HomeMy WebLinkAboutContract 52223-CO5 CSC No.52223-CO5
FORT WORTH City of Fort Worth
Change Order Request
Project Name:1 Meadow Lakes Lift Station Sanitary Sewer Force Main City Sec No.: 1 52223
Project No.(s): 56016-0700430-CO1783 DOE No. N/A CityProj.No.:l 01829
Project Description: The construction of the S.S.gravity main from Jenkin Heights Lift Stalon to Meadow Lakes Lift Station,the force main from Meadow
Lakes Lift Station to east of Boat Club Rd.and the decommissioning of Jenkin Heights Lift Station.
Contractor: Mountain Cascade of Texas,LLC Change Order# Date: 7/8/2021
City Project Mgr.1 Walter Norwood City Inspector: I Jesse Reed
Phone Number:1 817-392-5026 Phone Number: 817-392-8362
Dept. Sewer Force Main Sewer Gravity Totals Contract Time
Main (Calendar days)
Original Contract Amount $2,616,385.00 $1,379,690.00 $3,996,075.00 365
Extras to Dale $80,879.98 $80,879.98 167
Credits to Dale
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,697,264.98 $1,379,690.00 $4,076,954.98 532
Amount of Proposed Change Order $0.00 $0.00 $0.00 128
Revised Contract Amount $2,697,264.98 $1,379,690.00 $4.076,954.98 660
Original Funds Available for Change Orders $159,843.00 $159,843.00
Remaining Funds Available for this CO $78,963.02 $78,963.02
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 2.02%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $4,995,093.75
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No.5 will provide an additional 128 calendar days on the project due to the following:
• The time it took for grass seed to become established.
• The time it took to remove debris and re-tv a newly installed sewer main that initially appeared to have a sag
in it.
• The time it took to reconstruct an existing sewer service line that was originally constructed from the center
of a residence,across a driveway and underneath a storm drain curb inlet before connected to the project
sewer main.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order,
Contractor's Company Name Contractor Name nt a D to
Mountain Cascade of Texas,LLC Andy McCulloch
Inspector Date Project Uana r Date
Director(Water Dept Date Construction Supervisor Water Dept) Date
w Stu rorJul 12,2021 _ ����t/�>Io�iizfc✓� --
Assistant City Attorney Date Assistant City Manager Date
war, Ju119,2021 -3 Jul 21,2021
Council Action If Required)
M&C Number N/A M&C Date Approved OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Fcc P,"i WOP..-- " City of Fort Worth
Change Order Additions
Project Name Meadow Lakes Lift Station Sanitary Sewer Force Main City Sec No.: 52223
Project No.(s): 56016-0700430-CO1783 I DOE No. N/A City Proj,No.: 01829
Project The construction of the S.S.gravity main from Jenkin Heights Lift Staton to Meadow Lakes Lift Station,the force main
Description from Meadow Lakes Lift Station to east of Boat Club Rd.and the decommissioning of Jenkin Heights Lift Station.
Contractor Mountain Cascade of Texas,LLC I Change Order: Date:1 7/8/2021
City Project Mgr, Walter Norwood City Inspector F Jesse Reed
ADDITIONS
DEFT, ` 'Qt Unit' Unit Cott Totat"
1
Sewer Force Main
Sewer Gravity Main
Page 1 of i Additions Sub Total
FORT WoRTH City of Fort Worth
Change Order Deletions
Project Name Meadow Lakes Lift Station Sanitary Sewer Force Main City Sec No.: 52223
Project No.(s): F 56016-0700430-001783 DOE No. N/A City Proj,No.: 01829
Project Description The construction of the S.S.gravity main from Jenkin Heights Lift Staton to Meadow Lakes Lift Station,the force
main from Meadow Lakes Lift Station to east of Boat Club Rd.and the decommissioning of Jenkin Heights Lift
Contractor Mountain Cascade of Texas,LLC Change Order: F 5-1 Date 7/812021
City Project Mgr. Walter Norwood City Inspector: Pesse Reed
DELETIONS
ITEM:DESCRIPTION DEPT City Unit Unit Cost Total
Sewer Force Main
Sewer Gravity Main
Page 1 of 1 IDeletions Sub Total
MMBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co-# DATE AMOUNT
Total $0.00
Page 1 of 1
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements,
Signature
"4A0y Alviloao CP
Name of Bmployee
Title
� a
)jrp�°FORT�
ATTEST: 9�°° oO1 �d
0
Rd�c�t/y P. �CdrUza/ee� o o
Ronald P.Gonzales(Jul 202111:41 CDT) °
tag g=d
o
Ronald Gonzales ��� °°°OO°°°pO°o Aa
Acting City Secretary ail rEXArro�1
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX