOVE FROM SITE THE BRUSH AND
DESIGNATED TREES FROM THE NORTHWEST SECTION
OF THE DAM (i.e . NORTH OF THE SPILLWAY)
INCLUDING GROWTH IN THE WATER NEXT TO DAM.
ACCESSABLE ONLY VIA THE NATURAL SPILLWAY
DISCHARGE ZONE JUST EAST OF THE SPILLWAY.
THE APPROX. SIZE OF THIS AREA IS 800 FEET LONG
BY 60 FEET WIDE.
. · . rcr2 ..Sevei0Je,eµ=f"-aw-:->S~ c S~~uudred DOLLARS
B-9
3. LS
4. LS
CUT I SHRED I REMOVE FROM SITE THE BRUSH AND
DESIGNATED TREES FROM THE SOUTHWEST SECTION
OF THE DAM (i.e . SOUTH OF THE SPILLWAY)
INCLUDING GROWTH IN THE WATER NEXT TO DAM
AND ALL GROWTH IN THE RIP-RAP AREA THE APPROX .
SIZE OF THIS AREA IS 800 FEET LONG BY 80 FEET WIDE.
(10 ' g~,y
t ,f1'(.'6V Thou sai0d f 5'-eve,v ~#./d,.d 1DOLLARS
t{o CENTS -----=--=--------$4-?lb . /}~s $ /~ 7so .oo
CUT/ SHRED / REMOVE FROM SITE THE BRUSH AND
DESIGNATED TREES FROM THE SOUTHWEST SECTION
OF THE DAM (i.e . SOUTH OF THE SPILLWAY) AN AREA
(APPROXIMATELY 60 FEET WIDE BY 550 FEET
LONG) FROM THE TOE OF SLOPE ON THE
WEST SIDE OF THE DAM NOT IN THE RIP-RAP AREA.
l ~\} 6-~'2. .]J~~sc...vd DOLLARS
tt1> CENTS
p{I 0
$ ~~ oOO,Ls $ _?~ oo o. t)
B-10
I'
5. LS CUT/ SHRED/ REMOVE FROM THE SITE BRUSH AND
DESIGNATED TREES FROM THE SOUTHEAST SECTION
OF THE DAM (i.e. SOUTH OF THE SPILLWAY) AN AREA
IN THE RIP-RAP APPROX. 200 FEET BY 80 FEET ON THE
SLOPE OF THE DAM.
{I 0 , 0 l w-->J.H-d. ~ r~<L T~5µvd ( /-ive DOLLARS
Ho CENTS
$_ ~/ )OU, tJcLS $ l( .)OU, uU
TOTAL BID FoR UNIT In $-7~Z_1_(}_o_o_· ____ _
(?. Ctt f eµdc..r d~i-s
B-11
' .
The Bidder agrees to begin construction within 10 calendar days after issue of the Work
Order, and to complete the contract within 90 calendar days after beginning construction
as set forth in the written Work Order to be furnished by the Owner.
State of Residency: ( Complete A or B below, as applicable: )
A. The principal place of business of our company is in
the State of !Ex V).5
Non resident bidders in the State of , our
principal place of business, are required to be percent lower
than resident bidders by state law. A copy of the statute is attached.
Non resident bidders in the State of , our
principal place of business, are not required to underbid resident bidders .
® The principal place of business of our company or our parent company
or majority holder is in the State of Texas.
I (We), acknowledge receipt of the following addenda to the plans and specifications,
all of the prov isions and requirements of which have been taken into consideration in
preparation of the foregoing bid :
Addendum No. 1 (Initials) _ _.p=-t.. __ _
Addendum No . 2 ( Initials ) 6L--~---
Addendum No. 3 ( Initials ) ____ _
Seal
If Bidder is Corporation
Date : l-2 l-Oj
. -...
B-13
g ature of Principal
&~112et1r
' Title or Position
LE.-l-tN ~ Ce ,-tSn'.Vt:.-1(4' N-J-r-1e,.
Contractor
!2-4.DC> l-lw't '71 W ,rr£ 5~0-I lg
Street '
City ,1 State , Zip Code
Telephone Number
-
MINORITY AND WOMEN BUSINESS
ENTERPRISE SPECIFICATIONS
fORTWORTH ----....----City of Fort Worth
Subcontractors/Suppliers Utilization Form
Identify fill subcontractors/suppliers you will use on this project
ATIACHM EN T 1A
Page 1 of 4
Fa ilu re to complete t his fo rm , in its entirety with req ues ted documentat ion . and received by the Managing
Departme nt on or before 5:00 pm . five (5) City business days after bid opening . exclus ive of bid opening date ,
will resu lt in the bi d be ing considered non-responsive to bid specifications.
T he undersigned Offeror agrees to enter in to a formal agreement w it h the M.tWBE firm (s) li sted in th is
utilization schedule , conditioned upon ex ecution of a contract with the City of Fort Worth . The intentiona l
and/or know in g misrepresentation of facts is grou nd s for consideration of disqua lifi cation and will result in the
bid being cons idered non-respons ive to bid spe cifications
M/WBEs listed toward meeting the project goal must be located in the nine (9) county marketplace or
currently doing business in the marketplace at the time of bid. Ma rke tplace is th e geographic area of Tarra nt ,
Parker , Johnson , Coll in, Da llas , Denton , Ellis , Kaufman and Rockwal l count ies .
Identify e~-h--Tie~--i~vel. Tier is the level of sub~~~t~~c"ti-;:;g-·bei;;-th-e-prime . co nt ract or , i.e., a d ire ct I
payment from the prime contractor to a subcontractor is considered 1 51 t ier, a payment by a subcontractor to !
[__i ts supplier is considere_d 2 nd t ier ....................... __ ·····--------···· ..... --·-·············· ............. ___ . ...... _ __ _ ______ J
ALL M/WBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD .
Certification means those firms . located or doing bus iness at the time of bid opening within the Marketplace , that have
been determ ined to be bonafide m inor ity or women bus inesses by the No rth Central Te xas Reg ional Certification
Agenc y (NCTRCA ), or the Texas Department of Transportat ion (TX DOT ). hi ghwa y d iv ision Dis advanta ged Bus in ess
Enter pr ise (DBE ) 1s synonym ous with Mi nority/Women Bus iness Enterp ri se (M/WBE )
l
'lfhauling services are utilize-cf -the --prime wi tt be --given credi t as lor1g· as the M.tWBE listed owns and ;
operates at least one fully li ce~sed _and operational truck to be used on the contract . The M.tWBE may lease :
1 tr ucks from anothe r M/WBE firm . 1nclud1 ng M/WBE owner-oper ators . and rece ive fu ll M/WBE credit. T he i
1 M/VVBE may lease trucks from non-M/VVB Es . 1nclud 1n g owner -operators . but will only recei ve cre dit for the
: fees and commission~-~~rned by tt)~[Y.1_/'{Y.~~-~§_Q.~tlin ed in th e le9se _a_gr!::e rr:i~nt.
Rev G/30/03
Fn RTWORTH
ATIACHMENT 1A
Page 2 of 4 --..,..--
,---P rim es a r~·;:~u ired to i::ntify A:: s u bcontra ~;~r s/s up ~;;:~::~e~ardl::::;:~a tus : i.e .. Min:~;ty . Wo men and ~-on-MiWBEs . ·1 I Pl ease list MiW BE fir ms fir st. use add it ional sh eets if ne ces sary .
j
SUBCONTRACTOR/SUPPLIER
Company Name
Address
Telephone/Fax
Certification N
0 I (c heck on e ) n
:t-~-1 w Ii ~, ~ :
r B !B R I O B E I E I C T E
A
Detail
Subcontracting Work
Detail
Suppl ies Purchased Dollar Amount
---~~fl} ~"A I --~ .... ····---·----------·--·-----··'
8ff II:, J//MElf~
A1 1/f ~ P 11 IY'I
I
I !----
1
I
f-----
1
I
!
I
t1N1f$
I
l ----+-··-····" ··--·----i-~--+----->---------
------+-+--I ----·--·-------------··-.. -.. --1
I
I
I
.... J
Re11 . 5130 /03
Frnn \Vmn H --....,...--
ATTAC HMEN T 1A
Pag e 3 of 4
-··-.. ----.. ········---------------··· .. ----···-·--------·-·-----·····-·· ----········---------------··---·----·····-------------·-·-,
Pr im es are required to identify ALL subcontra ctors/suppliers , rega rdless of status ; i _e , Minority , Wome n and non-MNVB Es _
Please list MI\IVBE firms first , us e add itio nal sheets if necessary _
! Certifi cation N
0
T ~-
__ (ch eck one)
SUBCONTRACTOR/SUPPLIER -.-,----,----,----=--l n . NI T De ta i l Company Name
Address
Te lephone/Fax
1 i c X M Subcontracti ng Wo rk
e j M W T I D \I',
r 1' B B R'I O B E E C T E
: I 'A
! I I i ' I i I
I I I
Detail
Supplies Purchased
. --------------------------------. -+~--+--+-···-.. ----·-········-···--···-·----+--
i I I I I . I I
I i I
Dollar Amount
I
I
............... ,.___ ;
I
1
!
i I I :
1
---------------------------------· -r-~-r+---1 --------------··-·--·----------------------------------1
I i 1 _
, I ! I i I ! 1 I . ,
1 • I I tti·i-~ ---------------------
1 ' I
• I
I I
-----------·-------------_____ __.___._:-+i-~-
1 i I :
' I
i
i r---------------------l i -+----r---r-------
I I iu·J· !___________________ -~~--· _L~------------------------·--------------------
J
I
·-------------------·-_____ J
Re v 5/30/03
FORT WORTH ---..,....--
Total Dolla r Amount of M/WBE Subcontractors/Suppl iers
Total Do llar Amount of Non-M/WBE Subcontractors /Supplie rs
$ 9~ t?C~. ~
$ 7J. 8tA· ~
ATIACHMENT 1A
Page 4 of 4
TOTAL DOLLAR AMOUNT OF ALL SUBCONTRACTORS/SUPPLIERS $ /J9 1/t~. ~ ,,
jThe Contractor will not make additions . de letions , or substitutions to th is certified list without the pr ior approval /
I of the Minority and Women Business Enterprise Office Manager or des ignee through the submitta l of a 1
I Request for Approval of Change/Addition. Any un j ustified change or delet ion shall be a material breach of
contract and may result in debarment in accord with the procedures outl ined in the ordinance . The contractor
I
shall submit a detailed explanation of how the requested ch ange /add it ion or de letion wi ll affect the committed
~tY.vBE go_a l. If the detail explanation is not subm itted , it wil l affect t hefi nal compl iance determ inat ion . -~--........... ..
By aff ixing a signature to this form , the Offerer further agrees to prov ide , d irectly to the City upon request.
complete and accurate informat ion regarding actual work performed by all subcontractors . includ ing
M/W/DBE (s) arrangements subm itted with the bid . The Offe rer also agrees to allow an aud it and /or
examination of any books , records and files held by their compan y The bidder agrees to a llow the
transmiss ion of interv iews with owners . pr inc ipals , offic ers , employees and applicable
subcontractors /suppliers/contractors part icipating on the cont ract that will substantiate the actual work
performed by the M/W/DBE (s) on th is contract , by an authorized officer or emp loyee of the C ity . Any
intentional and /or know ing misrepresentation of facts will be gro unds fo r terminating the contract or debarment
from City work for a per iod of not less than three (3) years and for in it iating action under Federal , State or
Loca l laws concerning fa lse statements . Any fai lu re to comp ly with th is ordinance and create a material
breac h of cont ract may resu lt in a determination of an ir resp ons ible Offere r an d barred from partic ipat ing in
City work for a per iod of time not less t han one ( 1) yea r .
Lf~ A.tru1orized Signat ure
rrwJJ-
·-------'--.__""""=..c;x.a:..L.C..-------------
Tit le Contact Name/T itle (I f d iffe re nt)
.,S1?i -~t3-tJ~5 ~Sf t1 I
Tele p hone and/o r Fax 7
)~ 't~d »wv 71 W ..
I f4,, fl')
E-mail Address
9-®7· ri/1 lpl! ~ Da te
Add~> -k-·
::-:-=--~~-CC..L~J;-~~u:....::::· ~· 2--=.i..L......:2:1;:.__::i:___. ··-
Cit y/State/Zip I
Rev 5/30 /03
PART "C"
GENERAL CONDITIONS
-
-
-
-
-
......
·-
-
-
-
Cl-1
Cl-I.I
C 1-1.2
C 1-1.3
Cl-1.4
C 1-1.5
C 1-1.6
Cl-1.7
C 1-1.8
Cl-1.9
Cl-I.IO
Cl-1.11
Cl-1.12
Cl-1.13
Cl-1.14
Cl-1.15
Cl-1.16
Cl-1.17
Cl-1.18
Cl-1.19
C 1-1.20
Cl-1.21
C 1-1.22
Cl-1.23
C 1-1.24
Cl-1.25
Cl-1.26
Cl-1.27
Cl-1.28
Cl-1.29
Cl-1.30
Cl-1.31
Cl-1.32
PART C -GENERAL CONDITIONS
TABLE OF CONTENTS
NOVEMBER 1, 1987
TABLE OF CONTENTS
DEFINITIONS
Definition of Terms
Contract Documents
Notice to Bidders
Proposal
Bidder
General Conditions
Special Conditions
Specifications
Bonds
Contract
Plans
City
City Council
Mayor
City Manager
City Attorney
Director of Public Works
Director, City Water Department
Engineer
Contractor
Sureties
The Work or Project
Working Day
Calendar Days
Legal Holidays
Abbreviations
Change Order
Paved Streets and Alleys
Unpaved Streets or Alleys
City Street
Roadway
Gravel Street
Cl-I (I)
Cl-1 (I)
Cl-1 (2)
Cl-1 (2)
Cl -1 (2)
Cl-1 (2)
Cl-1 (2)
Cl-1 (2)
Cl-1 (2)
Cl-1 (2)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (3)
Cl-1 (4)
Cl-1 (4)
Cl-1 (4)
Cl-I (4)
Cl-1 (4)
Cl-1 (4)
Cl-1 (5)
Cl-1 (5)
C 1-1 (6)
Cl-1 (6)
Cl-1 (6)
Cl-1 (6)
C2-2 INTERPRETATION AND PREPARATION
OF PROPOSAL
C2-2.l
C2-2.2
C2-2.3
C2-2.4
Proposal Form
Interpretation of Quantities
Examination of Contract Documents and Site of Project
Submitting of Proposal
(1)
C2-2 (I)
C2-2 (I)
C2-2 (2)
C2-2 (2)
,_,
·-
,.. ..
-
-
-
-
-
-
-
-
-
.....
C2-2 .5 Rejection of Proposals
C2-2.6 Bid Security
C2 -2.7 Delivery of Proposal
C2 -2.8 Withdrawing Proposals
C2-2 .9 Te legraphic Modifications of Proposals
C2 -2 .1 0 Public Opening of Proposa l
C2 -2. l l Irregular Proposals
C2-2 .12 Disqualification of Bidders
C3-3 AWARD AND EXECUTION OF DOCUMENTS:
C3-3.1 Consideration of Proposals
C3-3.2 Minority Business Enterprise/Women Business
Enterprise Compliance
C3 -3.3 Equal Employment Provisions
C3 -3.4 Withdrawal of Proposals
C3 -3.5 A ward of Contract
C3-3.6 Return of Proposal Securities
C3-3.7 Bonds
C3-3.8 Execution of Contract
C3-3.9 Failure to Execute Contract
C-3 -3.10 Beginning Work
C3-3.l l Insurance
C3-3 .12 Contractor's Obligations
C3-3 .13 Weekly Payrolls
C3 -3 .14 Contractor's Contract Administration
C3-3 .15 Venue
C4-4 SCOPE OF WORK
C4 -4.1 Intent of Contract Documents
C4 -4.2 Special Provisions
C4 -4.3 Increased or Decreased Quantities
C4-4.4 Alteration of Contract Documents
C4 -4.5 Extra Work
C4 -4.6 Schedule of Operation
C4-4.7 Progress Schedules for Water and Sewer Plant Facilities
CS-5 CONTROL OF WORK AND MATERIALS
CS-5 .1
CS-5 .2
CS-5.3
CS-5.4
CS-5 .5
CS -5.6
CS-5.7
Authority of Engineer
C~mformity with Plans
Coordination of Contract Documents
Cooperation of Contractor
Emergency and/or Rectification Work
Field Office
Construction Stakes
(2)
C2 -2 (3)
C2-2 (3)
C2 -2 (3)
C2-2 (3)
C2-2 (3)
C2-2(4)
C2 -2(4)
C2 -2 (4)
C3-3 (1)
C3 -3 (1)
C3-3 (1)
C3-3 (1)
C3-3 (2)
C3 -3 (2)
C3 -3 (2)
C3-3 (3)
C3-3 (3)
C3-3 (4)
C3-3 (4)
C3-3 (6)
C3-3 (6)
C3-3 (6)
C3-3 (7)
C4 -4 (1)
C4 -4 (1)
C4-4 (1)
C4-4 (2)
C4-4 (2)
C4-4 (3)
C4-4 (4)
CS-5 (1)
CS -5 (1)
CS -5 (1)
CS -5 (2)
CS-5 (2)
CS -5 (3)
CS-5 (3)
-C5-5.8 Authority and Duties of City Inspector C5-5 (3)
C5-5 .9 Inspection C5-5 (4)
C5-5.10 Removal of Defective and Unauthorized Work C5-5 (4)
C5 -5. l l Substitute Materials or Equipment C5-5 (4)
C5 -5.12 Samples and Tests of Materials C5-5 (5)
,.. C5-5.13 Storage of Materials C5-5 (5)
C5-5.14 Existing Structures and Utilities C5-5 (5)
C5-5.15 Interruption of Serv ice C5-5 (6) -CS-5.16 Mutual Responsibility of Contractors CS -5 (7)
CS-5 .17 Clean-Up CS-5 (7)
CS-5.18 Final Inspection C5 -5 (8)
C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY -C6 -6 .1 Laws to be Observed C6-6 (1)
C6-6.2 Permits and Licenses C6-6 (1)
C6-6.3 Patented Devices, Materials, and Processes C6 -6 (1) -C6-6.4 Sanitary Provisions C6-6 (1)
C6-6.5 Public Safety and Convenience C6-6 (2)
C6-6.6 Privileges f Contractor in Streets, Alleys, C6-6 (3) -and Right-of-Way
C6-6 .7 Railway Crossings C6-6 (3)
C6-6 .8 Barricades, Warnings and Flagmen C6-6 (3) ,..
C6-6.9 Use of Explosives, Drop Weight, Etc. C6-6 (4)
C6-6 .10 Work Within Easements C6-6 (5) -C6.6 .1 l Independent Contractor C6-6 (6)
C6-6.12 Contractor's Responsibility for Damage Claims C6-6 (6)
C6-6.13 Contractor's Claim for Damages C6-6 (8)
C6-6.14 Adjustment or Relocation of Public Utilities, Etc . C6-6 (8)
C6-6.15 Temporary Sewer and Drain Connections C6-6 (8)
C6-6.16 Arrangement and Charges for Water Furnished by the City C6-6 (9) -C6-6 .l 7 Use of a Section or Portion of the Work C6-6 (9)
C6-6.18 Contractor's Responsibility for the Work C6-6 (9)
C6-6.19 No Waiver of Legal Rights C6-6 (9) .-C6-6.20 Personal Liability of Public Officials C6-6 (10)
C6-6 .21 State Sales Tax C6-6 (10)
C7-7 PROSECUTION AND PROGRESS
C7-7.l Subletting C7-7 (1) -C7-7.2 Assignment of Contract C7-7 (1)
C7-7 .3 Prosecution of The Work C7-7 (1)
C7-7.4 Limitation of Operations C7-7 (2) -C7-7 .5 Character of Workmen and Equipment C7-7(2)
C7-7.6 Work Schedule C7-7 (3)
C7-7.7 Time of Commencement and Completion C7-7(3)
C7-7.8 Extension of Time Completion C7-7(3)
-(3)
-
--..
... -.
-l
!
-,.
}
-
...... I
;
~
f
'"""'
• -
,. -·•
-
C7-7.9
C7-7.10
C7-7.ll
C7-7.12
C7 -7.13
C7-7.14
C7-7.15
C7-7.16
C7-7.17
C8 -8
C8 -8 . l
C8 -8.2
C8 -8.3
C8 -8.4
C8 -8.5
C8-8.6
C8 -8.7
C8-8.8
C8-8.9
C8 -8.10
C8 -8. l l
C8 -8.12
C8-8.13
De lays C7-7 (4)
Time of Completion C7-7 (4)
Suspension by Court Order C7-7(5)
Temporary Suspension C7-7 (5)
Termination of Contract due to National Emergency C7-7 (6)
Suspension or Abandonment of the Work C7-7 (6)
and Annulment of the Contract:
Fulfillment of Contract C7-7 (8)
Termination for Convenience of the Owner C7 -7 (8)
Safety Methods and Practices C7-7(11)
MEASUREMENT AND PAYMENT
Measurement Of Quantities C8-8 (1)
Unit Prices C8-8 (l)
Lump Sum C8 -8 (l)
Scope of Payment C8-8 (1)
Partial Estimates and Retainage C8 -8 (2)
Withholding Payment C8-8 (3)
Final Acceptance C8-8 (3)
Final Payment C8-8 (3)
Adequacy of Design C8-8 (4)
General Guaranty C8-8 (4)
Subsidiary Work C8-8 (4)
Miscellaneous Placement of Material C8 -8 (4)
Record Documents C8-8 ( 4)
(4)
--
-
-
-
-
PART C -GENERAL CONDITIONS
C 1-1 DEFINITIONS
SECTION Cl-1 DEFINITIONS
Cl-1.1 DEFINITIONS OF TERMS: Whenever in these Contract Documents the
following terms or pronouns in place of them are used, the intent and meaning shall be
understood and interpreted as follows:
Cl-1.2 CONTRACT DOCUMENTS : The Contract Documents are in all of the written
and drawn documents, such as specifications, bonds, addenda, plans, etc., which govern
the terms and performance of the contract. These are contained on the General Contract
Documents and the Special Contract Documents.
a. GENERAL CONTRACT DOCUMENTS: The General Contract
Documents govern all Water Department Projects and Include the
following Items
PART A -NOTICE TO BIDDERS
PART B -PROPOSAL
PART C-GENERAL CONDITIONS
PART D-SPECIAL CONDITIONS
PART E-SPECIFICATIONS
PERMITS /EASEMENTS
PART F -BONDS
PART G -CONTRACT
(Sample)
(Sample)
(CITY)
(Developer)
(Sample)
(Sample)
White
White
Canary Yellow
Brown
Green
El-White
E2-Golden Rod
E2A-White
Blue
White
White
b. SPECIAL CONTRACT DOCUMENTS: The Special Contract
Documents are prepared for each specific project as a supplement to the
General Contract Documents and include the following items:
PART A -NOTICE TO BIDDERS (Advertisement) same as above
PART B -PROPOSAL (Bid)
PART C-GENERAL CONDITIONS
PART D-SPECIAL CONDITIONS
PART E-SPECIFICATIONS
PERMITS/EASEMENTS
PART F-BONDS
PART G -CONTRACT
PART H -PLANS (Usually bound separately)
Cl-1 (1)
-
-
--
-
-
Cl-1.3 NOTICE TO BIDDERS : All of the legal publica tions e ither actually published
in public advertising mediums or furnished direct to interested parties pertaining to the
work contemplated under the Contract Documents constitutes the notice to bidders.
Cl-1.4 PROPOSAL: The completed written and signed offer or tender of a bidder to
perform the work which the Owner desires to have done , together with the bid security,
constitutes the Proposal , which becomes binding upon the Bidder w hen it is officially
received by the Owner, has been publicl y opened and read and not rejected by the Owner.
Cl-1.5 BIDD ER: Any person, persons , firm , partnership , company, association,
corporation, acting directly or through a duly authorized representative , submitting a
proposal for performing the work contemplated under the Contract Documents,
constitutes a bidder.
C 1-1 .6 GENERAL CONDITIONS: The G eneral Conditions are the usua l construction
and contract requirements which govern the performance of the work so that it will be ·
carried on in accordance with the customary procedure, the local statutes, and
requirements of the City of Fort Worth's charter and promulgated ordinances.
Whenever there may be a conflict between the General Conditions and the Special
Conditions, the latter shall take precedence ..
Cl-1.7 SPECIAL CONDITIONS: Special conditions are the specific requirements
which are necessary for the particular project covered by the Contract Documents and not
specifically covered in the General Conditions. When considered with the General
Conditions and other elements of the Contract Documents they provide the information
which the Contractor and Owner should have in order to gain a thorough knowledge of
the project.
C 1-1.8 SPECIFICATIONS: The Specifications is that section or part of the Contract
Documents which set forth in detail the requirements which must be met by all materials,
construction, workmanship, equipment and services in order to render a completed an
useful project. Whenever reference is made to standard specifications, regulations,
requirements , statutes, etc., such referred to documents shall become a part of the
Contract Documents just as though they were embodied therein.
Cl-1.9 BONDS: The bond or bonds are the written guarantee or security furnished by
the Contractor for prompt and faithful performance of the contract and include the
following :
a.
b.
C.
d.
Performance Bond (see paragraph C3-3 .7)
Payment Bond (see paragraph C3-3.7)
Maintenance Bond (see paragraph C3-3.7)
Proposal or Bid Security (see Special Instructions to Bidders, Part A and
C2-2 .6)
Cl-1 (2)
-
-
I!' ••
-
-
-
-
C 1-1.10 CONTRACT: The Contract is a formal signed agreement between the owner
and the Contractor covering the mutual understanding of the two contracting parties about
the project to be completed under the Contract Documents.
C 1-1.11 PLANS : The plans are the drawings or reproductions therefrom made by the
Owner's representative showing in detail the location, dimension and position of the
various elements of the project, including such profiles, typical cross-sections, layout
diagrams, working drawings, preliminary drawings and such supplemental drawings as
the Owner may issue to clarify other drawings or for the purpose of showing changes in
the work hereinafter authorized by the Owner. The plans are usually bound separately
from the other parts of the Contract Documents, but they are part of the Contract
Documents just as though they were bound therein.
Cl-1.12 CITY: The City of Fort Worth , Texas, a municipal corporation, authorized and
chartered under the Texas State Statutes, acting by and through its governing body or its
City Manager, each of which is required by charter to perform specific duties ..
Responsibility for final enforcement of the Contracts involving the City of Fort Worth is
by Charter vested in the City Manager. The terms City and Owner are synonymous.
Cl-1.13 CITY COUNCIL: The duly elected and qualified governing body of the City of
Fort Worth, Texas.
Cl-1.14 MAYOR: The officially elected Mayor, or in his absence, the Mayor Pro tern
of the City of Fort Worth, Texas.
C 1-1.15 CITY MANAGER : The officially appointed and authorized City Manager of
the City of Fort Worth, Texas, or his duly authorized representative.
C 1-1.16 CITY ATTORNEY: The officially appointed City Attorney of the City of Fort
Worth, Texas, or his duly authorized representative .
Cl-1.17 DIRECTOR OF PUBLIC WORKS: The officially appointed official of the City
of Fort Worth, Texas, referred to in the charter as the City Engineer, or his duly
authorized representative.
Cl-1.18 DIRECTOR, CITY WATER DEPARTMENT: The officially appointed
Director of the City Water Department of the City of Fort Worth, Texas, or his duly
authorized representative, assistant, or agents.
Cl-1.19 ENGINEER: The Director of Public Works, the Director of the Fort Worth
City Water Department, or their duly authorized assistants, agents, engineers, inspectors,
or superintendents, acting withirt the scope of the particular duties entrusted to them.
Cl-1.20 CONTRACTOR: The person, person's, partnership, company, firm, association,
or corporation, entering into a contract with the Owner for the execution of work, acting
Cl-I (3)
...
-
,,.,
-
.-
directly or through a duly authorized representative . A sub-contractor is a person, firm ,
corporation, supplying labor and materials or only labor, for the work at the site of the
project.
Cl-1.21 SURETIES: The Corporate bodies which are bound by such bonds as are
required with and for the Contractor. The sureties engaged are to be fully responsible for
the entire and satisfactory fulfillment of the Contract and for any and all requirements as
set forth in the Contract Documents and approved changes therein.
C 1-1.22 THE WORK OR PROJECT: The completed work contemplated in and
covered by the Contract Documents, including but not limited to the furnishing of all
labor, materials , tools , equipment, and incidentals necessary to produce a completed and
serviceable project.
Cl-1.23 WORKING DAY: A working day is defined as a calendar day, not including
Saturdays, Sundays, and legal holidays, in which weather or other conditions not under .
the control of the Contractor permit the performance of the principal unit of work for a
period of not less than seven (7) hours between 7 :00 a.m. and 6:00 p.m., with exceptions
as permitted in paragraph C7-7.6
C 1-1.24 CALENDAR DAYS: A calendar day is any day of the week or month, no days
being excepted.
Cl-1.25: LEGAL HOLIDAYS: Legal holidays shall be observed as prescribed by the
City Council of the City of Fort Worth for observance by City employees as follows:
1.
2.
3 .
4 .
5.
6.
7.
8.
9.
New Year's day
M.L. King, Jr. Birthday
Memorial Day
Independence Day
Labor Day
Thanksgiving Day
Thanksgiving Friday
Christmas Day
Such other days in lieu of holidays as
the City Council may determine
January 1
Third Monday in January
Last Monday in May
July 4
First Monday in September
Fourth Thursday in November
Forth Friday in November
December 25
When one of the above named holidays or a special holiday is declared by the City
Council, falls on a Saturday, the holiday shall be observed on the preceding Friday, or if it
falls on Sunday, it shall be observed on the following Monday, by those employees
working on working day operations. Employees working calendar day operations will
consider the calendar as the holiday.
Cl-1.26 ABBREVIATIONS: Whenever the abbreviations defined herein appear in the
Contract Documents, the intent and meaning shall be as follows:
Cl-1 (4)
.....
..-
-
-
_.., ........
-
.. -.
-
AASHTO -American Association of State MGD Million Gallons
Highway Transportation Officials per Day
ASCE American Society of Civil CFS Cubic Foot per
Engineers Second
IAW In Accordance With Min. Minimum
ASTM American Society of Testing Mono. Monolithic
Materials % Percentum
AWWA American Water Works R Radius
Association I.D. Inside Diameter
ASA American Standards Association 0 .0. Outside Diameter
HI Hydraulic Institute Elev. Elevation
Asph. Asphalt F Fahrenheit
Ave. Avenue C Centigrade
Blvd. Boulevard In. Inch
CI Cast Iron Ft. Foot
CL Center Line St. Street
GI Galvanized Iron CY Cubic Yard
Lin. Linear or Lineal Yd. Yard
lb. Pound SY Square yard
MH Manhole L.F. Linear Foot
Max. Maximum D.I. Ductile Iron
Cl-1.27 CHANGE ORDER: A "Change Order" is a written supplemental agreement
between the Owner and the Contractor covering some added or deducted item or feature
which may be found necessary and which was not specifically included in the scope of
the project on which bids were submitted. Increase in unit quantities stated in the
proposal are not the subject matter of a Change Order unless the increase or decrease is
more than 25% of the amount of the particular item or items in the original proposal.
All "Change Orders" shall be prepared by the City from information as necessary
furnished by the Contractor.
C 1-1.28 PAVED STREETS AND ALLEYS: A paved street or alley shall be defined as
a street or alley having one of the following types of wearing surfaces applied over the
natural unimproved surface :
1.
2.
3.
4.
5.
Any type of asphaltic concrete with or without separate base material.
Any type of asphalt surface treatment, not including an oiled surface, with
or without separate base material.
Brick, with or without separate base material.
Concrete, with or without separate base material.
Any combination of the above.
Cl-1 (5)
-
-
-
.. -"
-
Cl-1.29 UNPAVED STREETS OR ALLEYS: An unpaved street, alley, roadway or
other surface is any area except those defined for "Paved Streets and Alleys."
C 1-1.30 CITY STREET: A city street is defined as that area between the right-of-way
lines as the street is dedicated.
Cl-1.31 ROADWAY: The roadway is defined as the area between parallel lines two
(2') back of the curb lines or four ('4) feet back of the average edge of pavement where
no curb exists.
C 1-1.32 GRAVEL STREET: A gravel street is an unimproved street to which has been
added one or more applications of gravel or similar material other than the natural
material found on the street surface before any improvement was made.
Cl-I (6)
-
-·
-
.....
-
-
-
-
SECTION C -GENERAL CONDITIONS
C2-2 INTERPRETATION AND
PREPARATION OF PROPOSAL
SECTION C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL
C2-2 . l PROPOSAL FORM: The Owner will furnish bidders with Proposal form , which
will contain an itemized list of the items of work to be done or materials to be furnished
and upon which bid prices are requested. The Proposal form will state the Bidder 's
general understanding of the project to be completed, provide a space for furnishing the
amount of bid security, and state the basis for entering into a formal contract. The Owner
will furnish forms for the Bidder's "Experience l_{.ecord ," "Equipment Schedule ," and
"Financial Statement," all of which must be properly executed and filed with the Director
of the City Water Department one week prior to the hour for opening of bids.
The financial statement required shall have been prepared by an independent certified
public accountant or an independent public accountant holding a valid permit issued by
an appropriate state licensing agency, and shall have been so prepared as to reflect the
current financial status. This statement must be current and no more than one (l) year old .
In the case that bidding date falls within the time a new statement is being prepared, the
previous statement shall be updated by proper verification. Liquid assets in the amount of
ten (10) percent of the estimated project cost will be required .
For an experience record to be considered to be acceptable for a given project, it must
reflect the experience of the firm seeking qualification in work of both the same nature
and magnitude as that of the project for which bids are to be received , and such
experience must have been completed not more than five (5) years prior to the date on
which Bids are to be received. The Director of the Water Department shall be sole judge
as to the acceptability of experience for qualification to bid on any Fort Worth Water
Department project.
The prospective bidder shall schedule the equipment he has available for the project and
state that he will rent such additional equipment as may be required to complete the
project on which he submits a bid.
C2-2.2 INTERPRETATION OF QUANTITIES: The quantities of work and materials
to be furnished as may be listed in the proposal forms or other parts of the Contract
Documents will be considered as approximate only and will be used for the purpose of
comparing bids on a uniform basis. Payment will be made to the Contractor for only the
actual quantities of work performed or materials furnished in strict accordance with the
Contract Documents and Plans. The quantities of work to be performed and materials to
be furnished may be increased or decreased as hereinafter provided, without in any way
invalidating the unit prices bid or any other requirements of the Contract.Documents.
C2-2(1)
-
-
-
-
-
-
-
C2-2.3 EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF PROJECT:
Bidders are advised that the Contract Documents on file with the Owner shall constitute
all of the information which the Owner will furnish. All additional information and data
which the Owner will supply after promulgation of the formal contract documents shall
be issued in the form of written addenda and shall become part of the Contract
Documents just as though such addenda were actually written into the original Contract
Documents.
Bidders are required, prior to filing of proposal, to read and become familiar with the
Contract Documents, to visit the site of the project and examine carefully all local
conditions , to inform themselves by their own independent research and investigations ,
tests, boring, and by such other means as may be necessary to gain a complete knowledge
of the conditions which will be encounterec;l during construction of the project. They must
judge for themselves the difficulties of the work and all attending circumstances affecting
the cost of doing the work or the time required for its completion, and obtain all
information required to make an intelligent proposal. No information given by the Owner ·
or any representative of the Owner other than that contained in the Contract Documents
and officially promulgated addenda thereto, shall be binding upon the Owner. Bidders
shall rely exclusively and solely upon their own estimates, investigation, research, tests,
explorations, and other data which are necessary for full and complete information upon
which the proposal is to be based. It is mutually agreed that the submission of a proposal
is prima-facie evidence that the bidder has made the investigation, examinations and tests
herein required. Claims for additional compensation due to variations between conditions
actually encountered in construction and as indicated in the Contract Documents will not
be allowed.
The logs of Soil Borings, if any, on the plans are for general information only and may
not be correct. Neither the Owner nor the Engineer guarantee that the data shown 1s
representative of conditions which actually exist.
C2-2.4 SUBMITTING OF PROPOSAL: The Bidder shall submit his Proposal on the
form furnished by the Owner. All blank spaces applicable to the project contained in the
form shall be correctly filled in and the Bidder shall state the prices, written in ink in both
words and numerals, for which he proposes to do work contemplated or furnish the
materials required. All such prices shall be written legibly. In case of discrepancy
between price written in words and the price written in numerals, the price most
advantageous to the City shall govern.
If a proposal is submitted by an individual, his or her name must be signed by him (her)
or his (her) duly authorized agent. If a proposal is submitted by a firm, association, or
partnership, the name and address of each member of the firm, association, or partnership,
or by person duly authorized. If a proposal is submitted by a company or corporation, the
company or corporation name and business address must be given, and the proposal
signed by an official or duly authorized agent. The corporate seal must be affixed. Power
C2-2(2)
-
--.
-
of Attorney authori zing agents or others to sign proposal must be prop e rly certified and
must be in writing and submitted with the proposal.
C2-2.5 REJECTION OF PROPOSALS: Proposals may be rejected if they show any
alteration of words or figures, additions not called for, conditional or uncalled for
alternate bids, erasures, or irregularities of any kind , or contain unbalanced value of any
items . Proposal tendered or delivered after the official time designated for receipt of
proposal shall be returned to the Bidder unopened.
C2-2.6 BID SECURITY: No proposal will be considered unless it is accompanied by a
"Proposal Security" of the character and the amount indicated in the "Notice to Bidders"
and the "Proposal." The Bid Security is required by the Owner as evidence of good faith
on the part of the Bidder, and ~y way of a guaranty that if awarded the contract, the
Bidder will within the required time execute a formal contract and furnish the required
performance and other bonds . The bid security of the three lowest bidders will be retained
until the contract is awarded or other disposition is made thereof. The bid security of all ·
other bidders may be returned promptly after the canvass of bids .
C2-2 .7 DELIVERY OF PROPOSAL: No proposal will be considered unless it is
delivered , accompanied by its proper Bid Security, to the City Manager or his
representative in the official place of business as set forth in the "Notice to Bidders." It is
the Bidder's sole responsibility to deliver the proposal at the proper time to the proper
place. The mere fact that a proposal was dispatched will not be considered. The Bidder
must have the proposal actually deli ve red. Each proposal shall be in a sealed envelope
plainly marker with the word "PROPOSAL ," and the name or description of the project
as designated in the "Notice to Bidders." The envelope shall be addressed to the City
Manager, City Hall , Fort Worth, Texas .
C2-2.8 WITHDRAWING PROPOSALS: Proposals actually filed with the City
Manager cannot be withdrawn prior to the time set for opening proposals. A request for
non-consideration must be made in writing, addressed to the City Manager, and filed with
him prior to the time set for opening of proposals. After all proposals not requested for
non-consideration are opened and publicly read aloud, the proposals for which non-
consideration requests have been properly filed may , at the option of the Owner, be
returned unopened .
C2-2.9 TELEGRAHIC MODIFICATIONS OF PROPOSALS: Any Bidder may modify
his proposal by telegraphic communication at any time prior to the time set for opening
proposals, provided such telegraphic communication is received by the City Manager
prior to the said proposal opening time, and provided further, that the City Manager is
satisfied that a written and duly authenticated confirmation of such telegraphic
communication over the signature of the bidder was mailed prior to the proposal opening
time: If such confirmation is not received within forty-eight ( 48) hours after the proposal
opening time, no further consideration will be given to the proposal.
C2-2(3)
-
-
-
--
-
C2-2.10 PUBLIC OPENING OF PROPOSAL : Proposals which have been properly
filed and for which no "Non-consideration Reques t" has bee n recei ved will be publicl y
opened and read aloud by the City Manager or his authorized representative at the time
and place indicated in the "Notice to Bidders." All proposals which have been opened and
read will remain on file with the Owner until the contract has been awarded. Bidders or
their authorized representatives are invited to be present for the opening of bids .
C2-2.1 l IRREGULAR PROPOSALS: Proposals shall be considered as "Irregular" if
they show any omissions , alterations of form, additions, or conditions not called for,
unauthorized alternate bids , or irregularities of any kind. However, the Owner reserves
the right to waive any all irregularities and to make the award of the contract to th e best
interest of the City . Tendering a proposal after th e closing hour is an irregularity which
can not be waived .
C2-2.12 DISQUALIFICATION OF BIDDERS: Bidders may be disqualified and their
proposals not considered for any of, but not limited to, the following reasons:
a) Reasons for believing that collusion exists among bidders.
b) Reasonable grounds for believing that any bidder is interested in more than
v one proposal for work contemplated.
c) The bidder being interested in any litigation against the Owner or where
the Owner may have a claim against or be engaged in litigation against the
bidder.
d) The bidder being in arrears on any existing contract or having defaulted on
e)
f)
g)
h)
a previous contract.
The bidder having performed a prior contract in an unsatisfactory manner.
Lack of competency as revealed by financial statement, experience
statement, equipment schedule , and such inquiries as the Owner may see
fit to make.
Uncompleted work which, in the judgment of the Owner, will prevent or
hinder the prompt completion of additional work if awarded .
The bidder not filing with the Owner, one week in advance of the hour of
the opening of proposals the following :
l.
2.
3.
Financial Statement showing the financial condition of the bidder
as specified in Part "A" -Special Instructions
A current experience record showing especially the projects of a
nature similar to the one under consideration, which have been
successfully completed by the Bidder.
An equipment schedule showing the equipment the bidder has
available for use on the project.
The Bid Proposal of the bidder who, in the judgment of the Engineer, is disqualified
under the requirements stated herein, shall be set aside and not opened.
C2-2(4)
-
....
.. -.
-
--
-
-
-
-
....
PART C -GENERAL CONDITIONS
C3-3 AW ARD AND EXECUTION OF
DOCUMENTS
SECTION C3-3 AW ARD AND EXECUTION OF DOCUMENTS:
C3-3.1 CONSIDERATION OF PROPOSALS: After proposals have been opened and
read aloud, the proposals will be tabulated on the basis of the quoted prices , the quantities
shown in the proposal, and the application of such formulas or other methods of bringing
items to a common basis as may be established in the Contract Documents.
The total obtained by taking the sum of the products of the unit prices quoted and the
estimated quantities plus any lurhp sum items and such other quoted amounts as may
enter into the cost of the completed project will be considered as the amount of the bid.
Until the ward of the contract is made by the Owner, the right will be reserved to reject
any or all proposals and waive technicalities, to re-advertise for new proposals, or to
proceed with the work in any manner as may be considered for the best interest of the
Owner.
C3-3.2 MINORITY BUSINESS ENTERPRISE/WOMEN-OWNED BUSINESS
ENTERPRISE COMPLIANCE: Contractor agrees to provide to Owner, upon request,
complete and accurate information regarding actual work performed by a Minority
Business Enterprise (MBE) and/or a Woman-owned Business Enterprise (WBE) on the
contract and the payment therefor. Contractor further agrees , upon request by the Owner,
to allow and audit and/or an examination of any books, records, or files in the possession
of the Contractor that will substantiate the actual work performed by an MWE or WBE .
Any material misrepresentation of any nature will be grounds for termination of the
contract and for initiating any action under appropriate federal, state or local laws and
ordinances relating to false statements; further, any such misrepresentation may be
grounds for disqualification of Contractor at Owner's discretion for bidding on future
Contracts with the Owner for a period of time of not less than six ( 6) months.
C3-3.3 EQUAL EMPLOYMENT PROVISIONS: The Contractor shall comply with
Current City Ordinances prohibiting discrimination in employment practices. The
Contractor shall post the required notice to that effect on the project site , and at his
request, will be provided assistance by the City of Fort Worth's Equal Employment
Officer who will refer any qualified applicant he may have on file in his office to the
Contractor. Appropriate notices may be acquired from the Equal Employment Officer.
C3-3.4 WITHDRAWAL OF PROPOSALS: After a proposal has been read by the
Owner, it cannot be withdrawn by the Bidder within forty-five (45) days after the date on
which the proposals were opened .
C3-3 (I)
--
-
-
C 3-3.5 A WARD OF CONTRACT: Th e Owne r reserv es the right to withhold final
action on the proposals for a reasonable time , not to exceed forty-five (45) days after the
date of opening proposals, and in no event will an award be mad e until after
investigations have been made as to the responsibility of the proposed awardee.
The award of the contract, if award is made , will be to the lowest and best responsive
bidder.
The award of the contract shall not become effective until the Owner has notified the
Contractor in writing of such award .
C3-3.6 RETURN OF PROPOSAL SECURITIES : As soon as proposed price totals
have b_een determined for comparison of bids, the Owner may, at its discretion , return the
proposal security which accompanied the proposals which, in its judgment, would not be
considered for the award . All other proposal securities, usually those of the three lowest
bidders , will be retained by the Owner until the required contract has been executed and
bond furnished or the Owner has otherwise disposed of the bids , after which they will be
returned by the City Secretary .
C3-3 .7 BONDS: With the execution and delivery of the Contract Documents, the
Contractor shall furnish to , and file with the owner in the amounts herein required , the
following bonds :
a. PERFORMANCE BOND : A good and sufficient performance bond in
the amount of not less than 100 percent of the amount of the contract, as
evidenced by the proposal tabulation or otherwise, guaranteeing the full
and faithful execution of the work and performance of the contract, and for
the protection of the Owner and all other persons against damage by
reason of negligence of the Contractor, or improper execution of the work
or use of inferior materials. This performance bond shall guarantee the
payment for all labor, materials, equipment, supplies, and services used in
the construction of the work, and shall remain in full force and effect until
provisions as above stipulated are accomplished and final payment is made
on the project by the City .
b. MAINTENANCE BOND: A good and sufficient maintenance bond, in
the amount of not less than 100 percent of the amount of the contract, as
evidenced by the proposal tabulation or otherwise, guaranteeing the
prompt, full and faithful performance of the general guaranty which is set
forth in paragraph C8-8.10.
c. PAYMENT BOND : A good and sufficient payment bond, in the
amount of not less than 100 percent of the amount of the contract, as
evidenced by the proposal tabulation or otherwise, guaranteeing the
prompt, full and faithful payment of all claimants as defined in Article
C3-3 (2)
.-
'-.
-
-
d.
5160, Revised Civil Statutes of Texas, 1925 , as amended by House Bill
344, Acts 56 1h Legislature, Regular Session , 1959, effective April 27,
1959 , and/or the latest version thereof, supplying labor and materials in the
prosecution of the work provided for in the contract being constructed
under these specifications. Payment Bond shall remain in force until all
payments as above stipulated are made.
OTHER BONDS : Such other bonds as may be required by these
Contract Documents shall be furnished by the Contractor.
No sureties will be accepted by the Owner which are at the time in default or delinquent
on any bonds or which are interested in any litigation against the Owner. All bonds shall
be made on the forms furnished by the Owner and shall be executed by an approved
surety company doing business in the City of Fort Worth , Texas , and which is acceptable
to the Owner. In order to be acceptable , the name of the surety shall be included on the
current U .S . Treasury list of acceptable sureties, and the amount of bond written by any
one acceptable company shall not exceed the amount shown on the Treasury list for that
company . Each bond shall be properly executed by both the Contractor and Surety
Company .
Should any surety on the contract be determined unsatisfactory at any time by the Owner,
notice will be given the Contractor to that effect and the Contractor shall immediately
provide a new surety satisfactory to the Owner. No pay ment will be made under the
contract until the new surety or sureties, as required, have qualified and have been
accepted by the Owner. The contract shall not be operative nor will any payments be due
or paid until approval of the bonds by the Owner.
C3-3.8 EXECUTION OF CONTRACT: Within ten (10) days after the Owner has
appropriate resolution, or otherwise , awarded the contract, the Contractor shall execute
and file with the Owner, the Contract and such bonds as may be required in the Contract
Documents.
No Contract shall be binding upon the Owner until it has been attested by the City
Secretary , approved as to form and legality by the City Attorney, and executed for the
Owner by either the Mayor or City Manager .
C3 -3.9 FAILURE TO EXECUTE CONTRACT: The failure of the Awardee to
execute the required bond or bonds or to sign the required contract within ten (10) days
after the contract is awarded shall be considered by the owner as an abandonment of his
proposal , and the owner may annual the Award. By reason of the uncertainty of the
market prices of material and labor , and it being impracticable and difficult to accurately
determine the amount of damages occurring to the owner by reason of said awardee's
failure to execute said bonds and contract within ten ( 10) days, the proposal security
accompanying the proposal shall be the agreed amount of damages which the Owner will
C3-3 (3)
suffer by reason of such failure on the part of the Awa rdee and sh a ll thereupon
immediately by forfeited to the Owne r.
The filing of a proposal will be considered as acceptance of this provision by the Bidder.
C-3-3 .10 BEGINNING WORK: The Contractor shall not commence work until
authorized in writing to do so by the Owner. Should the Contractor fail to commence
work at the site of the project within the time stipulated in the written authorization
usually termed "Work Order" or "Proceed Order", it is agreed that the Surety Company
will , within ten (I 0) days after the commencement date set forth in such written
authorization, commence the physical execution o f the contract.
C3-3. l l INSURANCE: The Contractor shall not commence work under this
contract until he has obtained all insurance required under the Contract Documents, and
such insurance has been approved by the Owner. The prime Contractor shall be
responsible for delivering to the Owner the sub-contractor's certificate of insurance for
approval. The prime Contractor shall indicate on the certificate of insurance included in
the documents for execution whether or not his insurance covers sub-contractors. It is the
intention of the Owne r that the insurance coverage required h e rein shall include the
cov erage of all sub-contractors .
a. COMPENSATION INSURANCE: The Contractor shall maintain ,
during the life of this contract, Worker's Compensation Insurance on all of
his employ ees to be engaged in work on the project under this contract,
and for all sub-contractors. In case any class of employees engaged in
hazardous work on the project under this contract is not protected under
the Worker's Compensation Statute , the Contractor shall provide ad e quate
employe r 's general liability insurance for the protection of such of his
employee s not so protected.
b .
C.
COMPREHENSIVE GENERAL LIABILITY INSURANCE : The
Contractor Shall procure and shall maintain during the life of this contract,
Comprehensive General Liability Insurance (Public Liability and Property
Damage Insurance) in the amount not less than $500,000 covering each
occurrence on account of bodily injury, including death, and in an amount
not less than $500,000 covering each occurrence on account of property
damage with $2,000,000 umbrella policy coverage.
ADDITIONAL LIABILITY: The Contractor shall-furnish
insurance as a separate policies or by additional endorsement to one of the
above-mentioned policies, and in the amount as set forth for public
liability and property damage, the following insurance:
1. Contingent Liability (covers General Contractor's Liability for acts
of sub-contractors).
C3-3 (4)
2. Blasting, prior to any blasting being done.
3. Collapse of buildings or structures adjacent to excavation (if
excavation are performed adjacent to same).
4. Damage to underground utilities for $500,000.
5. Builder's risk (where above-ground structures are involved).
6. Contractual Liability (covers all indemnification requirements of
Contract).
d. AUTOMOBILE INSURANCE -BODILY INJURY AND PROPERTY
DAMAGE: The Contractor shall procure and maintain during the life of
this Contract, Comprehensive Automobile Liability Insurance in an
amount not less than $250,000 for injuries including accidental death to
any one person and subject to the same limit for each person an amount
not less than $500,000 on account of one accident, and automobile
property damage insurance in an amount not less than $100,000.
e.
f.
SCOPE OF INSURANCE AND SPECIAL HAZARD: The insurance
required under the above paragraphs shall provide adequate protection for
the Contractor and his sub-contractors , respectively , against damage
claims which may arise from operations under this contract, whether such
operations be by the insured or by anyone directly or indirectly employed
by him, and also against any of the following special hazards which may
be encountered in the performance of the Contract.
PROOF OF CARRIAGE OF INSURANCE: The Contractor shall furnish
the owner with satisfactory proof of coverage by insurance required in
these Contract Documents in the amounts and by carriers satisfactory to
the Owner. (Sample attached.) All insurance requirements made upon the
Contractor shall apply to the sub-contractors, should the Prime
Contractor's insurance not cover the sub-contractor's work operations.
g. LOCAL AGENT FOR INSURANCE AND BONDING: The insurance
and bonding companies with whom the Contractor's insurance and
C3-3 (5)
performance , payment, maintenance and a ll such other bond s are written ,
shall be represented by an agent or ag e nts having an office located within
the city limits of the City of Fort Worth . Tarrant County , Texas . E ach such
agent shall be a duly qualified, one upon whom authority and power to act
on behalf of the insurance and/or bonding company to negotiate and settle
with the City of Fort Worth, or any other claimant, and claims that the City
of Fort Worth or other claimant or any property owner who has be en
damaged, may have against the Contractor, insurance , and/or bonding
company . If the local insurance representati ve is not so empowered by the
insurance or bonding companies, then such authority must be vested in a
local agent or claims officer residing in th e Metropl e x, th e Fort Worth-
Dallas area . The name of the agent , or agents shall be set forth on all such
bonds and certificates of insurance.
C3-3.12 CONTRACTOR'S OBLIGATIONS: · Under the Contract, the Contractor
shall pay for all materials, labor and services when due.
C3 -3 . l3 WEEKLY PAYROLLS : A certified copy of each payroll covering payment
of wages to all persons engaged in work on the project at the site of the project shall be
furnished to the Owner 's representative within seven (7) days after the close of each
pay roll period . A copy or copies of th e applicable minimum wage rates as set forth in the
Contract Documents shall be kept posted in a conspicuous place at the site of the project
at all times during the course of the Contract. Copies of the wage rates will be furnished
the Contractor, by the Owner ; however , posting and prote ction of the wage rates shall be
the responsibility of the Contractor.
C3-3 .14 CONTRACTOR'S CONTRACT ADMINISTRATION: Any Contractor,
whether a person, persons , partnership , company, firm , association, corporation or other
who is approved to do business with and enters into a contract with the City for
construction of water and/or sanitary sewer facilities, will have or shall establish a full y
operational business office within the Fort Worth-Dallas metropolitan area. The
Contractor shall charge, delegate, or assign this office ( or he may delegate his Project
Superintendent) with full authority to transact all business actions required in the
performance of the Contract. This local authority shall be made responsible to act for the
Contractor in all matters made responsible to act for the Contractor in all matters
pertaining to the work governed by the Contract whether it be administrative or other
wise and as such shall be empowered, thus delegated and directed , to settle all material ,
labor or other expenditure, all claims against work or any other mater associated such as
maintaining adequate and appropriate insurance or security coverage for the prnject. Such
local authority for the administration of the work under the Contract shall be maintained
until all business transactions executed as part of the Contract are complete.
Should the Contractor's principal base of operations be other than in the Fort Worth-
Dallas metropolitan area, notification of the Contractor 's assignment of local authority
shall be made in writing to the Engineer in advance of any work on the project, all
C3 -3 (6)
appropriately signed and sealed , as applicable, by the Contractor's responsible offices
with the understanding that this written assignment of authority to the local representati ve
shall become part of the project Contract as though bound directly into the project
documents . The intent of these requirements is that all matters a s sociated with the
Contractor 's administration, whether it be oriented in furth e ring the work , or other, be
go verned direct by local authority. This same requirement is imposed on insurance and
surety coverage. Should the Contractor's local representative fail to perform to the
satisfaction of the Engineer, the Engineer, at his sole discretion , may demand that such
local representative be replaced and the Engineer may, at his sole discretion , stop all work
until a new local authority satisfactory to the Engineer is assigned . No credit of working
time will be allowed for periods in which work stoppage s are in effect for this reason.
C3-3.15 VENUE : Venue of any action hereinunder shall be exclusively in Tarrant
County, Texas .
C3-3 (7)
SECTION C4-4 SCOPE OF WORK
PART C -GENERAL CONDITIONS
C4-4 SCOPE OF WORK
C4-4.1 INTENT OF CONTRACT DOCUMENTS: It is the definite intention of these
Contract Documents to provide for a complete, useful project which the Contractor
undertakes to construct or furnish, all in full compliance with the requirements and intent
of the Contract Documents. It is definitely understood that the Contractor shall do all
work as provided for in the Contract Documents, shall do all extra or special work as may
be considered by the Owner as necessary to complete the project in a satisfactory and
acceptable manner. The Contractor shall, unless otherwise specifically stated in these
Contract Documents, furnish all labor, tools, materials, machinery, equipment, special
services, and incidentals necessary to the prosecution and completion of the project.
C4-4.2 SPECIAL PROVISIONS: Should any work or conditions which are not
thoroughly and satisfactorily stipulated or covered by General or Special Conditions of
these Contract Documents be anticipated, or should there be any additional proposed
work which is not covered by these Contract Documents, the "Special Provisions"
covering all such work will be prepared by the . Owner previous to the time of receiving
bids or proposals for any such work and furnished to the Bidder in the form of Addenda.
All such "Special Provisions" shall be considered to be part of the Contract Documents
just as though they were originally written therein .
C4-4.3 INCREASED OR DECREASED QUANTITIES: The Owner reserves the right
to alter the quantities of the work to be performed or to extend or shorten the
improvements at any time when and as found to be necessary , and the Contractor shall
perform the work as altered, increased or decreased at the unit prices. Such increased or
decreased quantity shall not be more than twenty-five (25) percent of the contemplated
quantity of such item or items. When such changes increase or decrease the original
quantity of any item or items of work to be done or materials to be furnished by the 25
percent or more, then either party to the contract shall upon written request to the other
party be entitled to a revised consideration upon that portion of the work above or below
the 25 percent of the original quantity stated in the proposal; such revised consideration to
be determined by special agreement or as hereinafter provided for "Extra Work." No
allowance will be made for any changes in anticipated profits not shall such changes be
considered as waiving or invalidating any conditions or provisions of the Contract
Documents.
Variations in quantities of sanitary sewer pipes in depth categories, shall be interpreted
herein as applying to overall quantities of sanitary sewer pipe in each pipe size, but not to
the various depth categories.
C4-4 (1)
-
C4-4.4 ALTERATION OF CONTRACT DOCUMENTS : By Change order, the
owner reserves th e right to make such changes in the Contract Documents and in the
character or quantities of the work as may be necessary or desirable to insure completion
in the most satisfactory manner, provided such changes do not materially alter the original
Contract Documents or change the general nature of the project as a whole. Such changes
shall not be considered as waiving or invalidating any condition or pro v ision of the
Contract Documents.
C4-4 .5 EXTRA WORK: Additional work made necessary by changes and alterations
of the Contract Documents or of quantities or for other reasons for which no prices are
provided in the Contract Documents, shall be defined as "Extra Work" and shall be
performed by the Contractor in accordance with these Contract Documents or approved
additions thereto ; provided however, that before any extra work is begun a "Change
order" shall be executed or written order issued by the Owner to do the work for
payments or credits as shall be determined by one or more combination of the following
methods:
a . Unit bid price previously approved.
b. An agreed lump sum.
c. The actual reasonable cost of (1) labor, (2) rental of equipment used on the
extra work for the time so used at Associated General Contractors of
America current equipment rental rates , (3) materials entering permanently
into the project, and ( 4) actual cost of insurance, bonds, and social security
as determined by the Owner, plus a fixed fee to be agreed upon but not to
exceed 10 percent of the actual cost of such extra work. The fixed fee is
not to include any additional profit to the Contractor for rental of
equipment owner by him and used for extra work. The fee shall be full and
complete compensation to cover the cost of superintendence, overhead,
other profit, general and all other expense not included in (1), (2), (3), and
(4) above. The Contractor shall keep accurate cost records on the form and
in the method suggested by the Owner and shall give the Owner access to
all accounts, bills, vouchers, and records relating to the Extra Work.
No "Change Order" shall become effective until it has been approved and signed by each
of the Contracting Parties.
No claim for Extra Work of any kind will be allowed unless ordered in writing by the
Owner. In case any orders or instructions, either oral or written, appear to the Contractor
to involve Extra Work for which he should receive compensation, he shall make written
request to the Engineer for written orders authorizing such Extra Work, prior to beginning
such work.
C4-4 (2)
-
Should a diffe ren ce arise as to what do es or dose not con sti t ut e Ex tra Work , o r as to th e
payment thereof, and the Engineer insists upon its perform a nce , the Contractor shall
proceed with the work afte r making written request for w ritte n orders and shall keep
accurate account of the actual reasonable cost thereof as provided under method (Item C).
Claims for extra work will not be paid unless the Contractor sha ll file his cl a im with the
Owner within five (5) days before the time for making th e fir st es timate a ft er such work is
done and unless the claim is supported by satisfactory vouche rs and certifi ed payrolls
covering all labor and materials expended upon said Ex tra Work.
The Contractor shall furnish the Owner such insta llation record s of all dev iations from
the original Contract Documents as may be necessary to enable the Owner to prepare for
permanent record a corrected set of plans showing th e actua l in s ta llation.
The compensation agreed upon for "Extra Work" whether or not initiated by a "Change
Order" shall be a full, complete and final payment for all costs Contractor incurs as a
result or relating to the change or extra work, whether said costs are known , unknown ,
foreseen or unforeseen at that time, including without limitation, any costs for delay ,
extended overhead , ripple or impact cost, or any other effect on changed or unchanged
work as a result of the change or extra work.
C4-4.6 SCHEDULE OF OPERATION : Before comme ncing any work under this
contract, the Contractor shall submit to the Owner and rece ive the Owner 's approval
thereof, a "Schedule of Operations," showing by a strai g ht line method the date of
commencing and finishing each of the major elements of th e Contract. There s hall be also
shown the estimated monthly cost of work for which estimates a re to be expected. There
shall be presented also a composite graph showing the anticipated progress of
construction with the time being plotted horizonta ll y and pe rcentage of completion
plotted vertically . The progress charts shall be prepared on 8-1/2 " x 11 " sheets and at
least five black or blue line prints shall be furnished to the O w ne r.
C4-4.7 PROGRESS SCHEDULES FOR WATER AND SE WER PLANT FACILITIES :
Within ten (10) days prior to submission of the first monthly progress payment , the
Contractor shall prepare and submit to the owner for approv al six copies of the schedule
in which the Contractor proposes to carry on activities (including procurement of
materials , plans, and equipment) and the contemplated dates for completing the same.
The schedule shall be in the form of a time schedule Critical Path Method (CPM)
network diagram. As the work progresses, the Contractor shall enter on the diagram the
actual progress at the end of each partial payment period or at such intervals as directed
by the Engineer. The Contractor shall also revise the schedule to reflect any adjustments
in contract time approved by the Engineer. Three copies of the updated schedule shall be
delivered at such intervals as directed by the Engineer.
As a minimum, the construction schedule shall incorporate all work elements and
activities indicated in the proposal and in the technical specifications .
C4-4 (3)
...
. ..
...
' .
Prior to the final drafting of the detailed construction schedule , the Contractor shall
review the draft schedule with the Engineer to ensure the Contractor's understanding of
the contract requirements .
The following guidelines shall be adhered to in preparing the construction schedule :
a . Milestone dates and final project completion dates shall be developed to
conform to the time constraints, sequencing requirements and completion
time.
b. The construction progress shall be divided into act1v1tles with time
durations of approximately fourteen days (14) days and construction
values not to exceed $50,000. Fabrication, delivery and submittal activities
are exceptions to this guideline .
C. Durations shall be in calendar days and normal holidays and weather
conditions over the duration of the contract shall be accounted for within
the duration of each activity .
d. One critical path shall be shown on the construction schedule.
e. Float time is defined as the amount of time between the earliest start date
and the latest start date of a chain of activities of the CPM construction
schedule. Float time is not for the exclusive use or benefit of either the
Contractor or the Owner.
f. Thirty days shall be used for submittal review unless otherwise specified.
The construction schedule shall as a minimum, be divided into general categories as
indicated in the Proposal and Technical Specifications and each general category shall be
broken down into activities in enough detail to achieve activities of approximately
fourteen (14) days duration.
For each general category, the construction schedule shall identify all trades or
subcontracts whose work is represented by activities that follow the guidelines of this
Section .
For each of the trades or subcontracts, the construction schedule shall indicate the
following procurements, construction and preacceptance activities and events in their
logical sequence for equipment and materials.
1. Preparation and transmittal of submittals
2. Submittal review periods .
C4-4 (4)
' ' . -
L.
.. '
..
'
3 . Shop fabrication and delivery .
4. Erection or installation.
5 . Transmittal of manufacturer's operation and maintenance instructions.
6. Installed equipment and materials testing.
7. Owner's operator instruction (if applicable).
8. Final inspection.
9 . Operational testing.
If, in the opinion of the Owner, work accomplished falls behind that scheduled, the
Contractor shall take such action as necessary to improve his progress. In addition, the
Owner may require the Contractor to submit a revised schedule demonstrating his
program and proposed plan to make up lag in scheduled progress and to insure
completion of the work within the contract time. If the owner finds the proposed plan not
acceptable, he may require the Contractor to increase the work force, the construction
plant and equipment, the number of work shifts or overtime operations without additional
cost to the Owner.
Failure of the Contractor to comply with these requirements shall be considered grounds
for determination by the Owner that the Contractor is failing to prosecute the work with
diligence as will insure its completion within the time specified .
C4-4 (5)
-
.....
......
-
PART C -GENERAL CONDITIONS
CS-5 CONTROL OF WORK AND
MATERIALS
SECTION CS-5 CONTROL OF WORK AND MATERIALS
CS-5.1 AUTHORITY OF ENGINEER: The work shall be performed to the
satisfaction of the Engineer and in strict compliance with the Contract Documents. The
Engineer shall decide all questions which arise as to the quality and acceptability of the
materials furnished, work performed, rate of progress of the work, overall sequence of the
construction, interpretation of the Contract Documents, acceptable fulfillment of the
Contract, compensation, mutual rights between Contractor and Owner under these
Contract Documents, supervision of the work, resumption of operations, and all other
questions or disputes which may arise . Engineer will not be responsible for Contractor's
means, methods, techniques, sequence or procedures of construction, or the safety
precaution and programs incident thereto, and he will not be responsible for Contractor's
failure to perform the work in accordance with the contract documents.
The .Engineer shall determine the amount and quality of the work completed and
materials furnished, and his decisions and estimates shall be final. His estimates in such
event shall be a condition to the right of the Contractor to receive money due him under
the Contract. The Owner shall have executive authority to enforce and make effective
such necessary decisions and orders as the Contractor fails to carry out promptly.
In the event of any dispute between the Engineer and Contractor over the decision of the
Engineer on any such matters, the Engineer must, within a reasonable time, upon written
request of the Contractor, render and deliver to both the owner and Contractor, a written
decision on the matter in controversy.
CS-5.2 CONFORMITY WITH PLANS: The finished project in all cases shall
conform with lines, grades, cross-sections, finish, and dimensions shown on the plans or
any other requirements other wise described in the Contract Documents. Any deviation
from the approved Contract Documents required by the Engineer during construction will
in all cases be determined by the Engineer and authorized by the Owner by Change Order.
CS-5.3 COORDINATION OF CONTRACT DOCUMENTS: The Contract
Documents are made up of several sections, which, taken together, are iRtended to
describe and provide for a complete and useful project, and any requirements appearing in
one of the sections is as binding as though it occurred in all sections. In case of
discrepancies, figured dimension shall govern over scaled dimensions, plans shall govern
over specifications, special conditions shall govern over general conditions and standard
specification, and quantities shown on the plans shall govern over those shown in the
proposal. The Contractor shall not take advantage of any apparent error or omission in the
CS-5 (1)
-
-
.....
-
-
Contract Documents, and the owner shall be permitted to make such corrections or
interpretations as may be deemed necessary for fulfillment of the intent of the Contract
Documents. In the event the Contractor discovers an apparent error or discrepancy, he
shall immediately call this condition to the attention of the Engineer. In the event of a
conflict in drawings, specifications, or other portions of the Contract Documents which
were not reported prior to the award of Contract, the Contractor shall be deemed to have
quoted the most expensive resolution of the conflict.
CS-5.4 COOPERATION OF CONTRACTOR: The Contractor will be furnished
with three sets of Contract Documents and shall have available on the site of the project
at all times, one set of such Contract Documents.
The Contractor shall give to the work the constant attention necessary to facilitate the
progress thereof and shall cooperate with the Engineer, his inspector, and other
Contractors in every possible way.
The Contractor shall at all times have competent personnel available to the project site for
proper performance of the work. The Contractor shall provide and maintain at all times at
the site of the project a competent, English-speaking superintendent and an assistant who
are fully authorized to act as the Contractor's agent on the work. Such superintendent and
his assistant shall be capable of reading and understanding the Contract Documents and
shall receive and fulfill instructions from the Owner, the Engineer, or his authorized
representatives. Pursuant to this responsibility of the Contractor, the Contractor shall
designate in writing to the project superintendent, to act as the Contractor's agent on the
work. Such assistant project superintendent shall be a resident of Tarrant County, Texas,
and shall be subject to call, as is the project superintendent, at any time of the day or night
on any day of the week on which the Engineer determines that circumstances require the
presence on the project site of a representative of the Contractor to adequately provide for
the safety or convenience of the traveling public or the owners of property across which
the project extends or the safety of the property contiguous to the project routing.
The Contractor shall provide all facilities to enable the Engineer and his inspector to
examine and inspect the workmanship and materials entering into the work.
CS-5.5 EMERGENCY AND/OR RECTIFICATION WORK: When, in the opinion
of the Owner or Engineer, a condition of emergency exists related to any part of the work,
the Contractor, or the Contractor through his designated representative, shall respond
with dispatch to a verbal request made by the Owner or Engineer to alleviate the
emergency condition. Such a response shall occur day or night, whether the-project is
scheduled on a calendar-day or a working-day basis .
Should the Contractor fail to respond to a request from the Engineer to rectify any
discrepancies, omissions, or correction necessary to conform with the requirements of the
project specifications or plans, the Engineer shall give the Contractor written notice that
such work or changes are to be performed. The written notice shall direct attention to the
CS-5 (2)
-
.....
....
-
....
discrepant condition and request the Contractor to take remedial action to correct the
condition. In the event the Contractor does not take positi ve steps to fulfill this written
request, or does not shoe just cause for not taking the proper action, within 24 hours , the
City may take such remedial action with City forces or by contract. The City shall deduct
an amount equal to the entire costs for such remedial action , plus 25%, from any funds
due the Contractor on the project.
CS-5.6 FIELD OFFICE: The Contractor shall provide, at no extra compensation, an
adequate field office for use of the Engineer, if specifically called for. The field office
shall be not less than 10 x 14 feet in floor area, substantial! y constructed, well heated, air
conditioned , lighted , and weather proof, so that documents will not be damaged by the
elements.
CS-5.7 CONTRUCTION STAKES: The City, through its Engineer, will furnish
the Contractor with all lines, grades, and measurements necessary to the proper
prosecution and control of the work contracted under these Contract Documents, and
lines, grades and measurements will be established by means of stakes or other customary
method of marking as may be found consistent with good practice .
These stakes or markings shall be set sufficiently in advance of construction operations to
avoid delay. Such stakes or markings as may be established for Contractor's use or
guidance shall be preserved by the Contractor until he is authorized by the Engineer to
remove them . Whenever , in the opinion of the Engineer, any stakes or markings have
been carelessly or willfully destroyed, disturbed, or removed by the Contractor or any of
his employees, the full cost of replacing such stakes or marks plus 25% will be charged
against the Contractor, and the full amount will be deducted from payment due the
Contractor.
CS-5.8 AUTHORITY AND DUTIES OF CITY INSPECTOR: City Inspectors will
be authorized to inspect all work done and to be done and all materials furnished. Such
inspection may extend to all or any part of the work, and the preparation or manufacturing
of the materials to be used or equipment to be installed. A City Inspector may be
stationed on the work to report to the Engineer as to the progress of the work and the
manner in which it is being performed, to report any evidence that the materials being
furnished or the work being performed by the Contractor fails to fulfill the requirements
of the Contract Documents, and to call the attention of the Contractor to any such failure
or other infringements. Such inspection or lack of inspection will not relieve the
Contractor from any obligation to perform the work in accordance with the requirements
of the Contract Documents. In case of any dispute arising between the Contractor and the
City Inspector as to the materials or equipment furnished or the manner of performing the
work, the City Inspector will have the authority to reject materials or equipment, and/or to
suspend work until the question at issue can be referred to and decided by the Engineer.
The City Inspector will not, however, be authorized to revoke, alter, enlarge, or release
any requirement of these Contract Documents, nor to approve or accept any portion or
section of the work, nor to issue any instructions contrary tot he requirement s of the
CS-5 (3)
-
-
-
»
-
Contract Documents. The City Inspector will in no case act as superintendent or foreman
or perform any other duties for the Contractor, or interfere with the management or
operation of the work. He will not accept from the Contractor any compensation in any
form for performing any duties. The Contractor shall regard and obey the directions and
instructions of the City Inspector or Engineer when the same are consistent with the
obligations of the Contract Documents of the Contract Documents , provided, however,
should the Contractor object to any orders or instructions or the City Inspector, the
Contractor may within six days make written appeal to the Engineer for his decision on
the matter in Controversy.
CS-5.9 INSPECTION: The Contractor shall furnish the Engineer with every
reasonable facility for ascertaining whether or not the work as performed is in accordance
with the requirements of the Contract Documents. If the Engineer so requests, the
Contractor shall, at any time before acceptance of the work, remove or uncover such
portion of the finished work as may be directed. After examination, the Contractor shall
restore said portions of the work to the standard required by the Contract Documents .
Should the work exposed or examined prove acceptable, the uncovering or removing and
replacing of the covering or making good of the parts removed shall be paid for as extra
work, but should Work so exposed or examined prove to be unacceptable, the uncovering
or removing and replacing of all adjacent defective or damaged parts shall be at the
Contractor's expense . No work shall be done or materials used without suitable
supervision or inspection .
CS-5 .10 REMOVAL OF EDEFCTIVE AND UNAUTHORIZED WORK:All work,
materials , or equipment which has been rejected shall be remedied or removed and
replaced in an acceptable manner by the Contractor at this expense. Work done beyond
the lines and grades given or as shown on the plans , except as herein specially provided ,
or any Extra Work done without written authority, will be considered as unauthorized and
done at the expense of the Contractor and will not be paid for by the Owner. Work so
done may be ordered removed at the Contractor's expense. Upon the failure on the part of
the Contractor to comply with any order of the Engineer made under the provisions of
this paragraph, the Engineer will have the authority to cause defective work to be
remedied or removed and replaced and unauthorized work to be removed, and the cost
thereof may be deducted from any money due or to become due tot he Contractor. Failure
to require the removal of any defective or unauthorized work shall not constitute
acceptance of such work.
CS-5.11 SUBSTITUTE MATERIALS OR EQUIPMENT: If the Speeifications,
law, ordinance, codes or regulations permit Contractor to furnish or use a substitute that is
equal to any material or equipment specified, and if Contractor wishes to furnish or use a
proposed substitute, he shall, prior to the preconstruction conference, make written
application to ENGINEER for approval of such substitute certifying in writing that the
proposed substitute will perform adequately the function called for by the general design,
be similar and of equal substance to that specified and be suited to the same use and
CS-5 (4)
-
-
-
-
.-
-
-
-
capable of performing the same function as that specified ; and identifying all variations
of the proposed substitute from that specified and indicating available maintenance
service . No substitute shall be ordered or installed without written approval of Engineer
who will be the judge of the equality and may require Contractor to furnish such other
data about the proposed substitute as he considers pertinent. No substitute shall be
ordered or installed without such performance guarantee and bonds as Owner may require
which shall be furnished at Contractor's expense. Contractor shall indemnify and hold
harmless Owner and Engineer and anyone directly or indirectly employees by either of
them from and against the claims, damages, losses and expenses (including attorneys
fees) arising out of the use of substituted materials or equipment.
C5-5.l2 SAMPLES AND TESTS OF MATERIALS: Where, in the opinion of the
Engineer, or as called for in the Contract Documents, tests of materials or e9uipment are
necessary , such tests will be made at the expense of and paid for direct to the testing
agency by the Owner unless other wise specifically provided . The failure of the Owner to
make any tests of materials shall in no way relieve the contractor of his responsibility of
furnishing materials and equipment fully conforming to the requirements of the Contract
Documents. Tests and sampling of materials, unless otherwise specified , will be made in
accordance with the latest methods prescribed by the American Society for Testing
Materials or specific requirements of the Owner. The Contractor shall provide such
facilities as the Engineer may require for collecting and forwarding samples and shall not,
without specific written permission of the Engineer, use materials represented by the
samples until tests have been made and the materials approved for use . The Contractor
will furnish adequate samples without charge to the Owner.
In case of concrete, the aggregates, design minimum, and the mixing and transporting
equipment shall be approved by the Engineer before any concrete is placed , and the
Contractor shall be responsible for replacing any concrete which does not meet the
requirements of the Contract Documents. Tests shall be made at least 9 days prior to the
placing of concrete , using samples from the same aggregate, cement, and mortar which
are to be used later in the concrete. Should the source of supply change, new tests shall be
made prior to the use of new materials.
C5-5.13 STORAGE OF MATERIALS : All materials which are to be used in the
construction contract shall be stored so as to insure the preservation of quality and fitness
of the work. When directed by the Engineer, they shall be placed on wooden platforms or
other hard, clean durable surfaces and not on the ground, and shall be placed under cover
when directed. Stored materials shall be placed and located so as to facilitate prompt
inspection.
C5-5.14 EXISTING STRUCTURES AND UTILITIES: The location and dimensions
shown on the plans relative to the existing utilities are based on the best information
available. Omission from, the inclusion of utility locations on the Plans is not to be
considered as nonexistence of, or a definite location of, existing underground utilities.
The location of many gas mains, water mains, conduits, sewer lines and service lines for
C5 -5 (5)
-
-
...
all utilities, etc., is unknown to the Owner, and the Owner assumes no responsibility for
failure to show any or all such structures and utilities on the plans or to show them in
their exact location. It is mutually agreed that such failure will not be considered
sufficient basis for claims for additional compensation for Extra Work or for increasing
the pay quantities in any manner whatsoever, unless an obstruction encountered is such as
to necessitate changes in the lines and grades of considerable magnitude or requires the
building of special works, provision of which is not made in these Contract Documents,
in which case the provision in these Contract Documents for Extra Work shall apply .
It shall be the Contractor's responsibility to verify locations of the adjacent and/or
conflicting utilities sufficiently in advance of construction in order that he may negotiate
such local adjustments as necessary in the construction process to provide adequate
clearances. The Contractor shall take all necessary precautions in order to protect all
existing utilities, structures, and service lines. Verification of existing utilities, structures,
and service lines shall include notification of all utility companies at least forty-eight ( 48)
hours in advance of construction including exploratory excavation if necessary. All
verification of utilities and their adjustment shall be considered subsidiary work.
CS-5.15 INTERRUPTION OF SERVICE:
a. Normal Prosecution: In the normal prosecution of work where the
interruption of service is necessary, the Contractor, at least 24 hours in
advance, shall be required to:
1. Notify the Water Department's Distribution Division as to
location, time, and schedule of service interruption .
2. Notify each customer personally through responsible personnel as
to the time and schedule of the interruption of their service, or
3. In the event that personal notification of a customer cannot be
made, a prepared tag form shall be attached to the customer's door
knob. The tag shall be durable in composition, and in large bold
letters shall say:
CS-5 (6)
....
-
-
-
-
-
-
-
"NOTICE"
Due to Utility Improvement in your neighborhood, your
(water) (sewer) service will be interrupted on ____ _
between the hours of and ----
This inconvenience will be as short as possible .
Thank You ,
Contractor
Address Phone
b. Emergency: In the event that an unforeseen service interruption occurs,
notice shall be as above, but immediate.
CS-5.16 MUTUAL RESPONSIBILITY OF CONTRACTORS: If, through act or
neglect on the part of the Contractor, or any other Contractor or any sub-contractor shall
suffer loss or damage of the work , the Contractor agrees to settle with such other
Contractor or sub-contractor by agreement or arbitration. If such other Contractor or sub-
contractor shall assert any claim against the owner on account of damage alleged to have
been sustained, the owner will notify the Contractor, who shall indemnify and save
harmless the owner against any such claim .
C5-5. l 7 CLEAN-UP : Clean-up of surplus and/or waste materials accumulated on
the job site during the prosecution of the work under these Contract Documents shall be
accomplished in keeping with a daily routine established to the satisfaction of the
Engineer. Twenty-four (24) hours after written notice is given the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the Engineer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct
action as the Engineer deems appropriate to correct the clean-up deficiencies cited to the
Contractor in the written notice, and the costs of such direct action, plus 25 % of such
costs, shall be deducted from the monies due or to become due to the Contractor.
Upon the completion of the project as a whole as covered by these Contract Documents,
and before final acceptance and final payment will be made, the Contractor shall clean
and remove from the site of the project all surplus and discarded materials , temporary
structures, and debris of every kind. He shall leave the site of all work in 11 neat and
orderly condition equal to that which originally existed. Surplus and waste materials
removed from the site of the work shall be disposed of at locations satisfactory to the
Engineer. The Contractor shall thoroughly clean all equipment and materials installed by
him and shall deliver over such materials and equipment in a bright, clean, polished and
new appearing condition. No extra compensation will be made to the Contractor for any
clean-up required on the project.
C5-5 (7)
,.--4,
-
-
.-
C5-5.18 FINAL INSPECTION: Whenever the work provided for in and
contemplated under the Contract Documents has been satisfactorily completed and final
clean-up performed, the Engineer will notify the proper officials of the Owner and request
that a Final Inspection be made . Such inspection will be made within l O days after such
notification. After such final inspection, if the work and materials and equipment are
found satisfactory, the Contractor will be notified in writing of the acceptance of the same
after the proper resolution has been passed by the City Council. No time charge will be
made against the Contractor between said date of notification of the Engineer and the date
of final inspection of the work.
C5-5 (8)
-
PART C -GENERAL CONDITIONS
C6-6 LEGAL RELATIONS AND PUBLIC
RESPONSIBILITY
SECTION C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY
C6-6.1 LAWS TO BE OBSERVED:The Contractor shall at all times observe and
comply with all Federal and State Laws and City ordinances and regulations which in any
way affect the conduct of the work or his operations, and shall observe and comply with
all orders , laws, ordinances and regulations which exist or which may be enacted later by
bodies having jurisdiction or authority for such enactment. No plea or misunderstanding
or ignorance thereof will be considered . The Contractor and his Sureties shall indemnify
and save harmless the City and all of its o_fficers, agents, and employees against any and
all claims or liability arising from or based on the violation of any such law, ordinance,
regulation, or order, whether it be by himself or his employees .
C6-6 .2 PERMITS AND LICENSES: The Contractor shall procure all permits and
licenses, pay all charges, costs and fees , and give all notices necessary and incident to the
due and lawful prosecution of the work.
C6-6 .3 PATENTED DEVICES, MATERIALS, AND PROCESSES: If the Contractor
is required or desires to use any design, device, material, or process covered by letter,
patent, or copyright, he shall provide for such use by suitable legal agreement with the
patentee or owner of such patent, letter, or copyrighted design. It is mutually agreed and
understood that without exception the contract price shall include all royalties or cost
arising from patents , trademarks, and copyrights in any way involved in the work. The
Contractor and his sureties shall indemnify and save harmless the Owner from any and all
claims for infringement by reason of the use of any such trade-mark or copyright in
connection with the work agreed ·to be performed under these Contract Documents , and
shall indemnify the Owner for any cost, expense, or damage which it may be obliged to
pay by reason of such infringement at any time during the prosecution of the work or after
completion of the work, provided, however, that the Owner will assume the responsibility
to defend any and all suits brought for the infringement of any patent claimed to be
infringed upon the design, type of construction or material or equipment specified in the
Contract Documents furnished the Contractor by the Owner, and to hold the Contractor
harmless on account of such suits.
C6-6.4 SANITARY PROVISIONS: The Contractor shall establish and enforce
among his employees such regulations in regard to cleanliness and disposal -of garbage
and waste as will tend to prevent the inception and spread of infectious or contagious
diseases and to effectively prevent the creation of a nuisance about the work on any
property either public or private, and such regulations as are required by Law shall be put
into immediate force and effect by the Contractor. The necessary sanitary conveniences
for use of laborers on the work, properly secluded from public observation, shall be
constructed and maintained by the Contractor and their use shall be strictly enforced by
C6-6(1)
....
the Contractor. All such facilities shall be kept in a clean and sanitary condition , free from
objectionable odors so as not to cause a nuisance. All sanitary laws and regulations of the
State of Texas and the City shall be strictly complied with.
C6-6.5 PUBLIC SAFETY AND CONVENIENCE: Materials or equipment
stored about the work shall be placed and used , and the work shall at all times be so
conducted, as to cause no greater obstruction or inconvenience to the public than is
considered to be absolutely necessary by the Engineer. The Contractor is required to
maintain at all times all phases of his work in such a manner as not to impair the safety or
convenience of the public, including , but not limited to , safe and convenient ingress and
egress to the property contiguous tot he work area . The Contractor shall make adequate
provisions to render reasonable ingress and egress for normal vehicular traffic, except
during actual trenching or pipe iI).stallation operations, at all driveway crossings. Such
provisions may include bridging, placement or crushed stone or gravel or such other
means of providing proper ingress and egress for the property served by the driveway as
the Engineer may approve as appropriate. Such other means may include the diversion of
driveway traffic, with specific approval by the Engineer, If diversion of traffic is
approved by the Engineer at any location, the Contractor may make arrangements
satisfactory to the Engineer for the diversion of traffic , and shall , at his expense, provide
all materials and perform all work necessary for the construction and maintenance of
roadways and bridges for such diversion of traffic . Sidewalks must not be obstructed
except by special permission of the Engineer.
The materials excavated and the construction materials such as pipe used in construction
of the work shall be placed so as not to endanger the work or prevent free access to all
fire hydrants, fire alarm boxes, police call boxes, water valves , gas valves, or manholes in
the vicinity . The Owner reserves the right to remedy any neglect on the part · of the
Contractor as regards to public convenience and safety which may come to its attention,
after twenty-four hours notice in writing to the Contractor, save in cases of emergency
when it shall have the right to remedy any neglect without notice, and in either case, the
cost of such work or materials furnished by the Owner or by the City shall be deducted
from the monies due or to become due to the Contractor.
The Contractor, after approval of the Engineer, shall notify the Fire Department
Headquarters, Traffic Engineer, and Police Department, when any street or alley is
requested to be closed or obstructed or any fire hydrant is to be made inaccessible, and
when so directed by the Engineer, shall keep any street, streets, or highways in condition
for unobstructed use by fire apparatus. The Contractor shall promptly notify the Fire
Department Headquarters when all such obstructed streets, alleys, or hydrants-are placed
back in service.
Where the Contractor is required to construct temporary bridges or make other
arrangements for crossing over ditches or streams, his responsibility for accidents in
connection with such crossings shall include the roadway approaches as well as the
structures of such crossings.
C6-6(2)
-
-
The Contractor shall at all times conduct his operation and use of construction machinery
so as not to damage or destroy trees and scrubs located in close proximity to or on the site
of the work. Wherever any such damage may be done, the Contractor shall immediately
satisfy all claims of property owners, and no payment will be made by the Owner in
settlement of such claims. The Contractor shall file with the Engineer a written statement
showing all such claims adjusted .
C6-6.6 PRIVILEGES OF CONTRACTOR IN STREETS, ALLEYS, AND
RIGHT-OF-WAY: For the performance of the contract, the Contractor will be
permitted to use and occupy such portions of the public streets and alleys, or other public
places or other rights-of-way as provided for in the ordinances of the City, as shown in
the Contract Documents, ~r as may be specifically authorized in writing by the Engineer.
A reasonable amount of tools, materials, and equipment for construction purposes may be
stored in such space, but no more than is necessary to avoid delay in the construction
operations. Excavated and waste materials shall be piled or staked in such a way as not to
interfere with the use of spaces that may be designated to be left free and unobstructed
and so as not to inconvenience occupants of adjacent property. If the street is occupied by
railroad tracks , the work shall be carried on in such manner as not to interfere with the
operation of trains, loading or unloading of cars, etc. Other contractors of the Owner may,
for all purposes required by the contract, enter upon the work and premises used by the
Contractor and shall be provided all reasonable facilities and assistance for the
completion of adjoining work. Any additional grounds desired by the Contractor for his
use shall be provided by him at his own cost and expense.
C6-6. 7 RAILWAY CROSSINGS: When the work encroaches upon any right-of-way
of any railroad, the City will secure the necessary easement for the work. Where the
railroad tracks are to be crossed, the Contractor shall observe all the regulations and
instructions of the railroad company as to the methods of performing the work and take
all precautions for the safety of property and the public . Negotiations with the railway
companies for the permits shall be done by and through the City. The Contractor shall
give the City Notice not less than five days prior to the time of his intentions to begin
work on that portion of the project which is related to the railway properties . The
Contractor will not be given extra compensation for such railway crossings unless
specifically set forth in the Contract Documents.
C6-6.8 BARRICADES, WARNINGS AND WATCHMEN: Where the work is
carried on in or adjacent to any street, alley, or public place, the Contractor shall at his
own expense furnish, erect, and maintain such barricades, fences, lights, and danger
signals, shall provide such watchman, and shall take all such other precautionary
measures for the protection of persons or property and of the work as are necessary.
Barricades and fences shall be painted in a color that will be visible at night. From sunset
to sunrise the Contractor shall furnish and maintain at least one easily visible burning
light at each barricade. A sufficient number of barricades shall be erected and maintained
to keep pedestrians away from, and vehicles from being driven on or into, any work under
C6-6(3)
......
.-
construction or being maintained . The Contractor shall furnish watchmen and keep them
at their respective assignments in sufficient numbers to protect the work and prevent
accident or damage .
All installations and procedures shall be consistent with provisions set forth in the "1980
Texas Manual on Uniform Traffic Control Devices for Streets and Highways" issued
under the authority of the "State of Texas Uniform Act Regulating Traffic on Highways",
codified as Article 6701d Veron's Civil Statues , pertinent section being Section Nos. 27 ,
29, 30 and 31.
The Contractor will not remove any regulatory sign, instructional sign, street name sign,
or other sign which has been erected by the City . If it is determined that a sign must be
removed to permit required construction, the Contractor shall contact the Transportation
and Public Works Department, Signs and Markings Division (phone number 871-8075),
to remove the sign. In case of regulatory signs , the Contractor must replace the permanent
sign with a temporary sign meeting the requirements of the above referred manual and
such temporary sign must be installed prior to the removal of the permanent sign. If the
temporary sign is not installed correctly or if it does not meet the required specifications,
the permanent sign shall be left in place until the temporary sign requirements are met.
When construction work is completed to the extent that the permanent sign can be re-
installed, the Contractor shall again contact the Signs and Markings Division to re-install
the permanent sign and shall leave his temporary sign in place until such re-installation is
completed.
The Contractor will be held responsible foe all damage to the work or the public due to
failure of barricades, signs , fences, lights, or watchmen to protect them . Whenever
evidence is found of such damage to the work the Engineer may order the damaged
portion immediately removed and replaced by the Contractor at the Contractor's own
expense. The Contractor's responsibility for the maintenance of barricades, signs, fences
and lights, and for ·providing watchmen shall not cease until the project shall have been
completed and accepted by the Owner.
No compensation, except as specifically provided in these Contract Documents, will be
paid to the Contractor for the Work and materials involved in the constructing, providing ,
and maintaining of barricades , signs, fences, and lights or salaries of watchmen, for the
subsequent removal and disposal of such barricades, signs , or for any other incidentals
necessary for the proper protection , safety, and convenience of the public during the
contract period, as this work is considered to be subsidiary to the several items for which
unit or lump sum prices are requested in the Proposal.
C6-6 .9 USE OF EXPLOSIVES, DROP WEIGHT, ETC.: Should the Contractor elect to
use explosives, drop weight, etc ., in the prosecution of the work, the utmost care shall be
exercised at all times so as not to endanger life or property. The Contractor shall notify
the proper representative of any public service corporation, any company, individual, or
utility, and the Owner, not less than twenty-four hours in advance of the use of any
C6-6(4)
-
-. ,
activity which might damage or endanger their or his property along or adjacent to the
work.
Where the use of explosives is to be permitted on the project , as specified in the Special
Conditions Documents, or the use of explosives is requested , the Contractor shall submit
notice to the Engineer in writing twenty-four hours prior to commencing and shall furnish
evidence that he has insurance coverage to protect against any damages and/or injuries
arising out of such use of explosives.
C6-6. l0 WORK WITHIN EASEMENTS: Where the work passes over, through , or into
private property, the Owner will provide such right-of-way or easement privileges, as the
City may deem necessary for the prosecution of the work. Any additional rights-of-way or
work ar~a considered necessary by the Contractor shall be provided by him at his
expense. Such additional rights-of-way or work area shall be acquired for the benefit of
the City . The City shall be notified in writing as to the rights so acquired before work
begins in the affected area . The Contractor shall not enter upon private property for any
purpose without having previously obtained permission from the owner of such property.
The Contractor will not be allowed to store equipment or material on private property
unless and until the specified approval of the property owner has been secured in writing
by the Contractor and a copy furnished to the Engineer. Unless specifically provided
otherwise, the Contractor shall clear all rights-of-way or easements of obstructions which
must be removed to make possible proper prosecution of the work as a part of the project
construction operations. The Contractor shall be responsible for the preservation of and
shall use every precaution to prevent damage to , all tress , shrubbery, plants, lawns,
fences, culverts , curbing , and all other types of structures or improvements , to all water,
sewer, and gas lines, to all conduits , overhead pole lines , or appurtenances thereof,
including the construction of temporary fences and to all other public or private property
adjacent to the work.
The Contractor shall notify the proper representatives of the owners or occupants of the
public or private lands of interest in lands which might be affected by the work. Such
notice shall be made at least 48 hours in advance of the beginning of the work. Notices
shall be applicable to both public and private utility companies or any corporation,
company, individual, or other, either as owners or occupants, whose land or interest in
land might be affected by the work. The Contractor shall be responsible for all damage or
injury to property of any character resulting from any act, omission, neglect, or
misconduct in the manner or method or execution of the work, or at any time due to
defective work, material, or equipment.
When and where any direct or indirect or injury is done to public or private property on
account of any act, omission, neglect, or misconduct in the execution of the work, or in
consequence of non-execution thereof on the part of the Contractor, he shall restore or
have restored as his cost and expense such property to a condition at least equal to that
existing before such damage or injury was done, by repairing, rebuilding, or otherwise
C6-6(5)
--
-
-
-
.....
-
replacing and restoring as may be directed by the Owner, or he shall make good such
damages or injury in a manner acceptable to the owner of the property and the Engineer.
All fences encountered and removed during construction of this project shall be restored
to the original or a better than original condition upon completion of this project. When
wire fencing, either wire mesh or barbed wire is to be crossed, the Contractor shall set
cross brace posts on either side of the permanent easement before the fence is cut. Should
additional fence cuts be necessary, the Contractor shall provide cross-braced posts at the
point of the proposed cut in addition to the cross braced posts provided at the permarnmt
easements limits, before the fence is cut.
Temporary fencing shall be erected in place of the fencing removed whenever the work is
~ot in progress and when the site is vacated overnight, and /or at all times to prevent
livestock from entering the construction area. The cost for fence removal, temporary
closures and replacement shall be subsidiary to the various items bid in the project
proposal. Therefore, no separate payment shall be allowed for any service associated with
this work .
In case of failure on the part of the Contractor to restore such property or to make good
such damage or injury, the Owner may, upon 48 hour written notice under ordinary
circumstances, and without notice when a nuisance or hazardous condition results,
proceed to repair, rebuild, or otherwise restore such property as may be determined by the
Owner to be necessary, and the cost thereby will be deducted from any monies due to or
to become due to the Contractor under this contract.
C6.6.11 INDEPENDENT CONTRACTOR: It is understood and agreed by the
parties hereto that the Contractor shall perform all work and services hereunder as an
independent contractor, and not as an officer, agent, servant, or employee of the Owner.
Contractor shall have exclusive control of and exclusive right to control the details of all
work and services performed hereunder, and all persons performing the same, and shall
be solely responsible for the acts and omissions of its officers, agents, servants,
employees, contractor, subcontractors, licensees and invitees. The doctrine of respondeat
superior shall not apply as between Owner and Contractor, its officers, agents, employees,
contractors and subcontractors, and nothing herein shall be construed as creating a
partnership or joint enterprise between Owner and Contractor.
C6-6.12 CONTRACTOR'S RESPONSIBILITY FOR DAMAGE CLAIMS: Contractor
covenants and agrees to, and does hereby indemnify, hold harmless and defend Owner, its
officers, agents, servants, and employees from and against any and all claims or suits for
property damage or loss and/or personal injury, including death, to any and all persons, of
whatsoever kind or character, whether real or asserted, arising out of or in connection
with, directly or indirectly, the work and services to be performed hereunder by the
Contractor, its officers, agents, employees, contractors, subcontractors, licensees or
invitees, whether or not caused, in whole or in apart, by alleged negligence on the part of
officers, agents, employees, contractors, subcontractors, licensees or invitees of the
C6 -6(6)
...
-
--
Owner; and said Contractor doe s hereb y covenant and agre e to assume all liability and
responsibility of Owner, its officers , agents, servants, and emplo y ees for property damage
or loss , and/or personal injuries , including death , to an y and all person of whatsoever kind
or character, whether real or asserted, arising out of or in connection with, directly or
indirectly , the work and services to be performed here under by th e Contractor, its
officers , agents , employees, contractors , subcontractors, licensees or invitees , whether or
not caused, in whole or in apart , by alleged negli gence of officers , agents, employees ,
contractors, subcontractors , licensees or invitees of the Owner. Contractor likewise
covenants and agre e s to , and does hereby , indemnify and hold harmless Owner from and
against any and all injuries , loss or damag es to property of the Owner during the
performance of any of the terms and conditions of this Contract, whether arising out of or
in connection with or resulting from , in whole or in apart , any and all alleged acts of
omission of officers , agents , employees , contractors , subcontractors, licensees , or invitees
of the Owner.
In the event a written claim for damages against the contractor or its subcontractors
remains unsettled at the time all work on the project has been completed to the
satisfaction of the Director of the Water Department, as evidenced by a final inspection ,
final payment to the Contractor shall not be recommended to the Director of the Water
Department for a period of 30 days after the date of such final inspection, unless the
Contractor shall submit written evidence satisfactory to the Director that the claim. has
been settled and a release has been obtained from the claimant in v olved .
If the claims concerned remains unsettled as of the expiration of the above 30-day period ,
the Contractor may be deemed to be entitled to a semi-final payment for work completed,
such semi-final payment to be in the amount equal to the total dollar amount then due less
the dollar value of any written claims pending against the Contractor arising out of
performance of such work, and such semi-final payment may then be recommended by
the Director.
The Director shall not recommend final payment to a Contractor against whom such a
claim for damages is outstanding for a period of six months following the date of the
acceptance of the work performed unless the Contractor submits evidence in writing
satisfactory tot he Director that:
1.
2.
The claim has been settled and a release has been obtained from the
claimant involved, or
Good faith efforts have been made to settle such outstanding o-laims, and
such good faith efforts have failed.
If condition (I) above is met at any time within the six month period, the Director shall
recommend that the final payment to the Contractor be made . If condition (2) above is
met at any time within the six month period , the Director may recommend that final
payment to the Contractor be made. At the expiration of the six month period, the
C6-6(7)
-
-
Director may recommend that final payment be made if all other work has been
performed and all other obligations of the Contractor have been met to the satisfaction of
the Director.
The Director may, if he deems it appropriate, refuse to accept bids on other Water
Department Contract work from a Contractor against whom a claim for damages is
outstanding as a result of work performed under a City Contract.
C6-6.13 CONTRACTOR'S CLAIM FOR DAMAGES: Should the Contractor claim
compensation foe any alleged damage by reason of the acts or omissions of the Owner, he
shall within three days after the actual sustaining of such alleged damage , make a written
statement to the Engineer, setting out in detail the nature of the alleged damage, and on or
before the 25th day of the month succeeding that in which ant such damage is claimed to
have been sustained, the Contractor shall file with the Engineer an itemized statement of
the details and the amount of such alleged damage and, upon request, shall give the
Engineer access to all books of account, receipts, vouchers, bills of lading, and other
books or papers containing any evidence as to the amount of such alleged damage. Unless
such statements shall be filed as hereinabove required, the Contractor's claim for
compensation shall be waived, and he shall not be entitled to payment on account of such
damages.
C6-6.14 ADJUSTMENT OR RELOCATION OF PUBLIC UTILITIES, ETC.: In case
it is necessary to change, move, or alter in any manner the property of a public utility or
others, the said property shall not be moved or interfered with until orders thereupon have
been issued by the Engineer. The right is reserved to the owners of public utilities to enter
the geographical limits of the Contract for the purpose of making such changes or repairs
to the property that may be necessary by the performance of this Contract.
C6-6. l 5 TEMPORARY SEWER AND DRAIN CONNECTIONS: When existing
sewer lines have to be taken up or removed, the Contractor shall, at his own expense and
cost, provide and maintain temporary outlets and connections for all private or public
drains and sewers. The Contractor shall also take care of all sewage and drainage which
will be received from these drains and sewers, and for this purpose he shall provide and
maintain, at his own cost and expense, adequate pumping facilities and temporary outlets
or divisions.
The Contractor, at his own cost and expense, shall construct such troughs, pipes, or other
structures necessary, and be prepared at all times to dispose of drainage and sewage
received from these temporary connections until such times as the permanent connections
are built and are in service . The existing sewers and connections shall be kept in service
and maintained under the Contract, except when specified or ordered to be abandoned by
the Engineer. All water, sewage, and other waste shall be disposed of in a satisfactory
manner so that no nuisance is created and so that the work under construction will be
adequately protected.
C6-6(8)
-.
-
-
--
-
C6-6.16 ARRANGEMENT AND CHARGES FOR WATER FURNISHED BY THE
CITY: When the Contractor desires to use City water in connection with any construction
work, he shall make complete and satisfactory arrangements with the Fort Worth City
Water Department for so doing.
City water furnished to the Contractor shall be delivered to the Contractor from a
connection on an existing City main. All piping required beyond the point of delivery
shall be installed by the Contractor at his own expense .
The Contractor's responsibility in the use of all existing fire hydrant and/or valves is
detailed in Section E2-l .2 USE OF FIRE HYDRANTS AND VAL YES in these General
Contract Documents .
When meters are used to measure the water, the charges, if any, for water will be made at
the regular established rates. When meters are not used , the charges, if any, will be as
prescribed by the City ordinance, or where no ordinances applies, payment shall be made
on estimates and rates established by the Director of the Fort Worth Water Department.
C 6-6 .17 USE OF A SECTION OR PORTION OF THE WORK : Whenever, m the
opinion of the Engineer, any section or portion of the work or any structure is in suitable
condition, it may be put into use upon the written notice of the Engineer, and such usage
shall not be held to be in any way an acceptance of said work or structure or any part
thereof or as a waiver of any of the provisions of these Contract Documents. All
necessary repairs and removals of any section of the work so put into use , due to defective
materials or workmanship, equipment, or deficient operations on the part of the
Contractor, shall be performed by the Contractor at his expense.
C6-6 . l 8 CONTRACTOR'S RESPONSIBILITY FOR THE WORK: Until written
acceptance by the Owner as provided for in these Contract Documents, the work shall be
under the charge and care of the Contractor, and he shall take every necessary precaution
to prevent injury or damage to the work or any part thereof by action of the elements or
from any cause whatsoever, whether arising from the execution or nonexecution of the
work. The Contractor shall rebuild , repair , restore, and make good at his own expense all
injuries or damage to any portion of the work occasioned by any of the hereinabove
causes.
C6-6.19 NOWAIVEROFLEGALRIGHTS: Inspection by the Engineer or any
order by the Owner by payment of money or any payment for or acceptance of any work,
or any extension of time, or any possession taken by the City shall not operate as a waiver
of any provision of the Contract Documents. Any waiver of any breach or Contract shall
not be held to be a waiver of any other or subsequent breach .
The Owner reserves the right to correct any error that may be discovered in any estimate
that may have been paid and to adjust the same to meet the requirements of the Contract
Documents .
C6-6(9)
-
C6-6.20 PERSONAL LIABILITY OF PUBLIC OFFICIALS: In carrymg out the
provisions of these Contract Documents or in exercising any power of authority granted
thereunder, there shall be no liability upon the authorized representative of the Owner,
either personally or other wise as they are agents and representatives of the City .
C6-6.2l STATE SALES TAX: On a contract awarded by the City of Fort Worth,
and organization which qualifies for exemption pursuant the provisions of Article 20.04
(H) of the Texas Limited Sales, Excise, and Use Tax Act, the Contractor may purchase ,
rent or lease all materials, supplies and equipment used or consumed in the performance
of this contract by issuing to his supplier an exemption certificate in lieu of the tax, said
exemption certificate to comply with State Comptroller's Ruling .007. Any such
exemption certificate issued to the Contractor in lieu of the tax shall be subject to and
shall comply with the provision of State Comptroller's Ruling .011, and any other
applicable State Comptroller's rulings pertaining to the Texas Limited Sales, Excise, and
Use Tax Act.
On a contract awarded by a developer for the construction of a publicly-owner
improvement in a street right-of-way or other easement which has been dedicated to the
public and the City of Fort Worth, an organization which qualifies for exemption
pursuant the provisions of Article 20.04 (H) of the Texas. Limited Sales, Excise, and Use
Tax Act, the Contractor can probably be exempted in the same manner stated above.
Texas Limited Sales, Excise, and Use Tax Act permits and information can be obtained
from:
Comptroller of Public Accounts
Sales Tax Division
Capitol Station
Austin, TX
C6-6(10)
-
-
-
-
-
PART C -G ENERAL CONDITIONS
C7-7 PROS ECUTION AND PROGRESS
SECTION C7-7 PROSECUTION AND PROGRESS :
C7-7. l SUBLETTING: The Contractor shall perform with his own organi zation ,
and with the assistance of workmen under his immediate superintendance, work of a
value of not less than fifty (50%) percent of the value embraced on the contract. If the
Contractor sublets any part of the work to be done under these Contract Documents , he
will not under any circumstances be relieved of the responsibility and obligation assumed
under these Contract Documents. All transactions of the Engineer will be with the
Contractor. Subcontractors will be considered only in the capacity of employees or
workmen of the Contractor and shall be subject tot he same requirements as to character
and competency. The Owner will not recognize any subcontractor on the work. The
Contractor shall at all times , when the work is in operation, be represented either in
person or by a superintendent or other designated representatives.
C7-7.2 ASSIGNMENT OF CONTRACT: The Contractor shall not assign, transfer,
sublet, or otherwise dispose of the contract or his rights , title , or interest in or to the same
or any part thereof without the previous consent of the Owner expressed by resolution of
the City Council and concurred in by the Sureties .
If the Contractor does, without such previous consent, assign, transfer, sublet, convey, or
otherwise dispose of the contract or his right, title , or interest therein or any part thereof,
to an y person or persons , partnership, company , firm, or corporation, or does by
bankruptcy , voluntary or involuntary, or by assignment under the insolvency laws of any
states, attempt to dispose of the contract may, at the option of the Owner be revoked and
annulled, unless the Sureties shall successfully complete said contract, and in the event of
any such revocation or annulment, any monies due or to become due under or by virtue of
said contract shall be retained by the Owner as liquidated damages for the reason that it
would be impracticable and extremely difficult to fix the actual damages .
C7-7.3 PROSECUTION OF THE WORK: Prior to beginning any construction
operations, the Contractor shall submit to the Engineer in five or more copies, if
requested by the Engineer, a progress schedule preferably in chart or diagram form, or a
brief outlining in detail and step by step the manner of prosecuting the work and ordering
materials and equipment which he expects to follow in order to complete the project in
the scheduled time. There shall be submitted a table of estimated amounts to b~ earned by
the Contractor during each monthly estimate period.
The Contractor shall commence the work to be performed under this contract within the
time limit stated in these Contract Documents and shall conduct the work in a continuous
manner and with sufficient equipment, materials , and labor as is necessary to insure its
completion within the time limit.
C7-7(1)
......
,.F. ...
-
-
-
7
-,
The sequence requested of all construction operations shall be at all times as specified in
the Special Contract Documents. Any Deviation from such sequencing shall be submitted
to the Engineer for his approval. Contractor shall not proceed with any deviation until he
has received written approval from the Engineer. Such specification or approval by the
Engineer shall not relieve the Contractor from full responsibility of the complete
performance of the Contract.
The contract time may be changed only as set forth in Section C7-7.8 EXTENSION OF
TIME OF COMPLETION of this Agreement, and a progress schedule shall not constitute
a change in the contract time.
C7-7.4 LIMITATION OF OPERATIONS: The working operations shall at all
times be conducted by the Contractor so as to create a minimum amount of inconvenience
to the public. At any time when, in the judgment of the Engineer, the Contractor has
obstructed or closed or is carrying on operations in a portion of a street or public way
greater than is necessary for proper execution of the work, the Engineer may require the
Contractor to finish the section on which operations are in progress before the work is
commenced on . any additional section or street.
C7-7.5 CHARACTER OF WORKMEN AND EQUIPMENT: Local labor shall be
used by the Contractor when it is available. The Contractor may bring from outside the
City of Fort Worth his key men and his superintendent. All other workmen, including
equipment operators, may be imported only after the local supply is exhausted. The
Contractor shall employ only such superintendents , foremen , and workmen who are
careful, competent, and fully qualified to perform the duties and tasks assigned to them,
and the Engineer may demand and secure the summary dismissal of any person or persons
employed by the Contractor in or about or on the work who , in the opinion of the Owner,
shall misconduct himself or to be found to be incompetent, disrespectful, intemperate,
dishonest, or otherwise objectionable or neglectful in the proper performance of his or
their duties, or who neglect or refuses to comply with or carry out the direction of the
owner, and such person or persons shall not be employed again thereon without written
consent of the Engineer.
All workmen shall have sufficient skill, ability, and experience to properly perform the
work assigned to them and operate any equipment necessary to properly carry out the
performance of the assigned duties.
The Contractor shall furnish and maintain on the work all such equipment as is
considered to be necessary for the prosecution of the work in an acceptable manner and at
a satisfactory rate of progress. All equipment, tools , and machinery used for handling
materials and executing any part of the work shall be subject to the approval of the
Engineer and shall be maintained in a satisfactory, safe and efficient working condition.
Equipment on any portion of the work shall be such that no injury to the work. Workmen
or adjacent property will result from its use.
C7-7(2)
-
-
-
C7-7 .6 WORK SCHEDULE: Elapsed working day s shall be computed starting
with the first day of the work completed as defined in C 1-1.23 "WORKING DAYS " or
the date stipulated in the "WORK ORDER" for beginning work, whichever comes first.
Nothing in these Contract Documents shall be construed as prohibiting the Contractor
from working on Saturday, Sunday or Legal Holidays , providing that the following
requirements are met:
a.
b.
A request to work on a specific Saturday, Sunday or Legal Holiday must
be made to the Engineer no later that the preceding Thursday.
Any work to be done on the project on such a specific Saturday, Sunday or
Legal Holiday must be, in the opinion of the Engineer, esse ntial to the
timely completion of the project.
The Engineer's decision shall be final in response to such a request for approval to work
on a specific Saturday, Sunday or Legal Holiday , and no extra compensation shall be
allowed to the Contractor for any work performed on such a specific Saturday, Sunday or
Legal Holiday.
Calendar Days shall be defined in C 1-1.24 and the Contractor may work as he so desires.
C7-7 .7 TIME OF COMMENCEMENT AND COMPLETION: The Contractor shall
commence the working operations within the time specified in the Contract Documents
and set forth in the Work Order. Failure to do so shall be considered by the owner as
abandonment of the Contract by the Contractor and the Owner may proceed as he sees fit.
The Contractor shall maintain a rate of progress such as will insure that the whole work
will be performed and the premises cleaned up in accordance with the Contract
Documents and within the time established in such documents and such extension of time
as may be properly authorized.
C7-7.8 EXTENSION OF TIME COMPLETION: The Contractor's request for an
extension of time of completion shall be considered only when the request for such
extension is submitted in writing to the Engineer within seven days from and after the
time alleged cause of delay shall occurred. Should an extension of the time of completion
be requested such request will be forwarded to the City Council for approval.
In adjusting the contract time for completion of work, consideration will be given to
unforeseen causes beyond the control of and without the fault or negligence of the
Contractor, fire, flood, tornadoes, epidemics, quarantine restrictions, strikes, embargoes,
or delays of sub-contractors due to such causes .
C7-7(3)
...
-
-
-
When the date of completion is based on a calendar day bid , a request for extension of
time because of inclement weather will not be consid e red . A request for ex tension of time
due to inability to obtain supplies and materials will be considered only when a review of
the Contractor's purchase order dates and other pertinent data as requested by the
Engineer indicates that the Contractor has made a bonafide attempt to secure delivery on
schedule. This shall include efforts to obtain the supplies and materials from alternate
sources in case the first source cannot make delivery .
If satisfactory execution and completion of the contract should require work and materials
in greater amounts or quantities than those set forth in the approved Contract Documents,
then the contract time mat be increased by Change Order.
C7-7 .9 DELAYS: The Contractor shall receive no compensation for delays or
hindrances to the work, except when direct and unavoidable extra cost to the Contractor
is caused by the failure of the City to provide information or material, if any, which is to
be furnished by the City . When such extra compensation is claimed, a written statement
thereof shall be presented by the Contractor to the Engineer and if by the Engineer found
correct, shall be approved and referred by the Engineer to the City Council for final
approval or disapproval; and the action thereon by the City Council shall be final and
binding . If delay is caused by specific orders given by the Engineer to stop work , or by
the performance of extra work, or by the failure of the City to provide material or
necessary instructions for carrying on the work, then such delay will entitle the Contractor
to an equivalent extension of time, his application for shall, however, be subject to the
approval of the City Council: and no such extension of time shall release the Contractor
or the surety on his performance bond from all his obligations hereunder which shall
remain in full force until the discharge of the contract.
C7-7 .10 TIME OF COMPLETION: The time of completion is an essential
element of the Contract. Each bidder shall indicate in the appropriate place on the last
page of the proposal, the number of working days or calendar days that he will require to
fully complete this contract or the time of completion will be specified by the City in the
proposal section of the Contract Documents.
The number of days indicated shall be a realistic estimate of the time required to complete
the work covered by the specific contract being bid upon. The amount of time so stated
by the successful bidder or the City will become the time of completion specified in the
Contract Documents .
For each calendar day that any work shall remain uncompleted after the time specified in
the Contract Documents, or increased time granted by the Owner, or as automatically
increased by additional work or materials ordered after the contract is signed, the sum per
day given in the following schedule, unless otherwise specified in other parts of the
Contract Documents, will be deducted from the monies due the Contractor, not as a
penalty , but as liquidated damages suffered by the Owner.
C7-7(4)
(~
f
.-
,,
AMOUNT OF CONTRACT AMOUNT OF
LIQUIDATED
DAMAGES
PER DAY
Less than $ 5,000 inclusive $ 35.00
$ 5,001 to $ 15,000 inclusive $ 45 .00
$ 15,001 to $ 25,000 inclusive $ 63.00
$ 25 ,001 to $ 50,000 inclusive $ 105.00
$ 50,001 to $ 100,000 inclusive $ 154.00
$ 100,001 to $ 500,000 inclusive $ 210 .00
$ 500 ,001 to $ 1,000 ,000 inclusive $ 315 .00
$1,000,001 to $2,000 ,000 inclusive $ 420.00
$2,000,000 and over $ 630 .00
The parties hereto understand and agree that any harm to the City caused by the
Contractor's delay in completing the work hereunder in the time specified by the Contract
Documents would be incapable or very difficult to calculate due to lack of accurate
information, and that the "Amount of Liquidated Damages Per Day", as set out above, is
a reasonable forecast of just compensation due the City for harm caused by any delay.
C7-7.1 l SUSPENSION BY COURT ORDER: The Contractor shall suspend
operations on such part or parts of the work ordered by any court, and will not be entitled
to additional compensation by virtue of such court order. Neither will he be liable to the
City in the vent the work is suspended by a Court Order. Neither will the Owner be liable
to the Contractor by virtue of any Court Order or action for which the Owner is not solely
responsible .
C7-7.12 TEMPORARY SUSPENSION: The Owner shall have the right to suspend
the work operation wholly or in part for such period or periods of time as he may deem
necessary due to unsuitable weather conditions or any other unsuitable conditions which
in the opinion of the Owner or Engineer cause further prosecution of the work to be
unsatisfactory or detrimental to the interest of the project. During temporary suspension
of the work covered by this contract, for any reason, the Owner will make no extra
payment for stand-by time of construction equipment and/or construction crews.
If it should become necessary to suspend work for an indefinite period, the Contractor
shall store all materials in such manner that they will not obstruct or impede the public
unnecessarily nor become damaged in any way, and he shall take every prncaution to
prevent damage or deterioration of the work performed; he shall provide suitable drainage
about the work, and erect temporary structures where necessary.
Should the Contractor not be able to complete a portion of the project due to causes
beyond the control of and without the fault or negligence of the Contractor as set forth in
Paragraph C7-7 .8 EXTENSION OF THETIME OF COMPLETION , and should it be
C7-7(5)
-,
...
--
,.
determined by mutual consent of the Contractor and th e E ngin eer that a solution to allow
construction to procee d is not avail a ble within a re as onabl e period of time , then the
Contractor may be reimbursed for the cost of moving his equipment off the job and
returning the necessary equipment to the job when it is dete rmined by the Engineer that
construction may be resumed . Such reimbursement shall be based on actual cost to the
Contractor of moving the equipment and no profit will be a llowed .
No reimbursement shall be allowed if the equipment is mo ved to another construction
project for the City of Fort Worth .
The Contractor shall not suspend work without written notice from the Engineer and shall
proceed with the work operations promptly when notifi e d by the Engineer to so resume
operations.
C7-7.13 TERMINATION OF CONTRACT DUE TO NATIONAL EMERGENCY:
Whenever, because of National Emergency, so declared by the president of the United
States or other lawful authority, it becomes impossible for the Contractor to obtain all of
the necessary labor, materials , and equipment for the prosecution of the work with
reasonable continuity for a period of two months , the Contractor shall within seven days
notify the City in writing, giving a detailed statement of the efforts which have been made
and listing all necessary items of labor, materials, and equipment not obtainable . If, after
investigations , the owner finds that such conditions existing and that the inability of the
Contractor to proceed is not attributable in whole or in part to the fault or neglect of the
Contractor, than if the Owner cannot after reasonable effort assist the Contractor in
procuring and making available the necessary labor, mate rials, and equipment within
thirty days , the Contractor my request the owner to terminate the contract and the owner
may comply with the request, and the termination shall be conditioned and based upon a
final settlement mutually acceptable to both the Owner and the Contractor and final
payment shall be made in accordance with the terms of the agreed settlement, which shall
include. But not be limited to the payment for all work executed but not anticipated
profits on work which has not been performed.
C7-7.14 SUSPENSION OR ABANDONMENT OF THE WORK AND ANNULMENT
OF THE CONTRACT: The work operations on all or any portion or section of the
work under Contract shall be suspended immediately on written order of the Engineer or
the Contract may be declared canceled by the City Council for any good and sufficient
cause. The following , by way of example, but not of limitation, may be considered
grounds for suspension or cancellation:
a. Failure of the Contractor to commence work operations within the time
specified in the Work Order issued by the Owner.
b . Substantial evidence that progress of the work operations by the
Contractor is insufficient to complete the work within the specified time.
C7-7(6)
\-
and for completing the work in an acceptable manner according to the terms of the
Contract Documents .
The payment of any current or partial estimate prior to the final acceptance of the work by
the Owner shall in no way constitute an acknowledgment of the acceptance of the work,
materials, or equipment, nor in any way prejudice or affect the obligations of the
Contractor to repair, correct, renew, or replace at his own and proper expense any defects
or imperfections in the construction or in the strength or quality of the material used or
equipment or machinery furnished in or about the construction of the work under contract
and its appurtenances, or any damage due or attributed to such defects , which defects,
imperfections, or damage shall have been discovered on or before the final inspection and
acceptance of the work or during the one year guaranty period after the final acceptance .
The Owner shall be the sole judge of such defects, fmperfections, or damage, and the
Contractor shall be liable to the Owner for failure to correct the same as provided herein.
C8-8.5 PARTIAL ESTIMATES AND RETAINAGE: Between the 151 and the 5th
day of each month, the Contractor shall submit to the Engineer a statement showing an
estimate of the value of the work done during the previous month, or estimate period
under the Contract Documents. Not later than the 10 1h day of the month, the Engineer
shall verify such estimate, and if it is found to be acceptable and the value of the work
performed since the last partial payment was made exceeds one hundred dollars ($100.00)
inn amount, 90% of such estimated sum will be paid to the Contractor if the total contract
amount is less than $400,000.00, or 95% of such estimated sum will be paid to the
Contractor if the total contract amount is $400,000.00 or greater, within twenty-five (25)
days after the regular estimate period. The City will have the option of preparing
estimates on forms furnished by the City . The partial estimates may include acceptable
nonperishable materials delivered to the work which are to be incorporated into the work
as a permanent part thereof, but which at the time of the estimate have not been installed
(such payment will be allowed on a basis of 85% of the net invoice value thereof). The
Contractor shall furnish the Engineer such information as he may request to aid him as a
guide in the verification or the preparation of partial estimates .
It is understood that partial estimates from month to month will be approximate only, all
partial monthly estimates and payment will be subject to correction in the estimate
rendered following the discovery of an error in any previous estimate, and such estimate
shall not, in any respect, be taken as an admission of the Owner of the amount of work
done or of its quantity of sufficiency, or as an acceptance of the work done or the release
of the Contractor of any of his responsibilities under the Contract Documents.
The City reserves the right to withhold the payment of any monthly estimate if the
Contractor fails to perform the work strictly in accordance with the specifications or
provisions of this Contract.
C8-8(2)
C8-8 .6 WITHHOLDING PAYMENT: Payment on any estimate or estimates may
be held in abeyance if the performance of the construction operation s is not in accordance
with the requirements of the Contract Documents .
C8 -8. 7 FINAL ACCEPTANCE : Whenever the improvements provided for by
the Contract Documents shall have been completed and all requirements of the Contract
Documents shall have been fulfilled on the part of the Contractor, the Contractor shall
notify the Engineer in writing that the improvements are ready for final inspection . The
Engineer shall notify the appropriate officials of the Owner, will within a reasonable time
make such final inspection, and if the work is satisfactory , in an acceptable condition, and
has been completed in accordance with the terms of the Contract Documents and all
approved modifications thereof, the Engineer will initiate the processing of th e final
estimate and recommend final acceptance of_ the project and final payment thereof as
outlines in paragraph C8-8.8 below.
C8-8.8 FINAL PAYMENT: Whenever all the improvements provided for by the
Contract Documents and all approved modifications thereof shall have been completed
and all requirements of the Contract Documents have been fulfilled on the part of the
Contractor, a final estimate showing the value of the work will be prepared by the
Engineer as soon as the necessary measurements, computations , and checks can be made.
All prior estimates upon which payment has been made are subject to necessary
corrections or revisions in the final payment.
The amount of the final estimate, less previous payments and any sums that have been
deducted or retained under the provisions of the Contract Documents , will be paid to th e
Contractor within 60 days after the final acceptance by the Owner on a proper resolution
of the City Council, provided the Contractor has furnished to the owner satisfactory
evidence of compliance as follows : Prior to submission of the final estimate for payment,
the Contractor shall execute an affidavit as furnished by the City, certifying that ;
A . all persons, firms, associations, corporations, or other organizations
furnishing labor and/or materials have been paid in full,
B. that the wage scale established by the City Council in the City of Fort
Worth has been paid, and
C. that there are no claims pending for personal mJury and/or property
damages .
The acceptance by the Contractor of the last or final payment as aforesaid shall operate as
and shall release the owner from all claims or liabilities under the Contract for anything
done or furnished or relating to the work under the Contract Documents or any act or
neglect of said City relating to or connected with the Contract.
C8-8(3)
The making of the final payment by the Owner shall not relieve the Contractor of any
guarantees or other requirements of the Contract Documents which specifically continue
thereafter .
C8-8.9 ADEQUACY OF DESIGN: It is understood that the Owner believes it
has employed competent engineers and designers to prepare the Contract Documents and
all modifications of the approved Contract Documents. It is , therefore, agreed that the
Owner shall be responsible for the adequacy of its own design features, sufficiency of the
Contract Documents, the safety of the structure, and the practicability of the operations of
the completed project, provided the Contractor has complied with the requirements of the
said Contract Documents, all approved modifications thereof, and additions and
alterations thereof approved in writing by the Owner. The burden of proof of such
compliance shall be upon the Contra_ctor to show that he has complied with the Contract
Documents; approved modifications thereof, and all alterations thereof.
C8-8.10 GENERAL GUARANTY: Neither the final certificate of payment nor
any provision in the Contract Documents nor partial or entire occupancy or use of the
premises by the Owner shall constitute an acceptance of the work not done in accordance
with the Contract Documents or relieve the Contractor of liability in respect to any
express warranties or responsibility for faulty materials or workmanship. The Contractor
shall remedy any defects or damages in the work and pay for any damage to the other
work resulting therefrom which shall appear within a period of one year from the date of
final acceptance of the work unless a longer period is specified and shall furnish a good
and sufficient maintenance bond in the amount of 100 percent of the amount of the
contract which shall assure the performance of the general guaranty as above outlined .
The Owner will give notice of observed defects with reasonable promptness.
C8-8. l 1 SUBSIDIARY WORK: Any and all work specifically governed by
documentary requirements for the project, such as conditions imposed by the Plans, the
General Contract Documents or these Special Contract Documents, in which no specific
item for bid has been provided for in the Proposal, shall be considered as a subsidiary
item of work, the cost of which shall be included in the price bid in the Proposal, for each
bid item . Surface restoration, rock excavation and cleanup are general items of work
which fall in the category of subsidiary work.
C8-8.12 MISCELLANEOUS PLACEMENT OF MATERIAL: Material may be
allocated under various bid items in the Proposal to establish unit prices for
. miscellaneous placement of material. These materials shall be used only when directed by
the Engineer, depending on field conditions . Payment for miscellaneous placement of
material will be made for only that amount of material used, measured to the nearest one-
tenth unit. Payment for miscellaneous placement of material shall be in accordance with
the General Contract Documents regardless of the actual amount used for the Project.
C8-8.13 RECORD DOCUMENTS:. The Contractor shall keep on record a copy
of all specifications, plans, addenda, modifications, shop drawings and samples at the
C8 -8(4)
•.
,.
site, in good order and annotated to show all changes made during the construction
process . These shall be delivered to the Engineer upon completion of the work.
C8-8(5)
PART "CS"
SUPPLEMENTARY CONDITIONS
SUPPLEMENTARY CONDITIONS
FORT WORTH, WATER DEPARTMENT
WATER AND WASTEWATER TREATMENT PLANT PROJECTS
October 1, 2008
1. .CONTRACT DOCUMENTS: In Section Cl-1.2 CONTRACT DOCUMENTS,
delete Paragraph Cl-l .2b SPECIAL CONTRACT DOCUMENTS and add the following:
"b. SPECIAL CONTRACT DOCUMENTS: The Special Contract Documents are
prepared for each specific project as a supplement to the General Contract Documents
and include the following items:
PART A -NOTICE TO BIDDERS (Advertisement)
SPECIAL INSTRUCTION TO BIDDERS
PART B -PROPOSAL (Bid)
M/WBE BID SPECIFICATIONS
PART C -GENERAL CONDITIONS
PART CS-SUPPLEMENTARY CONDITIONS
PART D -SPECIAL CONDITIONS
PART E-TECHNICAL SPECIFICATIONS
PERMITS/EASEMENTS (Some Permits are Multicolored)
PART F-BONDS AND INSURANCE
PART G-CONTRACT
PART H -PLANS/FIGURES (may be bound separately)
White
White
White
Golden Rod
Canary Yellow
Green
Green
White
White
White
White
White"
2. DIRECTOR OF TRANSPORATION AND PUBLIC WORKS: Delete entire
Paragraph C 1-1.17, and replace with the following:
Cl-1.17 DIRECTOR OF TRANSPORATION AND PUBLIC WORKS: The
officially appointed Director of the Transportation and Public Works Department of
the City of Fort Worth, or his duly authorized representative, assistant, or agents.
3. ENGINEER: Delete entire Paragraph Cl-1.19, and replace with the following:
The Director of Fort Worth Transportation and Public Works Department, the
Director of the Fort Worth Water Department, or their duly authorized assistants,
agents, engineers, inspectors, or superintendents, acting within the scope of the
particular duties entrusted to them.
4. PROPOSAL FORM: In Section C2-2.1, Paragraph 1, revise last sentence_ to read as
follows: "The Bidder shall furnish a Financial Statement, Equipment Schedule, and
Experience Record, all of which must be properly executed and filed with the Director of
the Water Department one week prior to the hour for opening of bids. Information shall
be on forms provided by the Bidder and acceptable to the City.
CS-I
5. EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF PROJECT: In
Section C2-2.3, Paragraph 2, add the following to the last sentence: "except for changes
in the site conditions caused by factors outside of the control of the Contractor which
occur after the Contractor's inspection and prior to installation."
6. INTERPRETATION AND PREPARATION OF PROPOSAL: Part C-General
Conditions, Section C2-2, exchange Paragraphs C2-2.7, C2-2.8, and C2-2.9 with the
following:
C2-2.7 DELIVERY OF PROPOSAL: No proposal will be considered unless it is
delivered, accompanied by its proper Bid Security and other required material, to the
Purchasing Manager or his representative at the official location and stated time set
forth in the proposal at the proper time to the proper place. The mere fact that a
proposal was dispatched will not be considered. The Bidders must have the proposal
actually delivered. Each proposal shall be in a sealed envelope plainly marked with
the word "PROPOSAL" and the name or description of the project designated in the
"Notice To Bidders". The envelope shall be addressed to the Purchasing Manager,
City of Fort Worth Purchasing Division, PO Box 17027, Fort Worth, Texas 76102."
C2-2.8 WITHDRAWING PROPOSALS: Proposals actually filed with the
Purchasing Manager cannot be withdrawn prior to the time set for the opening of
proposals. A request for non consideration of a proposal must be made in writing,
addressed to the City Manager, and filed with him prior to the time set for the opening
of proposals. After all proposals not requested for non-consideration are opened and
publicly read aloud, the proposals for which non-consideration requests have been
properly filed may, at the option of the Owner, be returned unopened.
C2-2.9 TELEGRAPHIC MODIFICATION OF PROPOSALS: Any bidder may
modify his proposal by telegraphic communication at any time prior to the time set for
opening proposals, provided such telegraphic communication is received by the
Purchasing Manager prior to the said proposal opening time, and provided further,
that the City Manager is satisfied that a written and duly authenticated confirmation of
such telegraphic communication over the signature of the bidder was mailed prior to
the proposal opening time. If such confirmation is not received within forty-eight
( 48) hours after the proposal opening time, no further consideration will be given to
the proposal.
7. MINORITY BUSINESS ENTERPRISE/WOMEN BUSINESS ENTERPRISE
COMPLIANCE: Delete entire Paragraph C3-3.2, and replace with the following:
C3-3.2 MINORITY AND WOMEN BUSINESS ENTERPRISES: In a accord with
City of Fort Worth Ordinance No. 15530, the City of Fort Worth has goals for the
participation of minority business enterprises and women business enterprises in City
contracts. A copy of the Ordinance can be obtained from the Office of the City
Secretary. The bidder shall submit the MBE/WBE SUBCONTRACTOR/SUPPLIER
UTILIZATION FORM, PRIME CONTRACTOR W AIYER FORM, and/or the
CS-2
-
-
GOOD FAITH EFFORT FORM ("with Documentation") and/or the JOINT
VENTURE FORM as appropriate. The Documentation must be received by the
managing department no later than 5:00 p.m, five (5) City business days after the bid
opening date. The bidder shall obtain a receipt from the appropriate employee of the
managing department to whom delivery was made. Such receipt shall be evidence
that the documentation was received by the City. Failure to comply shall render the
bid non-responsive.
Upon request, Contractor agrees to provide the Owner complete and accurate
information regarding actual work performed by a minority business enterprise
(MBE) and/or women business enterprise (WBE) on the contract and payment
thereof. Contractor further agrees to permit any audit and/or examination of any
books, records or files in its possession that will substantiate the actual work
performed by an MBE and/or WBE. The misrepresentation of facts (other than a
negligent misrepresentation) and/or commission of fraud by the Contractor will be
grounds for termination of the contract and/or initiating action under appropriate
Federal, State or local laws or ordinances relating to false statements. Further, any
such misrepresentation facts (other than a negligent misrepresentation) and/or
commission of fraud will result in the Contractor being determined to be irresponsible
and barred from participating in City work for a period of time of not less that three
(3) years.
8. C3-3.5 AWARD OF CONTRACT is modified to read as follows:
"The Owner reserves the right to withhold final action on the proposals for a
reasonable time, not to exceed the period stated for the duration of the Bid Security
stated in the Notice to Bidders or 90 days, whichever is shorter."
9. C3-3.7 BONDS. For the Paragraph after Paragraph C3-3.7d OTHER BONDS, which
begins with "No sureties", change the entire paragraph to read as follows:
"In order for a surety to be acceptable to the City, the surety must (1) hold a certificate
of authority from the United States Secretary of the Treasury to qualify as a surety on
obligations permitted or required under federal law; or (2) have obtained reinsurance
for any liability in excess of $100,000 from a reinsurer that is authorized and admitted
as a reinsurer in the state of Texas and is the holder of a certificate of authority from
the United States Secretary of the Treasury to qualify as a surety on obligations
permitted or required under federal law. Satisfactory proof of any such reinsurance
shall be provided to the City upon request. The City, in its sole discretion, will
determine the adequacy of the proof required herein. Each bond shall be properly
executed by both the Contractor and the Bonding Company."
CS-3
10. INSURANCE. Delete entire Paragraph C3-3.l l INSURANCE, and replace with the
following::
C3-3.11 INSURANCE: The Contractor shall not commence work under this
contract until he has obtained all insurance required under the Contract Documents,
and such insurance has been approved by the Owner and certificates of Insurance
shall be delivered to the Owner (City of Fort Worth, Contract Administrator in the
respective department as specified in the bid documents, 1000 Throckmorton Street,
Fort Worth, Texas 76102) prior to commencement of work on the contract project.
The prime Contractor shall be responsible for delivering to the Owner the sub-
contractor's certificate of insurance for approval. The prime Contractor shall indicate
on the certificate of insurance included in the documents for execution whether or not
his insurance covers sub-contractors. It is the intention of the Owner that the
insurance coverage required herein shall include the coverage of all sub-contractors.
The General Contractor may require all subcontractors to be insured and submit
documentation ensuring that the requirements of C3-3.11 are met for all
subcontractors. Failure of the Owner to request required documentation, shall not
constitute a waiver of the insurance requirements specified herein. The Contractor's
liability shall not be limited to the specified amounts of insurance required herein.
a.
b.
C.
COMPENSATION INSURANCE: The Contractor shall maintain,
during the life of this contract, Worker's Compensation Insurance on all of
his employees to be engaged in work on the project under this contract,
and for all sub-contractors. In case any class of employees engaged in
hazardous work on the project under this contract is not protected under
the Worker's Compensation Statute, the Contractor shall provide adequate
employer's general liability insurance for the protection of such of his
employees not so protected. Worker's compensation insurance covering
employees in the project site shall be indorsed with a waiver of
subrogation providing rights of recovery in favor of the OWNER.
COMMERICAL GENERAL LIABILITY INSURANCE: The Contractor
Shall procure and shall maintain during the life of this contract, General
Liability Insurance (Public Liability and Property Damage Insurance) in
the amount not less than $500,000 covering each occurrence/aggregate on
account of bodily injury, including death, and in an amount not less than
$500,000 covering each occurrence/aggregate on account of property
damage with $2,000,000 umbrella policy coverage. Certificates of
insurance shall state that Insurance is on an "occurrence" basis. Certificate
shall also contain a statement that no exclusions by endorsement have
been made to the Commercial General Liability Policy.
ADDITIONAL LIABILITY: The Contractor shall furnish
insurance as a separate policies or by additional endorsement to one of the
above-mentioned policies, and in the amount as set forth for public
liability and property damage, the following insurance:
CS-4
I. Contingent Liability (covers General Contractor's Liability for acts
of sub-contractors).
2. Blasting, prior to any blasting being done.
3. Collapse of buildings or structures adjacent to excavation .G..f
excavation are performed adjacent to same).
4. Damage to underground utilities for $500,000.
5. Builder's risk (where above-ground structures are involved).
6. Contractual Liability ( covers all indemnification requirements of
Contract). The City, its offices, employees and servants shall be
endorsed as additional insured on Contractor's insurance policies
excepting employer's liability insurance coverage under
Contractor's worker's compensation insurance policy. Contractor's
insurance policies shall be indorsed to provide that such insurance
is primary protection and any self-funded or commercial coverage
maintained by the OWNER shall not be called upon to contribute
to loss recovery.
7. When required by the Contract Documents, Environmental
Impairment Liability Coverage must be provided in the limits of
$1,000,000 per occurrence and $2,000,000 annual aggregate. The
Environmental Impairment Liability (EIL) must contain coverage
for sudden and accidental contamination or pollution, liability for
gradual emissions, and clean-up costs. The EIL coverage shall
include two year completed operations coverage on a per Project
basis. A separate insurance policy may be needed to fulfill this
requirement. EIL for damages incurred in the course of
transporting sludge shall be covered under the contractor's
insurance policy(s).
d. AUTOMOBILE INSURANCE -BODILY INJURY AND PROPERTY
DAMAGE: The Contractor shall procure and maintain during the life of
this Contract, Comprehensive Automobile Liability Insurance in an
amount not less than $250,000 for injuries including accidental death to
any one person and subject to the same limit for each person an amount
not less than $500,000 aggregate on account of one accident, and
automobile property damage insurance in an amount not less than
$100,000 aggregate.
e. SCOPE OF INSURANCE AND SPECIAL HAZARD: The insurance
required under the above paragraphs shall provide adequate protection for
the Contractor and his sub-contractors, respectively, against damage
CS-5
-
claims which may arise from operations under this contract, whether such
operations be by the insured or by anyone directly or indirectly employed
by him, and also against any of the following special hazards which may
be encountered in the performance of the Contract.
f. PROOF OF CARRIAGE OF INSURANCE: The Contractor shall furnish
the owner with satisfactory proof of coverage by insurance required in
these Contract Documents in the amounts and by carriers satisfactory to
the Owner. (Sample attached.) Other than Worker's Compensation
Insurance, in lieu of specified insurance, the City may consider alternative
coverage or risk treatment measures through insurance pools or risk
retention groups. The City must approve in writing any alternative
coverage. All insurance requirements made upon the Contractor shall
apply to the sub-contractors, should the Prime Contractor's insurance not
cover the sub-contractor's work operations.
g. DEDUCTIBLE LIMITS. The deductible limits or self-funded retention
limits, on each policy must not exceed $10,000 per occurrence unless
otherwise approved by the City.
h. INSURANCE COMPANY: The insurance company with whom the
Contractor's insurance is written shall be authorized to do business in the
State of Texas and shall have a current A.M. Best Rating of "A:VII" or
equivalent measure of financial strength and solvency .
1. NOTIFICATION. During the lifetime of this contract, the Contractor shall
notify the ENGINEER in writing, of any known loss occurrence that could
give rise to a liability claim or lawsuit or which could result in a property
loss .
J. CANCELLATION: Insurance shall be endorsed to provide the City with a
minimum of thirty days notice of cancellation, non-renewal and/or
material change in insurance policy terms or coverage. A minimum 10 day
notice shall be acceptable in the event of non-payment of insurance
premium to insurance company.
CITY RESPONSIBILITIES. The City shall not be responsible for direct payment of
insurance premium costs for Contractor's Insurance.
11 C3-3.13 WAGE RATES: Delete Paragraph C3-3-13 WEEKLY PAYROLLS in its
entirety and replace with C3-3-13 WAGE RA TES as shown below:
"The Contractor shall comply with all requirements of Chapter 2258, Texas
Government Code, including the payment of not less than the rates determined by the
City Council of the City of Fort Worth to be the prevailing wage rates in accordance
with Chapter 2258, Texas Government Code. Such prevailing wage rates are included
in these contract documents.
. CS-6
The Contractor, for a period of three (3) years following the date of acceptance of the
work, maintain records that show (i) that name and occupation of each worker
employed by the contractor in the construction of the work provided for in this
contract; (ii) the actual per diem wages paid to each worker. These records shall be
open, all reasonable hours, for inspection by the City. The provisions of Section C8-8-
14, RIGHT TO AUDIT, pertain to this inspection.
The Contractor shall include in its subcontract's and/or shall otherwise require all of
its subcontractors to comply with paragraphs above.
With each partial payment estimate or payroll period, whichever is less, an affidavit
stating that the contractor has complied with the requirements of Chapter 2258, Texas
Government Code.
The Contractor shall post the prevailing wage rates in a conspicuous place at the site
of the project at all times."
12. INCREASED OR DECREASED QUANTITIES: Revise Paragraph C4-4.3 to read as
follows:
The Owner reserves the right to alter the quantities of the work to be performed or to
extend or shorten the improvements at any time when and as found to be necessary,
and the Contractor shall perform the work as altered, increased or decreased at the
unit prices established in the contract documents. No allowance will be made for any
changes in lost or anticipated profits not shall such changes be considered as waiving
or invalidating any conditions or provisions of the Contract Documents.
Variations in quantities of sanitary sewer pipes in depth categories shall be interpreted
herein as applying to overall quantities of sanitary sewer pipe in each pipe size, but
not to the various depth categories.
13. LIMITATION OF INCIDENTAL GIARGES (Reference C4-4.5c):
The Contractor agrees that should any change in the work of extra work be ordered, the
following applicable percentage shall be added to Material and Labor Costs to cover
overhead and profit:
1. Allowance to the Contractor for overhead and profit for extra work performed by
the Contractor's own forces shall not exceed 15%.
2. Allowance to the Contractor for overhead and profit for extra work performed by a
subcontractor and supervised by the Contractor shall not exceed 10%.
Contractor shall be reimbursed for direct field overhead when the change requires an
extension of the Contract period. Contractor shall not be reimbursed for indirect
overhead or indirect costs related to changes to this contract.
CS-7
14. TESTING COSTS: Paragraph 5-5.12, revise the first sentence to read as follows:
"Where, as called for in the Contract Documents, tests of materials or equipment are
necessary, such tests will be made at the expense of and paid for by the Contractor
unless otherwise specifically provided for in the Technical Specifications."
15. LAWS TO BE OBSERVED: Paragraph C6-6.1, delete "or which may be enacted
later". After the word "exist," add "at the time of the Contract or may be hereafter exist
during the performance of the Contract. 11
16. BUILDING PERMITS: Paragraph C6-6.2 Insert the following at the end of the
paragraph;
"Contractors are responsible for obtaining all construction permits from the governing
agencies. Contractor shall schedule all code inspections with the Code Inspection
Department in accordance with the permit requirements and submit copy of updated
schedule to the Engineer weekly. Building, plumbing, electrical and mechanical
building permits are issued without charge. Water and sewer access fees will be paid
by the Water Department. Any other permit fees are the responsibility of the
Contractor."
17. BARRICADES, WARNINGS AND FLAGMEN: In Paragraph C6-6.8, replace the
word "watchmen" wherever in appears with the word "flagmen". In the first paragraph,
lines five (5) and six (6), replace "take all such other precautionary measures" with "take
all reasonable necessary measures".
18. CONTRACTOR'S RESPONSIBILITY FOR DAMAGE CLAIMS: Delete entire
Paragraph C6-6.12, and replace with the following:
"C6-6.12 CONTRACTOR'S RESPONSIBILITY FOR DAMAGE CLAIMS:
Contractor covenants and agrees to indemnify the City' Engineer and Architect, and
their personnel at the project site for the Contractor's sole negligence. In addition, the
Contractor covenants and agrees to indemnify, hold harmless and defend at its own
expense, the Owner, its officers, agents, servants, and employees, from and against all
claims or suits for property loss, property damage, personal injury, including death,
arising out of, or alleged to arise of, the work and services to be performed hereunder
by the Contractor, its officers, agents, employees subcontractors, licensees or invitees,
whether or not any such iniury, damage or death is caused, in whole or in part, by
the negligence or alleged negligence o(the Owner, its officers, agents, servants, or
employees. Contractor likewise covenants and agrees to indemnify and hol_d harmless
Owner from and against any and all injuries to the Owner's officers, agents, servants,
and employees, loss or destruction of property of the Owner arising form the
performance of any of the terms and conditions of this Contract, whether or not any
such iniury or damage is caused, in whole or in part, by the negligence or alleged
negligence ofthe Owner, its officers, agents, servants, or employees
CS-8
In the event the Owner receives a written claim for damages against the Contractor or
its subcontractors prior to final payment, final payment shall not be made until the
Contractor either (a) submits to the Owner satisfactory evidence that the claim has
been settled and/or a release from the claimant involved, or (b) provides the Owner
with a letter from the Contractor's liability insurance carrier that the claim has been
referred to the insurance carrier.
The Director may, if he deems it appropriate, refuse to accept bids on other City of
Fort Worth public work from a Contractor against whom a claim for damages is
outstanding as a result of work performed under a City Contract."
19. STATE SALES TAX:
A. Delete Paragraph C6-6.21 STATE SALES TAX in its entirety .
B. This contract is issued by an organization, which qualifies for exemption pursuant
to the provisions of Article 20.04 (F) of the Texas Limited Sales, Excise, and Use Tax
Act. All equipment and materials not consumed by or incorporated into the project
construction are subject to State Sales Tax under House Bill 11, enacted August 15,
1991. All such taxes shall be included in the various amounts on the Proposal Form.
The successful Bidder shall be required to submit a breakdown between costs of labor,
consumable material and other construction costs and costs of material incorporated
into the project construction prior to execution of this contract.
B. At the time of execution of the Contract Documents by the Contractor, the
Contractor shall complete the "Statement of Materials and Other Charges" which
identifies the project costs anticipated in the Project into "Materials Incorporated into
the Project" and "All Other Charges". The Contract shall be a "Separated Contract".
C. The City of Fort Worth will issue appropriate Certificates of Resale to the
Contractor.
D. All Change Orders to the Contract will separate charges for materials and labor
and will contain the following statement:
"For purposes of complying with Texas Tax Code, the Contractor agrees that the
charges for material incorporated into the project in excess of the estimated quantity
provided for herein will be no less than the invoice price for such material to the
Contractor."
20 AIR POLLUTION WATCH DAYS: Add the following to Section C7-7:
C7-7.18 AIR POLLUTION WATCH DAYS: The Contractor shall be required to
observe the following guidelines relating to working on City construction sites on
days designated as "AIR POLLUTION WATCH DAYS". Typically, the OZONE
SEASON, within the Metroplex area, runs from May 1, through OCTOBER 31, with
6:00 a.m. -10:00 a.m. being critical BECAUSE EMISSIONS FROM THIS TIME
CS-9
PERIOD HA VE ENOUGH TIME TO BAKE IN THE HOT ATMOSPHERE THAT
LEADS TO EARLY AFTERNOON OZONE FORMATION ..
The Texas Commission on Environmental Quality (TCEQ), in coordination with the
National Weather Service, will issue the Air Pollution Watch by 3:00 p.m. on the
afternoon prior to the WATCH day. On designated Air Pollution Watch Days, the
Contractor shall bear the responsibility of being aware that such days have been
designated Air Pollution Watch Days and as such shall not begin work until 10:00
a.m. whenever construction phasing requires the use of motorized equipment for
periods in excess of 1 hour. However, the Contractor may begin work prior to 10:00
a.m. if use of motorized equipment is less than 1 hour, or if equipment is new and
certified by EPA as "Low Emitting", or equipment burns Ultra Low Sulfur Diesel
(ULSD), diesel emulsions, or alternative fuels such as CNG.
If the Contractor is unable to perform continuous work for a period of at least seven
hours between the hours of 7:00 a.m. -6:00 p.m., on a designated Air Pollution
Watch Day, that day will be considered as a weather day and added onto the allowable
weather days of a given month.
21. C8-8.4 SCOPE OF PAYMENT: Delete C8-8.4 SCOPE OF PAYMENT in its
entirety and replace with the following:
"The Contractor shall receive and accept the compensation as herein provided, in full
payment for furnishing all labor, tools, materials, and incidentals for performing all
work contemplated and embraced under these Contract Documents, for all loss and
damage arising out of the nature of the work or from the action of the elements, for
any unforeseen defects or obstructions which may arise or be encountered during the
prosecution which may arise or be encountered during the prosecution of the work at
any time before its final acceptance by the Owner, ( except as provided in paragraph
CS-5.14) for all risks of whatever description connected with the prosecution of the
work, for all expenses incurred by or in consequence of the suspension or
discontinuance of such prosecution of the working operations as herein specified, or
any and all infringements of patents, trademarks, copyrights, or other legal
reservations, and for completing the work in an acceptable manner according to the
terms of the Contract Documents.
The payment of any current or partial estimate prior to the final acceptance of the
work by the Owner shall in no way constitute an acknowledgment of the acceptance
of the work, materials, or equipment, nor in any way prejudice or affect the
obligations of the Contractor to repair, correct, renew, or replace at his own and
proper expense any defects or imperfections in the construction or in the -strength or
quality of the material used or equipment or machinery furnished in or about the
construction of the work under contract and its appurtenances, or any damage due or
attributed to such defects, which defects, imperfections, or damage shall have been
discovered on or before the final inspection and acceptance of the work or during the
two (2) year guaranty period after the final acceptance. The Owner shall be the sole
CS-10
judge of such defects, imperfections, or damage, and the Contractor shall be liable to
the Owner for failure to correct the same as provided herein."
22. PARTIAL PAYMENTS: Change Paragraph C8-8.5 to read as follows:
"Partial pay estimates shall be submitted by the Contractor 5th day and the 20th day
of the month that work has been is in progress. The estimate shall be processed by the
City on the 10th day and 25th day respectively. Estimates will be paid within 25 days
following the end of the estimate period, less the appropriate retainage as set out
below. Partial pay estimates may include acceptable nonperishable materials delivered
to the work place which are to be incorporated into the work as a permanent part
thereof, but which at the time of pay estimate have not been so installed. If such
materials are included within a pay estimate, payment shall be based upon 85% of the
net invoice value thereof. The Contractor will furnish the engineer such information
as may be reasonably requested to aid in the verification or the preparation of the pay
estimate.
For contracts of less than $400,000.00 at the execution, retainage shall be ten percent
(10%). For contracts of $400,000.00 or more at the time of execution, retainage shall
be five percent (5%).
Contractor shall pay subcontractors in accord with subcontract agreement, within five
(5) business days after receipt by the Contractor of the payment by the City.
Contractor's failure to make the required payment to subcontractors will authorize the
City to withhold future payments from the Contractor until compliance with this
paragraph is accomplished.
It is understood that the partial pay estimates will be approximate only, and all partial
pay estimates and payment of the same will be subject to correction in the estimate
rendered following the discovery of an error in any previous estimate. Payment of any
partial pay estimate shall not, in any respect, be taken as an admission of the Owner of
the amount of work done or of its quality of sufficiency, or as an acceptance of the
work done or the release of the Contractor of any of his responsibilities under the
Contract Documents.
The City reserves the right to withhold the payment of any partial estimate if the
Contractor fails to perform the work in strict accordance with the specifications or
other provisions of this Contract."
23. GENERAL GUARANTY. Delete Paragraph C8-8.10 GENERAL GUARANTY in
its entirety and replace with the following:
Neither the final certificate of payment nor any provision in the Contract Documents
nor partial or entire occupancy or use of the premises by the Owner shall constitute an
acceptance of the work not done in accordance with the Contract Documents or
relieve the Contractor of liability in respect to any express warranties or responsibility
for faulty materials or workmanship. The Contractor shall remedy any defects or
CS-11
damages in the work and pay for any damage to the other work resulting therefrom
which shall appear within a period of two (2) years from the date of final acceptance
of the work unless a longer period is specified and shall furnish a good and sufficient
maintenance bond in the amount of 100 percent of the amount of the contract which
shall assure the performance of the general guaranty as above outlined. The Owner
will give notice of observed defects with reasonable promptness.
Any reference to any shorter period of time of warranty contained elsewhere within
the specifications shall be resolved in favor of this specification, it being the City 's
intent that the Contractor guarantee its work for a period of two (2) years following
the date of acceptance of the project.
24. RIGHT TO AUDIT: Add the following to Section C8-8 :
C8-8.14 RIGHT TO AUDIT :
"(a) The Contractor agrees that the City shall , until the expiration of three (3) years
after final payment under this contract, have access to and the right to examine and
photocopy any directly pertinent books, documents , papers, and records of the
Contractor involving transactions relating to this Contract. Contractor agrees that the
City shall have access during normal working hours to all necessary Contractor
facilities and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this section . The City shall give
Contractor reasonable advance notice of intended audits.
(b) Contractor further agrees to include in all its subcontracts hereunder a provision
to the effect that the subcontractor agrees that the City shall, until the expiration of
three (3) years after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents , papers , and records
of such subcontractor, involving transactions to the subcontract, and further, that City
shall have access during normal working hours to all subcontractor facilities, and
shall be provided adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this article together with subsection (c) hereof. The
City shall give subcontractor reasonable advance notice of intended audits.
( c) Contractor and subcontractor agree to photocopy such documents as may be
requested by the City. The City agrees to reimburse contractor for the cost of the
copies as follows:
1. 50 Copies and Under -10 cents per page.
2. More than 50 copies -85 cents for the first page plus fifteen cents for-each page
thereafter." (5/25/93)
CS-12
25. SCHEDULE OF COSTS: Add the following to Section C8-8:
C8-8.15 SCHEDULE OF COSTS: Following the completion of all work on the
Project and prior to submittal of a request for final payment, the Contractor shall
provide a Schedule of Costs to City for approval which lists all equipment systems,
structures, building electrical and HVAC systems, overhead and project related costs.
The items will be grouped into categories using the Owner's list of category codes
which will be provided by the Owner at the Preconstruction Conference.
The Schedule of Costs will be used by the City as input to the Capital Assets System,
and will not be considered in preparation of modifications to the Contract. Costs
associated with the preparation and processing of this schedule of costs shall be
subsidiary to the price bid.
The Contractor will also provide a projected payment schedule tied to the project
schedule and the schedule of values which projects the monthly payments through the
end of the Project. The Payment schedule must be submitted along with the first
request for payment. This information is necessary to arrange financing of the Project
by the City .
END OF SECTION
CS-13
PART "D"
SPECIAL CONDITIONS
-
-
-
-
·-
-
D-1 GENERAL:
Subject to modifications as herein contained, the Fort Worth Water Department's General
Contract Documents and General Specifications. effective July I, 1978, are made part of
the Contract Documents for this Project. The Plans, Special conditions and Provisions
Documents, and the rules, regulations, requirements, instructions, drawings and details
referred to by manufacturer's name, number or identification included therein as
specifying, referring or implying product control, performance, quality, or other shall be
binding upon the Contractor. The Specifications and drawings shall be considered
cooperative; therefore, work or material called for by one and not shown or mentioned in
the other shall be accomplished or furnished in a faithful manner as though required by
all. The order or precedence in case of conflicts or discrepancies between various parts of
the Contract Documents subject to the ruling of the Engineer shall generally, but not
necessarily, follow the guidelines listed below:
1. Plans
2. Special Contract Documents
3. General Contract Documents and General Specifications
The following Special Conditions shall be applicable to this project and shall govern any
conflicts with the General Contract documents under the provisions stated above.
D-2 PROJECT DESIGNATION:
Construction under these Special Documents shall be performed under the Fort Worth
Water Department Project Designations:
Water Project Number _____ _
Sewer Project Number , and/or
Other
D-4 PROJECT SIGNS:
Project Signs are required at all locations which will be under construction for more than
thirty (30) calendar days as indicated in Part B Proposal. Project Signs shall be in
accordance with Figure 30 (dated 8-28-89) of the General Contract Documents. The
signs may be mounted on skids or on posts . The exact locations and methods of
mounting shall be approved by the engineer. Any and all costs for the required materials,
labor, and equipment necessary for the furnishing of Project Signs shall be considered as
a subsidiary cost of the project and no additional compensation will be allowed.
D-5 CITY FURNISHED MATERIALS:
For water projects, the City will furnish "pipe cleaning pigs," chlorine gas or chlorinated
lime (HTH) and all water for initial cleaning and sterilization of water lines. All other
materials for construction of the project, including water for compaction, shall be
furnished by the Contractor.
D-6 WAGE RATES:
-
-
-
-
-
-
-
The labor classifications and mm1mum wage rates set forth herein have been
predetermined by the City Council of the City of Fort Worth, Texas, in accordance with
statutory requirements, as being the prevailing classifications and rates that shall govern
on all work performed by the Contractor or any subcontractor on the site of the project
covered by these Contract Documents. In no event shall less that the following rates be
paid. (see attached wage rates) When two or more wage rate scales are shown and wage
rates shown in specific classifications are in conflict, the higher wage will be used.
D-8 DEW ATERING:
The Contractor shall be responsible for determining the method of dewatering operation
for the water or sewage flows from the existing mains and ground water. The Contractor
shall be responsible for damage of any nature resulting from the dewatering operations.
The DISCHARGE from any dewatering operation shall be conducted as approved by the
Engineer. Ground water shall not be discharged into sanitary sewers.
Dewatering shall be considered as incidental to a construction and all costs incurred will
be considered to be included in the linear foot bid price of the pipe.
D-9 CROSSING OF EXISTING UTILITIES:
Where a proposed water line crosses over a sanitary sewer or sanitary sewer service line
and/or a proposed sewer line crosses over a water line and the clear vertical distance is
less than 9 feet barrel to barrel, the sanitary sewer or sanitary sewer service line shall be
made water tight or be constructed of ductile iron pipe. The required length of
replacement shall be determined by the Engineer. The material for sanitary sewer mains
and sanitary sewer laterals shall be Class 51 Ductile Iron Pipe with polyethylene
wrapping as specified in Material Standard E 1-6 contained in the General Contract
Documents. The material for sanitary sewer service lines shall be extra strength cast iron
soil pipe with polyethylene wrapping as specified in the General Contract Documents.
Adaptor fittings shall be a urethane or neoprene coupling A.S.T.M. C.-425 with series
300 Stainless Steel compression straps.
Payment for work such as backfill, fittings, tie-ins and all other associated appurtenances
required, shall be included in the linear foot price of appropriate bid item.
D-10 EXISTING UTILTIES:
The plans show the locations of all known surface and subsurface structures. However,
the Owner assumes no responsibility for failure to show any or all of these structures on
the Plans, or to show them in their exact location. It is mutually agreed that sµch failure
shall not be considered sufficient basis for claims for additional compensation for extra
work or for increasing the pay quantities in any manner whatsoever.
The Contractor shall be responsible for verifying the locations of and protecting all
existing utilities, service lines, or other property crossed or exposed by his construction
operations. Contractor shall make all necessary provisions for the support, protection,
Claselflcatlons Hou Rates ·---
AJr Conditionina Mechanic $17.55
Air Conditioning Mechanic Helcer $10.74
Acoustic CeHing Installer $14.26
Acoustic Celling Installer Heloer $10.53
Bricklaver/stone Mason $19.29
.... : ___ er/Stone Mason Heloer $13.07
Csroenter $15.76
Caroenter Helcer $11.69
Concrete Finisher $14.29
Concrete Finisher Helcer $10.09
Conaete Form Builder $12.16
Conaete Form Builder Helper $8.81
Orvwall Tacer $13.25
DrywaU Taper Helper $8.00
Elecb'ician Joumevman $19.79
Electrician Heloer $12.95
Electronic Technician $20.06
Electronic Technician Helcer $12.27
Floor Laver CCaroet) $15.17
F100r Layer (Resilient) $15.94
Floor Laver HelDer $11.00
Glazier $14.35
Glazier Heloer $10.32
Insulator (Picel $15.05
Insulator Heloer (Picel $10.12
Laborer Common $9.21
Laborer Skilled $11.59
Lather $15.94
Lather Helcer $11.12
Metal Building Assembler $14.29
Metal Building Assembler Helcer $9.33
Painter $12.86
Painter Helcer $8.66
Pioefltter $18.22
Pioemter Heloer $12.90
Plasterer $16.16
Plasterer Helcer $9.98
Reinforcing Steel Setter $13.00
Roofer $15.33
Roofer Heloer $10.24
Sheet Metal Worker $15.73
Sheet Metal Worker Heloer $10.53
Source is Fort Worth Chapter
Associated General Contractors (www.Quoln.org)
12/19/2008
ClaHlflcatfona Hou Rates ----
Sheetrock Hanger $13.37
Sheetrock Hanaer HelDer $9.48
Sorinkler Svstem Installer $17.86
Sorinkler System Installer Helper $13.33
Steel Worker Structural $16.20
Steel Worker Structural Heloer $11.71
Welder $15.88
Welder Helcer $11.25
Ho Rates
$16.07
$12.62
$17.55
$13.27
$12.66
-
-
-
-
-
-
-
-
-
-
relocation, and or temporary relocation of all utility poles, gas lines, telephone cables,
utility services, water mains, sanitary sewer lines, electrical cables, drainage pipes, and all
other utilities and structures both above and below ground during construction. The
Contractor is liable for all damages done to such existing facilities as a result of his
operations and any and all cost incurred for the protection and or temporary relocation of
such facilities shall be included in the cost bid per linear foot of pipe installed. NO
ADDITIONAL COMPENSATION WILL BE ALLOWED.
Where existing utilities or service lines are cut, broken or damaged, the Contractor shall
replace or repair the utilities or service lines with the same type of original material and
construction, or better, unless otherwise shown or noted on the plans, at his own cost and
expense. The Contractor shall immediately notify the Owner of the damaged utility or
service line. He shall cooperate with the owners of all utilities to locate existing
underground facilities and notify the Engineer at once of any conflicts in grades and
alignment.
In case it is necessary to change or move the property of any owner of a public utility,
such property shall not be moved or interfered with until ordered to do so by the
Engineer. The right is reserved to the owner of public utilities to enter upon the limits of
the project for the purpose of making such changes or repairs, of their property that may
be made necessary by performance of this contract.
D-11 EXPLORATORY EXCAVATIONS:
In addition to those areas as may be designated on the Drawings, it shall be the
Contractor's responsibility to excavate and locate existing utilities which may affect
construction of the water and/or sewer facilities. All exploratory excavations shall occur
far enough in advance to permit any necessary relocation to be made with minimum
delay. All costs incurred by the Contractor in making exploratory excavations shall be
considered to be included in the unit price bid for constructing of water/sewer line or the
associated structures.
D-12 TEST HOLES:
The matter of subsurface exploration to ascertain the nature of the soils, including the
amount of rock, if any, through which this pipeline installation is to be made is the
responsibility of any and all prospective bidders, and any bidder on this project shall
submit his bid under the condition. Whether prospective bidders perform this subsurface
exploration jointly or independently, and whether they make such determinations by the
use of test holes or other means, shall be left to the discretion of such prospective bidders.
The cost of the rock removal and other associated appurtenances, if required, shall be
included in the linear foot bid price of the pipe.
D-13 SUBSTITUTIONS:
The specifications for materials set out the minimum standard of quality which the City
believes necessary to procure a satisfactory project. No substitutions will be permitted
until the Contractor has received written permission of the Engineer to make a
-
-
-
-
-
-
substitution for the material which has been specified. Where the term "or equal," or" or
approved equal" is used, it is understood that if a material, product, or piece of equipment
bearing the name so used is furnished it will be approvable, as the particular trade name
was used for the purpose of establishing a standard of quality acceptable to the City. If a
product of any other name is proposed for use, the Engineer's approval thereof must be
obtained before the proposed substitute is procured by the Contractor. Where the term
"or equal," or "or approved equal" is not used in the specifications, this does not
necessarily exclude alternative items or material or equipment which may accomplish the
intended purpose. However, the Contractor shall have the full responsibility of proving
that the proposed substitution is, in fact , equal, and the Engineer, as the representative of
the City, shall be the sole judge of the acceptability of substitutions. The provisions of
this sub-section as related to "Substitutions" shall be applicable to all sections of these
specifications.
D-14 CONCRETE DRAINAGE CHANNEL/ CURB AND GUTTER REPLACEMENT:
At locations in the project where mains are required to be placed under the existing
drainage channel, the channel shall be completely replaced for the full existing width with
3000# concrete and reinforcing steel on a sand cushion as shown on the plan detail.
At locations where the mains are required to be placed under existing curb and gutter,
such curb and gutter shall be replaced to match type and geometry of the removed curb
and gutter and shall be installed in accordance with City of Fort Worth Public Works
Department Standard Specification for Construction, Item 502 .
Payment for cutting, backfill, concrete, forming materials and all other associated
appurtenants required, shall be included in the bid price.
D-15 CRUSHED LIMESTONE BACKFILL:
Where specified on the plans or directed by the Engineer, crushed limestone shall be used
for trench backfill on this project. The material shall be conform to the Transportation
and Public Works Standard Specifications for Street and Storm drain Construction
Division 2, Item 208.2 Materials and Division 2 Item 208.3 Material Sources. Trench
Backfill and compaction shall meet the requirements of E2-2 Excavation and Backfill of
the General Contract Documents.
Payment for crushed limestone backfill in place shall be made at the unit price bid in the
Proposal multiplied by the quantity of material used measured in accordance with E2-
2.16 Measurement of Backfill Materials of the General Contract Documents and
Specifications.
D-16 2:27 CONCRETE:
Transportation and Public Works Department typical Sections for Pavement and Trench
Repair for Utility Cuts Figures 1 through 5 refer to using 2 :27 Concrete as base repair.
Since this call-out includes the word "concrete", the consistent interpretation of the
Transportation Public Works Department is that this ratio specifies two (2) sacks of
-
-
-
-
-
cement per cubic yard of concrete. With the exception of the cement content, all other
requirements shall meet or exceed Transportation and Public Works Department Standard
Specification Item 406 Class D Concrete.
D-17 PAVEMENT REPAIR:
The unit price bid under the appropriate bid item in the proposal shall cover all the cost
for providing pavement repair equal to or superior in composition, thickness, etc., to
existing pavement as detailed in the Public Works Department typical pavement sections
for Pavement and Trench Repair for Utility Cuts, Figures 1 through 5.
All required paving cuts shall be made with a concrete saw in a true and straight line on
both sides of the trench, a minimum of twelve (12) inches outside the trench walls. The
trench shall be backfilled and the top nine (9) inches shall be filled with required
materials as shown on paving details, compacted and level with the finished street
surface. This finished grade shall be maintained in a serviceable condition until the
paving has been replaced. All resident's driveways shall be accessible at night and over
weekends.
It has been determined by the Transportation and Public Works Department that the strip
of existing HMAC pavement between the existing gutter and the edge of the trench
pavement repair will not hold up if such strip of existing pavement is two (2) feet or less
in width .
Therefore, at the locations in the project where the trench wall is three (3) feet or less
from the lip of the existing gutter, the Contractor shall be required to remove the existing
paving to such gutter. The pavement repair shall then be made from a minimum distance
of twelve ( 12) inches outside the trench wall nearest the center of the street to the gutter
line.
The pavement shall be replaced within a maximum of five (5) working days, providing
job placement conditions will permit repaving. If paving conditions are not suitable for
repaving, in the opinion of the Owner, the repaving shall be done at the earliest possible
date.
A permit must be obtained from the Department of Engineering's Permit Desk by the
Contractor in conformation with Ordinance No. 3449 and/or Ordinance No. 792 to make
utility cut in the street. City Inspectors will inspect the paving repair after construction
of each water and/or sanitary sewer main replacement.
D-18 PAVEMENT REPAIR IN PARKING AREA:
The contract cost shall cover all cost for providing pavement repair equal to or superior in
composition, thickness, etc., to existing pavement. All required paving cuts shall be made
with a concrete saw in a true and straight line on both sides of the trench, a minimum of
twelve (12) inches outside the trench walls. The trench shall be backfilled and the top
nine (9) inches shall be filled with crushed limestone base material, compacted and level
-
-
-
-
-
-
-
-
-
f -
-
-
-
-
-
-
with the finished adjacent surface. This finished grade shall be maintained in a
serviceable condition until the paving has been replaced.
D-19 TRENCH SAFETY:
1. GENERAL: This specification covers the trench safety requirements for all trench
excavations in order to protect workers from cave-ins. The requirements of this item
govern all trenches for mains, manholes, vaults, service lines, and all other
appurtenances.
2. STANDARDS: The latest version of the U.S. Department of Labor, Occupational
Safety and Health Administration Standards, 29 CFR Part 1926, Subpart P-
Excavations, are hereby made a part of this specification and shall be the minimum
governing requirements for trench safety.
3. DEFINITIONS:
A. TRENCHES: A trench is referred to as a narrow excavation made below the
surface of the ground in which the depth is greater than the width, where the width
measured at the bottom is not greater than fifteen ( 15) feet. If forms or other
structures are installed or constructed in an excavation so as to reduce the
dimension measured from the forms or structure to the side of the excavation to
fifteen (15) feet or less at the bottom of the excavation, the excavation is also
considered to be a trench.
B. BENCHING SYSTEM: Benching means excavating the sides of a trench to
form one or a series of horizontal levels or steps, usually with vertical or near-
vertical surfaces between levels.
C. SLOPING SYSTEM: Sloping means excavating to form sides of a trench that
are inclined away from the excavation.
D. SHIELD SYSTEM: Shields used in trenches are generally referred to as "trench
boxes" or "trench shields." Shield means a structure that is able to withstand the
forces imposed on it by a cave-in and protect workers within the structure. Shields
can be permanent structures or can be designed to be portable and move along as
the work progresses. Shields can be either premanufactured or job-built in
accordance with OSHA standards.
E. SHORING SYSTEM: Shoring means a structure such as a metal_ hydraulic,
mechanical or timber system that supports the sides of a trench and which is
designed to prevent cave-ins. Shoring systems are generally comprised of
crossbraces, vertical rails (uprights), horizontal rails (wales) and/or sheeting .
-
-
-
-
-
4. MEASUREMENT: Trench depth is the vertical measurement from the top of the
existing ground to the bottom of the pipe or structures. The quantity of trench safety
systems shall be based on the linear foot amount of trench depth greater than five (5)
feet.
5. PAYMENT: Separate payment will be made only when trench excavations exceed
a depth of five (5) feet and shall be full compensation for safety system design, labor,
tools, materials, equipment and incidentals necessary for the installation and removal
of trench safety systems.
D-20 SANITARY SEWER MANHOLES:
The installation, replacement, and/or rehabilitation of sanitary sewer manholes will be
required as shown on the plans, and/or as described in these Special Contract Documents
in addition to those located in the field and identified by the Engineer. All manholes shall
be in accordance with sections El-14 Materials for Sanitary Sewer Manholes, Valve
Vaults, Etc., and E2-14 Vault and Manhole Construction of the General Contract
Documents and Specifications, unless amended or superseded by requirements of this
Special Condition.
1. Concrete Collars: Concrete collars when indicated on the plans will be required as per
Fig. 121.
2. Watertight Manhole Inserts: Watertight gasketed manhole inserts shall be installed in
sanitary sewer manholes when indicated on the plans. Inserts shall be constructed in
accordance with Fort Worth Water Department Standard EI00-4 and shall be fitted and
installed according to the manufacturer's recommendations.
3. Lift-Holes: All lift holes shall be plugged with a precast concrete plug. The lift hole
shall be sealed on the outside of the manhole with Ram-Nek or an approved equal sealant.
The lift hole shall be sealed on the inside of the manhole with quick setting cement grout.
4. Final Rim Elevations:
A. Manhole rims in parkways, lawns, alleys, and other improved lands shall be at an
elevation not more than one (1) nor less than one-half (1/2) inch above the surrounding
ground. Backfill shall provide a uniform slope from the top of manhole casting for not
less than three (3) feet each direction to existing finish grade of the ground. The grade
of all surfaces shall be checked for proper slope and grade by string lining the entire
area regraded near the manhole.
B. Manholes in open fields, unimproved land, or drainage courses shall be at an
elevation shown on the drawings or minimum of 6 inches above grade.
5. Manhole Covers: All lids shall have pick slots in lieu of pick holes. Manhole frames
and covers shall be McKinley, Type N, with indented top design, or equal, with pick
slots. Covers shall be flush with the rim of the frame and shall have no larger than 1/8-
-
-
-
-
-
-
-
-
-
-
-
-
inch gap between the frame and cover. Bearing surfaces shall be machine finished.
Locking manhole lids and frames will be restricted to locations within the 100 year flood
plain and areas specifically designated on the plans. Certaninteed Ductile Iron Manhole
Lids and Frames are acceptable for use where Locking lids are specified.
6. Shallow Manholes: Shallow manhole construction will be used when manhole depth is
four (4) feet or less. All shallow manholes shall be built in accordance with Fig. 106 or
per Fig. 103 but with a flat slab top (no cones sections will be allowed). All shallow
manholes shall have a 24" x 40" cast iron lid and frame with pick slots . NOTE:
MANHOLES PER FIG. 105 WILL NOT BE ALLOWED.
7. Manhole Steps: No Manhole steps are to be installed on any Sanitary Sewer Manhole.
8. Exterior surfaces of all manholes shall be coated with two mop coats of coal tar epoxy
paint, Koppers "Bitumastic Super Service Black", Tnemec, "46-450 Heavy Tnemecol", or
equal to a minimum of 14 mils dry film thickness.
9. Manhole Joint Sealing:
A. General: All interior and/or exterior joints on concrete manhole sections
constructed for the City of Fort Worth Water Department, excluding only the joints
using a trapped type performed 0-ring rubber gasket shall require bitumastic joint
sealant as per attached Figure M.
B. Materials: This sealant shall be performed and trowelable bitumastic as
manufactured by Kent-Seal, Ram-Nek, E-Z Stick or equal. The joint sealer shall be
supplied in either extruded rope-form of suitable cross-sectional area or flat-tape form
and shall be sized as recommended by the manufacturer and approved by the Engineer.
The joint sealer shall be protected by a suitable removable wrapper and shall not in any
way depend on oxidation, evaporation, or any other chemical action for either its
adhesive properties or cohesive strength. The joint sealer shall remain totally flexible
without shrinking, hardening, or oxidizing regardless of the length of time it is
exposed to the elements. The manufacturer shall furnish an affidavit attesting to the
successful use of the product as a preformed flexible joint sealant on concrete pipe and
manhole sections for a period of at least five years.
C. Installation of Joint Sealant: Each grade adjustment ring and manhole frame shall
be sealed with the above specified materials. All surfaces to be in contact with the
joint sealant shall be thoroughly clean of dirt, sand, mud or other foreign matter. A
primer shall be applied to all surfaces prior to installing the joint sealant in accordance
with the recommendations by the manufacturer. The protective wrapper shall remain
on the joint sealant until immediately prior to placement of the pipe in the trench.
After removal of the protective wrapper, the joint sealant shall be kept clean. Install
frames and cover over manhole opening with the bottom of the rings resting on
bitumastic joint sealer. Frames and grade rings shall rest on two (2) rows (inside and
outside) of bitumastic joint sealer.
-
10: Sealing and/or Adjusting Existing Manholes: Excavate (rectangular full depth saw
cut if in pavement) adjacent to the manhole to expose the entire manhole frame and a
minimum of 6 inches of the manhole wall keeping the sides of the trench nearly vertical.
A. Remove manhole frame from the manhole strUcture and observe the condition of
the frame and grade rings. Any frame or grade ring that is not suitable for use as
determined by the Engineer shall be replaced. Grade rings that are constructed of
bri~ block, or materials other than precast concrete shall be replaced with precast
concrete rings, or where necessary and approved by the Engineer, a precast flattop
section. Precast concrete rings, or precast concrete flattop section will be the only
adjustments allowed.
B. In brick or block manholes replace the upper portion of the manhole to a point 24
inches below the frame. If the walls or cone section below this level are structurally
unsound, notify the Engineer prior to replacement of the grade rings and manhole
frame. Existing brickwork, if damaged by the Contractor, shall be replaced at the
Contractor's expense.
C. Wire brush manhole frame and exposed manhole surfaces to remove dirt and loose
debris. Coat exposed manhole surfaces with an approved bonding agent followed with
an application of a quick setting hydraulic cement to provide a smooth working
surface.
D. If the inside diameter of the manhole is too large to safely support new adjustment
rings or frame, a flattop section shall be installed.
E. Joint surfaces between the frame, adjustment rings, and cone section shall be :free of
dirt, stones, debris, and voids to ellSW'C a watertight seal. Place a flexible gasket joint
material in two concentric rings along the inside and outside edge of each joint, or use
trowelable material in lieu of prefonned gasket material. Position the butt joint for
each length of joint material on opposite sides of the manhole. No steel shims, wood,
stones, or any material not specifically ac~ by the Engineer may be used to obtain
final surface elevation of the manhole frame.
F. In paved areas or future paved areas, castings-shall be installed by using a straight
edge not less than ten (10) feet long so that the top of casting will confonn to the slope
and finish elevation of the paved surface. The top of the casting shall be 1/8 inch
below the finished elevation. Allowances for the compression of the joint material
shall be made to assure a proper final grade elevation.
0. All exposed exterior surfaces shall be coated with two mop coats of coal tar epoxy
paint, Koppers "Bitumastic Super Service Black", Tnemec, "46-450 Heavy Tnemecol",
or equal to a minimum of 14 mils dry film thickness ..
-
-
-
-
-
-
-
-
-
11. Measurement and Payment:
A. The price bid for new/replacement manhole installations shall include all labor,
equipment, and materials necessary for construction of the manhole including but not
limited to joint sealing, lift hole sealing and exterior surface coating.
B. The price bid for adjusting and/or sealing of existing manholes shall include all
labor, equipment, and materials necessary for adjusting and/or sealing the manhole
including but not limited to joint sealing, lifthole sealing and exterior surface coating.
C. Payment for concrete collars and watertight manhole inserts, if required, will be
made separately, based on the appropriate bid items.
D.
D-23 REMOVAL, SALVAGE AND ABANDONMENT OF EXISTING FACILITIES:
Any removal, salvaging and/or abandonment of existing facilities will necessarily be
required as shown on the plans, and/or described in these Special Contract Documents in
addition to those located in the field and identified by the Engineer. This work shall be
done in accordance with Section E2-1.5 Salvaging of Material and E2-27 Removing Pipe,
of the General Contract Documents and Specifications unless amended or superseded by
requirements of this Special Condition.
1. SALVAGING OR EXISTING WATER METER AND METER BOX. Existing water
meter and meter box shall be removed and returned to the Water Department Warehouse
by the contractor in accordance with Section E2-l .5 Salvaging of Materials. Backfill
material for the void meter box shall be suitable excavated material approved by the
Engineer. Surface restoration shall be compatible with the existing surrounding surface
and grade. If water main is to remain active, the contractor will be required to plug
service line at the main.
2. SALVAGING OF EXISTING WATER METER AND CONCRETE VAULT LID.
Existing water meter and concrete vault lid shall be removed and returned to the Water
Department Warehouse by the contractor in accordance with Section E2-1.5 Salvaging of
Materials. The void shall be backfilled and compacted in accordance with backfill
method as specified in Section E2-2.9 Backfill. Backfill material shall be suitable
excavated material approved by the Engineer. Surface restoration shall be compatible
with the existing surrounding surface and grade.
3. SALVAGE OFF EXISTING FIRE HYDRANTS. Existing fire hydrants shall be
removed and returned to the Water Department Warehouse by the contractor in
accordance with Section E2-l .5 Salvaging of Materials. The void shall be backfilled and
compacted in accordance with backfill method as specified in Section E2-2.9 Backfill.
Backfill material shall be suitable excavated material approved by the Engineer. Surface
restoration shall be compatible with the existing surrounding surface and grade.
-
-
-
-
4. SALVAGE OF EXISTING GATE VAL VE. Existing gate valve and valve box and lid
shall be removed and returned to the Water Department Warehouse by the contractor in
accordance with Section E2-1.5 Salvaging of Materials. The void area caused by the
valve removal shall be backfilled and compacted in accordance with backfill method as
specified in Section E2-2.9 Backfill. Backfill material shall be suitable excavated material
approved by the Engineer. Surface restoration shall be compatible with the existing
surrounding surface and grade. If the valve is in a concrete vault, the vault shall be
demolished in place, to a point no less than 18 inches below the final grade.
5. ABANDONMENT OF EXISTING GA TE VALVES. Existing gate valve and box lid
shall be abandoned by first closing the valve to fully closed position and demolishing the
valve box in place to a point not less than 18 inches below the final grade. Concrete shall
then be used as backfill material to match existing grade.
6 . ABANDONMENT OF EXISTING VAULTS. Vaults to be demolished in place shall
have the top slab and lid removed and vault walls demolished to a point no less than 18
inches below the final grade. The void area caused shall then be backfilled and
compacted in accordance with backfill method as specified in Section E2-2.9 Backfill.
Backfill material shall be suitable excavated material approved by the Engineer. Surface
restoration shall be compatible with the existing surrounding surface and grade.
7. ABANDONMENT OF MANHOLES. Manholes to be demolished in place shall have
all pipes entering and exiting the structure plugged with lean concrete. Manhole tops or
cone section shall be removed to the top of the full barrel diameter section or to a point no
less than 18 inches below the final grade. The structure then shall then be backfilled and
compacted in accordance with backfill method as specified in Section E2-2.9 Backfill.
Backfill material may be either clean washed sand or clean, suitable excavated material
approved by the Engineer. Surface restoration shall be compatible with surrounding
surface. Payment for work involved in backfilling, plugging of pipe and all other
appurtenant required, shall be included in the appropriate bid items.
8. REMOVAL OF MANHOLES. Manholes to be removed shall have all pipes entering
or exiting the structure disconnected . The complete manhole, including top or cone
section, all full barrel diameter sections and base section shall be removed. The
excavation shall then be backfilled and compacted in accordance with backfill method as
specified in Section E2-2.9 Backfill. Backfill material may be Type C Backfill or Type B
Backfill as approved by the Engineer. Surface restoration shall be compatible with
surrounding surface.
9. CUTTING AND PLUGGING OF EXISTING MAINS. At various location on this
project, it may be required to cut, plug and block existing water mains/services or sanitary
sewer mains/services in order to abandon these lines. Cutting and plugging existing mains
and/or services shall be considered incidental and all costs incurred will be considered to
be included in the linear foot bid price of pipe, unless separate trenching is required.
10. REMOVAL OF EXISTING PIPE. Where removal of existing pipe is required, it shall
be the Contractor's responsibility to properly dispose of all removed pipe. All removed
valves, fire hydrants, and meter boxes shall be delivered to Water Department Field
Operations Storage Yard.
11. PAYMENT. Payment for all work and material involved in salvaging, abandoning
and/or removing of existing facilities shall be included in the linear foot bid price of the
pipe except as follows: Separate Payment will be made for removal of all Fire Hydrants,
Gate Valves 16-inch and larger, and Sanitary Sewer Manholes regardless of location.
Payment will be made for salvaging, abandoning and/or removing of all other facilities
when said facility is not being replaced in the same trench, i.e. when removal requires a
separate trenching operation.
D-24 VAL VE BLOCKING:
All valves shall have concrete blocking for support. Valves shall have polyethylene
wrapping per Material Specification E 1-13 and Construction Specification E2-l 3
installed prior to concrete blocking. No separate payment will be made for any of the
work involved for this item and all costs incurred will be considered to be included in the
bid price of the valve.
D-25 DUCTILE IRON PIPE AND ORA Y-IRON FITTINGS:
Reference Part E2 Construction Specifications, Section E2-7 Installing Cast Iron Pipe,
Fittings, and Specials, Sub Section E2-7 .11 Cast Iron Fittings: the first Paragraph shall be
revised to read as follows:
"E2-7. l l DUCTILE-IRON AND ORA Y-IRON FITTINGS: All ductile-iron and gray-
iron fittings shall be furnished with cement mortar lining as stated in Section E 1-7.
The price bid per ton of fittings shall be payment in full for all fittings, joint
accessories, polyethylene wrapping, horizontal concrete blocking, vertical tie-down
concrete blocking, and concrete cradle necessary for construction as designed.
All ductile-iron and gray-iron fittings, valves and specials shall be wrapped with
polyethylene wrapping conforming to Material Specification E 1-13 and Construction
Specification E2-l 3. Wrapping shall precede horizontal concrete blocking, vertical
tie-down concrete blocking, and concrete cradle. Payment for the polyethylene
wrapping, horizontal concrete blocking, vertical tie-down concrete blocking, and
concrete cradle shall be included in bid items for valves and fittings and no other
payment will be allowed."
D-26 DETECTABLE WARNING TAPES:
Detectable underground utility warning tapes which can be located from the surface by a
pipe detector shall be installed directly above non-metallic water or sanitary sewer pipe.
The detectable tape shall be "Detect Tape" manufactured by Allen Systems Inc. or
approved equal, and shall consist of a minimum thickness 0.35 mils solid aluminum foil
encased in a protective inert plastic jacket that is impervious to all known alkalis, acids,
chemical reagents and solvents found in the soil. The minimum overall thickness of the
tape shall be 5.5 mils. and the width shall not be less than 2" inches with a minimum unit
weight of 2-1/2 pounds/1 "/l 000'. The tape shall be color coded and imprinted with the
message as follows:
Type of UtilityColor Code
Water
Sewer
Safety Blue
Safety Green
Legends
Caution Buried Water Line Below
Caution Buried Sewer Line Below
Installation of detectable tapes shall be per manufacturer's recommendations and shall be
as close to the grade as is practical for optimum protection and detectability. Allow a
minimum of 18" inches between the tape and the pipe. Payment for work such as
backfill, bedding, blocking, detectable tapes and all other associated appurtenances
required shall be included in the subsidiary to the cost of pipe installation.
D-30 VAL VE CUT-INS:
It may be necessary to cut-in gate valves to isolate the water main from which the
extension and/or replacement is to be connected. This may require closing valves in other
lines and putting consumers out of service for that period of time necessary to cut in the
new valve; the work must be expedited to the utmost and all such cut-ins must be
coordinated with the engineer in charge of inspection. All consumers shall be individually
advised prior to the shut out and advised of the approximate length of time they may be
without service .
Payment for work such as backfill , bedding, fittings, blocking and all other associated
appurtenances required, shall be included in the price of the appropriate bid items.
D-31 CONNECTION OF EXISTING MAINS:
The Contractor shall determine the exact location, elevation, configuration and angulation
of existing water or sanitary sewer lines prior to manufacturing of the connecting piece.
Any differences in locations, elevation, configuration, and or angulation of existing lines
between the contract drawings and what may be encountered in the said work shall be
considered as incidental to construction. Where it is required to shut down existing mains
in order to make proposed connections, such down time shall be coordinated with the
Engineer, and all efforts shall be made to keep this down time to a minimum. In case of
shutting down an existing main, the Contractor shall notify the Engineering Construction
Services Manager or Superintendent, Phone 817-871-8306, at least 48-hours prior to the
required shut down time. The Contractor's attention is directed to Paragraph C5-5 .15
INTERRUPTION OF SERVICE, Page C5-5(5), PART C -GENERAL CONDITIONS
OF THE WATER DEPARTMENT GENERAL CONTRACT DOCUMENTS AND
GENERAL SPECIFICATIONS. The Contractor shall notify customer, both personally
and in writing, as to the location, time, and schedule of the service interruption.
The cost of removing any existing concrete blocking shall be included in the cost of
connection. Unless bid separately all cost incurred shall be included in the linear foot
price for the appropriate pipe size.
D-34 EASEMENTS AND PERMITS:
Easements and permits, both temporary and permanent, have been secured for this project
at this time and made a part thereto. Any easements and/or permits, both temporary and
permanent, that have not been obtained by the time of publication shall be secured before
construction starts. No work is to be done in areas requiring easements and/or permits
until the necessary easements are obtained. The Contractor's attention is directed to the
easement description and permit requirements, as contained herein, along with any
special conditions that may have been imposed on these easements and permits.
Where the pipeline crosses privately owned property, the easements and construction
areas are shown on the plans. The easements shall be cleaned up after use and restored to
their original conditions or better. In the event additional work room or access is required
by the Contractor, it shall be the Contractor's responsibility to obtain written permission
from the property owners involved for the use of additional property required . No
additional payment will be allowed for this item .
D-37 CONCRETE ENCASEMENT:
Concrete encasement shall be Class E (1500 psi) concrete and for sewer line encasements
shall conform to Fig. 113; for water line encasements it shall conform to Fig . 20 of the
General Contract Documents . Requirements for such encasement are specified in
Sections E 1-20 and E2-20 of the General Contract Documents . Payment for work such as
forming, placing, and finishing including all labor, tools, equipment and material
necessary to complete the work shall be included in the linear foot price bid for Concrete
Encasement.
D-38 CONNECTION TO EXISTING STRUCTURES:
All connections between proposed and existing facilities, shall consist of a watertight
seal. Concrete used in the connection shall be Class A (3000 psi) concrete and meet the
requirements of Section E 1-20 and E2-20 of the General Contract Documents . Prior to
concrete placement, a gasket, RAM-Nek or approved equal, shall be installed around
penetrating pipe.
Payment for such work as connecting to existing facilities including all labor, tools,
equipment, and material necessary to complete the work shall be included in the linear
price of the appropriate pipe size .
D-39 BID ALTERNATIVES:
The Proposal section of this documents is arranged to allow the Contractor to base his bid
on either ductile iron pipe or polyvinyl chloride plastic pipe . Contractor shall indicate
type of pipe to be used. However, regardless of the general type pipe specified by the
Contractor at certain locations, a specific type pipe has been specified on the plans. All
cost for this shall be considered as subsidiary and no additional compensation will be
allowed.
D-41 SITE PREPARATION:
The Contractor shall clear rights-of-way or easements of obstruction which must be
removed to make possible proper prosecution of the work as a part of this project
construction operations. The contractor's attention is directed to Paragraph C6-6.10 Work
Within Easements, Page 6-6(4), Part C -General Conditions of the Water Department
General Contract Document and General Specifications .
Clearing and restoration shall be considered as incidental to construction and all costs
incurred will be included in the Linear Foot price of the pipe.
D-47 CONCRETE AND ASSESSORIES:
1. SCOPE: The requirements of this section shall govern for all materials used and for the
storage, handling, measuring, proportioning, and mixing or combining such materials in
producing concrete for special manholes and incidental pier construction.
All other concrete construction shall be governed by the General Contract Document
Specifications. All materials shall be in accordance with requirements of ACI 30 I, unless
amended or superseded by requirements of following articles or general notes on the
Plans.
Concrete shall be composed of normal Portland cement or high early strength cement,
coarse aggregate, fine aggregate, and water proportioned and mixed as hereinafter
provided in these specifications.
When not specifically shown on the plans or stated in the Special Contract Documents,
all concrete shall be 3000 psi Type II, unless otherwise directed by the Engineer.
"Central Plant", or "Transit Mixed" concrete may be permitted, but only with Engineer's
approval.
2. TESTING AGENCY: All testing shall be done by an approved testing laboratory
selected and paid by the Contractor. Three (3 )cylinder samples should be performed at
each 20-yard interval of concrete that is placed.
3. CEMENT (ACI 301 2.1): Only one brand of cement shall be used in any one structure,
except by written permission of the Engineer. When such permission is granted and more
than one brand is used in one structure, the resulting concrete shall be uniform in color.
Portland cement shall meet the requirements of ASTM C 150, Type II with a maximum of
5% tricalcium aluminate for exposure to sewage. All cement shall be sampled and tested
in accordance with ASTM CI83, C184, CI87, CI88, C190, and C191 , "Sampling and
Testing Portland Cement".
4. WATER (ACI 301 2.3): The water used in all concrete shall be free from objectionable
quantities of silt, organic matter, alkali, salts, and other impurities.
5. COARSE AGGREGATE (ACI 301 2.4): Coarse aggregate shall consist of gravel or
crushed stone meeting the requirements of ASTM C33. When tested by ASTM Cl3 l
procedures, coarse aggregate shall have a percentage of wear of not more than forty ( 40).
Coarse aggregate for Class F concrete shall have a minimum of fifty (50%) percent
calcium carbonate equivalent.
6. FINE AGGREGATE (ACI 301 2.4): Fine aggregate shall consist of natural sand,
manufactured sand, or a combination thereof conforming to ASTM C-33.
When tested in accordance with ASTM 40, "Test of Organic Impurities in Sands for
Concrete", the fine aggregate shall not show a color darker than the standard color.
When the fine aggregate, to be used on the job, is mixed with High Early Strength
Portland Cement in the proportion of one to three , the average tensile strength of not less
than three standard mortar briquets shall be equal to or greater than the tensile strength of
Ottawa sand mortar briquets of the same consistency when tested at the age of three days.
7. ADMIXTURES (ACI 301 2.2):
A. General: Unless specified, no admixtures may be used without specific approval of
the Engineer. Admixtures containing more than 1 % chloride ions may not be used ..
B. Air Entraining Agent: Conform to ASTM C260. Add air entraining agent as
indicated in ACI 301, Table 3.4.1.
C. Water Reducing Admixtures: Conform to ASTM C494, Type A; Euclid Chemical
Co. Eucon WR-75, Master Builders Pozzolith 200N, Protex PDA or approved equal.
(At Contractor's option, water reducing admixture may be used to reduce cement
content and improve workability.) Use according to manufacturer's recommendations.
D. High Range Water Reducing Admixture (Super Plasticizer): Conform to ASTM
C494, Type F or Type G; Euclid Chemical Co . Euco n37, Sike Chemical Corp.
Sikament or approved equal.
8. STORAGE OF CEMENT (ACI 301 2.5): Unless otherwise provided, all cement shall
be stored in well ventilated weatherproof buildings which will protect the cement from
dampness. The floor supporting the cement shall clear the ground a sufficient distance to
prevent the absorption of moisture by the cement. Provisions for storage shall be ample in
capacity, and the shipments shall be segregated in such a manner as to provide easy
access for identification and inspection of each shipment.
The Engineer may permit small quantities of cement to be stored in the open for a short
period of time, (maximum 48 hours) if a raised storage platform and adequate waterproof
covering are provided. No cement shall be used which has become lumped, caked or
hardened.
9. STORAGE OF AGGREGATES(ACI 301 2.5): The handling and storage of aggregate
to be used in making concrete shall be such as to prevent the admixture of foreign
materials. If the aggregates are stored on the ground, the site of the stock piles shall be
grubbed, cleared of all weeds, grass and other vegetation, and leveled off so that the entire
area will be properly drained. The bottom layer of aggregate shall not be disturbed or
used.
When the contract requires the use of two (2) or more sizes of aggregates, the different
sizes shall be stored in such a manner as to prevent intermixing.
Materials in stock piles shall be handled and placed in such a manner that segregation of
materials within the pile will be avoided, and each pile shall be built up in horizontal
layers of not more than three (3) feet in depth .
10. CONSTRUCTION JOINT BONDING (ACI 301 6.1.4 .1): Polyvinyl acetate type
bonding compound. Euclid Chemical Co. Euco Weld, Larsen Welacrete or approved
equal. Omit 6.1.4.2 and 6.1.4 .3
11. ACCESSORIES FOR FORMS (ACI 301, Chapter 4):
A. Cone Ties: 11/16" diameter, I" depth, plastic cone and neoprene waterstop ring with
suitable snap tie.
B. Chamfer Strips: 3/4" 45 degree job cut wood.
12. STRUCTURAL REPAIR MATERIALS (ACI 301 9.4): With prior approval of the
Engineer as to methods and procedures, make structural repairs with Euclid Chemical Co .
Euco Epoxy 456, 400, 463 or Sika Chemical Corp . Culma Dur Mortar, Sikadur Hi-Mod
L.V. ,or Sikadur Hi-Mod or approved equal.
13 . MIXING OF CONCRETE:
A. Central Mixing Plant: A central mixing plant will be allowed provided the method of
mixing and handling has first been approved by the Engineer, and concrete produced is
in conformity with the specification requirements. Concrete:
1. Hauling Time: Discharge all concrete transmitted in a truck mixer, agitator or other
transportation device within 1-1/2 hours after the mixing water has been added.
2. Extra Water: Deliver concrete to the job in exact quantities required by the design
mix . Should extra water be required before depositing the concrete, the Engineer shall
have sole authority to authorize the addition of water. Any additional water added to
the mix after leaving the batch plant shall be indicated on the truck ticket and signed
by the person responsible. Where extra water is added to the concrete it shall be mixed
thoroughly for 40 revolutions of the drum or 3-1/2 minutes at mixing speed, whichever
is greater.
B. Transit Mixing: When transit mixing is used, the transit mixer shall be of an
approved revolving drum or revolving blade type so constructed as to produce a
thoroughly mixed concrete with a uniform distribution of the materials throughout the
mass and shall be equipped with a discharge mechanism which will insure the
discharging of the mixed concrete without segregation.
The mixer drum shall be water-tight when closed and shall be equipped with a locking
device which will automatically prevent the discharging of the mixer prior to receiving
the required number of revolutions.
The entire quantity of mixing water shall be accurately measured and controlled. Each
batch shall be mixed to the consistency as described herein. Any additional mixing shall
be done at a slower speed specified by the manufacturer for agitation and shall be
continuous until the batch is discharged.
14. CONSTRUCTION JOINTS: Construction joints shall be placed as shown on the
plans unless otherwise specifically authorized by the Engineer. All construction joint
shall be made on horizontal and vertical planes and formed with mortises or keys made in
the concrete unless shown otherwise on the plans.
A. Construction Joint Bonding (ACI 302 6.1.4.1) Polyvinyl Acetate type bonding
compound. Euclid Chemical Co., Euco Weld, Larsen Welacrete or approved equal and
applied as recommended. Omit 6.1.4.1 and 6.1.4.3.
15. FORMS:
A. FORMWORK(ACI 301, CHAPTER4)
I. Earth Cuts (ACI 301 4.1.3): Shall not be used as forms for vertical surfaces unless
approved by the Engineer.
2. Chamfer Strips (ACI 301 4.2.4): Install 45 degrees chamfer strips at exposed outside
comers.
B. FORM REMOVAL (ACI 301 4.5)
I. Form Removal: Remove formwork supporting weight of concrete only after
notifying Engineer and in a manner to insure safety of the structure. Under normal
conditions. Formwork may be removed when concrete is at least 14 days old and has
reached 90 percent of specified strength. When temperature is below 45 degrees F,
leave formwork in place an additional period of the equaling time structure was
exposed to lower temperature. No live load permitted on new construction after form
removal until concrete is at least 28 days old and has reached full specified strength.
2. Form Facing Material Removal: Form facing material which is removable without
disturbing shores may be removed when concrete is at least 7 days old. Facing may be
removed earlier if specifically approved by the Engineer and acceptable curmg
compound is applied to all surfaces immediately after form removal.
C. RESHORING (ACI 301 4.6)
Reshoring permitted only after prior review by Engineer.
D. FORM REUSE
Clean all form material suitable for reuse before erection. No form material will be
acceptable for reuse if, in the opinion of the Engineer it will not produce a finished
surface required by these Specifications or called for on the drawings.
16. PLACING CONCRETE (ACI 301): On vertical formwork, use approved bar chairs
or spacer as required to maintain proper concrete cover and bar position.
17. REPAIR OF SURFACE DEFECTS (ACI 309 9.1): Allow Engineer to inspect
concrete surfaces immediately upon removal of forms. Modify or replace concrete not
conforming to required lines, detail and elevations. Repair or replace concrete not
properly placed resulting in excessive honeycombing and other defects. Do not patch,
repair or replace exposed architectural finished concrete except upon express directions of
Engineer. Patching of tie holes and defects is required.
18. FORMED SURFACE FINISHED (ACI 301 10.4): Formed surface finished per ACI
301 10.4.
19. CURING (ACI 301 12.1):
A. Impervious Coating: Applied specified curing compounds immediately after final
finishing of slabs. Apply in quantities recommended by the manufacturer.
B. Wet Covering: Curing shall be continued for at least four curing days after the
concrete is placed.
20. MISCELLANEOUS FINISH REQUIREMENTS: All other concrete finish work not
indicated on the plans shall be provided herein, even though not specifically mentioned,
as follows:
1. Finishing Exposed Surfaces: All tie wires shall be cut below surface then pointed
over. All imperfections such as fins shall be removed and local surface depressions
pointed over.
21. PAYMENT FOR CONCRETE: The concrete quantities for the various structures will
be paid for at the lump sum for the construction of the special manhole and piers. Price
will be full compensation for furnishing, hauling, and mixing all concrete materials;
placing, curing and finishing all concrete; all grouting and pointing; cost of concrete mix
-
design except as provided in Special Contract Documents; furnishing and placing metal
flashing strips; and for all forms and formwork, labor, tools, equipment, and incidentals
necessary to complete the work.
D-48 TEMPORARY PAVEMENT REPAIR:
The Contractor shall provide a temporary pavement repair immediately after trench
backfill and compaction using a minimum of I -inch cold mix asphalt. This temporary
repair shall be rolled to provide a smooth transition between the existing pavement and
the temporary repair. The unit price bid under the appropriate bid item of the proposal
shall cover all cost for providing temporary pavement repair for all streets cuts prior to
street reconstruction.
D-55 TEMPORARY SOIL EROSION SEDIMENT AND WATER POLLUTION
CONTROL:
I. DESCRIPTION: This item shall consist of temporary soil erosion sediment and water
pollution control measures deemed necessary by the Engineer for the duration of the
contract. These control measures shall at no time be used as a substitute for the
permanent control measures unless otherwise directed by the Engineer and they shall
not include measures taken by the CONTRACTOR to control conditions created by his
construction operations. The temporary measures shall include dikes, dams, berms,
sediment basins, fiber mats, jute netting, temporary seeding, straw mulch, asphalt
mulch, plastic liners, rubble liners, baled-hay retards, dikes, slope drains and other
devices.
2. CONSTRUCTION REQUIREMENTS: The Engineer has the authority to define
erodible earth and the authority to limit the surface area of erodible-earth material
exposed by preparing right-of-way, clearing and grubbing, the surface area of erodible-
earth material exposed by excavation, borrow and to direct the CONTRACTOR to
provide temporary pollution-control measures to prevent contamination of adjacent
streams, other water courses, lakes, ponds or other areas of water impoundment. Such
work may involve the construction of temporary berms, dikes, dams, sediment basins,
slope drains and use of temporary mulches, mats seeding or other control devices or
methods directed by the Engineer as necessary to control soil erosion. Temporary
pollution-control measures shall be used to prevent or correct erosion that may develop
during construction prior to installation of permanent pollution-control features, but are
not associated with permanent control features on the project.
The Engineer will limit the area of preparing right of way, clearing and grubbing,
excavation and borrow to be proportional to the CONTRACTOR'S capability and
progress in keeping the finish grading, mulching, seeding, and other such permanent
pollution-control measures current in accordance with the accepted schedule. Should
seasonal conditions make such limitations unrealistic, temporary soil-erosion-control
measures shall be performed as directed by the Engineer. The amount of surface area of
erodible-earth material exposed at one time shall not exceed 750,000 square feet for
each excavation operation, 750,000 square feet for each material source operation ( other
-
than from commercially operated sources), 750,000 square feet for each preparing of
right-of-way operation or 750,000 square feet for each clearing and grubbing operation,
unless otherwise shown on the plans or with prior approval by the Engineer in writing.
The CONTRACTOR shall also conform to the following practices and controls. All
labor, tools, equipment and incidentals to complete the work will not be paid for directly
but shall be considered as subsidiary work to the various items included in the contract.
(a). Waste or disposal areas and construction roads shall be located and constructed in
a manner that will minimize the amount of sediment entering streams.
(b ). Frequent fording of live streams will not be permitted; therefore, temporary
bridges or other structures shall be used wherever an appreciable number of stream
crossings are necessary. Unless otherwise approved in writing by the Engineer,
mechanized equipment shall not be operated in live streams.
(c). When work areas or material sources are located in or adjacent to live streams,
such areas shall be separated from the stream by a dike or other barrier to keep
sediment from entering a flowing stream. Care shall be taken during the construction
and removal of such barriers to minimize the muddying of a stream.
( d). All waterways shall be cleared as soon as practicable of falsework, piling, debris
or other obstructions placed during construction operations that are not a part of the
finished work.
(e). The CONTRACTOR shall take sufficient precautions to prevent pollution of
streams, lakes and reservoirs with fuels, oils, bitumens, calcium chloride or other
harmful materials. He shall conduct and schedule his operations so as to avoid or
minimize siltation of streams, lakes and reservoirs and to avoid interference with
movement of migratory fish.
3. SUBMITTAL: Prior to the start of the applicable construction, the CONTRACTOR
shall submit for approval his schedules for accomplishment of soil-erosion-control work
and his plan to keep the area of erodible-earth material to a minimum. He shall also
submit for acceptance his proposed method of soil-erosion control on construction and
haul roads and material sources and his plan for disposal of waste materials . No work
shall be started until the soil-erosion control schedules and methods of operations have
been reviewed and approved by the Engineer.
4. MEASUREMENT AND PAYMENT: All work, materials and equipment necessary
to provide temporary erosion control shall be considered subsidiary to the contract
and no extra pay will be given for this work.
D-57 HYDRO MULCH SEEDING AND SODDING:
-
Any sodding or hydro mulching required will be done in accordance with Fort Worth
Public Works Department Standard Specifications item 118 and 120.
If in the opinion of the Engineer, additional seeding and/or sodding is required due to the
Contractor's construction, this will be seeded and sodded at the expense of the Contractor.
Payment for work and all associated appurtenants required, shall be included in the
appropriate bid item(s).
D-65 TRAFFIC CONTROL:
The Contractor shall be responsible for providing traffic control during the construction
of this project consistent with the provisions set forth in the "1980 Texas Manual on
Uniform Traffic Control Devices for Streets and Highways" issued under the authority of
the "State of Texas Uniform Act Regulating Traffic on Highways", codified as Article
6701d Vernon's Civil Statues, pertinent sections being Section Nos. 27, 29, 30 and 31.
The Contractor shall execute this work in such a manner as to create a minimum of
interruption to traffic and pedestrian facilities and to the flow of vehicular and pedestrian
traffic within the project area.
Barricades, warning and detour signs shall conform to be the Standard Specifications for
street and storm drain construction, "Barriers and Warning and/or Detour Signs", Item
524, and/or as directed by Engineer.
The Contractor will not remove any regulatory sign, instructional sign, street name sign,
or other sign which has been erected by the City. If it is determined that a sign must be
removed to permit required construction, the Contractor shall contact the Transportation
and Public Works Department, Signs and Markings Division (phone number 871-8075),
to remove the sign. In the case of regulatory signs, the Contractor must replace the
permanent sign with a temporary sign meeting the requirements of the above referenced
manual and such temporary sign must be installed prior to the removal of the permanent
sign. If the temporary sign is not installed correctly or if it does not meet the required
specifications, the permanent sign shall be left in place until the temporary sign
requirements or met. When construction work is completed to the extent that the
permanent sign can be re-installed, the Contractor shall again contact the Signs and
Markings Division to re-install the permanent sign and shall leave his temporary sign in
place until such re-installation is completed.
D-70 TRENCH BACKFILL (UTIL. CUT):
The Water Department shall place the pipe embedment and backfill with washed rock per
the following specification.
Washed Rock: All washed rock used for embedment or as otherwise directed by the
engineer shall be washed gravel or washed crushed stone or washed crushed gravel and
shall meet the following gradation and abrasion:
Sieve Percent Sieve
Size Retained Size
1-1/2" 0-2 3/8"
l" 7-55 #4
%" 23-100
Los Angeles abrasion test: 50% Maximum wear per ASTM.
D-79 CURB ON CONCRETE PAVEMENT:
Percent
Retained
85-100
95-100
Standard Specification Item 502 shall apply except as herein modified.
INTEGRAL CURB: Integral curb shall be constructed along the edge of the pavement as
an integral part of the slab and of the same concrete as the slab. The concrete for the curb
shall be deposited not more than thirty (30) minutes after the concrete in the slab.
SUPERIMPOSED CURB: Concrete shall have a minimum compressive strength of three
thousand (3,000) pounds per square inch at twenty-eight (28) days. The quantity of
mixing water shall not exceed seven (7) U.S. gallons per sack (94 lbs.) of Portland
Cement. The slump of the concrete shall not exceed three (3) inches. A minimum cement
content of five (5) sacks of cement per cubic yard of concrete is required.
PAYMENT: Payment shall be made for cutting and replacing curbs and gutters required
in this Project under the appropriate bid item and shall be in compliance with Public
Works Department standard requirement Item 502.
D-80 ADJUST WATER VALVE BOX, MANHOLES, AND VAULTS (UTIL. CUT}:
Contractor will be responsible for adjusting water valve boxes, manholes and vaults to
match new pavement grade. The unit price bid will be full payment for materials
including all labor, equipment, tools and incidentals necessary to complete the work.
D-86 WORKER'S COMPENSATION INSURANCE:
A. Contractor's Worker's Compensation Insurance.
Contractor agrees to provide the Owner (City) a certificate showing that it has obtained a
policy of worker's compensation insurance covering each of its employees employed on
the project in compliance with state law. No Notice to Proceed will be issued until the
Contractor has complied with this section.
B. Subcontractor's Worker's Compensation Insurance.
Contractor agrees to require each and every subcontractor who will perform work on the
project to provide to it a certificate from such subcontractor stating that the subcontractor
has a policy of worker's compensation insurance covering each employee on the project.
Contractor will not permit any subcontractor to perform work on the project until such
certificate has been acquired. Contractor shall provide a copy of all such certificates to the
Owner (City).
C. Worker's Compensation Insurance Coverage.
1. Definitions:
Certificate of coverage ("certificate"). A copy of a certificate of insurance, a
certificate of authority to self-insure issued by the Texas Workers' Compensation
Commission, or a coverage agreement (TWCC-81, TWCC-82, TWCC-83, or
TWCC-84), showing statutory worker's compensation insurance coverage for
person's or entity's employees providing services on a project, for the duration of
the project.
Duration of the Project -includes the time from he beginning of the work on the
project until the contractor's/person's work on the project has been completed and
accepted by the City.
Persons providing services on the project ("subcontractor" in Texas Labor Code
Section 406.096) -includes all persons or entities performing all or part of the
services the contractor has undertaking to perform on the project, regardless of
whether that person contracted directly with the contractor and regardless of
whether that person has employees. This included, without limitation, independent
contractors, subcontractors, leasing companies, motor carriers, owner-operators,
employees of any entity which furnishes persons to provide services on the
project. "Services" include without limitation, providing, hauling, or delivering
equipment or materials, or providing labor, transportation, or other service related
to a project. "Services" does not include activities unrelated to the project, such as
food/beverage vendors, office supply deliveries, and delivery of portable toilets.
2. The contractor shall provide coverage, based on proper reporting of classification
codes and payroll amounts and filing of any coverage agreements, which meets
the statutory requirements of Texas Labor Code, Section 401.011(44) for all
employees of the contractor providing services on the project, for the duration of
the project.
3. The Contractor must provide a certificate of coverage to the City prior to
being awarded the contract.
4. If the coverage period shown on the contractor's current certificate of
coverage ends during the duration of the project, the contractor must, prior to the
end of the coverage period, file a new certificate of coverage with the City
showing the coverage has been extended.
5. The contractor shall obtain from each person providing services on a project, and
provide to the City:
-
(a) a certificate of coverage, prior to that person beginning work on the
project, so the City will have on file certificates of coverage showing
coverage for all persons providing services on the project; and
(b) no later than seven days after receipt by the contractor, a new certificate of
coverage showing extension of coverage, if the coverage period shown on
the current certificate of coverage ends during the duration of the project.
6. The contractor shall retain all required certificates of coverage for the duration of
the project and for one year thereafter.
7. The Contractor shall notify the City in writing by certified mail or personal
delivery, within ten (10) days after the contractor knew or should have known, of
any change that materially affects the provision of coverage of any person
providing services on the project.
8. The contractor shall post on each project site a notice, in the text, form and
manner prescribed by Texas Worker's Compensation Commission, informing all
persons providing services on the projects that they are required to be covered and
report lack of coverage.
9. The contractor shall contractually require each person with whom it contracts to
provide services on a project, to:
(a) provide coverage, based on proper rep01iing on the classification codes and
payroll amounts and filling of any coverage agreements, which meets the
statutory requirements of Texas Labor Code, Section 401.011(44) for all of
its employees providing services on the project, for the duration of the
project;
(b) provide to the contractor. prior to that person beginning work on the project, a
certificate of coverage showing that coverage is being provided for all
employees of the person providing services on the project, for the duration of
the project;
(c) provide the contractor. pnor to the end of the coverage period a new
certificate
of coverage showing the extension of coverage, if the coverage period shown
on the current certificate of coverage ends during the duration of th€ project;
( d) obtain from each other person with it contracts, and provide to the contractor:
( 1) a certificate of coverage, prior to the other person beginning on the
project; and
(2) a new certificate of coverage showing extension of coverage, prior to the
end of the coverage period, if the coverage period shown on the current
certificate of coverage ends during the duration of the project;
( e) retain all required certificates of coverage on file for duration of project and
for one year thereafter.
(f) notify the City in writing by certified mail or personal delivery, within 10 days
after the person knew or should have known, of any change that materially
affects the provision of coverage of any person providing services on the
project; and
(g) contractually require each person with whom it contracts, to perform as
required by paragraphs (a) -(g), with the certificates of coverage to be
provided to the person for whom they are providing services.
10. By signing this contract or providing or causing to be provided a certificate of
coverage, the contractor is representing to the City that all employees of ·the
contractor who will provide services on the project will be covered by worker's
compensation coverage for the duration of the project, that the coverage will be
based on the proper reporting of classification codes and payroll amounts, and that
all coverage agreements will be filed with the appropriate insurance carrier or, in
the case of a self-insured, with the Texas Workers' Compensation Commission's
Division of Self-Insurance Regulation. providing false or misleading information
may subject the contractor to administrative penalties, criminal penalties, civil
penalties or other civil actions.
11. The Contractor's failure to comply with any of these provisions is a breach of
contract by the contractor which entitles the City to declare the contract void if the
contractor does not remedy the breach within ten days after receipt of notice of
breach from the City.
D. Posting of Required Worker's Compensation Coverage.
The contractor shall post a notice on each project site informing all persons providing
services on the project that they are required to be covered, and stating how a person may
verify current coverage and report failure to provide coverage. This notice does not satisfy
other posting requirements imposed by the Texas Workers' Compensation Act or other
Texas Workers' Compensation Commission rules. This notice must be printed with a title
in at least 30 point bold type and text in at least 10 point normal type, and shall-be in both
English and Spanish and any other language common to the worker population. The text
for the notices shall be the following text, without additional words or changes:
REQUIRED WORKERS' COMPENSATION COVERAGE
The law requires that each person working on this site or providing services
related to this construction project must be covered by workers' compensation
insurance. This includes persons providing, hauling, or delivering equipment or
materials, or providing labor or transportation or other service related to the
project, regardless of the identity of their employer or status as an employee.
"Call the Texas Workers' Compensation Commission at 512-440-3789 to receive
information on the-legal requirement for coverage, to verify whether your
employer has provided the required coverage, or to report an employer's failure to
provide coverage.
D-89 TRENCH EXCAVATION, BACKFILL AND COMPACTION:
Trench excavation and backfill under parking lots, driveways, gravel surfaced roads,
within easements, and within existing or future R.O.W. shall be in accordance with
Sections El-2 Backfill and E2-2 Excavation and Backfill of the General Contract
Documents and Specifications except as specified herein.
I. TRENCH EXCAVATION: In accordance with Section E2-2 Excavation and
Backfill, if the stated maximum trench widths are exceeded, either through accident or
otherwise, and if the Engineer determines that the design loading of the pipe will be
exceeded, the Contractor will be required to support the pipe with an improved trench
bottom. The expense of such remedial measures shall be entirely the Contractor's own.
All trenching operations shall be confined to the width of permanent rights-of-way,
permanent easements, and any temporary construction easements. All excavation shall
be in strict compliance with the Trench Safety Systems Special Condition of this
document.
2. TRENCH BACKFILL: Trenches which lie outside of existing or future pavement
shall be backfilled above the top of the embedment material with Type "C" backfill
material. Excavated material used for Type "C" backfill must be mechanically
compacted unless the Contractor can furnish the Engineer with satisfactory evidence
that the P.I. of the excavated material is less than 8. Such evidence shall be a test report
from an
independent testing laboratory and must include representative samples of soils in all
involved areas, with a map showing the location and depth of the various test holes. If
excavated material is obviously granular in nature, containing little or no plastic
material, the Engineer may waive the test report requirement. See El-2.3, Type "C" or
"D" Backfill, and E2-2. l 1 Trench Backfill for additional requirements. When Type "C"
back-
fill material is not suitable, at the direction of the Engineer, Type "B" backfill material
shall be used.
In general, all backfill material for trenches in existing paved streets shall be in
accordance with Figure A. Sand material specified in Figure A shall be obtained from
an approved source and shall consist of durable particles free of thin or elongated
pieces, lumps of clay, soil, loam or vegetable matter and shall meet the following
gradation:
Size Sieve
#4
#16
% Retained
0-5
0-20
(P.I. = 8 or less)
Size Sieve
#50
#100
#200
% Retained
0-50
60-95
90-100
3. TRENCH COMPACTION: All trench backfill shall be placed in lifts per E2-2.9
Backfill. Trenches which lie outside existing or future pavements shall be compacted to
a minimum of90% Standard Proctor Density (A.S.T.M. D698) by means ohamping
only.
Trenches which lie under existing or future pavement shall be backfilled per Figure A
with 95% Standard Proctor Density by jetting, mechanical tamping, or a combination of
methods. Backfill material to be mechanically tamped must be within +-4% of its
optimum moisture content. The top two (2) feet of sewer line trenches and the top
eighteen (18) inches of water line may be rolled in with heavy equipment tires, provided
it is placed in lifts appropriate to the material being used and the operation can be
performed without damage to the installed pipe.
The Contractor shall obtain the services of an independent testing laboratory to perform
trench compaction tests per A.S.T.M. standards on all trench backfill . Any retesting
required as a result of failure to compact the backfill material to meet the standards will
be at the expense of the Contractor and will be billed at the commercial rates as
determined by the City. These soil density tests shall be performed at two (2) foot
vertical intervals beginning at a level two (2) feet above the top of the installed pipe and
continuing to the top of the completed backfill at intervals along the trench not to
exceed
300 linear feet. The Contractor will be responsible for providing access and trench
safety system to the level of trench backfill to be tested. No extra compensation will be
allowed for exposing the backfill layer to be tested or providing trench safety system for
tests conducted by the City.
4. MEASUREMENT AND PAYMENT: All material, including any and all Type "B"
backfill, and labor costs of excavation and backfill will be included in the price bid
per linear foot of water and sewer pipe . All costs involved in performing the trench
compaction tests made by independent laboratories shall be subsidiary to the cost of
the contract.
D-91 SHOP DRAWINGS:
1. Submit seven (7) copies of shop drawings, layouts, manufacturer's data and material
schedules as may be required by the Engineer for his review. Submittals may be checked
by and stamped with the approval of the Contractor and identified as the Engineer may
require . Such review by the Engineer shall include checking for general conformance
with the design concept of the project and general compliance with information given in
the General Contract Documents. Indicated actions by the Engineer, which may result
-
-from his review, shall not constitute concurrence with any deviation from the plans and
specifications unless such deviations are specifically identified by the method described
below, and further shall not relieve the Contractor of responsibility for errors or
omissions in the submitted data. Processed shop drawing submittals are not change
orders. The purpose of submittals by the Contractor is to demonstrate that the Contractor
understands the design concept, and that he demonstrates his understanding by indicating
which equipment and materials he intends to furnish and install, and by detailing the
fabrication and installation methods he intends to use. If deviations, discrepancies or
conflicts between submittals and the design drawings and/or specifications are
discovered, either prior to or after submittals are processed, the design drawings and
specifications shall govern.
The Contractor shall be responsible for dimensions which are to be confirmed and
correlated at the job site, fabrication processes and techniques of constriction,
coordination of his work with that of other trades and satisfactory performance his work.
The Contractor shall check and verify all measurements and review submittals prior to
being submitted, and sign or initial a statement included with the submittal, which
signifies compliance with plans and specifications and dimensions suitable for the
application. Any deviation from the specified criteria shall be expressly stated in writing
in the submittal. Three (3) copies of the approved submittals shall be retained by the
Contractor until completion of the project and presented to the City in bound form.
2. Shop drawings shall be submitted for the following items prior to installation:
***List the required submittals here***
Additional shop drawing requirements are described in some of the material
specifications.
3. Address for Submittals -The submittals shall be addressed to the Chief Design
Engineer:
D-101 TESTING:
David R. Townsend, P.E.
Fort Worth Water Department
Engineering Division
P.O. Box 870
Fort Worth, TX 76101
a. The Contractor shall furnish, at his own expense, certifications by a private laboratory
for all materials proposed to be used on the project, including a mix design for any
asphaltic and/or Portland cement concrete to be used, and gradation analysis for sand
and crushed stone to be used along with the name of the pit from which the material
was taken. The Contractor shall provide manufacturer's certifications for all
-
-manufactured items to be used in the project and will bear any expense related
thereto.
b. Tests of the design concrete mix shall be made by the Contractor's laboratory at least
nine days prior to the placing of concrete using the same aggregate, cement, and
mortar which are to be used later in the concrete. The Contractor shall provide a
certified copy of the test results to the City.
c. Quality control testing of in-place material on this project will be performed by the
City at its own expense. Any retesting required as a result of failure of the material to
meet project specifications will be at the expense of the Contractor and will be billed
at commercial rates as determined by the City. The failure of the City to make any
tests of materials shall in no way relieve the Contractor of his responsibility to furnish
materials and equipment conforming to the requirements of the contract.
d. Not less than 24 hours notice shall be provided to the City by the Contractor for
operations requiring testing. The Contractor shall provide access and trench safety
system (if required) for the site to be tested, and any work effort involved is deemed
to be included in the unit price for the item being tested.
e. The Contractor shall provide a copy of the trip ticket for each load of fill material
delivered to the job site. The ticket shall specify the name of the pit supplying the fill
material.
D-102 SUBSIDIARY WORK:
Any and all work specifically governed by documentary requirements for the project,
such as conditions imposed by Plans, the General Contract Documents or these Special
Contract Documents, in which no specific item for bid has been provided for in the
proposal, shall be considered as a subsidiary item of work, the cost of which shall be
included in the price bid in the Proposal for each bid item. Surface restoration and
cleanup are general items of work which fall in the category of subsidiary work.
D-103 ADDENDA:
Bidders wanting further information, interpretation or clarification of the contract
documents must make their request in writing to the Fort Worth Water Department
Engineering Services, at least 96 hours prior to bid opening. Answers to all such requests
will be bound and made a part of the Contract Documents. No other explanation or
interpretation will be considered official or binding. Should a bidder find discrepancies
in, or omissions from, the Contract Documents, or should the bidder be in doubt as to
their meaning, the bidder should at once notify the Fort Worth Water Department
Engineering Services, in order that a written addendum may be sent to all bidders. Any
addenda issued will be mailed or be delivered to each prospective bidder. The bid
proposal as submitted by the bidder must be so constructed as to include anyaddenda
issued by the Fort Worth Water Department, prior to 24 hours of the opening of bids with
appropriate recognition of addenda so noted in the bid proposal.
-
D-104 OSHA STANDARDS:
All work performed under this contract shall meet the requirements of the Occupational
Safety and Health Administration (OSHA).lt is the responsibility of the Contractor to
become familiar with the provisions of the regulations published by the OSHA in the
Federal Register and to perform all the responsibilities thereunder. It is the Contractor's
responsibility to see that the project is constructed in accordance with OSHA regulations
and to indemnify and save harmless the City from any penalties resulting from the
Contractor's failure to so perform.
D-105 PROJECT SUPERINTENDENTS:
The Contractor shall keep a competent resident superintendent at the project site at all
times during the progress of the work. A resume listing the qualifications and experience
record of the proposed resident superintendent, as well as references from similar projects
shall be submitted to the Owner prior to award of contract. This resident superintendent,
if found to be acceptable, shall not be replaced without written notice to and consent from
the Owner except under extraordinary circumstances, Qualifications of a proposed
replacement shall be submitted when a request is made for replacement of the
superintendent and shall be approved by the Owner prior to withdrawing the
superintendent.
During the construction of the project, the resident superintendent shall demonstrate an
ability to properly execute the work outlined in the contract documents in a timely
manner and shall consistently produce work of an acceptable quality and in accordance
with the contract documents. If the Owner shall have a reasonable objection to the
performance of the resident superintendent, the Contractor shall replace the resident
superintendent upon written notice from the Owner. The resident superintendent is to be
replaced with a superintendent acceptable to the Owner. No extension of time will be
allowed for delays caused by the replacement of a resident representative.
D-106 RESIDENT ENGINEER:
The General Conditions, Section C 1-1 .19 ENGINEER, defmes various persons who may
be designated as the Engineer. For the prosecution of this contract, the Tenn Engineer
shall mean the Resident Engineer as designated by the Director of the Fort Worth Water
Department together with members of the staff of the Engineer who are assigned to the
Project. Any contacts the contractor may wish to make with any City personnel, including
the Water Production Supervisor, members of the plant operating staff, members of the
City Administration, or Consulting Engineers, shall be arranged through the Engineer.
The Contractor shall not act upon requests or instructions he may receive from any City
personnel or Consulting Engineers nor shall he give instructions or directions to such
persons without the approval or consent of the Engineer.
D-107 PROGRESS PHOTOGRAPHS:
The Contractor shall take photographs of the project site prior to construction, monthly
during construction of the project and after completion of the project. Photographs may
be taken with a quality 35mm or better camera, equipped to photograph either interior or
exterior exposures, with lenses ranging from wide angle to 135mm. Photographs shall be
taken at locations as designated by the Engineer.
Contractor shall video tape all roads and work areas to be affected prior to starting
construction and furnish a copy of the video tape to the Engineer.
Two glossy color 3" x 5" prints and the negative shall be provided for each photograph
taken. Each print shall be marked on the reserve side to indicate project name, date and
time, location, direction of exposure, and description of what is being photographed.
Prints shall be clear and sharp with proper exposure. If prints of adequate quality are not
produced from exposures, additional photographs shall be taken.
D-108 TERMINATION;
It is understood and agreed that this contract may be tenninated by the City without
obligation to the Contractor, in whole or from time to time in part, whenever such
tennination is detennined by the City to be in the best interests of the City. Tennination
may be effected by delivering to the Contractor or his designated representative a notice
of tennination, specifying to what extent perfonnance of the work under the contract is
being terminated and the effective date of tennination. After receipt of notice of
tennination Contractor shall:
1. Stop work specified in the notice on the date and to the extent specified in the notice
of termination.
2. Place no further order or subcontract except as necessary to complete work already
underway.
3. Terminate all orders and contracts to the extent that they relate to the perfonnance of
the Work tenninated by the Notice ofTennination.
D-109. HAZARDOUS AND TOXIC MATERIALS:
Insofar as pennitted by law, the Owner shall indemnify and hold hannless the Contractor
from and against any and all liabilities, losses, cost, damages and expenses, arising out of
use of the materials at the Owners site which are not under the direct control of the
Contractor, including, but not limited to, any and all liability resulting from personal
injury, including death, property liability, at any time, however caused, due to the
presence or release of, or exposure, whether to the person of property injured or
otherwise, whether to the person of property injured or otherwise, to any hazardous or
toxic substance, provided, however, that the City liability shall be limited to that
established in Article 6252-19, Texas Revised Code and other applicable State statutes
and Constitutional provisions.
D-110. SPOIL AND FILL MATERIAL:
Prior to disposing on any spoiVfill material, the contractor shall advise the Director of
Transportation and Public Works, acting as the City of Fort Worth's Flood Plain
Administrator (" Administrator"), of the location of all sites where the contractor intends
to dispose of such material. Contractor shall not dispose of such material until the
proposed sites have been determined by the Administrator to meet the requirements of the
Flood Plain Ordinance of the City of Fort Worth (Ordinance No 10056). All disposal
sites must be approved by the Administrator to ensure that filling is not occurring within
a flood plain without a permit.
A flood plain permit can be issued upon approval of necessary engineering studies. No
fill permit is required if disposal sites are not in a flood plain. Approval of the
contractor's disposal sites shall be evidenced by a letter signed by the Administrator
stating the site is not in a known flood plain of by a Flood Plain Fill Permit authorizing
fill within the flood plain. Any expenses associated with obtaining the fill permit,
including any necessary engineering studies, shall be at the contractor's expense.
In the event the contractor disposes of spoiVfill material at a site without a fill permit or a
letter from the Administrator approving the disposal site, upon notification by the
Director of Transportation and Public Works, the contractor shall remove the spoiVfill
material at its expense and dispose of such materials in accordance with the Ordinances
of the City and this section.
D-111 AGE:
In accordance with the policy "(Policy") of the Executive Branch of the Federal
Government, Contractor covenants that neither it nor any of its officers, members, agents,
employees, program participants or subcontractors, while engaged in performing this
contract, shall, in connection with the employment, advancement or discharge of
employees or in connection with the terms, conditions or privileges of their employment,
discriminate against persons because of their age except on the basis of a bona fide
occupational qualification, retirement plant or statutory requirement.
Contractor further covenants that neither it nor its officers, members, agents, employees,
subcontractors, program participants, or persons acting on their behalf, shall specify, in
solicitations or advertisements for employees to work on this contract, a maximum age
limit for such employment unless the specified maximum age limit is based upon a bona
fide occupational qualification, retirement plan or statutory requirement.
Contractor warrants it will fully comply with the policy and will defend, indemnify and
hold City harmless against any claims or allegations asserted by third -parties or
subcontractor against City arising out of Contractor's and/or its subcontractors' alleged
failure to comply with the above referenced Policy concerning age discrimination in the
performance of this agreement.
D-112 DISABILITY:
In accordance with the provisions of the Americans With Disabilities Act of 1990
(" ADA"), Contractor warrants that it any and all of its subcontractors will not unlawfully
discriminate on the basis of disability in the provision of services to the general public,
nor in the availability, terms and/or conditions of employment for applicants for
employment with, or employees of Contractor or any of its subcontractors. Contractor
warrants it will fully comply with ADA's provisions and any other applicable federal,
state and local laws concerning disability and will defend, indemnify and hold City
harmless agail)St any claims or allegations asserted by third parties or subcontractors
against City arising out of Contractor's and/or its subcontractor's alleged failure to comply
with the above-referenced law concerning disability discrimination in the performance of
this agreement.
D-113 INDEMNIFICATION:
To clarify Section C6-6.12 of the General Conditions of the Contract, it is the intent of
the Owner that the Contractor indemnify, hold harmless and defend the Owner, and the
Owner's officers, agents, servants, and employees from and against any and all claims as
listed herein, even though causes by the Owner's sole negligence.
With respect to the last sentence of the first paragraph of Section C6-6 . l 2, it is the
Owner's intent that the language be site specific to the general area where the work to be
performed under the Contract is being performed. It is not the Owner's intent that the
Contractor be required to indemnify the Owner for damages to property other than that
caused to property located in close proximity to this project, unless such damage is
caused wholly or in part by the Contractor's negligence.
D-114 CONSTRUCTION ADMINISTRATION
A. CONTRACTOR MODIFICATION REQUEST(CMR)/PROPOSED CONTRACT
MODIFICA TION(PCM):
Any Change in the Contract Documents will ~ initiated either by the Contractor
issuing a Contractor's Modification request (CMR) or by the Owner issuing a
Proposed Contract Modification (PCM) on forms provided by the Owner. Proposals
will be reviewed by the Owner and if found acceptable, will be incorporated in a
Change Order or a Field Order in accordance with Section C4-4 of the Contract
Documents.
The Contractor's Modification request (CMR) shall fully identify and describe the
deviations and associated costs, time factors and impacts, and state the reason the
change is requested. Any savings in costs related to the substitution/repalcement or
change is to be stated in th erequest for consideration. ·
Cost of the Engineer's evaluation of any substitution or deviation requested by the
Contractor shall be charged to the Contractor by the Owner.
B.PROJECT INFORMATION REQUEST
-
-
-
-
When necessary, the Contractor shall request additional information, clarification or
interpretation of the contract documents or when the Contractor believes there is a
conflict between the contract drawings and specification, the Contractor shall identify
the conflict and/or request clarification/additional information using the Project
Information Request (PIR) form provided by the Owner. Sufficient information shall
be attached to permit a written response without further information.
The Owner will log each request and will review the request. If review of the Project
information request (PIR) indicates that a change to the contract documents is
required, the Owner will issue either a Field Order(FO) or Proposed Contract
Modification (PCM).
C. RECORD ORA WINGS
The Contractor shall keep on record at the site a copy of all Contract Specifications,
Plans, Addenda, modifications, record and shop drawings and samples, in good
condition and annotated in erasable red pencil to show all changes made during the
construction process. These shall be delivered to the Engineer upon completion of the
work and before final payment is made.
The Contractor shall retain for record purposes only, all designs and plans prepared
for construction which are prepared and sealed by a State of Texas Registered
Professional Engineer. Said design and plans shall include, but not be limited to.
paving, buildings, mechanical and electrical systems, foundation, etc .
-
PART "E"
TECHNICAL SPECIFICATIONS
PART 3 -TECHNICAL SPECIFICATIONS
UNIT I -BOAT RAMP REPLACEMENT
1. Concrete Design Mix to be 4000 psi with 7% entrained air
and 1.5 pounds per cubic yard of Propex Concrete System's
Fibermesh 650 synthetic fibers (or approved equal).
2. Sub-Grade to be compacted to 90% standard density.
If necessary due to unstable existing conditions, it will be
required to provide a stabilized sub-grade using cement
stabilized base ( i.e. two sack concrete mix ).
3. Rebar to be Fiberglass Reinforced Polymer type product.
All spliced joints to have minimum overlap of 40 X bar diameter.
All bends to be factory bends. Minimum concrete coverage of 3 inches.
4. The Cofferdam System to be supplied / installed by the Portadam, Inc. ( or
equal) per their Business Policy requirements (which includes limited duties /
requirements on the part of the General Contactor associated with the
installation and maintenance of this temporary construction dam).
UNIT II -MARKER BUOY/ FLOAT LINE REPLACEMENT
1. All new Buoys, Floats, Fittings, Cable to be Rolyan Manufactured Products
(or equal)
2. The two new line-end anchorage support structures to be primed with
Tnemec Series 91-H20 Hydro-Zinc and painted with second coat of Tnemec
Series 66 Hi-Build Epoxoline and a third coat of Tnemec Series 74 Endura-
Shield white epoxy paint ( or equal)
UNIT III -REMOVAL OF BRUSH AND TREES AT THE DAM
1. Contactor to take considerable care to not damage/ rut the existing
sodded grass surface at the Lake Worth Dam. All damage(s) to be repaired
by the placement of new bermuda grass turf as directed by the Engineer.
2. Contactor to use the existing access roads at the Dam Area for all necessary
equipment needed for this work task unit with the exception of Item four ( 4)
which will allow the Contractor to use the natural ground surface southwest
of the actual Dam's Toe of Slope.
PART "F"
BONDS AND INSURANCE
i
PERF_ORMANCE BOND
THE STATE OF TEXAS § Bond No . 4374880
COUNTY OF TARRANT §
K.NOW ALL MEN BY THESE PRESENTS: That we c1 J.:ehne Construction, Inc.
____ , a (2) Corporation of Aust in Texas
hereinafter called Principal, and (3) Sure Tee Insurance Compa~n-Y--~
a corporation organized and existing under the laws of the State and fully authorized to
transact business in the State of Texas, as Surety, are held and firmly bound unto the City
of Fort Worth, a municipal corporation organized and existing under the laws of the State
of Texas, hereinafter called Owner, in the penal sum of:
Three Hundred Fifty Nine Thousand Seven ~~ndred Thirty Two and No/1 OO's
($3 59 ,732.00 ) Dollars in lawful money of the United States, to be paid in Fort Worth,
Tarrant County, Texas, for the payment of which sum well and truly be made, we hereby
bind ourselves, our heirs, executors, administrators, and successors, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal
entered into a certain contract with the City of Fort Worth, the Owner, dated the
2nd day of June , A.D. 2009 , a copy of which is hereto attached and
made a part hereof, for the construction of:
Lake Worth Restoration and Maintenance
designated as Project No,(s) WTR-2009-560001
which
, a copy of
contract is hereby attached, referred to, and made a part hereof as fu1ly and to the same
extent as if copied at length herein, such project and construction b eing hereinafter
referred to as the "work".
NOW THEREFORE, if the Principal shall well, truly, and faithfully p_erform the
work in accordance with the plans, specifications, and contract documents during the
original term thereof, and any extensions thereof which may be granted by the Owner,
with or without notice to the Surety, and he shall satisfy all claims and demands incurred
under the contract, and shall fully indemnify and save harmless the Owner from all costs
and damages which it may suffer by reason of failure to do so, and shall reimburse and
repay the owner all outlay and expense which the Owner may incur in making good any
default, then this obligation shall be void; otherwise to remain in full force and effect.
F-1
'
PROVIDED FURTHER. that if any legal action be filed upon this bond, venue
shall lie in Tarrant County, State of Texas.
AND PROVIDED FURTHER, that the said Surety, for value received, hereby
stipulates and agrees that no charge, extension of time, alteration or addition to the terms
of the contract or to the work to be performed thereunder, or the specifications
accompanying the same shall in any wise affect its obligation on this bond, and it does
hereby waive notice of any such change, extension of time, alteration or addition to the
terms of the contract or to the work or to the specifications.
IN WITNESS WHEREOF, this instrument is executed in six counterparts each
one of which shall be deemed an original, this the _?net__ day of June , A.D.,
2009
Lehne Construction, Inc.
ATTEST: (4)
12400 H
(SE AL) Austin, TX 78738
(Address)
SureTec Insurance Company
ATTEST: -/--.., · .. .....
(Surety) Secretary
(SE AL)
(Attorney-in-fact) (5)
John W. Schuler -:.._ .... -:, ·-....... ____ ... -·-'"'
1405 E Riverside Dr, Austin , TX 787 41
(Address)
(Address)
NOTE: Date of Bond must not be prior to
date of Contract
(1) Correct Name of Contractor
(2) A Corporation, a Partnership or an
Individual, as the case may be
(3) Correct name of Surety
( 4) If Contractor is Partnership, all Partners
should execute Bond
(5) A True copy of Power of Attorney shall
be attached to Bond by Attorney-in-fact
F-2
............ _ .. ..
::--
..
1 1 11111,,,,,
,1 "I > ,,., ''-). ' ' ",,.
\ ······· ·· ... ~ ... ,··
·.'
<')
r
PAYMENT BOND Bond No. 4374880
THE ST A TE OF TEXAS §
COUNTY OF TARRANT §
KNOW ALL BY THESES PRESENTS:
That we , (1) Lehne Constructio n, Inc a (2) Corporation of
Travis County, Texas hereinafter called Principal and (3)
Sure Tee Insurance Compaoy , a corporation organized anct
existing under the laws of the State Texas and fully authorized to transact business in the State of
Texas, as Surety, are held and firmly bound unto the City of Fort Worth, a municipal corporation
organized and existing under the laws of the State of Texas, hereinafter called Owner, and unto al!
persons, firms, and corporations who may furnish materials for, or perform labor upon, the building or
improvements hereinafter referred tO in the penal SUffi Of Three ~ndred Fifty Nine Thousand Sev en Hundred Thirty Two and No/.100 's
__ Dollars ($ 359,732.00 ) in lawful money of the United
States to be paid in Fort Wo1th, Tarrant County, Texas, for the payment of which sum we11 and truly be
made, we bind ourselves , our heirs, executors, administrators and successors jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such th at w herea s, the Principal entered into a
certain contract with the City of Fort Worth, the Owner, dated the 2nd day of_J_u_n.;...;e;..._ ___ _
20 09 , a copy of which is hereto attached and made a part hereof, for the considerati on of:
Lake Worth Restoration and Maintenance
designated as Project Number WTR-2009-560001 , a copy of which contract is hereto
attached, referred to , and made a part hereof as fully and to the same extent as if copied at _ length
herein, such project and construction being hereinafter referred to a s the "work".
NOW THEREFORE, the condition of this obligation is s uch that, if the Principal shall
promptly make payment to al l claimants as defined in Chapter 2253 , Texas Government Code,
supplying labor and materials in the prosecution of the work provided for in said Contract, then this
obl igation shall be null and void, otherwise it shall remain in full force and effect.
THIS BOND IS MADE AN D ENTERED into solel y for the protection of all claimants
supplying labor and material in the prosecution of the work provided for in said Contract, as claimants
are defined in said Chapter 2253, and all such claimants shall have a direct right of action under the
bond as provided in Chapter 2253 , Texas Government Code .
PROVIDE FURTHER, that if any legal action be filed upon this bond, venue shall lie in
Tarrant Cotmty, Texas, State of Texas , and that the said Surety, for val ue recei ved, hereby st ipulates
and agrees that no change extension of time , alteration or addition to the terms of the contract or to the
work be performed thereunder or the spec ification accompanying the same shall in any wise affect its
obligation on this bond, and it does hereby waive notice of any such change, extension of time ,
alteration or addition to the terms of the contract or to the work or the s pecifications.
PROVIDED FURTHER, that no final settlement between the Owner and the Contractor shall
abridge the right of any beneficiary hereunder whose claim shall be unsatisfied.
IN WITNESS WHEREOF, this instrument is executed in six counterparts, each one of which
shall be deemed an original, this 2nd day of June , 20~
(SEAL)
ATTEST:
(Surety) Secretary
Witness~ Surety
1405 E Riverside Dr, Austin , TX 7?]_41
Address
Lehne Construction , Inc.
Principal
BY:
(Printed Name/Title)
12400 Hwy 71 W #350 -118
Address
Austin ,_I?<_7_8_7_3_8 ___ _
City/State/Zip
SureTec Insurance Company
(Surety)
~
----.... _ ... : -=--
BY : ~~::-./ ----
Attory-inYact~er' -,.-,---
9737 Great Hills Trail. Ste. 320 -;._~ ·._. :: .
Address --,"' ::::-------··
Austin, TX 78 75 9 --::::_~=~-~-:---·
City/State/Zip
Note : Date of bond must no t be before the due of award of cont rac t
(I) Co rre ct mune or Contracto r
(2) A corpo ration, partn ership , or iJ,d ividu al as the ca.~e may be
(3 ) Correct nam e of Su rety
(4) 1 f Co nrractor is a partn ersh ip, the Contrn cl mu st be executed by
the managing or gene ra l pan ner of the part nershi p
ii
THE STA TE OF TEXAS
COUNTY OF TARRANT
MAINTENANCE BOND
§
§
Bond No. 4374880
KNOW ALL MEN BY THESE PRESENTS: That we (1) Lehne Construction, Inc.
as Principal, acting herein by and through (2)Lehne Construction, Inc.
its duly authorized Corporation and
(3) SureTec Insurance Company
a corporation organized and existing under the laws of the State of Texas , as
surety, do hereby acknowledge themselves to be held and bound to pay unto the City of
Fort Worth, a Municipal Corporation, chartered by virtue of Constitution and laws of the
State of Texas, at Fort Worth, in Tarrant County, Texas, the sum of:
Three Hundred Fifty Nine Thousand Seven Hundred Thirty Two and No 100's Dollars ($359,732.00 ), lawful
money of the United States, for the payment of which sum well and truly be made unto
said City of Fort Worth and its successors, said Contractor and surety do hereby bind
themselves, their heirs, executors, administrators, and assigns and successors, jointly and
severally.
This obligation is conditioned, however; that,
WHEREAS, the Principal has entered into a certain contract with the City of Fort
Worth, the Owner, dated June 2, 2009 for the performance of the following
described public work and the construction of the following described public
improvements:
Lake Worth Restoration and Maintenance
all of the same being referred to herein and in said contract as the Work and being
designated as Project No.(s)_W_T_R_-2_0_0_9 _-5_6_0_0 _01 ____________ _
and said contract, including all of the specifications, conditions and written instruments
referred to therein as contract documents being hereby incorporated herein by reference
for all purposes and made a part hereof, the same as if set out verbatim herein; and,
WHEREAS, in said Contract, Contractor binds itself to use such materials and to
so construct tlie work that it will remain in good repair and condition for and during the
period Two (2) Years after the date of the final acceptance of the work by the City; and,
WHEREAS, said Contractor binds itself to maintain said work in good repair and
condition for said term of Two (2) Years · and --~·-' ,
WHEREAS, sad Contractor binds itself to repair or reconstruct the work in whole
or in part at any time within said period, if in the opinion of the Director ofthe Water
Department of the City of Fort Worth, it is necessary; and,
WHEREAS, said Contractor binds itself, upon receiving notice of the need
thereof to repair or reconstruct said work as herein provided.
NOW THEREFORE, if said Contractor shall keep its said agreement to maintain,
repair or reconstruct said work in accordance with all the terms and conditions of said
F-5
contract, these presents shall be nulJ and void, and have no force or effect. Otherwise, this
Bond shall remain in full force and effect, and said City shall have and recover from the
said Contractor and its surety damages in the premises as prescribed by said contract.
This obligation shall be continuing one and successive reco veries may be had hereon for
successive breaches until the full amount hereof is exhausted.
WHEREAS, all parties covenant and agree that if any legal action be filed upon
this bond, venue shall lie in Tarrant County, Texas; and,
IN WITNESS WHEREOF, this instrument is executed in ___ counterparts,
each one of which shall be deemed an original, dated_J_u_n_e_2_;_,_2_0_0_9 _______ _
ATTEST:
ATTEST:
(Surety) Secretary
(SE AL)
/Jkt!1~
1405 E Riverside Dr , Austin, TX 78741
(Address)
12400 H
Austin TX 78738
(Address)
SureTec Insurance Company
By ~~)~~--
John-~ ~-
(Attorney-in-fact) (5) ---::::--""'v --...... ~ .. ~ ......
9737 Great Hills Trail. Ste. 320, A tfst ip ;-1')(7 8759
(Address)
NOTE: Date of Bond must not be prior to
date of Contract
(1) Correct Name of Contractor
(2) A Corporation, a Partnership or an
Individual, as the case may be
(3) Correct name of Surety
(4) If Contractor is Partnership, all
Partners should execute Bond
(5) A True copy of Power of Attorney
shall be attached to Bond by
Attorney-in-fact
F-6
Bond Number: 437 4880
POA #: 4221095
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
Know All Men by These Presents, That SURETEC INSURANCE COMPANY (the "Company"), a corporation duly organized and
existing under the laws of the State of Texas, and having its principal office in Houston, Harris County, Texas, does by these presents
make, constitute and appoint
John W. Schuler
of Austin , Texas its true and lawful Attorney(s)-in-fact, with full power and authority hereby conferred in its name, place and stead , to
execute, acknowledge and deliver any and all bonds, recognizances, undertakings or other instruments or contracts of suretyship to
include waivers to the conditions of contracts and consents of surety, providing the bond penalty does not exceed
Five Million Dollars and no/100 ($5,000,000.00)
and to bind the Company thereby as fully and to the same extent as if such bonds were signed by the President, sealed with the corporate
seal of the Company and duly attested by its Secretary, hereby ratifying and confirming all that the said Attomcy(s)-in-Fact may do in the
premises. Said appointment shall continue in force until 12/31/09 and is made under and by authority of the following
resolutions of the Board of Directors of the SureTec Insurance Company:
Be it Resolved, that the President, any Vice-President, any Assistant Vice-President, any Secretary or any Assistant Secretary shall be and is
hereby vested with full power and authority to appoint any one or more suitable persons as Attomey(s)-in-Fact to represent and act for and on
behalf of the Company subject to the following provisions :
Attorney-in-Fact may be given full power and authority for and in the name of and of behalf of the Company, to execute, acknowledge and
deliver, any and all bonds , recognizances, contracts, agreements or indemnity and other conditional or obligatory undertakings and any and all
notices and documents canceling or tetminating the Company 's liability thereunder, and any such instruments so executed by any such
Attorney-in-Fact shall be binding upon the Company as if signed by the President and sealed and effected by the Corporate Secretary.
Be it Resolved, that the signature of any authorized officer and seal of the Company heretofore or hereafter affixed to any power of attorney or
any certificate relating thereto by facsimile, and any power of attorney or certificate bearing facsimile signarure or facsimile seal shall be valid
and binding upon the Company with respect to any bond or undertaking to which it is attached . (Adopted al a meeting held on 2t1• of April,
1999)
In Witness Whereof, SURETEC INSURANCE COMP ANY has caused these presents to be signed by its President, and its corporate seal
to be hereto affixed this 20th day of June, A.O. 2005.
!:>~~_c~ ruf~-,.. ~-.. ..a)i
itiu [J': State of Texas s.s : i \,.:'._;· _,/ '<" County of Harris --,
On this 20th day of June, A.O. 2005 before me personally came Bill King, to me known, who, being by me duly sworn , did depose and say, that he
resides in Houston, Texas, that he is President of SURETEC INSURANCE COMPANY, the company described in and which executed the above
instrument ; that he knows the seal of said Company; that the seal affixed to said instrument is such corporate seal; that it was so affixed by order of the
Board of Directors of said Company; and that he signed his name thereto by like order.
My commission expires August 27, 2008
I, M. Brent Beaty, Assistant Secretary ofSURETEC INSURANCE COMPANY , do hereby certify that the above and foregoing is a true and correct copy
of a Power of Attorney, executed by said Company, which is still in full force and effect; and furthermore , the resolutions of the Board of Directors, set
out in the Power of Attorney are in full force and effect.
Given under my hand and the seal of said Company at Houston, Texas this 2nd ,A.D.
--;: Any Instrument Issued In excess of the penalty stated above is totally vo·i_ii fin d wlttiout anpalldlty.
For verification of the authority of this power you may call (713) 812-0BOltany ti_uslness day be.tween 8:00 am and 5:00 pm CST.
, ---
. '
SureTec Insurance Company
THIS BOND RIDER CONTAINS IMPORTANT COVERAGE INFORMATION
Statutory Complaint Notice
To obta in information or make a compla int: You may call the Surety's toll free telephone number for information or to
make a complaint at: 1-866-732-0099. You may also write to the Surety at:
SureTec Insurance Company
9737 Great Hills Trail , Suite 320
Austin , Tx 78759
You may contact the Texas Department of Insurance to obtain information on compan ies, coverage , rights or complaints
at 1-800-252-3439. You may write the Texas Department of Insurance at:
PO Box 149104
Austin , TX 78714-9104
Fax#: 512-475-1771
Web : http://www.tdi.state.tx.us
Email: ConsumerProtection@tdi.state .tx .us
PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning your premium or about a claim , you should
contact the Surety first. If the dispute is not resolved, you may contact the Texas Department of Insurance .
Terrorism Risks Exclusion
The Bond to which this Rider is attached does not provide coverage for , and the surety shall not be liable for, losses
caused by acts of terrorism , riot , civil insurrection , or acts of war.
Exclusion of Liability for
Mold, Mycotoxins, Fungi & Environmental Hazards
The Bond to which this Rider is attached does not provide coverage for, and the surety thereon shall not be liable for ,
molds, living or dead fungi , bacteria , allergens, histamines, spores , hyphae, or mycotoxins , or the ir related products or
parts , nor for any environmental hazards , bio-hazards, hazardous materials, environmental spills, contamination , or
cleanup , nor the remediation thereof, nor the consequences to persons , property, or the performance of the bonded
obligations , of the occurrence , existence, or appearance thereof.
. .
CONTRACTOR COMPLIANCE WITH
WORKER'S COMPENSATION LAW
Pursuant to Article 8308-3.23 ofVeron's Annotated Civil Statues, Contractor Certifies
that it provides worker's compensation insurance coverage for all of its employees
employed on City of Fort Worth Project
Number Aov1'J -5?!?elJ /
STATE OF TEXAS §
COUNTY OF TARRANT §
Date
BEFORE ME, the undersigned authority, on this day personally appeared ___ _
/3 1/11)/IJ L~HA ft . known to me to be the person whose name is subscribed
to the forego~ng instrument, and acknowledged to me that he executed the same as the act
and deed of Lf:H1t!E: f ~.,i J:f[~, ;J:t/&I the purpose and consideration therein
expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this ~t!J of ~,
~Ro o1-
Billie D Whaley
My Commission Expires
03/0812010
Notary Public in and for the State of
Page 1 Of 1
.
VENDOR COMPLIANC E TO ST AT E L AW
The 1985 Session of the Texas Legi slature passed House Bill 620 relative to the
award of contracts to nonresident bidders . This law provides that , i n order to be
awarded a contract as low bidder, nonresident bidders (out-of-state contractors
whose corporate offices or principal place of business are outside of the State of
Texas) bid projects for construction , improvements , supplies or services in Texas at
an amount lower than the lowest Texas resident bidder by the same amount that a
Texas resident bidder would be required too underbid a nonresident bidder in order
to obtain a comparable contract in the State in which the nonresident's principal
place of business is located . The appropriate blanks in Section A must be filled out
by all out-of-state or nonresident bidders in order for your bid to meet specifications .
The failure of out-of-state or nonresident contractors to do so will automat ically
disqualify that bidder. Resident bidders must check the box in Section B.
A. Nonresident vendors in (give State), our principal place of
business , are required to be percent lower than resident bidders
by State law. A copy of the Statute is attached .
Nonresident vendors in (give State), our principal
place of business , are not required to underbid resident bidders .
B. Our principal place of business or corporate offices are in the State of Texas . .tJ
BIDDER:
By :____cd;:.._.:_J?..J.....LL./lf.<...C...l.}y~j £'--..L))...:.....:....:W~k __
(Please print)
Address
City /State/Z(p
Title :--'-~-X _£_5 --"f P_E:_..ctv__.T'-----
(Please print)
TH IS F ORM MUST BE RETURNED W IT H YOU R Q UOTATI ON
HEAVY & HIGHWAY CONSTRUCTION
PREVAILING WAGE RATES 2008
Air Tool Ooerator
Asphalt Distributor Operator
Asphalt Paving Machine Operator
Asphalt Raker
Asphalt Shoveler
Batching Plant Weigher
Broom or Sweeper Operator
Bulldozer Operator
Carpenter
Concrete Finisher, Paving
Concrete Finisher, Structures
Concrete Paving Curbing Machine Operator
Concrete Paving Finishing Machine Operator
Concrete Paving Joint Sealer Operator
Concrete paving Saw Operator
Concrete Paving Spreader Operator
Concrete Rubber
Crane, Clamshell , Backhoe, Derrick, Dragline, Shovel Operator
Electrician
FJagger
Fonn Builder/Setter, Structures
Form Setter, Paving & Curb
Foundation Drill Operator, Crawler Mounted
Foundation Drill Operator, Truck Mounted
Front End Loader Operator
Laborer, Common
Laborer, Utility
Mechanic
Milling Machine Operator, Fine Grade
Mixer Operator
Motor Grader Operator, Fine Grade
Motor Grader Operator, Rough
Oiler
Painter, Structures
Pavement Marking Machine Operator
Pioelayer
Reinforcing Steel Setter, Paving
Reinforcing Steel Setter, Structure
Roller Operator, Pneumatic, Self-Propelled
Roller Operator, Steel Wheel, Flat Wheel/Tamping
Roller Operator, Steel Wheel, Plant Mix Pavement
Scraper Operator
Servicer
Slip Form Machine Operator
Spreader Box Operator
Tractor Operator, Crawler Type
Tractor Operator, Pneumatic
Traveling Mixer Operator
Truck Driver, Lowboy-Float
Truck Driver Single Axle, Heavy
Truck Driver, Single Axle, Light
Truck Driver, Tandem Axle, Semi-Trailer
Truck Driver, Transit-Mix
Wagon Drill , Boring Machine, Post Hole Driller Operator
Welder
Work Zone Barricade Servicer
$10 .06
$13 .99
$12 .78
$11.01
$ 8.80
$14 .15
$ 9 .88
$13 .22
$12 .80
$12 .85
$13.27
$12 .00
$13.63
$12 .50
$13.56
$14.50
$10 .61
$14.12
$18 .12
$ 8.43
$11.63
$1 1.83
$13.67
$16.30
$12 .62
$ 9.18
$10 .65
$16.97
$11.83
$11.58
$15.20
$14 .50
$14 .98
$13 .17
$10 .04
$11.04
$14 .86
$16 .29
$11.07
$10.92
$11.28
$11.42
$12.32
$12.33
$10 .92
$12.60
$12 .91
$12 .03
$14 .93
$11.47
$10 .9 1
$11.75
$12.08
$14.00
$13.57
$10.09
Classification
AC Mechan ic
AC Mechani c Helper
Acoustical Ceiling Mechan i c
Bricklayer/Stone Mason
Bricklayer/Stone Mason Helper
Carpenter
Car penter Helper
Concrete Finisher
Concrete Form Bu ilder
Drywall Mechanic
Drywall Helper
Drywall Taper
Drywall Taper Helper
Electrician (Journeyman)
Electrician Helper
Electron ic Technician
Electronic Te chnician Helper
Floor Laye r (Resilient)
Floor Layer Helper
Glazie r
Glazier Helper
Insulator
Insulator Helper
Laborer Common
Laborer Skilled
Lather
Painter
Painter Helper
Pipefitter
Pipefitter Helper
Plasterer
Pl asterer Helper
2008 PREVAILING WAGE RATES
CONSTRUCTION INDUSTRY
I Hdy Ra<e ! Classification
$21.69 Plumber
$12.00 Plumber Helper
$15.24 Re i nfor cing Steel Setter
$19.12 Roofer
$10 .10 Roofer He l per
$16 .23 Sheet Metal Worker
$11.91 Sheet Metal Worker Helper
$13.49 Sprinkler System Installer
$13 .12 Sprinkler Svstem Insta ller Helper
$14.62 Steel Worker Structural
$10. 91 Concrete Pump
Crane , Clamsheel , Backhoe, Derrick, D'Line
$13.00 Shovel
$9 .00 Forkl i ft
$20.20 Front End Loader
$14 .43 Truck Dri ver
$19.86 Welder
$12 .00 Welder Helper
$20 .00
$13.00
$1 8.00
$13 .00
$14.78
$11.25
$1 0.27
$13.18
$16.10
$14.83
$8.00
$18 .85
$12.83
$17 .25
$12 .25
Hrly Rate
$20.4 3
$14.90
$10 .00
$14.00
$10.00
$16 .96
$12 .31
$18 .00
$9.00
$17.43
$20.50
$17. 76
$12 .63
$10 .50
$14 .91
$16.06
$9.75
PART "G"
CONTRACT
-
PART G -CONTRACT
THE STATE OF TEXAS §
COUNTY OF TARRANT §
THIS CONTRACT, made and entered into June 2 2009 ~=~~~---------
______________ by and between the City of Fort Worth , a home-rule
municipal corporation located in Tarrant County. Texas, acting through its City Manager
thereunto duly authorized so to do , Party of the First Part, hereinafter termed "OWNER"
and Lehne Construction Inc.
of the City of _A_u_st_in _________ , County of _T_r_a_v_is ________ _
and State of Texas Party of the Second Part. Hereinafter termed
"CONTRACTOR"
WITNESSETH: That for and in consideration of the payments and
agreements hereinafter mentioned, to be made and performed by the Party of the First
Part (Owner), said Party of the Second Part (Contractor) hereby agrees with the said Party
of the First Part (Owner) to commence and complete certain improvements described as
follows:
Lake Worth Restoration and Maintenance Project
WTR-2009-560001
and all extra work connected therewith, under the terms as stated in the Contract
Documents , and at his (their) own proper cost and expense to furnish all materials ,
supplies , machinery, equipment, tools , superintendence, labor , bonds , insurance , and
other accessories and services necessary to complete the said construction, in accordance
with all the requirements of the Contract Documents , which include all maps , plats ,
blueprints and other drawings and printed or other written explanatory matter thereof, and
the specifications thereof, as prepared by the Engineers employed by the Owner, each of
which has been identified by the endorsement of the Contractor and the Engineers
thereon , together with the Contractor 's Written Proposal and other parts of the Contract
Documents hereto attached , including the Fort Worth Water Department General
Contract Documents and General Specifications, all of which are made a part hereof and
collectively evidence and constitute the entire contract.
G-1
OFFICIAL RECORD
ITV SECRETARY
.WORTH , TX
I~
'
I
'!
I
The Contractor hereby agrees to commence work within ten (10) days after the
date written notice to do so shall have been given to him, and to substantially complete
same within the time stated in the Proposal.
The Owner agrees to pay the Contractor in current funds for the performance of
the contract in accordance with the Proposal submitted therefor, subject to additions and
deductions, as provided in the Contract Documents and all approved modifications
therefor, and to make payment on account thereof as provided therein.
IN WITNESS WHEREOF, the Parties to these presents have executed this ·
Contract in quadruplicate the year and the day first above written.
ATTEST:
-
ill ~~ Marty H~tary
(SEAL)
WITNESSES:
City of Fort Worth, Texas (Owner)
Party of the First Part
4
Fernando Costa, Assistant City Manager
con,~act Authorizatioa
\f'/£}05 _.
Da te
By~~~~~~~~~~~
the Fort Worth City Water Departmfnt:
S. Frank Crumb, PE, Water Director
Approved as to Form and Legality: .
G-2
Brian Lehne
President
Lehne Construction , Inc.
FFICIAL RECORD
ITV SECRETAR
.WORTH, TX
PART "H"
AREA LOCATIONS ( UNITS I,11,III ) & PROJECT SIGN DETAIL
Boat Ramp Replacement-Arrow S Park t
Marker Buoy -Float Line, Lake Worth t
Brush and Tree Removal Areas
2.f~"
2. S"'
l .5''
1.5"'
I. ..
FORT WORTH _.,,., .
Yoi1,r Water
J?u,ids ll1 Actio,z
White ----Background
~·. o·
----+-
3 It
Radius
Dark
Blue
PROJECT SIGN
Figure 30A Scale 1 " = I'