HomeMy WebLinkAboutContract 56036 Received Date: 07/21/2021
Received Time: 10:45 AM
Developer and Project Information Cover Sheet:
Developer Company Name: Lennar Homes of Texas Land and Construction,Ltd.
Address, State,Zip Code: 1701 Market Place Blvd.,Irving,TX, 75063
Phone &Email: 214-577-1056,jennifer.eller@lennar.com
Authorized Signatory,Title: Jennifer Eller,Authorized Agent
Project Name: Northpointe Phase 6
Brief Description: Water, Sewer,Paving, Storm Drain,and Street Lights
Project Location: Intersection of Old Decatur Rd. and Heritage Trace Blvd,
Plat Case Number: None Plat Name: None
Mapsco: Council District: 7
CFA Number: CFA21-0056 City Project Number: 103033
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth,Texas Page 1 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
CSC No.56036
STANDARD COMMUNITY FACILITIES AGREEMENT
This COMMUNITY FACILITIES AGREEMENT("Agreement") is made and entered into by
and between The City of Fort Worth ("City"), a home-rule municipal corporation of the State of Texas,
acting by and through its duly authorized Assistant City Manager,and Lennar Homes of Texas Land and
Construction, Ltd ("Developer"), acting by and through its duly authorized representative. City and
Developer are referred to herein individually as a"party"and collectively as the "parties."
WHEREAS, Developer is constructing private improvements or subdividing land within the
corporate limits of Fort Worth, Texas or its extraterritorial jurisdiction, for a project known as
Northpointe Phase 6("Project"); and
WHEREAS, the City desires to ensure that all developments are adequately served by public
infrastructure and that the public infrastructure is constructed according to City standards;and
WHEREAS, as a condition of approval of the Project, Developer is required to bear a portion of
the costs of municipal infrastructure by constructing the public infrastructure necessary for the Project as
described in this Agreement("Community Facilities"or"Improvements");and
WHEREAS,as a condition of approval of the Project,Developer is required to meet the additional
obligations contained in this Agreement,and Developer may be required to make dedications of land,pay
fees or construction costs,or meet other obligations that are not a part of this Agreement.; and
WHEREAS,the City is not participating in the cost of the Improvements or Project;and
WHEREAS, the Developer and the City desire to enter into this Agreement in connection with
the collective Improvements for the Project;
NOW,THEREFORE,for and in consideration of the covenants and conditions contained herein,
the City and the Developer do hereby agree as follows:
1.
CFA Ordinance
The Community Facilities Agreements Ordinance("CFA Ordinance"),as amended,is incorporated
into this Agreement by reference, as if it was fully set forth herein. Developer agrees to comply with all
provisions of the CFA Ordinance in the performance of Developer's duties and obligations pursuant to this
Agreement and to cause all contractors hired by Developer to comply with the CFA Ordinance in
connection with the work performed by the contractors. If a conflict exist between the terms and conditions
of this Agreement and the CFA Ordinance,the CFA Ordinance shall control.
2.
Incorporation of Engineering Plans
The engineering plans for the Improvements that have been accepted by the City ("Engineering
Plans")are incorporated into this Agreement by reference as if fully set out herein. Developer shall provide
City of Fort Worth,Texas Page 2 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
at its expense, unless otherwise agreed to by City, all engineering drawings and documents necessary to
construct the Improvements required by this Agreement.
3.
Description of Improvements; Exhibits and Attachments
The following exhibits describe the general location, nature and extent of the Improvements that
are the subject of this Agreement and are attached hereto and incorporated herein by reference:
❑X Exhibit A: Water
❑X Exhibit A-1: Sewer
❑X Exhibit B: Paving
❑X Exhibit B-1: Storm Drain
❑X Exhibit C: Street Lights & Signs
The Location Map and Cost Estimates are also attached hereto and incorporated herein by
reference. To the extent that Exhibits A, A-1, B, B-1, C, the Location Map, or the Cost Estimates
conflict with the Engineering Plans, the Engineering Plans shall control. If applicable,Attachment 1 —
Changes to Standard Community Facilities Agreement, Attachment 2 — Phased CFA Provisions, and
Attachment 3 — Concurrent CFA Provisions, are attached hereto and incorporated herein for all
purposes.
4.
Construction of Improvements
Developer agrees to cause the construction of the Improvements contemplated by this Agreement
and that said construction shall be completed in a good and workmanlike manner and in accordance with
all City standards and specifications, the Engineering Plans, the Cost Estimates provided for the
Improvements,and this Agreement. Developer acknowledges that City will not accept the Improvements
until the City receives affidavits and lien releases signed by Developer's contractors verifying that the
contractors, and all subcontractors and material suppliers, have been paid in full for constructing the
Improvements, and consent of the surety on payment and performance bonds provided for the
Improvements.
5.
Financial Guarantee
Developer has provided the City with a financial guarantee in the form and amounts set forth in
this Agreement which guarantees the construction of the Improvements and payment by Developer of
all contractors, subcontractors, and material suppliers for the Improvements ("Financial Guarantee").
Developer shall keep the Financial Guarantee in full force and effect until released by the City and shall
not reduce the amount of the Financial Guarantee unless authorized by the City in accordance with the
CFA Ordinance.
6.
Completion Deadline; Extension Periods
This Agreement shall be effective on the date this Agreement is executed by the City's Assistant
City Manager ("Effective Date"). Developer shall complete construction of the Improvements and
obtain the City's acceptance of the Improvements within two (2) years of the Effective Date ("Term").
City of Fort Worth,Texas Page 3 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
If construction of the Improvements has started during the Term, the Developer may request that this
Agreement be extended for an additional period of time ("Extension Period"). All Extension Periods shall
be agreed to in writing by the City and the Developer as set forth in a written amendment to this Agreement.
In no event shall the Term of this Agreement plus any Extension Periods be for more than three years.
7.
Failure to Construct the Improvements
(a) The City may utilize the Developer's Financial Guarantee to cause the completion of the
construction of the Improvements if at the end of the Term, and any Extension Periods, the
Improvements have not been completed and accepted by the City.
(b) The City may utilize the Developer's Financial Guarantee to cause the completion of the
construction of the Improvements or to cause the payment of costs for construction of the
Improvements before the expiration of the Term, and any Extension Period, if the Developer
breaches this Agreement,becomes insolvent,or fails to pay costs of construction.
(c) If the Financial Guarantee is a Completion Agreement and the Developer's contractors or suppliers
are not paid for construction costs or materials supplied for the Improvements the contractors and
suppliers may place a lien upon any property which the City does not have an ownership interest
that is the subject of the Completion Agreement.
(d) Nothing contained herein is intended to limit the Developer's obligations under the CFA
Ordinance, this Agreement, the Financial Guarantee, Developer's agreements with Developer's
contractors,or other related agreements.
8.
Termination
If Developer desires to terminate this Agreement before Developer's contractors begin
constructing the Improvements, Developer agrees to the following:
(a) that Developer and City must execute a termination of this Agreement in writing;
(b) that Developer will vacate any final plats that have been filed with the county where the Project
is located; and
(c) to pay to the City all costs incurred by the City in connection with this Agreement, including
time spent by the City's inspectors at preconstruction meetings.
9.
Award of Construction Contracts
(a) Developer will award all contracts for the construction of the Improvements and cause the
Improvements to be constructed in accordance with the CFA Ordinance.
(b) Developer will employ construction contractors who meet the requirements of the City to construct
the Improvements including,but not limited,to being prequalified,insured,licensed and bonded to
construct the Improvements in the City.
City of Fort Worth,Texas Page 4 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
(c) Developer will require Developer's contractors to provide the City with payment and performance
bonds naming the City and the Developer as dual obligees, in the amount of one hundred percent
(100%) of the cost of the Improvements as required by the CFA Ordinance. The payment and
performance bonds shall guarantee construction of the Improvements and payment of all
subcontractors and material suppliers. Developer agrees to require Developer's contractors to
provide the City with a maintenance bond naming the City as an oblige, in the amount of one
hundred percent(100%) of the cost of the Improvements, that guarantees correction of defects in
materials and workmanship for the Improvements by the contractor and surety for a period of two
(2)years after completion and final acceptance of the Improvements by the City. All bonds must
be provided to the City before construction begins and must meet the requirements of the City's
Standard Conditions,Chapter 2253 of the Texas Government Code,and the Texas Insurance Code.
(d) Developer will require Developer's contractors to provide the City with insurance equal to or in
excess of the amounts required by the City's standard specifications and contract documents for
developer-awarded infrastructure construction contracts. The City must be named as an additional
insured on all insurance policies. The Developer must provide the City with a Certificate of
Insurance (ACORD or form approved by the State of Texas), supplied by each contractor's
insurance provider,which shall be made a part of the Project Manual.
(e) Developer will require the Developer's contractors to give forty-eight(48)hours' advance notice
of their intent to commence construction of the Improvements to the City's Construction Services
Division so that City inspection personnel will be available. Developer will require Developer's
contractors to allow construction of the Improvements to be subject to inspection at any and all
times by the City's inspectors. Developer will require Developer's contractors to not install or
relocate any sanitary sewer, storm drain,or water pipe unless a City inspector is present and gives
consent to proceed, and to allow such laboratory tests as may be required by the City.
M Developer will not allow Developer's contractors to begin construction of the Improvements until
a notice to proceed to construction is issued by the City.
(g) Developer will not allow Developer's contractors to connect buildings to service lines of sewer and
water mains constructed pursuant to this Agreement, if any, until said sewer, water mains and
service lines have been completed to the satisfaction of the City.
10.
Utilities
Developer shall cause the installation or adjustment of utilities required to: (1) serve the Project;
and (2) to construct the Improvements required herein. City shall not be responsible for payment of any
costs that may be incurred by Developer in the relocation of any utilities that are or may be in conflict with
any of the Improvements to be constructed pursuant to this Agreement.
11.
Easements and Rights-of-Way
Developer agrees to provide,at its expense,all necessary rights-of-way and easements required for
the construction and dedication to the City of the Improvements provided for by this Agreement.
City of Fort Worth,Texas Page 5 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
12.
Liability and Indemnification
(a) DEVELOPER HEREBY RELEASES AND AGREES TO INDEMNIFY, DEFEND AND
HOLD THE CITY HARMLESS FOR ANY INADEQUACIES IN THE PRELIMINARY
PLANS, SPECIFICATIONS, ENGINEERING PLANS, AND COST ESTIMATES
SUPPLIED BY THE DEVELOPER FOR THIS AGREEMENT.
(b) THE DEVELOPER COVENANTS AND AGREES TO,AND BY THESE PRESENTS DOES
HEREBY FULLY INDEMNIFY, HOLD HARMLESS AND DEFEND THE CITY, ITS
OFFICERS,AGENTS AND EMPLOYEES FROM ALL SUITS,ACTIONS OR CLAIMS OF
ANY CHARACTER, WHETHER REAL OR ASSERTED,BROUGHT FOR OR ONACCOUNT
OFANYINJURIES OR DAMAGES SUSTAINED B YANY PERSONS,INCL UDING DEATH,
OR TO ANY PROPERTY, RESULTING FROM OR IN CONNECTION WITH THE
CONSTRUCTION,DESIGN, PERFORMANCE OR COMPLETION OF ANY WORK TO BE
PERFORMED BY SAID DEVELOPER, ITS CONTRACTORS, SUBCONTRACTORS,
OFFICERS, AGENTS OR EMPLOYEES, OR IN CONSEQUENCE OF ANY FAIL URE TO
PROPERLY SAFEGUARD THE WORK, OR ONACCOUNT OFANYACT,INTENTIONAL
OR OTHERWISE, NEGLECT OR MISCONDUCT OF SAID DEVELOPER, ITS
CONTRACTORS, SUB-CONTRACTORS, OFFICERS, AGENTS OR EMPLOYEES,
WHETHER OR NOT SUCHINJURIES,DEATH OR DAMAGESARE CAUSED,IN WHOLE
OR IN PART, BY THE ALLEGED NEGLIGENCE OF THE CITY OF FORT WORTH, ITS
OFFICERS,SERVANTS, OR EMPLOYEES.
(c) DEVELOPER WILL REQUIRE ITS CONTRACTORS TO INDEMNIFY, DEFEND AND
HOLD HARMLESS THE CITY, ITS OFFICERS, AGENTS AND EMPLOYEES FROM
AND AGAINST ANY AND ALL CLAIMS, SUITS OR CAUSES OF ACTION OF ANY
NATURE WHATSOEVER, WHETHER REAL OR ASSERTED, BROUGHT FOR OR ON
ACCOUNT OF ANY INJURIES OR DAMAGES TO PERSONS OR PROPERTY,
INCLUDING DEATH,RESULTING FROM, OR INANY WAY CONNECTED WITH, THE
CONSTRUCTION OF THE IMPROVEMENTS CONTEMPLATED HEREIN, WHETHER
OR NOT SUCH INJURIES, DEATH OR DAMAGES ARE CAUSED, IN WHOLE OR IN
PART, BY THE ALLEGED NEGLIGENCE OF THE CITY OF FORT WORTH, ITS
OFFICERS, SERVANTS, OR EMPLOYEES. FURTHER, DEVELOPER WILL REQUIRE
ITS CONTRACTORS TO INDEMNIFY, DEFEND, AND HOLD HARMLESS THE CITY
FOR ANY LOSSES, DAMAGES, COSTS OR EXPENSES SUFFERED BY THE CITY OR
CAUSED AS A RESULT OF SAID CONTRACTORS' FAILURE TO COMPLETE THE
WORK AND CONSTRUCT THE IMPROVEMENTS IN A GOOD AND WORKMANLIKE
MANNER, FREE FROM DEFECTS,IN CONFORMANCE WITH THE CFA ORDINANCE,
AND INACCORDANCE WITH ALL PLANS AND SPECIFICATIONS.
13.
Right to Enforce Contracts
Upon completion of all work associated with the construction of the Improvements,Developer will
assign to the City a non-exclusive right to enforce the contracts entered into by Developer with its
contractors,along with an assignment of all warranties given by the contractors,whether express or implied.
Further,Developer agrees that all contracts with any contractor shall include provisions granting to the City
the right to enforce such contracts as an express intended third parry beneficiary of such contracts.
City of Fort Worth,Texas Page 6 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
14.
Estimated Fees Paid by Developer; Reconciliation
Prior to execution of this Agreement, Developer has paid to the City the estimated cost of
administrative material testing service fees, construction inspection service fees,and water testing lab fees
in the amounts set forth in the Cost Summary section of this Agreement. Upon completion of the
construction of the Improvements, the City will reconcile the actual cost of administrative material testing
service fees, construction inspection service fees, and water testing lab fees with the estimated fees paid
by Developer. If the actual costs of the fees are more than the estimated payments made bythe Developer,
the Developer must pay the difference to the City before the Improvements will be accepted by the City. If
the actual costs of the fees are less than the estimated payments made by the Developer,the City will refund
the difference to the Developer.If the difference between the actual costs and the estimated payments made
by the Developer is less than fifty dollars($50.00),the City will not issue a refund and the Developer will
not be responsible for paying the difference. The financial guarantee will not be released by the City or
returned to the Developer until reconciliation has been completed by the City and any fees owed to the City
have been paid by the Developer.
15.
Material Testing
The City maintains a list of pre-approved material testing laboratories. The Developer must
contract with material testing laboratories on the City's list. Material testing laboratories will provide copies
of all test results directly to the City and the Developer. If the Improvements being constructed fail a test,
the Developer must correct or replace the Improvements until the Improvements pass all retests. The
Developer must pay the material testing laboratories directly for all material testing and retesting. The City
will obtain proof from the material testing laboratories that the material testing laboratories have been
paid in full by the Developer before the City will accept the Improvements.
16.
Notices
All notices required or permitted under this Agreement may be given to a party by hand-
delivery or by mail, addressed to such party at the address stated below. Any notice so given shall be
deemed to have been received when deposited in the United States mail so addressed with postage
prepaid:
CITY: DEVELOPER:
Development Coordination Office Lennar Homes of Texas Land and Construction, Ltd
City of Fort Worth 1707 Market Place Blvd.
200 Texas Street Irving, TX, 75063
Fort Worth, Texas 76102
With copies to:
City Attorney's Office
City of Fort Worth
200 Texas Street
Fort Worth, Texas 76102
City of Fort Worth,Texas Page 7 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
and
City Manager's Office
City of Fort Worth
200 Texas Street
Fort Worth, Texas 76102
Or to such other address one party may hereafter designate by notice in writing addressed and
mailed or delivered to the other party hereto.
17.
Right to Audit
Developer agrees that, until the expiration of three (3) years after acceptance by the City of the
Improvements constructed pursuant to this Agreement, that the City shall have access to and the right to
examine any directly pertinent books, documents, papers and records of the Developer involving
transactions relating to this Agreement. Developer agrees that the City shall have access during normal
working hours to all necessary Developer facilities and shall be provided adequate and appropriate
workspace in order to conduct audits in compliance with the provisions of this section. The City shall give
Developer reasonable advance notice of intended audits.
Developer further agrees to include in all contracts with Developer's contractors for the
Improvements a provision to the effect that the contractor agrees that the City shall,until the expiration of
three (3)years after final payment under the contract,have access to and the right to examine any directly
pertinent books, documents,papers and records of such contractor, involving transactions to the contract,
and further,that City shall have access during normal working hours to all of the contractor's facilities,and
shall be provided adequate and appropriate work space in order to conduct audits in compliance with the
provisions of this section. City shall give Developer's contractors reasonable advance notice of intended
audits.
18.
Independent Contractor
It is expressly understood and agreed that Developer and its employees, representative, agents,
servants,officers,contractors,subcontractors,and volunteers shall operate as independent contractors as to
all rights and privileges and work performed under this Agreement, and not as agents, representatives or
employees of the City. Subject to and in accordance with the conditions and provisions of this Agreement,
Developer shall have the exclusive right to control the details of its operations and activities and be solely
responsible for the acts and omissions of its employees, representatives, agents, servants, officers,
contractors, subcontractors, and volunteers. Developer acknowledges that the doctrine of respondeat
superior shall not apply as between the City and its officers, representatives, agents, servants and
employees, and Developer and its employees, representatives, agents, servants, officers, contractors,
subcontractors, and volunteers. Developer further agrees that nothing herein shall be construed as the
creation of a partnership or joint enterprise between City and Developer. It is further understood that the
City shall in no way be considered a co-employer or a joint employer of Developer or any employees,
representatives, agents, servants, officers, contractors, subcontractors, and volunteers of Developer.
Neither Developer,nor any officers,agents, servants,employees or subcontractors of Developer shall be
entitled to any employment benefits from the City. Developer shall be responsible and liable for any and
City of Fort Worth,Texas Page 8 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
all payment and reporting of taxes on behalf of itself, and any of employees, representatives, agents,
servants,officers,contractors, subcontractors,and volunteers.
The City,through its authorized representatives and employees, shall have the sole and exclusive
right to exercise jurisdiction and control over City employees.
19.
Applicable Law; Venue
This Agreement shall be construed under and in accordance with Texas law. Venue shall be in
the state courts located in Tarrant County, Texas or the United States District Court for the Northern
District of Texas,Fort Worth Division.
20.
Non-Waiver
The failure of the City to insist upon the performance of any term or provision of this Agreement
or to exercise any right herein conferred shall not be construed as a waiver or relinquishment to any extent
of City's right to assert or rely on any such term or right on any future occasion.
21.
Governmental Powers and Immunities.
It is understood that by execution of this Agreement, the City does not waive or surrender
any of its governmental powers or immunities.
22.
Headings
The paragraph headings contained herein are for the convenience in reference and are not intended
to define or limit the scope of any provision of this Agreement.
23.
Severability
In the event that any clause or provision of this Agreement shall be held to be invalid by any
court of competent jurisdiction, the invalidity of such clause or provision shall not affect any of the
remaining provisions hereof.
24.
Review of Counsel
City and Developer, and if they so choose,their attorneys, have had the opportunity to review
and comment on this document;therefore any rule of contract construction or interpretation that would
normally call for the document to be interpreted as against the drafting party shall not apply in
interpretation of this Agreement, and each section, portion, and provision of this Agreement shall be
construed solely on the basis of the language contained therein, regardless of who authored such
language.
City of Fort Worth,Texas Page 9 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
25.
Prohibition on Boycotting Israel
Developer acknowledges that in accordance with Chapter 2270 of the Texas Government Code,
the City is prohibited from entering into a contract with a company with 10 or more full-time employees
that has a value of$100,000 or more that is to be paid wholly or partly from public funds of the City for
goods or services unless the contract contains a written verification from the company that it: (1)does not
boycott Israel;and(2)will not boycott Israel during the term of the contract. The term"boycott Israel"has
the meaning ascribed to it by Section 808.001 of the Texas Government Code. The term "company"has
the meaning ascribed to it by Section 2270.001 of the Texas Government Code. To the extent that Chapter
2270 of the Government Code is applicable to this Agreement, by signing this Agreement, Developer
certifies that Developer's signature provides written verification to the City that Developer: (1) does not
boycott Israel; and(2)will not boycott Israel during the term of this Agreement.
26.
Immigration and Nationality Act
Developer shall verify the identity and employment eligibility of its employees who perform work
under this Agreement, including completing the Employment Eligibility Verification Form (I-9). Upon
request by City, Developer shall provide City with copies of all I-9 forms and supporting eligibility
documentation for each employee who performs work under this Agreement. Developer shall adhere to all
Federal and State laws as well as establish appropriate procedures and controls so that no services will be
performed by any Developer employee who is not legally eligible to perform such services.DEVELOPER
SHALL INDEMNIFY CITY AND HOLD CITY HARMLESS FROM ANY PENALTIES,
LIABILITIES, OR LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY DEVELOPER,
DEVELOPER'SEMPLOYEES,SUBCONTRACTORS,AGENTS,OR LICENSEES. City,upon written
notice to Developer, shall have the right to immediately terminate this Agreement for violations of this
provision by Developer.
27.
Amendment
No amendment,modification, or alteration of the terms of this Agreement shall be binding unless
the same is in writing,dated subsequent to the date hereof, and duly executed by the City and Developer.
28.
Assignment and Successors
Developer shall not assign or subcontract all or any part of its rights,privileges,or duties under this
Agreement without the prior written consent of City. Any attempted assignment or subcontract without the
City's prior written approval shall be void and constitute a breach of this Agreement.
29.
No Third-Party Beneficiaries
The provisions and conditions of this Agreement are solely for the benefit of the City and
Developer, and any lawful assign or successor of Developer, and are not intended to create any rights,
contractual or otherwise,to any other person or entity.
City of Fort Worth,Texas Page 10 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
30.
Compliance with Laws,Ordinances,Rules and Regulations
Developer, its officers, agents, servants, employees, and contractors, shall abide by and comply
with all laws, federal, state and local, including all ordinances,rules and regulations of City. It is agreed
and understood that,if City calls to the attention of Developer any such violation on the part of Developer
or any of its officers, agents, servants, employees, or subcontractors, then Developer shall immediately
desist from and correct such violation.
31.
Signature Authority
The person signing this Agreement on behalf of Developer warrants that he or she has the legal
authority to execute this Agreement on behalf of the Developer, and that such binding authority has been
granted by proper order,resolution,ordinance or other authorization of the entity. The City is fully entitled
to rely on this warranty and representation in entering into this Agreement.
32.
Counterparts
This Agreement may be executed in multiple counterparts, each of which will be deemed an
original, but which together will constitute one instrument.
33.
Entire Agreement
This written instrument, together with any attachments, exhibits, and appendices, constitutes the
entire understanding between the City and Developer concerning the work to be performed hereunder, and
any prior or contemporaneous, oral or written agreement that purports to vary from the terms hereof shall
be void.
[REMAINDER OF PAGE INTENTIONALLY BLANK]
City of Fort Worth,Texas Page 11 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
34.
Cost Summary Sheet
Pro]ect Name:Northpointe Phase 6
CFA No.: CFA21-0056 City Project No.: 103033
Items Developer's Cost
A. Water and Sewer Construction
1. Water Construction $ 528,005.00
2.Sewer Construction $ 915,233.00
Water and Sewer Construction Total $ 1,443,238.00
B. TPW Construction
1.Street $ 1,628,510.55
2.Storm Drain $ 1,212,005.00
3.Street Lights Installed by Developer $ 172,080.00
4. Signals $ -
TPW Construction Cost Total $ 3,012,595.55
Total Construction Cost(excluding the fees): $ 4,455,833.55
Estimated Construction Fees:
C. Construction Inspection Service Fee $62,500.00
D. Administrative Material Testing Service Fee $36,456.00
E. Water Testing Lab Fee $1,590.00
Total Estimated Construction Fees: $ 100,546.00
Choice
Financial Guarantee Options,choose one Amount (Mark one)
Bond= 100% $ 4,455,833.55 x
Completion Agreement= 100%/Holds Plat $ 4,455,833.55
Cash Escrow Water/Sanitary Sewer= 125% $ 1,804,047.50
Cash Escrow Paving/Storm Drain= 125% $ 3,765,744.44
Letter of Credit= 125% $ 5,569,791.94
City of Fort Worth,Texas Page 12 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
IN WITNESS WHEREOF,the City and Developer have each executed this Agreement by their
duly authorized signatories to be effective on the date executed by the City's Assistant City Manager.
CITY OF FORT WORTH DEVELOPER
Lennar Homes of Texas Land and
Oana BU(�hdoAc Construction,Ltd.
Dana Burghdoff(Tul 17,202110:10 CDT)
Dana Burghdoff 1
Assistant City Manager Jennifer Eller(Jul 9,202108:29 CDT)
Name: Jennifer Eller
Date: Jul 17,2021 Title: Authorized Agent
Recommended by: Date: Jul 9,2021
L41 e abgef
Evelyn Roberts(Jul 9,202108:50 CDT)
Evelyn Roberts/Jennifer Ezernack
Project Assistant
Planning and Development
Approved as to Form &Legality:
�-
Richard A.McCracken(Jul 9,202112:55 CDT)
Richard A.McCracken Contract Compliance Manager:
Sr.Assistant City Attorney
M&C No. /A By signing,I acknowledge that I am the person
Date: responsible for the monitoring and
administration of this contract,including
Form 1295: N/A ensuring all performance and reporting
requirements.
a
ATTEST: o�°FORr4(
° °O M��Ce�
p` oo °o Janie Sca rlett Morales(Jul 9,202110:14 CDT)
�o�raGcl Go�rzaGel Y 1
Ronald P.Gonzales(Jul 19,202113:02 CDT) 0()o o=d Name: Janie Scarlett Morales
Ronald P. Gonzales �� °° °°o�� Title: Development Manager
Acting City Secretary d� °°°°°°°
n�nEXAsa�Op
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth,Texas Page 13 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
The following attachments are incorporated into this Agreement. To the extent a
conflict exists between the main body of this Agreement and the following attachments, the
language in the main body of this Agreement shall be controlling.
Included Attachment
❑X Attachment 1 -Changes to Standard Community Facilities Agreement
❑ Attachment 2—Phased CFA Provisions
❑ Attachment 3 —Concurrent CFA Provisions
❑X Location Map
❑X Exhibit A: Water Improvements
❑X Exhibit A-1: Sewer Improvements
❑X Exhibit B: Paving Improvements
❑X Exhibit B-1: Storm Drain Improvements
❑X Exhibit C: Street Lights and Signs Improvements
❑X Cost Estimates
(Remainder of Page Intentionally Left Blank)
City of Fort Worth,Texas Page 14 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
ATTACHMENT"1"
Changes to Standard Community Facilities Agreement
City Project No. 103033
None
City of Fort Worth,Texas Page 15 of 15
Standard Community Facilities Agreement
Rev.10/5/19[NPC]
00 42 43
DAP-BID PROPOSAL
Page I o173
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Item Description Specification Unit of Bid Unit Price Bid Value
No. Section No. Measure Quantity UNIT 1:WATER IMPRO EMENTS
1 3311.0241-8"Water P 3311 10,33 LF
....................... ............ .......... ....................
2 3312.0001 Fire Hydrant Assembly wl 6"Gate Valve&Box 33 11 10,33 EA 16
............. ............................................?�..............................................I........... ...........
3 0241.1218 4"-12"Water Abandonment Plug 0241 14 EA 4 $
.................. ...........
331220 EA 30
............ ........... ..........- __$1,25 .00.._..._$ 75 0.00
5 3311.0001 Ductile Iron Water Fittings w/Restraint 3311 11 TON 4.10.........._$4500.00 $18,450.00. .
6' 33-1,2-.2-0-03 1"-Water,Service- ----3 3-1-2 1-0- ..........E A --l-1,8'' "$""9'5- 0-0-.*0-0-
................---- i i�0�------------11,P.QP.J -
.......... �.�-'Con'n'act'i`on to'Exist'inq-Water Main' 0
1000510 J $8.193.06
8 13305.0109 . ..... LF 8,193 $1.001
TOTAL UNIT 1:WATER IMPROVEMENTS
UNIT 11:SANITARY SEWER IMPROVEMENTS
1 3331.4115 8"Sewer Pipe 33 11 10,33 31 LF 9,827 $47. $ 61 869.00
.......... ...........- .............
2 3331.4116 8"Sewer Pipe,CSS Backfill 3311 10 LF 180 $64.
if--...--.- ----- -1 .......... ................. ...........
8"Sewer Pipe,CLSMBackfill 3311 10 LF 420 $74..00._,_____$3 .,08 .00
..............
4 3339.0001 Epoxy Manhole Liner 3339 10,33 VF 114.5 $385.00 $44.082.50
...... ......................... -3-3 ii,1,0-,3 3 EA 49
5 3339.1002 4'Manhole $4000.00 $196,000.00
1-1-1-1--........................... .................................................. ....... .................... ...........
7 3339.1002 4'Manhole Water Tight Manhole 3339 10,33 EA I
...........I ....... .......... .................. ................................... .. -.1.1 1.1-1.. ....... 1-1-1........ 1.--1..----.1..-.-1.1"'MI
8 3339.1002 4'Manholew/H�Kdr Hydraulic Slide 3339 10,33 EA 2 $4,800.00 $9,600.00
I............. -. .......... ..a� - ................................................................... ............................... ..................-..........
8 3339.1003 Extra Depth Manhole 33 39 10,33 VF -.-97'3 $185.00 $18.000,50
I.......... ......-1-1 ....................... ................... ............
9 3331.3101 4"Sewer Service 3331 50 E iii $650.00 $
...................................... ........... ..............
10 3301.0101 Manhole Vacuum Testing 3301 30 EA 52
.......... .....................................-- ............................ ..........-................... .................................... --................................................... .............. ..........
11 3305.0109 Trench Safety 00 05 10 LF 9,827
..................-, I.......................................................... ...............................................
1 3305.0112 Concrete Collar 000510 LF 17 0
---------- ........... ..................... ......................
3301.0002 Post CCTV Inspection 33 01-3.1 L..F 827 $19654.00
.. .............. .......
13 0241.21.0-3 8� S..e.w..e.r,.A.b..a,.n.d.o.n,m.ent Plug. 14 EA 2 $1.,0 0.00 $2.000.
00
.......... ......P.., I'll----111-1111-1-1-11
1,4-- 99-9,9".6-0011 Connect to Existing ManHole 000000"' EA 1 $2,500.001 $,2500.00
TOTAL UNIT It:SANITARY SEWER IMPROVEMENTS $915,233.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Forni Version May 22,2019 00 42 43 Bid Proposal DAP PHASE 6
00 42 43
DAP-BID PROPOSAL
Page 2 of
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
FProject Item Infonnation Bidder's Proposal
Bidli,t ftern Description Specification Unit of I Bid
No. I Section No. Measure Quantity Unit Price Bid Value
UNIT III:DRAINAGE IMPROVEMENTS
1 9999.0002 Neenah 4-Grate Inlet 334920 EA
............. ......................... ..... ............ ................. .................
2 3349.5001 10 Curb rb.iniet... . ........ 334920 EA 26
.........-.-............. . . .... ....3. 3349.5002 15'Curb Inlet 334920 EA 2 $4200.00 $8,4 0.00
.......... ...... ................................................ ...........--------.p...........
4 3349.0001 4'Storm Junction Box 334910 EA 1 $ 000.00
............. .......... ................ .............. '9w-�--.-I.- ............-
5 3349.0002 5'Storm Junction Box 33 EA 4 $6,500,00 $2 000.00
.......... ............ ........... ................. ............................-
6 3349.7001 4'Drop Inlet 334920 EA 1 $4 0........... $ 500.00
.............1---1..-1-.---..................... ........... ................ .............. ....................... ..............-.15,0,0.,0.- __ 1---------11-1.1
7 3341.0201 21"RCP,Class 111 3341 10 LF 726 $52.00 3 75 .00
.......................................................................... ........... ...........
8 3341.0205 24"RCP,Class 111 3341 10 LF 2,042 $57.00 $116,394.00
........................ ........ .................................
9 3341.0208 27"RCP,Class 111 3341 10 �LF 199 $65.00 $12.935.00
.......... ........... -------
10 3341.0208 30"RCP,Class 111 3341 10 1,685 $75.00 $126,375.00
.................................................. .......................I I �E --l.-- .............
1 3341.0309 36"RCP,Class 111 3341 10 LF 409 $
.......... ......
12 3341.0402 42"RCP,Class 111 3441 10 LF 675 $128.00
-............. ... ...---------- ............
13 3341.0409 48"RCP,Class 111 3341 10 . $1,52!-Q0. ......... 72 .00
............................ ........... ------- -P,. !�
14 3341.1303 2-61 x 4'Box Culvert 3341 10 LF 107 $730.00 $7 110.00
........... ...............................
15 3341.1401 5-Tx 3'Box Culvert 3341 10 LF 72 $2,050.00 $147.600.00
................. ................. ..........
16 3349.4105 24"SET, 1 pipe 33 49 40 EA 3 $3000.00 $9.000.00
...............- ..................... .................................
17 3349.4106 27"SET,1 pipe 334940 EA 1
........... ........- ........................................... ................... .......................
18 3349.4107 30"SET,1 pipe 33 49 40 EA 4 $ 800.00.............
............ .................... ............... ..........
19 3349.4109 36"SET,1 pipe 334940 EA
.................... ..................-pipe.......................................... ..................... ........................---......................... .
20 3349.4111 42"SET,I pipe 33 49 40.__.... __EA 2 $4,700.00 $9,400.00
........................ .......... ..........
21 3349.4113 48"SET,1 pipe 33 49 40 EA 1
------------ ............. ....... ....... ---
2-2'- 9696.6663 Rem"o-v'e Headwall and Connect to Existing Pipe 00 00 00 EA 1 -$1,1-500,00 ........... . .$1,500.00
.................. .... ...... . ...........
23 9999.0004 6'(2 OT S x 4')TXDW-0 - ,0 00.00
................... ................................................................................. ....... $16 500.00 $33 2
.......24--. 919.99..O..00,151,.,TxDOT-FW-,O--(5.-,7,'-,xl,-3.').-,-.,,.,-.,... ................... ............._9 00 2 $65 00.0.00.__.__ _EA $32,500-00
25 0241.3104 24"Storm Abandonment Plug 0241 14 EA 1 $750.00 $750.00
...... ..... ...........
26 0241.3106 30"Storm Abandonment Plug 0241 14 EA 1 $1 1.000.00
1127-1-arRe Sto-n-e-Riprap,dry 0000 SY 741 $90.00. $6
....Rip rap,.. .............. ............
28 9999.0007 18"Large Stone Riprap,dry 312 $105.00 $32,760.00
..................
29 3305.0109 Trench Safety LF 5,979 $1.001 $5,979.00
TOTAL UNIT III:DRAINAGE IMPROVEMENTS, $1,212,005.00
UNIT IV:PAVING IMPROVEMENTS
1 3213.0101 6"Conc Pvmt 3213 13 SY 24,425 $35.50 $
.......... ........ .......---...................................................-- ..........-............. ...............
2 3213.0101 6".0 nc A I Pvmt 3213 13 SY 2,277 8.00..............$..8.6.526,00,I--...........I--.........q.............!-!�Y-. ...... ............1."."..r..-................ -P
3 3211.0111 4"Flexible Base,Type A,GR-1 3211 23 SY 2,446.0 $14.00- 1 244'.-0-0
4 3211.0501 6"Lime Treatment Subgrade 3211 29 SY 25,987 $3.15 $81,859.05
................................ ----------------- ............ 11.......... ..................
5 3213.0101 7.5"Cone Pvmt 32 13 13 SY 41011 $40.50 $162,445.50
---........................... ......
6 3211.0501 8"Lime Treatment YS rade 3211 29 SY 4,212 __$3.50 ...... $AT4?.qQ
-- ............
7 3211.0400 Hydrated Lime @ 30#/SY 3211 29 TON 453 $180.00 $81,540.00
..........-..................... ...... .........---,--- ------
8 3213.0302 5'Conc Sidewalk 321320 LF 4,962 $16.25 $80.632.50
................. .......-.- -........................................... ................................... .... ........................ ----..........--------------------
9 3213.0303 6"Cone Sidewalk 321320 LF 1,452 $19.5 $2 314.00
--.-............ ..... ........-..--.1............ ....................................- ..................................... .................--2___ -1-1 -.11
10 3213.0504 Barrier Free Ram T E 50 $1,500.00 $ j00
11 9999.0008 Construct Concrete Header 00 00 00 LF 276 $20.��p �$51'5?0,0-0-
.......... ............Of,- 11 $50 12 9999.0009 Install Type III End- - dbe`rric-a-de-
............... .............. ------- .............
3 3441,4003 Furnish/Install Alum Sign Ground Mount Cdy Std 34 41 30 EA 31 $350.00 $10.850.00
2 14 .0501 24"SLD P mt Markin g HAE'VD..,............. .................... 32 17 23 LF 34 $ 000. ... .....
$680.0
....... ....--..... 0
.....------I I--
15 9999.0010 Install Street Name Blades 000000 EA 18 $200.00 $3 00.00
................................. ..........
16 9999.0011 Install Stop Sign 000000 EA 13 $300.00 $3,
........... .............. ...................... ----11--1-------------Np`pq
17 9999.0012 Sawcut and Remove Existing Curb 000000 LF 258 $20-00 $5,160.00
.....---------- ................. --........ .......... 1-.1-.-...-1--.1.--......
18 9999.0013 Connect to Existing P w/Longitudinal Butt Joint 000000 LF 258 $20.00 $5,160.00
-1-I.------ -11------ -- -- - .- ".. -.- 1-11... -1. -11-11 1,--,'-,.. 11--1-1-1-1--1- 1--.11--1--.............. -------------
19 3291.0100 Top Soil 32 91 19 .......... CY 970 $23 28000
20 00 Block Sod Placement 32 92 13 SY 8,745 $6.001 $52, 70.00
TOTAL UNIT IV:PAVING IMPROVEMENTS $1,628,510.55
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Fom Version May 22,2019 00 42 43 Bid PropwaLDAP PHASE 6
00 42 43
DAP-BID PROPOSAL
Page 3 or 3
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidders Proposal
Bidlist Item Specification Unit of Bid
Description Unit Price Bid Value
No. Section No. Measure Quantity
UNIT V:STREET LIGHTING IMPROVEMENTS
1 3441.3341 Rdwy Ilium TY 11 Pole 34 41 20 EA 27 $2,600.00 $70 200.00
_.__, ....,,_.__. .__......._..__.__� ._._._..._. _.._ __ .�..._._�W..�._._..--
2 3441.3301 Rdwy Ilium Foundation TY 1,2,and 4 34 41 20 EA 27 $1,000.00 $27,000.00
3 3441 1408 No 6 Insulated Elec Condr,Alum.#6 XHHW 34 41 10 ..w. LF 3 137
.... ....__ ..
4 3441 1632 Install Type 33A Arm 34 41 20 EA 27 $375„00 $10 125 00
�. ._..._-.._-._.__ ..�.e....�� ...,. _._W.._._..._.. ......___. .... _ __.......__� �. .._..,.. -.W-_ ..�_.�. -_.
5 9999.0014 ATBO-20BLEDE70 MVOLT-R2-3K-MP NL P7 Luminalre 34 41 20 EA 17 $650.00 $11 050.00
......._.. . ... .. ....... ............. ... . .. .................... ......,.,_ ...._._...... .. .m.,_........... .,..._. .,..,._....._.. ............. .............�.....,_.,_...».........._.._._,.._....._...._...__.......................L_............,...
4 41
6 _.99_9.9..0_.01..5-..T._ypR4 Luminaire �,...W��.._.�.,_...�-, _._...... .�.._..... , 7,_.. �$�6.,6_5.�0_.003
20
7 2605.3018 2"CONDT PVC SCH 80,Open Cut 26'OS33 _.. LF 3W37 $12.00 $37 644.00
,
TOTAL UNIT V:STREET LIGHTING IMPROVEMENTS $172,080.00
Bid Summary
UNIT I:WATER IMPROVEMENTS $528 005.00
UNIT II:SANITARY SEWER IMPROVEMENTS $91_5.,233;00
UNIT III:DRAINAGE IMPROVEMENTS $1,212,005.00
UNIT IV:PAVING IMPROVEMENTS $1,628,510._55
UNIT V:STREET LIGHTING IMPROVEMENTS $172 080 00
_........................__,_....,_............_.....-_._.-__._..._w.w .. ._�.�.. �.................._-... -. e ._...... .._......�.__.__.,__.-.......r__......._...__ ... ........ ��... �...
Total Construction Bid $4,455,833.55
This Bid is submitted by the entity named below:
BIDDER: BY:Brock Hu gins
Conatser Construction Tx,LP 4—& 1
5327 Wichita Steet —o
TITLE:President
Fort Worth,TX 76119 DATE:
Contractor agrees to complete WORK for FINAL ACCEPTANCE within 200 working days after the date when the
CONTRACT commences to run as provided in the General Conditions.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCITON SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Version May 22,2019 00 42 43_Bid Propwal_DAP PHASE 6
N
w E
PROJECT
LOCATION
I
E TRACE BLVD
FORK
ST
�r
ARK RO
�1®H
C
Q ®r
E BAILEY BOSWELL ROAD
VICINITY MAP
N.T.S.
NORTHPOINTE
PHASE 6
CITY PROJECT #103033
LOCATED IN
CITY OF FORT WORTH, TEXAS
MAPSCO NO. 032, 033 Owner: KImI 1 lew)>Hor
Lennar Homes of Texas Land and Construction MAY 2021 13455 Noel Road,Tw Galleria Office To—
Suite Market Place Blvd.#100 Dallae Texas 75240
Irving,TX 75063 State of Texas as Registration No.F-928
W E / w �� \ y �I
\ � FUTURE
1 18 _ NORTHPOINTE
S / 2 17 PHASE 7 11 —
SCALE: 1"=300' a 15 0� FORT cRdoK ROAD � I—-(SEE CPN #1013163)i
5 14 L —
�I
L06 13� 1 23 K I
7 12 2 22
11 J 3 21
NOQ�c 10 L
Loc 20 —
pT�C. ,N 4 19
5 6 18 17 �o
1615
7 8
1 91011 OC
\ 1 13 \ r —
14
FUTURE _
NORTHPOINTE 16 19 20 21 —
� � 22 23 24 25 —
M =
7 BLOCK L
6X — J
6 9
0
5 10
� BOCK L
4
NORTHPOINTE BLOCK L 11 12 13 14 15 16 17 ;
PHASE 2A 3 ITNEY CIRCLE
w
(SEE CPN #102552)- 2 —
1 BOCK L
26 25 24 23 22 21 20 19 18
NELAND DRIVE
I� 1 27 28 29B 30K 31 32 33 34 35 36 37 G
R fe BLOCK M
2 BRICHCRES DRIVE
M a — W
CONNECT TO
3 B oCK M �� EXISTING 8"
CONNECT TO Z 4 s s 7 s s 10 11 12 13 1a 15 1s WATERLINE
EXISTING 8" Xx (SEE CPN
WATERLINE NORTHPOINTE SKY BOULEVARD 102250)
(SEE CPN 102250) — — --
-W EX 16"WATERLINE
NOT EXISTING NORTHPOINTE
II PHASE 1 A
INFRASTRUCTURE (SEE L� (SEE CPN #102250) w
NORTHPOINTE PHASE — —
� I NORTHPOINTE
CPN 10230 )
PHASE 3
(SEE CPN #102656) LEGEND
-W- PROPOSED WATER LINE
EXISTING WATER LINE
NOTE:
WATER ALL WATER LINES SHOWN ARE 8" IN
Y 1p EXHIBIT "A" DIAMETER UNLESS OTHERWISE NOTED.
Northpointe Phase 6 Owner: KimCourt Hor
Lennar Homes of Texas Land and 5750 Genesis Court
Suite 200
Construction Frisco,Texas 75034
1707 Market Place Blvd.#100 972 335-3580
r.6
City,Texas State of Texas Registration No.F-928
Irving,TX75063 =P�=o.«.�..a.aE�oaE�PaooEow.o.
W E �y FUTURE
1 18 _ NORTHPOINTE
S / 2 17 PHASE 7 11 —
SCALE: 1"=200' 4 15 0� FORT CROOK ROAD (SEE CPN #103163)]
- �I
5 14 r � L
� � �J C LO 13� 1 23
�C3 'v 76 12� 2 22 K
11 J 3 21 J
Loc 20 —
$ OTFO 4 19
5 6 18 17
7 16 15
8
1011 OC a
13
14
FUTURE
16 NORTHPOINTE 19 20 21 —
N 22 23 24 25 —
i� SS -
7 BLOCK L
6X — J
6 9 0
5 10
4 J BOCK L
NORTHPOINTE BLOCK L >> 12 13 T1415 is 17
PHASE 2A 3 ITNEY CIRCLE
(SEE CPN #102552) 2 Ito ' ���
� BOCK L
26 25 24 23 22 21 20 19 18
VINELAND DRIVE
I� 1 OC
27 28 29B 30K 31 32 33 34 35 36 37 G
R BLOCK M
2 BRICHCR IS DRIVE
a
SS 3
BOCK M
z 4 5 6 7 8 9 10 11 12 13 14 15 16 t�
J N
X S.
1
K NORTHPOINTE SKY BOULEVARD
LS
—7
—FT
NORTHPOINTE LEGEND
PHASE 1A
_ ssH ss ss SS ss _ (SEE CPN #102250)_ ss —SS— PROPOSED SANITARY
— SEWER LINE
NORTHPOINTE SS EXISTING SANITARY SEWER
� PHASE 3
(SEE CPN #102656) LINE
PROPOSED SDR-26
SANITARY SEWER SERVICE
NOTE:
ALL SANITARY SEWER LINES SHOWN ARE
8" IN DIAMETER UNLESS OTHERWISE
WASTEWATER NOTED.
Y^ EXHIBIT "A-1 " (1 OF 3)
Northpointe Phase 6 Owner: KimCourt Horn
Lennar Homes of Texas Land and 5750 Genesis Court
Suite 200
Construction Frisco,Texas 75034
1707 Market Place Blvd.#100 972 335-3580
City,Texas State of Texas Registration No.F-928
G
Irving,TX75063 =P�=o.«.�..a.aE�oaE�PaooEow.o.
N
W E
S
SCALE: 1"=200'
MATCHLINE
SHEET 3 OF 3
TEXAS ELECTRIC SERVICE
COMPANY VOL. 2542, PG. 1
D.R.T.C.T.
SS
Yb
IRS
FUTURE ,a
NORTHPOINTE
�Q ry
r
LEGEND
NORTHPOINTE —SS— PROPOSED SANITARY
PHA
s (SEE cPNS#1 2250)E 1A
SEWER LINE
SS EXISTING SANITARY SEWER
LINE
PROPOSED SDR-26
SANITARY SEWER SERVICE
NOTE:
ALL SANITARY SEWER LINES SHOWN ARE
8" IN DIAMETER UNLESS OTHERWISE
WASTEWATER NOTED.
Y^ EXHIBIT "A-1 " (2 OF 3)
Northpointe Phase 6 Owner: Kimley >>Hor
Lennar Homes of Texas Land and 5750 Genesis Court
Suite 200
Construction Frisco,Texas 75034
1707 Market Place Blvd.#100 972 335-3580
City,Texas State of Texas Registration No.F-928
G
Irving,TX75063 =P�=o.«.�..a.aE�oaEPaooEow.o.
N
W E
S
SCALE: 1"=200'
CONNECT TO EXISTING 15"
SEWER LINE
(SEE CITY PROJ #X-20792)
SS
SS
/ SS
SS
CHAPEL HILL VENTURE L.L.L.P.
VOL. 14957, PG. 307 D.R.T.C.T.
4
MATCHLINE
TEXAS ELECTRIC SERVICE SHEET 2 OF 3
COMPANY VOL. 2542, PG. 1
D.R.T.C.T. LEGEND
-SS- PROPOSED SANITARY
FUTURE SEWER LINE
NORTHPOITNE
SS EXISTING SANITARY SEWER
LINE
PROPOSED SDR-26
SANITARY SEWER SERVICE
NOTE:
ALL SANITARY SEWER LINES SHOWN ARE
8" IN DIAMETER UNLESS OTHERWISE
WASTEWATER NOTED.
Y^ EXHIBIT "A-1 " (3 OF 3)
Northpointe Phase 6 Owner: Kimley >>Hor
Lennar Homes of Texas Land and 5750 Genesis Court
Suite 200
Construction Frisco,Texas 75034
1707 Market Place Blvd.#100 972 335-3580
City,Texas State of Texas Registration No.F-928
G
Irving,TX75063 =P�=o.«.�..a.aE�oaEPaooEow.o.
W E y FUTURE
> 18 _ NO
S / 2 17 PHASE 7 11
SCALE: 1"=200' a 15 0� FORT CRO gp LOK Rp (SEE CPN #103163)i
LO6 13� 1 23 K I
7 12 2 22
11 J 3 21
�OR'�c 10 LOC 20 L —
F �
°TF 4 19 Q� — � F — �I
s 18 17 �o
7 8 16 15 r — I
loll OC a
13
14 —
FUTURE
16 NORTHPOINTE 19 20 21
22 23 24 25
N —
7 BLOCK L
6X — J
6 9 I 0
LLL 5 10
n LL 4 JIJ1117�L`13
NORTHPOINTE L BLOCK L 14 1s 16 17
PHASE 2A3ITNEY CIRCLE
(SEE CPN #102552) 2 —
o L 1 BOCK L
L 26 25 24 23 22 21 20 19 18
a
L VI E N RI
L BOCK L
L
1
a L 27 28 29 30 31 32 33 34 35 36 37
L BLOCK M
L 2 BRICHCRESLRIVE
3
L BLOCK M CONNECT TO
CONNECT TO L 4 5 6 7 8 9 10 11 12 13 14 15 16 t�
xx EXISTING
EXISTING PAVEMENT L PAVEMENT (SEE
(SEE CPN 102250) L �L CPN 102250)
is
LEGEND
NORTHPOINTE _ — 5' SIDEWALK PER THIS CONTRACT
NORTHPOINTE PHASE 1A
PHASE 3 (SEE CPN #102250) 6' SIDEWALK PER THIS CONTRACT
(SEE CPN #102656) 1 1 1 1 1 1 1
6' BIKE LANE PER THIS CONTRACT
3 ® PROPOSED 29' B—B ROADWAY w/ 50'
= R.O.W. 6" THICK REINFORCED CONCRETE
€ PAVEMENT
LLLLLLLLPROPOSED 41' B—B ROADWAY w/ 60'
LLLLLLLL R.O.W. 7.5" THICK REINFORCED CONCRETE
PAVEMENT
PAVING IMPORVEMENTS ADA RAMP TO BE CONSTRUCTED BY
EXHIBIT »B» DEVELOPER
N o rth po i me Phase 6 Owner: Kiml
Lennar Homes of Texas Land and 5750 Genesis Court JFSuite 200
or
Construction Frisco,Texas 75034
1707 Market Place Blvd.#100 972 335-3580
G City,Texas State of Texas Registration No.F-928
Irving,TX75063 =P�=o.«.�..a.aE�oaE�PaooEow.o.
W E �y FUTURE
> 18 aN _ NORTHPOINTE
S / 2 17 l L PHASE 7 11
a wn 3 16 FORT CR (SEE CPN #103163)
SCALE: 1"=200' OK Roao
10,„n 4 15514 wlcv
LO6 13 1 23
12 2 K
7 to zP�, 22
�• 11 J 3 21 1a wn �•„�
310 L - �I
LOC 20 a R0°I
lF n 4 19
NIET ,�6 is NIET �Q
6 7 17I16/15
,a wcr 8
9 ,a„�
a NIET J 10 OC
10'IN za• 1213 za Ilci, —
r = �1
FUTURE az• _
NORTHPOINTE 10*wn �• 1920 21 —
1a NLU 22 2324 25
n iraEr�
IV wcr 2r /y 1a wcr —
4 ,a Iran ,a wn /Vf —
b•uv 7 BLOCK L x•wm
�' ax —
6 9 3 I
3
5 w 10
n z�• JI B OCK L zr 1,, m" •ncv
4
NORTHPOINTE z•^� BLOCK L 11 12 13 14 ,s aN�17 a,an arer
PHASE 2A 3 ITNEY CIRCLE
(SEE CPN #102552) 2 —
a rrcr 1a Iran zr acr
B OCK L
261 25 24 23 22 21 20 19 18
IA LAND IVE 3W acr
la NIET
o INLET 27 28 29B 30K 31 32 33 34 35 36 37 G
to„� BLOCK M
a„rn MCHCRESLRIVE
� 3
101„1U BOCK M
CONNECT TO 4 5 6 7 8 9 10 11 12 13 14 15 16 t�
EXISTING 24" RCP "X
(SEE CPN 102250)
is
NORTHPOINTE
PHASE 1A
(SEE CPN #102250)
NORTHPOINTE
' PHASE 3 FFTFT�
(SEE CPN #102656)
LEGEND
€ PROPOSED STORM DRAIN LINE
EXISTING STORM DRAIN LINE
Z PROPOSED STORM DRAIN INLET
PROPOSED STORM DRAIN DROP INLET
STORM DRAINAGE
EXHIBIT "B-1 "
Northpointe Phase 6 Owner: KimCourt Morn
Lennar Homes of Texas Land and 5750 Genesis Court
Suite 200
Construction Frisco,Texas 75034
1707 Market Place Blvd.#100 972 335-3580
G City,Texas State of Texas Registration No.F-928
March 2021 Irving,TX75063 =P�=o.«.�..a.aE�oaE�PaooEow.o.
W E _ �y FUTURE
1 18 _ NORTHPOINTE
S / 2 17 l L PHASE 7 11 —
SCALE: 1"=200' 3 15 I_(SEE CPN #103163)i
54 14 ~ �r � L -
LO6 13 1 23 K
7 12 2 22 lI
11 3 21 — J
10 _ _
4 C 20
5 6 19 18 r _ _
7/8///�9/ 17 16 15 J
1 13
14 —
FUTURE
16
NORTHPOINTE 19 20 21 —
22 23 24 25 —
7 BLOCK L
ax —
6 $ 9 I
5 5 10 —�
4 B OCK L
NORTHPOINTE BLOCK L 11 12 13 14 15 16 17
PHASE 2A 3
(SEE CPN #102552) 2
1 B OCK L
26 25 24 23 22 21 20 19 18
'ismamo
ul
1 B OCK L
LU
y al 27 28 29 30 31 32 33 34 35 36 37
BLOCK M
C cnEsi OPo� G
3
4 5 6 7 8 9 10 11B OCK 12 13 14 15 16
X X S.
iM
— NORTHPOINTE
PHASE 1A
11(SEE CPN #102250)
NORTHPOINTE I I I I I I I I I I LEGEND
PHASE 3 2" PVC CONDUIT
(SEE CPN #102656)
TYPE 11 W/ 33B ARM LIGHT POLE
X PROPOSED STREET NAME SIGN
■ PROPOSED REGULATORY SIGN
STREET NAME SIGNS & STREET LIGHTS
Y^ EXHIBIT "C-1 "
N o rth po i me Phase 6 Owner: Kimlourt JF or
Lennar Homes of Texas Land and 5750 Genesis Court
Suite 200
Construction Frisco,Texas 75034
1707 Market Place Blvd.#100 972 335-3580
City,Texas State of Texas Registration No.F-928
G
Irving,TX75063 =P�=o.«.�..a.aE�oaE�PaooEow.o.