HomeMy WebLinkAboutContract 46429-CO1 (2)FORT�OP��TH:., City of Fort Worth Change Order Request Breakdown Project Name 2014 CIP CONCRETE REPLACEMENT-CONTRACT 1 Client Project #(s)� DOE 7314 Profect # 02370 Contractor CD Builders PM T. Islam Change Order Submittal # Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Ortlers (in M&C Process) Contract Cost to Date t of Pro e Order Revisetl Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) T/PW $1,788,766.71 $15Q,245.00 $1,939,011.71 $0,00 $150,245.00 .� '., r, - _ - - _ City Sec # 46429 Inspector Ali Motamed � Date 7/30/2015 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTR.4CT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) Totals � $1,788,766.71 $150.245.00 $1,939,011.71 �� 8,40% $2,235,958.39 210 210 45 JUSTfFICATION (REASONS) FOR CHANGE ORQER This change order is to allow payment to the contractor for additional sub-drain to be installed within the parkway along Heritage Trace Parkway from North Freeway to Ben Hogan Lane. Additional utility adjustment quantities and sod repiacement are needed for work done on irrigation systems within the parkway. e � �l Pii�3�!/'iiii9 � ALf V��IU39dV_ %J �a C� r�'af��' �_ ` �. ��G����e , a`�0�6 FEe pR�l� r�,fi� Q��oCRti g�l ,� Isi4' �}r : � , ,t�, ' . i c�� ' 3 � ► � � � o� t� � o �� `�� Y pFFICIAL RECORD CITY SECRETARV F'T. WAR'�'H, TX Contract Time `` FaRt :��R��H city of Fort wortn , Change Order Additions Project Name 2014 CIP CONCRETE REPLACEMENT-CONTRACT 7 City Sec # 46429 Ciient Project # DOE 7314 Profect # 02370 ConVactor CD Builders PM� T. Islam Inspector Ali Motamed Change Order Submittal #�1 Date 7/30/2015 ADDITIONS TEM DE RIPTI N DEP ty mt nit ost ota -nc "PIPE DERORAI T PE T/P 5 12-inc MISCELLANEOUS ADJUSTMENT UTILITIES T/PW 2.00000000 LS �15,000.00 11-Inc BLOCK SOD PLACEMENT TlPW 1,700.00000000 SY $3.65 , 5. T/PW $150,245.00 S�b Total Additions 5150,245.00 Change Order Additions Page 1 ot 1 � c�ry of Fort wortn Change Order Deletions Project Name 2014 CIP CONCRETE REPLACEMENT-CONTR4CT 1 City Sec # 46429 Client Project # DOE 7314 Profect # 02370 Contractor CD Builders PM� T. Islam � Inspector Ali Motamed Change Order Submittal # O7 Date 7/30/2015 I�I���I[�I��' ITEM DESCRIPTION DEPT Qty Unit UnitCost Total T/PW $0.00 Sub Total Dele6ons Change Order Deletions Page 1 of 1 ■�IAl1l� !� � � • •� • w� w • CFW Change Order Approval St-COApp03 Routinq Assigned To: Assigned By: Links 3 Page 1 of 3 Due Date: Due Time: fortworthaov/Infrastructure Proiects/02370 - 2014 CIP Concrete Reqlacement Contract 1/Contractor/Chanqe Orders/Acceotance of Previous MBE Commitment Form 02370.ndf fortworthaov/Infrastructure Proiects/02370 - 2014 CIP Concrete Replacement Contract 1/Contractor/Chanqe Orders/Chanae Order #1 Breakdown DOE 7314.xis fortworthaov/Infrastructure Proiects/02370 - 2014 CIP Concrete Reolacement Contract 1/Contractor/Chancte Orders/M&C CD Builders ChanQe Orderi.odf Attachments (0) No Aftachments have been added to this form. https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 2/4/2016 CFW Change Order Approval St-COApp03 p s � . � �' �_ � �' � � � -�'"° . •' � •' �' • ' � • • • .� w�,...�� , ��� � �� -".;�,�.,�r.'-, • ' � � ' • • � . • Page 2 of 3 For Change Order Submittal No.: ......................... ,. ._ _ __ __ _ _ __. Change Order No.: St-COApp03 Date Started: 2015-12-21 City Sec. No.: 46429 Date Due: 2016-01-08 __ _ _ _..._ _.. -` -_ Project Name: 2014 CIP Concrete Replacement Contract 1 ; 02370 iDOE Numbers: Project Numbers: ; Project Description Remove and replace damaged concrete panels, driveways, subdrain at various locations. . -___ _ __ __ __ ____ _ __ ___ _ _ _ _ _ _ _ _. Project Manager: Tariqul Islam City Inspector:' Contractor: _ ._ _ _ _ _ __ _ _ _ __ _ __ COUNCIL ACTION (If Required): M&C Log Name: ° __ _ M&C Number: COST AND DAYS SUMMARY: Department: Cost($) __ _. _ __ _ tpw ;$ 150,245.00 _._ __ _. _ ._ _ __ _ _ _. __ _ __ _ _ _ __ _ ___ .__ _ _ Approval Status: Total Cost• � 150,245.00' M&C Date: i2015-12-15 Fund Account Center: Requested Days: ' 45 . __ __ Total Requested Days:;45 https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 2/4/2016 CFW Change Order Approval St-COApp03 _ _ __ _ !Approved : Yes 'Comments: User: Rebeca Cruz Date: 2016-01-06 4:04 PM Approved: Yes Cornments: User: Tariqul Islam Date: 2016-01-06 4:53 PM Approved: Yes Comments: User: Riad Nusrallah Date: 2016-01-06 11:01 PM Approved: Yes Comments: User: Todd Blomstrom Date: 2016-01-07 6:15 PM Approved: Yes Comments: User: Doug Wiersig Date: 2016-01-27 5:35 PM Approved: Yes Comments: User: Doug Black Date: 2016-02-03 2:37 PM Page 3 of 3 Approved: Yes Comments: User: )ay Chapa Date: 2016-02-04 10:35 PM Action Required: _ __ _ . ; https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 2/4/2016 o �(��� � co,oz ( i Lanauage to be insarted In khe MB�C for this Cantract CD Buifders inc. agrees to malntain its initlal M�� commitment of 19% fhat It made on the original contraci and exfend and maintain that same M�E commitment of 19% to this �rst change order. Therefore CD Builders lnc, remains In compllance with the City's BDE Ordinanoe and atfests to its aommitment by (ts signature�an the Acceptance of Previous MBE Commitment form executed by an authorized representative of Its company. To be Compl�ted by the �tepresentative of the ISMAEI. GARRASQUIl,1,0 PRESIU�NT Li���t-1�"'_�,�,�� � Prfnted Sfgnature T Title Aut rized Si ature/Date CD Buf(ders !na R�BECA CRUZ Company Name Contacf Name (if different) 90�8 TRINITY BOULEVAF�D Addrass FQRT WORTH, TEXAS 78053 RCRUz@CDBUILQERSTX.COM �-mail address 817-510•6557 $97-510-6558 Phone number �ax Number 3, 72� as of 09/08/2015 MBE % Paid to Aate Date � 1�. . ,�.�: ¢�� �tyf •�y;.:�.:..;'.i4tj}l,tit��,,4 �'{� ,�_ ��• at�vit;�.. 'fi.� it�,s.t. � } {' ?"'�,'s`�`:�"'�` '� F,•�'�`(t�q''{i:;u., .,.. .{t k,;� ,. �:�i'y;;u.l'dal•i+C _, �.�s.�.�'.Yx�_�? �.{: ,ci{ ; �i+'y.�� 1s.Si• z �y � dc:, ��ti�a • . y. .k..a�.�..;k.:� 2:. �', r., (D #� MB� Current % Level via i.ast Report Rec'd ';;>r>;���;':: � G��"r,::;.fa ';i'1 ,/�y� v j �...,i5>,•,,l�ytiyt•: :JE. ' ..;� 1 . �• .1.'.7j (;�,. ',c,; :` S,';'<1•`.•• ,; sy:�.yi..;. ;� f; :L��' t �'�i��.,'��_(=:i�; (+��:''�� ti � � •�i'. e 3.� :..4�: t {l5 :.;;t,�:::,:L}7{'S:,,;•.P..i?.�rl ate i i � ; I �„ r..�*`'�H City of Fort War�h ACCEP7ANCE OF PREVIUUS MBE CQMMf�'MENT F�RM (for usa with CNANGE ORD�F2S or AMENpMEN75 greater than �So,UDo) City of F,ort Worth, Texas Mayor and Council Communication COUNCIL ACTION: Approved on 12/15/2015 DATE: Tuesday, December 15, 2015 REFERENCE NO.: **G27559 LOG NAME: SUB.TECT: 202014 CIP CONCRETE REPLACEMENT CONTRACT 1 CHANGE ORDER 1 Authorize Execution of Change Order No. l to City Secretary Contract No. 46429 with CD Builders, Inc., in the Amount of $150,245.00 for Additional Sub—Drain to be Installed Within the Parkway Along Heritage Trace Parkway from North Freeway to Ben Hogan Lane for a Revised Total Contract Amount of $],939,01 l.7l (2014 BOND PROGRAM) (COLTNCIL DISTRICT 4) RECOMMENDATION: It is recommended that the City Council authorize the execution of Change Order No. 1 to City Secretary Contract No. 46429 with CD Builders, Inc., in the amount of $150,245.00, for additional sub—drain work within the parkway along Heritage Trace Parkway for a revised total contract amount of $1,939,011.71 and provide for construction management and other project costs in the amount of $22,000.00 for a revised total project amount of $2,231,011 .71. DISCUSSION: On December 9, 2014 (M&C C&minus;27129), the City Council awarded City Secretary Contract No. 46429 in the amount of $1,788,766.71 to CD Builders, Inc., for replacement of various street segments throughout the City of Fort Worth. Change Order No. 1 will provide additional funding for installation of sub—drain within the parkway along Heritage Trace Parkway from North Freeway to Ben Hogan Lane. Additional utility adjustment and sod replacement for work on the irrigation system within the parkway are also included in this change arder. Project budget is as follows: The estimated completion date will be extended to January 2016 as a result of the additional work capacity added by this change order. Upon completion of this capital project, there will be no annual operating impact to the Transportation and Public Works Department's operating budget. This project is included in the 2014 Bond Program. Available resources within the General Fund will be used to provide interim financing for these expenses until debt is issued. Once debt associated with this project is sold, bond proceeds will reimburse the General Fund in accordance with the statement expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance No. 21241—OS-2014). M/WBE OFFICE — CD Builders Inc., agrees to maintain its initial MBE commitment of 19 percent that it made on the original contract and extend and maintain that same MBE commitment of 19 percent to this first change order. Therefore CD Builders Inc., remains in compliance with the City's BDE Ordinance and attests to its commitment by its signature on the Acceptance of Previous MBE Commitment Form executed by an authorized representative of its company. In addition to the change order amount, $22,000.00 is required for project management, material testing and inspection. The project is located in COLTNCIL DISTRICT 4, Mapsco 21 Y. FISCAL INFORMATION / CERTIFICATION: The Financial Management Services Director certifies that funds are included in the approved budget to date of the 2014 Bond Program and funds are available in the General Fund to pay expenses which will be incurred on this contract until reimbursement can occur from the issuance of public securities. FUND Existing Efacumbrances/Fxpenditrcres Refnaining ppropriations Balance 2014 Bond � 2�g60,000.00 $ 2,028,043.16 $ 83],956.84 Program 34014 FUND IDENTIFIERS (FIDsI: TO FundDepartment IDAccountProject IDProgramActivityBudget Year Reference �) Chartfield Amount FRONI Department Project Budget Reference # (Chartfield Fund ID Account ID ProgramActivity year 2� Amount 34014 0200431 5740010 CO2370 14010199 $150,245.00 CERTIFICATIONS: Submitted for Citv Manager's Office b�:, Originating Department Head: Additional Information Contact: Jay Chapa Douglas W (5804) Wiersig (7801) Tariqul Islam (2486) ATTACHMENTS 1. Available Fund GL0019-07 — Project Budget Summarv.�df �cFw i,�rernal> 2. Ma� CO1 CIP CR 2014-1.�df �Public> 3. MBE APCF CO#1 .�df (CFw Internal)