Article IV
Obligations of the Engineer
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental thereto.
B. Standard of Care
The ENGINEER shall perform its services:
(1) with the professional skill and care ordinarily provided by competent
engineers practicing under the same or similar circumstances and
professional license; and
(2) as expeditiously as is prudent considering the ordinary professional
skill and care of a competent engineer.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise the
CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that could
affect the total PROJECT cost and/or execution. These conditions and
cost/execution effects are not the responsibility of the ENGINEER.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 2 of 15
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on-site representatives or otherwise, do not make the ENGINEER
or its personnel in any way responsible for those duties that belong to the
CITY and/or the CITY's construction contractors or other entities, and do not
relieve the construction contractors or any other entity of their obligations,
duties, and responsibilities, including, but not limited to, all construction
methods, means, techniques, sequences, and procedures necessary for
coordinating and completing all portions of the construction work in
accordance with the contract documents and any health or safety precautions
required by such construction work. The ENGINEER and its personnel have
no authority to exercise any control over any construction contractor or other
entity or their employees in connection with their work or any health or safety
precautions.
(2) Except to the e�ent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the progress
or quality of the completed work on the PROJECT or to determine, in general,
if the work on the PROJECT is being performed in a manner indicating that
the PROJECT, when completed, will be in accordance with the contract
documents, nor shall anything in the contract documents or this
AGREEMENT between CITY and ENGINEER be construed as requiring
ENGINEER to make exhaustive or continuous on-site inspections to discover
latent defects in the work or otherwise check the quality or quantity of the work
on the PROJECT. If the ENGINEER makes on-site observation(s) of a
deviation from the contract documents, the ENGINEER shall inform the CITY.
(3) When professional certification of performance or characteristics of materials,
systems or equipment is reasonably required to perform the services set forth
in the Scope of Services, the ENGINEER shall be entitled to rely upon such
certification to establish materials, systems or equipment and perFormance
criteria to be required in the contract documents.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 3 of 15
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of perFormance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate PROJECT
cost or schedule. Therefore, the ENGINEER makes no warranty that
the CITY's actual PROJECT costs, financial aspects, economic
feasibility, or schedules will not vary from the ENGINEER's opinions,
analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling and
observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the contract
documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are no other matters
at issue between the CITY and the construction contractor that affect the
amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for any
errors or omissions in the information from others that is incorporated into the
record drawings.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 4 of 15
I. Business Equity Participation
City has goals for the full and equitable participation of minority business
and/or women business enterprises in City contracts greater than
$100,000. In accordance with the City's Business Equity Ordinance
(Ordinance No. 24534-11-2020 as codified in Chapter 20, Article X of the
City's Code of Ordinances, as amended, and any relevant policy or guidance
documents), the City has goals for the full and equitable participation of
minority business and/or women business enterprises in City contracts
greater than $100,000. Engineer acknowledges the MBE and WBE goals
established for this contract and its execution of this Agreement is Engineer's
written commitment to meet the prescribed MBE and WBE participation
goals. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may result
in the termination of this Agreement and debarment from participating in City
contracts for a period of time of not less than three (3) years.
J. Right to A►udit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers and
records of the ENGINEER involving transactions relating to this contract.
ENGINEER agrees that the CITY shall have access during normal working
hours to all necessary ENGINEER facilities and shall be provided adequate
and appropriate work space in order to conduct audits in compliance with the
provisions of this section. The CITY shall give ENGINEER reasonable
advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the CITY
shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
facilities, and shall be provided adequate and appropriate work space, in order
to conduct audits in compliance with the provisions of this article together with
subsection (3) hereof. CITY shall give subconsultant reasonable advance
notice of intended audits.
(3) ENGINEER and subconsultant agree to reproduce such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for the
cost of hard copies at the rate published in the Texas Administrative Code in
effect as of the time copying is perFormed.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 5 of 15
K. INSURANCE
Engineer shall not commence work under this Agreement until it has
obtained all insurance required under Attachment F and City has approved
such insurance.
L. Independent Consultant
The ENGINEER agrees to perForm all services as an independent consultant
and not as a subcontractor, agent, or employee of the CITY. The doctrine
of respondeat superior shall not apply.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure in
writing of any existing conflicts of interest or potential conflicts of interest,
including per�onal financial intere�t, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing of
any conflicts of interest that develop subsequent to the signing of this contract
and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with published
design criteria and/or current engineering practice standards which the
ENGINEER should have been aware of at the time this Agreement was
executed, the ENGINEER shall revise plans and specifications, as required,
at its own cost and expense. However, if design changes are required due to
the changes in the permitting authorities' published design criteria and/or
practice standards criteria which are published after the date of this
Agreement which the ENGINEER could not have been reasonably aware of,
the ENGINEER shall notify the CITY of such changes and an adjustment in
compensation will be made through an amendment to this AGREEMENT.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 6 of 15
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
A. City-Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of the
information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of the
CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses required
by local, state, or federal authorities; and land, easements, rights-of-way, and
access necessary for the ENGINEER's services or PROJECT construction.
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches, drawings,
specifications, proposals, and other documents; obtain advice of an attorney,
insurance counselor, accountant, auditor, bond and financial advisors, and
other consultants as the CITY deems appropriate; and render in writing
decisions required by the CITY in a timely manner in accordance with the
project schedule prepared in accordance with Attachment D.
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 7 of 15
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perForm part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of such
materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos is
a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at the construction site,
and provisions providing for contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third-Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering services
perFormed. Only the CITY will be the beneficiary of any
undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third-party beneficiaries.
(3) The CITY will include in each agreement it enters into with any other entity or
person regarding the PROJECT a provision that such entity or person shall
have no third-party beneficiary rights under this Agreement.
(4) Nothing contained in this Section H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 8 of 15
I. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
J. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for perFormance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
Article VI
Ger�er�l L�g�l Pravi�i�r��
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
CITY and ENGINEER shall exercise their best efforts to meet their
respective duties and obligations as set forth in this Agreement, but shall
not be held liable for any delay or omission in performance due to force
majeure or other causes beyond their reasonable control, including, but not
limited to: acts of the public enemy, fires, strikes, lockouts, natural disasters,
epidemics/pandemics, wars, riots, material or labor restrictions by any
governmental authority and/or any other similar causes.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 9 of 15
D.
(1)
Termination
This AGREEMENT may be terminated
a.) by the City for its convenience upon 30 days' written notice to
ENGINEER.
b.) by either the CITY or the ENGINEER for cause if either party fails
substantially to perForm through no fault of the other and the
nonperforming party does not commence correction of such
nonperformance within 5 days' written notice or thereafter fails to
diligently complete the correction.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
E.
I�
a.) Reasonable cost of reproduction or electronic storage of partial or
complete studies, plans, specifications or otherforms of ENGINEER'S
work product;
b.) The reasonable time requirements for the ENGINEER'S personnel to
document the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all projected termination
expenses. The CITY'S approval shall be obtained in writing prior to
proceeding with termination services.
Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER for
the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors, and
ENGINEER's compensation will be made.
Indemnification
The ENGINEER shall indemnify or hold harmless the CITY against
liability for any damage committed by the ENGINEER or ENGINEER's
agent, consultant under contract, or another entity over which the
ENGINEER exercises control to the extent that the damage is caused by
or resulting from an act of negligence, intentional tort, intellectual
property infringement, or failure to pay a subcontractor or supplier. CITY
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 10 of 15
is entitled to recover its reasonable attorney's fees in proportion to the
ENGINEER's liability.
G. Assignment
ENGINEER shall not assign all or any part of this AGREEMENT without the
prior written consent of CITY.
H. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and perFormance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any reason
to be invalid, illegal, or unenforceable in any respect, such invalidity, illegality,
or unenforceability will not affect any other provision, and this AGREEMENT
shall be construed as if such invalid, illegal, or unenforceable provision had
never been contained herein. Articles V.F., VI.B., VI.D., VI.F., VI.H., and VI.I.
shall survive termination of this AGREEMENT for any cause.
J. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in any
way affect this AGREEMENT and the work hereunder, and shall observe and
comply with all orders, laws ordinances and regulations which may exist or
may be enacted later by governing bodies having jurisdiction or authority for
such enactment. No plea of misunderstanding or ignorance thereof shall be
considered. ENGINEER agrees to defend, indemnify and hold harmless
CITY and all of its o�cers, agents and employees from and against all
claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
K. Contract Construction/No Waiver
The parties acknowledge that each Party and, if it so chooses, its counsel,
have reviewed and revised Agreement and that the normal rule of contract
construction, to the effect that any ambiguities are to be resolved against
the drafting party, must not be employed in the interpretation of Agreement
or any amendments or exhibits hereto. The failure of CITY or ENGINEER
to insist upon the performance of any term or provision of this Agreement
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 11 of 15
or to exercise any right granted herein shall not constitute a waiver of CITY's
or ENGINEER's respective right to insist upon appropriate perFormance or
to assert any such right on any future occasion.
L
M
Immigration Nationality Act
ENGINEER shall verify the identity and employment eligibility of its
employees who perform work under this Agreement, including completing
the Employment Eligibility Verification Form (I-9). Upon request by CITY,
ENGINEER shall provide CITY with copies of all I-9 forms and supporting
eligibility documentation for each employee who perForms work under this
Agreement. ENGINEER shall adhere to all Federal and State laws as well
as establish appropriate procedures and controls so that no services will be
perFormed by any ENGINEER employee who is not legally eligible to
perform such services. ENGINEER SHALL INDEMNIFY CITY AND HOLD
CITY HARMLESS FROM ANY PENALTIES, LIABILITIES, OR LOSSES
DUE TO VIOLATIONS OF THIS PARAGRAPH BY ENGINEER,
ENGINEER'S EMPLOYEES, SUBCONTRACTORS, AGENTS, OR
LICENSEES. CITY, upon written notice to ENGINEER, shall have the right
to immediately terminate this Agreement for violations of this provision by
ENGINEER.
Prohibition On Contracts With Companies Boycotting Israel
ENGINEER acknowledges that in accordance with Chapter 2271 of the
Texas Government Code, CITY is prohibited from entering into a contract
with a company for goods or services unless the contract contains a written
verification from the company that it: (1) does not boycott Israel; and (2) will
not boycott Israel during the term of the contract. The terms "boycott Israel"
and "company" shall have the meanings ascribed to those terms in Section
808.001 of the Texas Government Code. By signing this contract,
ENGINEER certifies that ENGINEER'S signature provides written
verification to the CITY that ENGINEER: (1) does not boycott Israel;
and (2) will not boycott Israel during the term of the contract.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 12 of 15
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, which supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. This AGREEMENT may be
executed in one or more counterparts and each counterpart shall, for all purposes, be
deemed an original, but all such counterparts shall together constitute but one and the
same instrument. The following attachments and schedules are hereby made a part of this
AGREEMENT:
Attachment A- Scope of Services
Attachment B - Compensation
Attachment C- Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
Attachment F — Insurance Requirements
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 13 of 15
Duly executed by each party's designated representative to be effective on the date
subscribed by the City's designated Assistant City Manager.
BY:
CITY OF FORT WORTH
Dana Burghdoff
Assistant City Manager
Date: --------
APPROVAL RECOMMENDED:
By: ____________ _ Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
� � July 13, 2021
Russell Redder, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY
By: _____________ _ Doug Black
Senior Assistant City Attorney
ATIEST:
Ronald Gonzales
Acting City Secretary
City of Fort Worth, Texas Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 14 of 15
BY:
ENGINEER
Halff Associates, Inc.
Ben L. McGahey,.E.
Vice President
Operations Manager, Fort Worth
Date: 7/rlf./ �oz I, I
Form 1295 No. 2021-763036
M&C No.: 21-0474
M&C Date: June 22, 2021
Kara Shuror (Jul 16, 2021 15:42 CDT)
DBlack (Jul 19, 2021 13:47 CDT)
Dana Burghdoff (Jul 21, 2021 09:59 CDT)
Dana Burghdoff
Jul 21, 2021
Ronald P. Gonzales (Jul 27, 2021 10:36 CDT)
Ronald P. Gonzales
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
Revised Date: June 22, 2021
Page 15 of 15
ATfACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI< AND SOUTH WESTSIDE V TRANSh11SSI0N P,1AIN
CITY PROJECT NO.: 103428
ATTACHMENT A
Scope for Enqineerinq Desiqn Related Services for Water and/or Sanitary Sewer
I mprovements
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANK AND SOUTH WESTSIDE V
TRANSMISSION MAIN
CITY PROJECT NO.: 103428
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
The Project consists of a new Westside V 1.5 MG Elevated Storage Tank and 30-inch to 36-
inch Water Transmission Main in Walsh Ranch south of I-20. The Transmission Main will
start at the proposed WS4/WS5 Booster Station 3MG Ground Storage Tank (not included in
this Project) and end at the new Westside V 1.5 MG Elevated Storage Tank. The exact
length of the pipeline will be set by the actual alignment chosen (to be determined as part of
this Project), but an approximate length is 16,000 linear feet.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Conceptual Design
Task 3. Preliminary Design
Task 4. Final Design
Task 5. Bid Phase Services
Task 6. Construction Phase Services
Task 7. ROW/Easement Services
Task 8. Survey and Subsurface Utility Engineering Services
Task 9. Plan Submittal Checklists
Task 10.Additional Services
TASK 1. DESIGN MANAGEMENT.
ENGINEER shall ensure efficient and effective use of ENGINEER's and CITY's time and
resources.
ENGINEER shall manage change,
■ communicate effectively,
■ coordinate internally and externally as needed, and
■ proactively address issues with the CITY's Project Manager and others as
necessary to make progress on the work.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 1 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI<AND SOUTH WESTSI�E V TRANSh11SSI0N N1AIN
CITY PROJECT NO.: 103428
1.1. Managing the Team
• Internal team meetings
• Lead, manage and direct design team activities
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
• Attend a pre-design project kickoff/chartering meeting with CITY staff to confirm and
clarify scope, understand CITY objectives, and ensure economical and functional
designs that meet CITY requirements
• Conduct design submittal review meetings with the CITY at the end of each design
phase
• Project update meetings
• Prepare invoices and submit monthly in the format requested by the CITY.
• Prepare and submit monthly progress reports in the format provided by the Water
Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule updates
with a schedule narrative monthly, as required in Attachment D to this Standard
Agreement and according to the City of Fort Worth's Schedule Guidance Document.
• Complete Monthly M/WBE Report Form and Final Summary Payment Report Form at
the end of the project
• Coordinate with TCEQ and CITY as necessary for the design of the proposed
infrastructure and provide and obtain information needed to prepare the design and
obtain building permits, as required.
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub-consultants shall carry readily visible
information identifying the name of the company and the company representative.
ASSUMPTIONS
• 26 MWBE reports will be prepared
• 1 pre-design coordination meetings with city staff
• 8 review meetings (4 for each design package) with CITY
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.12014
Page 2 of 23
ATTACHMENTA
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANIC AND SOUTH WESTSIDE V TRANS�,IISSION PBAIN
CITY PROJECT NO.: 103428
• 26 monthly water department progress reports will be prepared
• 26 monthly project schedule updates will be prepared
f7�1�/�:7�\���
A. Meeting summaries with action items
B. Monthly invoices
C. Monthly progress reports
D. Baseline design schedule
E. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly M/WBE Report Form and Final Summary Payment Report Form
G. Plan Submittal Checklists (See Task 9)
TASK 2. CONCEPTUAL DESIGN (30 PERCENT).
The Conceptual Design shall be submitted to CITY per the approved Project Schedule.
The purpose of the conceptual design is for the ENGINEER to
■ Study the project,
■ Identify and develop alternatives that enhance the system,
■ Present (through the defined deliverables) these alternatives to the CITY
■ Recommend the alternatives that successfully addresses the design problem, and
■ Obtain the CITY's endorsement of this concept.
ENGINEER will develop the conceptual design of the infrastructure as follows.
2.1. Data Collection
• In addition to data obtained from the CITY, ENGINEER will research proposed
improvements in conjunction with any other planned future improvements that
may influence the project.
• The ENGINEER will also identify and seek to obtain data for existing conditions
that may impact the project including but not limited to; utilities, agencies (TxDOT
and railroads), City Master Plans, and property ownership as available from the
Tax Assessor's office.
• Coordinate with developer for transmission main alignment.
• Discuss project parameters, requirements, construction, and startup schedule
commitments with CITY.
• Review products and manufacturers approved for this project.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 3 of 23
ATTACHMENTA
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSP.1ISSION PnAIN
CITY PROJECT NO.: 103428
• The ENGINEER will confirm the water transmission main easement will be
sufficient for construction access to the EST site. Survey, easement preparation,
etc. for a separate construction access route are not included in this scope.
2.2. Section 404 of the Clean Water Act Assessment (Section 404)
• An on-the-ground jurisdictional determination will be performed to identify the
limits of waters of the United States, including wetlands along each alternative
alignment. The jurisdictional determination will employ the use of GPS surveying
techniques to map the edge ofjurisdictional areas. ENGINEER will complete
necessary wetland data forms and take on-site photography for representative
sites. A jurisdictional determination report consistent with the USACE
"Procedures for Jurisdictional Determinations" (dated March 24, 2003) in addition
to the "Interim Regional Supplement to the Corps of Engineers Wetlands
Delineation Manual: Great Plains Region (Version 2.0)" will be prepared
describing the methodology and results of the investigation. This study will
determine potential project impacts and permitting responsibilities pursuant to
Section 404.
The study will also include a literature review as it pertains to the potential
presence of threatened and endangered species, and the presence of potential
historic resources within the project corridor. These assessments are also
necessary to fully identify potential permitting responsibilities under Section 404.
2.3. The Conceptual Design Package shall include the following. It is assumed there will
be two separate design packages, divided at the EST site property/fence line.
A. The pipeline conceptual design package will include:
• Cover sheet
• Graphic exhibits (1"=100') and written summary of alternative design
concepts considered, strengths and weaknesses of each, and the rationale
for selecting the recommended design concept.
• Proposed phasing of any water and sanitary sewer work that is included in
this project documented in both the project schedule and narrative form.
• Documentation of key design decisions.
• Estimates of probable construction cost.
B. The EST conceptual design package will include:
• Site Planning
• Prepare schematic site plan with tank location, sizing, plans to be
prepared at scale of 1"-50'.
• Prepare preliminary alignments for interconnection and yard piping.
• Prepare preliminary drainage study with schematic detention pond
locations and preliminary sizing.
• Identify required utility services to facility.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 4 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSPdISSION P�1AIN
CITY PROJECT NO.: 103428
• Meet with ENGINEER and CITY to confirm tank sizing, tank operations,
requirements for construction and operation of the facility, plans and
requirements for winterization of facility.
• Technical Specifications Outline
• Piping, valves, fittings, restraints.
• Elevated storage tank.
• Site work, paving, grading.
• Preparation and Submission of FAA Documents for Approval
• Prepare and submit FAA Form 7460-1 with schematics, profiles and
elevation data.
• Coordinate reviews and approvals with FAA.
• Prepare Preliminary engineering report
• Summarizing facility requirements.
• Summarize facility hydraulics, and site conditions including drainage and
stormwater design issues.
• Identify issues and critical path tasks for permitting and construction.
• Prepare preliminary design, permitting and construction schedules.
ASSUMPTIONS
• For the pipeline submittal 5 copies of the conceptual design package (30%
design) will be delivered. Report shall be letter sized and comb- bound with a
clear plastic cover. Drawings will be 11x17 size fold outs bound in the report
• For the EST tank submittal 2 copies of the conceptual design package (30%
design) will be delivered. Report shall be letter sized and comb- bound with a
clear plastic cover. Drawings will be 22x34 size fold outs bound in the report
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in BIM 360.
• ENGINEER shall prepare the meeting minutes of the Concept Review meeting
and revise the report, if needed.
• ENGINEER shall not proceed with Preliminary Design activities without obtaining
written approval by the CITY of the Conceptual Design Package.
DELIVERABLES
A. Conceptual Design Packages (separate packages for each the EST and Pipeline
design)
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.12014
Page 5 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANf( AND SOUTH WESTSIDE V TRANSP,iISSION P,1AIN
CITY PROJECT NO.: 103428
TASK 3. PRELIMINARY DESIGN (60 PERCENT).
Preliminary plans and specifications shall be submitted to CITY per the approved Project
Schedule.
ENGINEER will develop the preliminary design of the infrastructure as follows.
3.1. Development of Preliminary Design Drawings and Specifications shall include the
following:
A. The pipeline preliminary design package will include:
• Cover Sheet
• A Prolect Control Sheet, showing all Control Points, used or set while
gathering data. Generally on a scale of not less than 1:400. The following
information shall be indicated for each Control Point: Identified (existing City
Monument #8901, PK Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an
identified coordinate system, and a referred bearing base. Z coordinate on City
Datum only; descriptive location (i.e. set in the centerline of the inlet in the
South curb line of North Side Drive at the East end of radius at the Southeast
corner of North Side Drive and North Main Street).
• Overall prolect easement layout sheet(s) with property owner information.
• Overall prolect water and/or sanitary sewer layout sheets. The water layout
sheet shall identify the proposed water main improvement/ existing water
mains in the vicinity and all water appurtenances along with pressure plane
boundaries, water tanks, pump stations, valves, and fire hydrants.
• Coordinates on all P.C.'s, P.T.'s, P.I.'s, manholes, valves, mainline fittings,
etc., in the same coordinate system as the Control Points.
• Benchmarks per 1,000 ft of plan/profile sheet — one.
• Bearinqs given on all proposed centerlines, or baselines.
• Station equations relating utilities to paving, when appropriate.
• Plan and profile sheets which show the following: proposed water and/or
sanitary sewer plan/profile and recommended pipe size, fire hydrants, water
service lines and meter boxes, gate valves, isolation valves, manholes,
existing meter numbers and sizes that are to be replaced, existing sample
locations, existing fire line locations, existing utilities and utility easements,
and all pertinent information needed to construct the project. Legal
description (Lot Nos., Block Nos., and Addition Names) along with property
ownership shall be provided on the plan view.
• The ENGINEER will prepare standard and special detail sheets for water line
installation and sewer rehabilitation or replacement that are not already
included in the D-section of the CITY's specifications. These may include
connection details between various parts of the project, tunneling details,
boring and jacking details, waterline relocations, details unique to the
Clty of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 6 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATE� STORAGE TANV( AND SOUTH WESTSIDE V TRANSP,IISSION P�1AIN
CITY PROJECT NO.: 103428
construction of the project, trenchless details, valve vault details and thrust
blocking details.
B. The EST preliminary design package will include:
• Cover Sheet
• A Proiect Control Sheet, showing all Control Points, used or set while
gathering data. Generally on a scale of not less than 1:400. The following
information shall be indicated for each Control Point: Identified (existing City
Monument #8901, PK Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an
identified coordinate system, and a referred bearing base. Z coordinate on City
Datum only; descriptive location (i.e. set in the centerline of the inlet in the
South curb line of North Side Drive at the East end of radius at the Southeast
corner of North Side Drive and North Main Street).
• Overall proiect easement layout sheet(s) with property owner information.
• Overall prolect water and/or sanitary sewer lavout sheets. The water layout
sheet shall identify the proposed water main improvement/ existing water
mains in the vicinity and all water appurtenances along with pressure plane
boundaries, water tanks, pump stations, valves, and fire hydrants.
• Bearinqs given on all proposed centerlines, or baselines.
• Station equations relating utilities to paving, when appropriate.
• Plan and profile sheets which show the following: proposed water plan/profile
and recommended pipe size, fire hydrants, water service lines and meter
boxes, gate valves, isolation valves, manholes, existing fire line locations,
existing utilities and utility easements, and all pertinent information needed to
construct the project. Legal description (Lot Nos., Block Nos., and Addition
Names) along with property ownership shall be provided on the plan view.
• Site and Dimensional Control Plan
• Prepare updated detailed Site Plan. Site plan to include verifications for
fire truck access, fire hydrant locations, typical maintenance vehicle
access, and parking.
• Illustrate alignment and locations of yard piping and valves, limits of
paving, security fencing.
• Prepare dimensional control plan with control points, benchmarks for
construction, providing detailed coordination for key construction
components including pipe fittings, valves, paving, borings, electrical
components including conduits, and security fencing.
• Provide specific coordinates on all P.C.'s, P.T.'s, P.I.'s, valves, vaults,
mainline fittings, etc., in the same coordinate system as the Control
Points.
• Minimum of two benchmarks for the elevated tank site, and a minimum of
one benchmark per 1,000 ft of temporary access route.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.12014
Page 7 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSP,IISSION PdAIN
CITY PROJECT NO,: 103428
• Erosion Control Plans and Stormwater Protection Plan
• Site Utility Plans - Prepare detailed utility plan for onsite piping, dry and wet
utilities as noted below:
• Water System — identify locations, alignments and sizing of yard piping,
valves, connections to off-site transmission mains, disinfection
connections, restraint lengths, details, construction notes.
• Electrical System — Illustrate locations and alignments of electrical
components, including transformers, conduits, control boxes, etc.
Coordinate with ENGINEER's Electrical/SCADA consultant to show all
components on civil plans, general notes and related details.
• Corrosion and Cathodic Protection — Coordinate with the ENGINEER's
consultant for their final report on the soil characteristics, design of the
corrosion protection systems for the proposed components that would
include cathodic protection, coatings, etc.
• Site Grading and Paving Plans for Elevated Storage Tank Site
• Prepare detailed grading plan, estimating cut and filis, spot elevations for
site work, edges of paving structures, curbing, grading, drainage patterns,
detention pond, and outfall.
• Prepare site drainage study, detention pond design, and report.
• Provide support calculations for design of detention pond for review and
approval by the CITY.
• Prepare site paving plan reflecting types and thickness of pavement,
locations of curbs, drainage inlets and catch basins, elevated tank
overflow basin, and outfall.
• Prepare schematic of security fencing, access drive, and security gate.
• Identify areas of erosion matting materials.
• Illustrate limits of clearing of vegetation, tree protection plans.
• Prepare limits and types of re-vegetation of disturbed areas.
• Provide construction details of paving, curbing, grading, access road, tree
protection, re-vegetation, fencing and access gate.
• Detailed Construction Plans for Elevated Storage Tank
• Prepare schematic design of elevated storage tank to accommodate
bidding by multiple tank manufacturers.
• Prepare elevated tank details for construction to include the following:
• Vertical tank profiles reflecting overall heights, bowl dimensions,
interior piping
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 8 of 23
ATTACHMENTA
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANK AND SOUTH WESTSIDE V TRANSPAISSION P,1AIN
CITY PROJECT NO.: 103428
• Interior piping, altitude control valve with fittings, isolation valves,
sensors, pressure gauges, sample ports, conduit locations, with
details for installation and operations
• Details for upper tube access, roof construction items including
access hatches, security railing, aviation lights, conduits, special
coatings for personnel access
• General construction notes required TCEQ construction notes,
construction standards, logo details and dimension as appropriate.
• Electrical Distribution and Control
• Coordination with the Power Company for new service
• No standby generator
• Lighting for tank e�erior, interior, and FAA obstruction
• Lightning protection (a performance spec)
• Power to cathodic protection impressed current rectifier (cathodic
protection design by others)
• Instrumentation and Controls
• Instrumentation
• Level, flow, and pressure analog instruments
• Intrusion alarms
• Motorized butterfly valves
• Altitude valve
• PLC cabinet
• Remote communications
• Security
• Motorized gate
• Access card readers (security design by others)
• Security cameras and DVR
• Technical Specifications
• Prepare technical specifications for yard piping, valves, elevated storage
tank, interior piping, altitude valves, control valve(s), internal valves, civil
controls, paving, curbs, sidewalks, pavement marking, security fencing,
gates, access, erosion protection and SWPPP requirements, concrete,
grading, trench excavation and compaction, and tree removals and
protection.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 9 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSP.IISSION h9AIN
CITY PROJECT NO.: 103428
• Prepare Special Conditions to the contract for review by the CITY.
• Prepare bid proposal form.
• Prepare updated Opinion of Probable Construction Cost for review.
• Prepare updated project schedule for review and comment.
• Updated Engineering Report
3.2. Geotechnicallnvestigation
• Soil investigations, including field and laboratory tests, borings, related
engineering analysis and recommendations for determining soil conditions will be
made. In addition to the above investigations, borings and appropriate field and
laboratory analysis will be made at reasonable intervals along the project
alignment for the Contractor's use in determining soil conditions for preparing
bids and a Trench Safety Plan.
3.3. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and government agencies to determine the
approximate location of above and underground utilities, and other facilities
(current and future) that have an impact or influence on the project. ENGINEER
will design CITY facilities to avoid or minimize conflicts with existing utilities, and
where known and possible consider potential future utilities in designs.
The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in BIM 360 for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
3.4. Traffic Control Plan
• Develop a traffic control plan utilizing standard traffic reroute configurations
posted as "Typicals" on the CITY's website. The typicals need not be sealed
individually, if included in the sealed contract documents.
• Develop supplemental traffic control drawings as needed for review and approval
by the Traffic Division of the Transportation and Public Works Department.
These drawings shall be sealed by a professional engineer registered in the
State of Texas.
3.5. Section 404 of the Clean Water Act Assessment (Section 404)
• Perform a formal pedestrian survey for cultural resources. Assumes no
trenching will be needed.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.�.2014
Page 10 of 23
ATTACHMENTA
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI<AND SOUTH WESTSIDE V TRANSPAISSION P�1AIN
CITY PROJECT NO,; 103428
ASSUMPTIONS
• 4 borings at an average bore depth of 50 feet each, 13 borings at
an average bore depth of 25 feet each, and 6 borings at an average
bore depth of 10 feet each will be provided.
• Traffic Control "Typicals" will be utilized to the extent possible. It is assumed no
additional project specific traffic control sheets will be developed.
• For the pipeline submittal 5 sets of 11x17 size plans will be delivered for
the Constructability Review
• For the EST submittal 2 sets of 22x34 size plans will be delivered for
the Constructability Review
• For the pipeline submittal 5 sets of 11 x17 size plans will be delivered for
the Preliminary Design (60% design).
• For the EST submittal 2 sets of 22x34 size plans will be delivered for
the Preliminary Design (60% design).
• For the pipeline submittal 5 sets of specifications will be delivered for the
Preliminary Design (60% design).
• For the EST submittal 2 sets of specifications will be delivered for the
Preliminary Design (60% design).
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in BIM 360.
• The CITY's front end and technical specifications will be used. The ENGINEER
shall supplement the technical specifications if needed.
• Electronic files will be uploaded to BIM 360 for Utility Clearance.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design plans.
DELIVERABLES
A. Preliminary Design drawings and specifications (separate packages for each the
EST and Pipeline design)
B. Utility Clearance drawings
C. Traffic Control Plan
D. Storm Water Pollution Prevention Plan
E. Estimates of probable construction cost
F. Geotechnical Engineering Report
G. Corrosion Control Design incorporated on Plan and Profile Sheets
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 11 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSh11SSI0N MAIN
CITY PROJECT NO.: 103428
TASK 4. FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• For projects that disturb an area greater than one (1) acre, the Contractor will be
responsible for preparing and submitting the Storm Water Pollution Prevention Plan
(SWPPP) with appropriate regulatory agencies. The Engineer will prepare the iSWM
Construction Plan according to the current CITY iSWM Criteria Manual forSife
Development and Construction which will be incorporated into the SWPPP by the
contractor.
• Draft Final plans (90%) and specifications shall be submitted to CITY per the approved
Project Schedule.
• Following a 90% construction plan review meeting with the CITY, the ENGINEER shall
submit Construction Documents (100%) to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered in
State of Texas.
• The ENGINEER shall submit a final design estimate of probable construction cost with
both the 90°/o and 100% design packages. This estimate shall use ONLY standard CITY
bid items.
• The EST design package also includes:
• 90% Design Submittal to TCEQ
• Submit a copy of the preliminary 60 percent design set that includes the updated
Engineering Report, drawings, and technical specifications.
• Coordinate with TCEQ, ENGINEER, and CITY through a preliminary review
process. Provide prompt responses to TCEQ comments to secure TCEQ
approval for construction during the 90 percent design phase.
ASSUMPTIONS
• Agency review fees or impact fees are not included herein.
• Engineer will coordinate with Oncor for power to the Elevated Storage Tank Site
• For the pipeline submittal 5 sets of 11x17 size drawings and 5
specifications will be delivered for the 90% Design package.
• For the EST submittal 1 sets of 22x34 size drawings and 1 specifications
will be delivered for the 90% Design package
• A DWF file for the 90% Design will be created from design CAD drawings and will be
uploaded to the project folder in BIM 360.
• For the pipeline submittal 3 sets of 11x17 size drawings and 3 specifications
will be delivered for the 100% Design package.
City of Fort Worth, Texas
Attachment A
PMO Release Date: OS.1.2014
Page 12 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI<AND SOUTH WESTSIDE V TRANSP,IISSION P�1AIN
CITY PROJECT NO.: 103428
• For the EST submittal 1 sets of 22x34 size drawings and _1_ specifications
will be delivered for the 100% Design package.
• A DWF file for the 100% Design will be created from design CAD drawings and will be
uploaded to the project folder in BIM 360.
• Transmission Main Sheet List:
Cover Sheet
Index and Legend
General Notes (2)
Layout and Survey Control (4)
Right of Way Map (8)
iSWM Construction Plan (8)
Plan and Profile (36)
Standard and Project Specific Details (15)
DELIVERABLES
A. 90% construction plans and specifications (separate packages for each the EST and
Pipeline design)
B. 100% construction plans and specifications (separate packages for each the EST and
Pipeline design)
C. Detailed estimates of probable construction costs including summaries of bid items and
quantities using the CITY's standard bid items and format.
D. Original cover mylar for the signatures of authorized CITY officials.
TASK 5. BID PHASE SERVICES.
ENGINEER will support the bid phase of the project as follows.
5.1. Bid Support
• It is assumed that the EST project and Pipeline project will be bid separately.
• The ENGINEER shall upload all plans and contract documents onto BIM 360 for
access to potential bidders.
• Contract documents shall be uploaded in a.xls file.
• Unit Price Proposal documents are to be created utilizing CFW Bidtools only
and combined in a specified spreadsheet workbook, Bid Proposal Worksheet
Template, and will be populated and configured so that all pages are
City of FoR Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 13 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSP.iISSION PnAIN
CITY PROJECT NO.: 103428
complete and the Summary Worksheet(s) in the workbook detail and
automatically summarize the totals from the inserted Unit Price Proposal
document worksheets.
• Plan Sets are to be uploaded to BIM 360 in two formats, .pdf and .dwf files.
The .pdf will consist of one file of the entire plan set. The .dwf will consist of
individual files, one for each plan sheet, and will be numbered and named in
a manner similar to that of the plan set index.
• The ENGINEER shall sell contract documents and maintain a plan holders list on
BIM 360 from documents sold and from Contractor's uploaded Plan Holder
Registrations in BIM 360.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
projecYs BIM 360 folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidders questions and requests, in the form of
addenda. The ENGINEER shall upload all approved addenda onto BIM 360 and
mail addenda to all plan holders.
• Attend the prebid conferences in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid openings in support of the CITY.
• Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation and the CFW Data Spreadsheet created utilizing CFW Bidtools only
are to be uploaded into the project's Bid Results folder on BIM 360.
• Incorporate all addenda into the contract documents and issue conformed sets.
5.2 Final Design Drawings
1) Final Design Drawings shall be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher) format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set. Each PDF and DWF file shall be created from the original
CAD drawing files and shall contain all associated sheets of the particular plan
set. Sinqular PDF and DWF files for each sheet of a plan set will not be
accepted. PDF and DWF files shall conform to naming conventions as follows:
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 14 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTN WESTSIDE V ELEVATE� STORAGE TANK AND SOUTH WESTSIDE V TRANS�dISSION P�1AIN
CITY PROJECT NO.: 103428
I. TPW file name example —"W-1956_org47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "_org" designating the file is
of an original plan set, "47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example —"X-35667_org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36" shall be the total number
of sheets in this file.
Example: X-12755_org18.pdf
Both PDF and DWF files shall be uploaded to the project's Final Drawing folder in
BIM 360.
2) In addition to the PDF and DWF files, the ENGINEER shall submit each plan sheet
as an individual DWG file with all reference files integrated into the sheet. If the
plans were prepared in DGN format, they shall be converted to DWG prior to
uploading. The naming convention to be used for the DWG files shall be as
follows:
I. TPW files shall use the W number as for PDF and DWF files, but shall
include the sheet number in the name —"W-1956_SHT01.dwg", "W-
1956_SHT02.dwg", etc.
II. Water and Sewer file names shall use the X number as for PDF and
DWF files, but shall include the sheet number in the name —"X-
12155_SHT01.dwg", "X-12755_SHT02.dwg", etc.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number (817) 392-8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
ASSUMPTIONS
• Each project (EST and Pipeline design packages) will be bid only once and
awarded to one contractor.
• Construction documents will be made available on BIM 360 for plan holders
and/or plan viewing rooms.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.12014
Page 15 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATE� STORAGE TANf<AND SOUTH WESTSIDE V TRANSP�IISSION MAIN
CITY PROJECT NO.: 103428
• 7 sets of 11x17 size and 3 sets of 22x34 size drawings plans
and 10 specifications (conformed, if applicable) will be delivered to the CITY
for each design package.
• PDF, DWF and DWG files will be uploaded to BIM 360.
• Engineer will attend the bid openings
DELIVERABLES
A. Addenda
B. Bid tabulations
C. CFW Data Spreadsheet
D. Recommendation of award
E. Construction documents (conformed, if applicable)
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1 Construction Support
• The ENGINEER shall attend the preconstruction conferences.
• The ENGINEER shall attend 10 construction site visits for the EST package and
10 construction site visits for the pipeline package.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents, review change orders, and make
recommendations as to the acceptability of the work.
• The ENGINEER shall attend the "Final" project walk throughs and assist with
preparation of final punch lists
6.2 Record Drawings
• The ENGINEER shall prepare Record Drawings from information provided by
the CITY depicting any changes made to the Final Drawings during construction.
The following information shall be provided by the CITY:
o As-Built Survey
o Red-Line Markups from Contractor
o Red-Line Markups from City Inspector
o Copies of Approved Change Orders
o Approved Substitutions
• The ENGINEER shall modify the Final Drawings electronically and shall place a
stamp on the plans indicating that they represent Record Drawings of the project
as constructed. The stamp shall be signed and dated by the ENGINEER and
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 16 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSh11SSI0N PdAIN
CITY PROJECT NO.: 103428
shall be placed on each plan sheet, whether there are any revisions on the sheet
or not. Each sheet shall clearly indicate all changes which apply to that sheet by
clouding and numbering, or other suitable means.
• The following disclaimer shall be included with the Record Drawing stamp:
o These Record Drawings were prepared using information provided by
others and represent the as constructed conditions to the e�ent that
documented changes were provided for recording. The ENGINEER
assumes no liability for undocumented changes and certifies only that the
documented changes are accurately depicted on these drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as Record Drawings, on mylar for record storage. The ENGINEER may
keep copies of the information provided by the CITY for their files, but all original
red-lined drawings shall be returned to the CITY with the mylars.
2) Record Drawings shall also be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher) format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set. Each PDF and DWF file shall contain all associated sheets
of the particular plan set. Sinqular PDF and DWF files for each sheet of a
plan set will not be accepted. PDF and DWF files shall conform to naming
conventions as follows:
I. TPW file name example —"W-1956_rec47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "_rec" designating the file is
of a record drawing plan set, "47" shall be the total number of sheets in this
file.
Example: W-0053_rec3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example —"X-35667_rec36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_rec"
designating the file is of a record drawing plan set, "36" shall be the total
number of sheets in this file.
Example: X-12755_rec18.pdf
Both PDF and DWF files shall be uploaded to the project's Record Drawings folder
in BIM 360.
ASSUMPTIONS
• 5 RFI's are assumed for the pipeline design package
• 30 RFI's are assumed for the EST design package
• 2 Change Orders are assumed for the pipeline design package
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 17 of 23
ATTACHMENTA
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELE4ATED STORAGE TANK AND SOUTH WESTSIDE V TRANSP�7ISSION PAAIN
CITY PROJECT NO.: 103428
• 10 Change Orders are assumed for the EST design package
• 50 Submittals are assumed for the pipeline design package
• 50 Submittals are assumed for the EST design package
• One copy of full size (22"x34") mylars will be delivered to the CITY for each
design package
• No public meeting is required
DELIVERABLES
A. Response to Contractor's Request for Information
B. Review of Change Orders
C. Review of shop drawings
D. Final Punch List items
E. Record Drawings on Mylar
TASK 7. ROW/EASEMENT SERVICES.
ENGINEER will support and perform activities related to ROW and land as outlined below,
per scoping direction and guidance from the CITY's Project Manager.
7.1. Right-of-Way Research
• The ENGINEER shall determine rights-of-way, easements needs for construction of the
project. Required temporary and permanent easements will be identified based on available
information and recommendations will be made for approval by the CITY.
7.2. Right-of-Way/Easement Preparation and Submittal.
• The ENGINEER shall prepare documents to be used to obtain right-of-way and
permanent and/or temporary easements required to construct the improvements.
• The ENGINEER shall submit the right-of-way and/or easement documents to CITY PM
for real property acquisition
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's website.
7.3. Temporary Right of Entry Preparation and Submittal
• Prior to construction, the ENGINEER shall prepare and submit Temporary Right of Entry
documents for landowners to CITY PM for real property acquisition. It is assumed that letters
will only be required for land owners adjacent to temporary construction easements or who
are directly affected by the project and no easement is required to enter their property.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.12014
Page 18 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSLIISSION C9AIN
CITY PROJECT NO.: 103428
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's website.
ASSUMPTIONS
• 1 Easements or right-of-way document will be necessary.
• 1 Temporary construction easement document will be necessary.
• 1 Temporary right-of-entry document will be necessary.
• Right-of-Way research and mapping includes review of property/right-of-way records
based on current internet based Tarrant Appraisal District (TAD) information available at the
start of the project and available on-ground property information (i.e. iron rods, fences,
stakes, etc.). It does not include effort for chain of title research, parent track research,
additional research for easements not included in the TAD, right-of-way takings, easement
vacations and abandonments, right-of-way vacations, and street closures.
DELIVERABLES
A. Easement exhibits and meets and bounds provided on CITY forms.
B. Temporary Right of Entry Letters
TASK 8. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES.
ENGINEER will provide survey support as follows.
8.1. Design Survey
• ENGINEER will perform field surveys to collect horizontal and vertical elevations and
other information needed by ENGINEER in design and preparation of plans for the project.
Information gathered during the survey shall include topographic data, elevations of all
sanitary and adjacent storm sewers, rim/invert elevations, location of buried utilities,
structures, trees (measure caliper, identify overall canopy, and species of trees), and other
features relevant to the final plan sheets.
• The minimum survey information to be provided on the plans shall include the following:
— A Project Control Sheet, showing ALL Control Points, used or set while gathering data.
Generally on a scale of not less than 1:400:
— The following information about each Control Point;
a. Identified (Existing. CITY Monument#8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a referred bearing
base. Z coordinate on CITY Datum only.
City of Fort Worih, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 19 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANK AND SOUTH WESTSIDE V TR,4NSPdISSION h9AIN
CITY PROJECT NO.: 103428
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South curb line of
North Side Drive at the East end of radius at the Southeast corner of North Side Drive and
North Main Street).
— Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the same coordinate
system, as the Control.
— No less than two horizontal benchmarks, per line or location.
— Bearings given on all proposed centerlines, or baselines.
— Station equations relating utilities to paving, when appropriate.
8.2. Temporary Right of Entry Preparation and Submittal
• Prior to entering property, the ENGINEER shall prepare and submit Temporary Right of
Entry for landowners to CITY PM.
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's website.
8.3. Subsurface Utility Engineering
• Engineer will perform the SUE work required for this project in general accordance with
the recommended practices and procedures described in ASCE Publication Cl/ASCE
38-02 (Standard Guideline for the Collection and Depiction of Existing Subsurface Utility
Data). As described in the mentioned ASCE publication, four levels have been
established to describe the quality of utility location and attribute information used on
plans. The four quality levels are as follows:
• Quality Level D(QL"D") — Information derived from existing utility records;
• Quality Level C(QL"C") - QL"D" information supplemented with information obtained
by surveying visible above-ground utility features such as valves, hydrants, meters,
manhole covers, etc.
• Quality Level B(QL"B") — Two-dimensional (x,y) information obtained through the
application and interpretation of non-destructive surface geophysical methods. Also
known as "designating" this quality level provides the horizontal position of
subsurface utilities within approximately one foot.
• Quality Level A(QL"A") — Three dimensional (x,y,z) utility information obtained
utilizing non-destructive vacuum excavation equipment to expose utilities at critical
points which are then tied down by surveying. Also known as "locating", this quality
level provides precise horizontal and vertical positioning of utilities within
approximately 0.05 feet.
• It is the responsibility of the SUE provider to perform due-diligence with regard to
records research (QL "D") and acquisition of available utility records. The due-diligence
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 20 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANV<AND SOUTH WESTSIDE V TRANS�dISSION PdAIN
CITY PROJECT NO.: 103428
provided for this project will consist of visually inspecting the work area for evidence of
utilities and reviewing the available utility record information. Utilities that are not
identified through these efforts will be here forth referred to as "unknown" utilities. TRG
personnel will scan the defined work area using electronic prospecting equipment to
search for "unknown" utilities. However, TRG is not responsible for designating and
locating these "unknown" utilities.
• SUE Engineer will produce a utility file, in AutoCAD format, depicting the type and
horizontal location of the designated utilities. The size of each utility will be presented in
the utility file if this information is indicated on available record drawings. Engineer will
also provide a summary sheet of the test hole coordinate data and depth information.
• Right of entry is not included in this scope
• Utilities to be designated include gas, telecommunications, electric, traffic signals, storm,
water and sanitary sewer.
o Scope includes 4 QL"A" Test Holes
ASSUMPTIONS
• Topographic survey assumes a 100' width along the pipeline alignment.
DELIVERABLES
A. Copies of field survey data and notes signed and sealed by a licensed surveyor.
B. Drawing of the project layout with dimensions and coordinate list.
TASK 9. PLAN SUBMITTAL CHECKLISTS
Engineer shall complete and submit Plan Submittal Checklists in accordance with the
following table:
PLAN SUBMITTAL CHECKLIST REQUIREMENTS
Traffic Traffic Traffic
Street Water Control Control Control
Traffic Traffic 30% 60% 90%
Storm Storm Lights /Sewer
Attachment "A" Signal Engineering
Water Water (Submit (Submit
Type (Submit All 30% 60% All @ All @ (Submit AII
@ 30%) 30% 60%) �° 60%� Required for all work in City
ROW
Street X X X X X' X X X X
Storm Water X X X X X
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.12014
Page 21 of 23
ATTACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANI( AND SOUTH WESTSIDE V TRANSGIISSION NIAIN
CITY PROJECT NO.: 103428
*If included in street project
ASSUMPTIONS
DELIVERABLES
A. Water/Sewer Checklist at 60% Preliminary Design
• ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existinq Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon the
CITY's written request. Any additional amounts paid to the ENGINEER as a result of any
material change to the Scope of the Project shall be agreed upon in writing by both parties
before the services are performed. These additional services include the following:
• Negotiation of easements or property acquisition including temporary right-of-
entries.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre-qualification, bid protests, bid rejection and
re-bidding of the contract for construction.
• Construction management and inspection services
• Periodic site visits during construction phase
• Public meetings
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services related to submitting for permits (ie.TxDOT, railroad, etc...)
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 22 of 23
ATfACHMENT A
DESIGN SERVICES FOR
SOUTH WESTSIDE V ELEVATED STORAGE TANV<AND SOUTH WESTSIDE V TRANSP�IISSION P�1AIN
CITY PROJECT NO.: 103428
• Services related to Survey Construction Staking
• Services related to acquiring real property including but not limited to easements,
right-of-way, and/or temporary right-of-entries.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Construction Shop drawing review, samples and other submittals submitted by the
contractor.
• Performance of miscellaneous and supplemental services related to the project as
requested by the CITY.
• Hydraulic Analysis
• Platting and acquisition of the EST site
• Survey, easement acquisition and/or negotiation of a construction access route
other than the pipeline alignment.
• Relocation of existing underground utilities, if identified after start of construction.
• Value engineering
• FEMA mapping, FEMA level flood studies, map revision.
• Structural design of the EST. Tank manufacturer will provide all structural
designs, calculations, and final details for its EST for submittal and approval by ENGINEER
and CITY.
• Building architectural or structural design services
• Tank inspections for structural components or coatings
• Construction Inspection
• Materials testing
• Evaluation of pipeline materials for the project
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.12014
Page 23 of 23
ATTACHMENT B
COMPENSATION
Design Services for
South Westside V Elevated Storage Tank and South Westside V Transmission Main
City Project No. 103428
Lump Sum Project
Compensation
A. The ENGINEER shall be compensated a total lump sum fee of $1,291,838.00 as
summarized in Exhibit B-1 — Engineer Invoice and Section IV — Summary of Total
Project Fees. The total lump sum fee shall be considered full compensation for
the services described in Attachment A, including all labor materials, supplies,
and equipment necessary to deliver the services.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. Partial payment shall be made to the ENGINEER monthly upon City's approval of
an invoice prepared and submitted by the ENGINEER in the format and including
content as presented in Exhibit B-1, Progress Reports as required in item III. of
this Attachment B, and Schedule as required in Attachment D to this Agreement.
B. The estimated current physical percent complete as required on the invoice shall
be calculated from the progress schedule as required in Attachment D to this
Standard Agreement and according to the current version of the City of Fort
Worth's Schedule Guidance Document.
C. The cumulative sum of such monthly partial fee payments shall not exceed the
total current project budget including all approved Amendments.
D. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Water Department monthly progress reports and schedules in the format
required by the City.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 8.09.2012
Page 1 of 3
B-1
ATTACHMENT B
COMPENSATION
IV.
Summary of Total Project Fees
Uesign
Project Number & Name Total Fee MBEISBE Fee MBE/SBE
°/a
103428-South Westside V Elevated $1,291,838 $168,369 13.0 °/o
Storage Tank and South Westside V
Transmission Main
City MBE/SBE Goal = 10%
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 8.09.2012
Page 2 of 3
Consultant Committed Goal = 13.0 %
B-2
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across work types and work phases.
City of Fort Worth, Texas
Attachment B
PMO Offcial Release Date: 8.09.2012
Page 3 of 3
B-3
-�
0
d
N
�
�
�'
7
<
O
Ci
m
�
�
�
O
�
G
�
w
� N
� �
Z w
C'1 W
�
� O
�
ca
N
�
�
N
7
rt
N
�
�
w
m
0
0 0 0 0 0 0�
-. -. . . S
F F F (p
`G K -i �i i � (p
�v a v "*
m m A �o m
m tn A w hf �
m
O �
v
d
�
a
0
�
�
�
m
�
N
N
c�
�
n�
O
7
�' D �
N 3 'm
' � 3C
� � N
� � K
O
D
D 3
� �
O 3
� �
3 �
K �
�„ D co
� v o �u
d C �D
K
w � ry
� p 3
O
Do
O 'd —rl
c � 0
3 �
r. Q
N �
� n
� �
K 7
� H9
< 3
O �
C �.
N n
`� Q,
3 n
� C
O i
n �
N ,�y.
� N
�' w 3
N 0) d
fD =
W fD 7
W �
� � � � � �
�.< <���
•�'D�
� N N � fD (D
O p p A � N
fD < 'O
�����.�
-iTC n ..
� O (�I1 �
� "�' i�
�..
v
�
;� �-ipm
3 x m � m
- �'O m=
D o D �
a � a
a m a
'm m
N N
N pl
N J o
w m
N A y
� V N.
J (T �
W O �
A A
N
0
z
X
rn
J
(7
O
�
v
v
7
�
Z
N
�
m
�
0
�
n �
o s
� �
m �
��
y O
� �
O �
� O
f �
S N
� o
v ,30
o, �
m �
.^. -
N H
d
O �
�
a
m �
� Q
O
m
N
a
p
m
£
�
D
a
a
�
°c
�
0
m
0
�
m
n
K
N
m
Z
3
�
C
v
�'
N
C
n
�
N
n � �
�G
.9 � �
o, n N
(�i �.�, (/)
x� O
�
�
�
�D
w o �
I�� f�D
3 �
� C
Q �.
<
m
m
<
v
cD
Q
�
0
v �
�
� �
� �
� ..
� A
Q y
O A
� �
� �
V/
C
�
�
C1
�
� D n
� m �
O�
� 3 T
A m �
r�
N �
O�
v m �
m}
� N
N 3
A �
A N N N N�
A A� N� i,� N� .� N.� F
N � Z
v�� o �� �n�czc�<v� �m�o� � �v
�', � , ^:oo � m _ � ° zzvfnv v oc3 � 3 O> >'o
� oo c? ° ��oc��3.3 m - n�m OOm _ ?� 30'�° -.^.
N.� N � 1, nry m� — CC°1 � m� ?'(� d� 3
o A� � O � ��� n' o m °' fn fil ��° �� ��� N� m�
vo "-No - ooF'- o00
� � N avm _ � n - �u10, �jQ� � - m 3 �.3 0 � 3 -i� m
� 3 3 - - � o ' `-' � �. � D �`0 3 � �n � N - - � 3 3 °
< N= °'_ o£ o _ 3� d�, o o � _ 3 o A _
� S v � m � � � . . m 9
N - m m `° 3� '° m "m � ���. o
v T 3 � o o A A � '
� � � _ � � - � �
O O - �� n� � f
_ _ - 3 0 3 0
o�
m o
d' ^ n
A
A A W N tN.f A o
3 �
N � �
�
A A o N A v � A N N N O� N N
m �
`m r
O N N A p �
m o N A N A N N A ^�
0
m �
_�
A A �
O� OWi N m N N �"�
n �
o 'O
� o
N J A m N A N A A tWi� O
D n
3 Z
- O
a
� o
N A W A
� N
o pp
o -
w�. aw �'mw e.c�'i� r:�n� i.�i H �
_ J � _ _ _ _ " " " _ _ _ _
A tmii A W A W A N o A (�ii N fJ.� N N
O N o N o �n A � A o
�
� 5q W N
o A A A RI
NW �
H
o Z —
O
A tfl �
m � N W m J A �
� ONi N � A p fll %
1
<
� � _
rn
A
IJ P N �
i
� a m
J x
o, m � ?
m_ _ _ _ (O A
N
'i
N
�
N N N V O� W� V� tNo A o � tNii N N N �
N N A N A N W N N f» N N N m N bi
Or O� � A � A o N
n
O
3
4
r�
3 �
=. io
N
0
C
3C
G
�
N
a
m
G
m
IU
N
N
a
�
0
n'i p
�
� N
� �.
�
��
N �
7 C
a �.
w�
O y
C O
SC
C
N
N
�
G
"''
�
�
�
N
�
�
fll
7
D�
N�
= o
om
C �
:U o
�
� �
m�
�d
p a
ON
�S
fD
Z ;;
N
� D n
3 d �
O n
� 3 T
- ^ a
=m�
� � o
r �
m -i
O �
� m °y'
m}
o N
N3
A d
IV p� p� p� V+ A !J >
� � m Z
[n A W !J N O
1 O t/1 1 p� A Z1 A .Z1 (7 ll ID W C) � (i <
H O n' O � C� �.Zl ;U N� fn G Cl D� - 1 D D fn N"D (n a a o n -
3 n 2 30 � m.� � n � � � o � m � m � 10 n ��� c z � O - m—
'm t�� m v, � cmi p`� m 3.n — n c �`—, n na`D =� � � d
� em 2�im- °�c �o.» � m av >o -- = c o
�m A�� 3 F �zN-�..=�� �o. >> > m ��n �}" �3 � � °
- - 3 � � � - � � � A _ o m � - o � � m c F - � �
? 3v v » - � <_<.`-' �'�n = � � Q ro ^- s �
0 0 � N o F N a n� n H o 3� �- x
m mn � 2 3 -c ��m o�.o -�- z= �
d� - N � 3 N c� (] 0� r�n
•z ^ � � ^ - � - � � � 'm ? A fn
� c v �� _� v� n Z ^ 3 - _
3 3 3�n s � o� n _� - �
- _ ^3 - z 3 � � £ o�m
H n
— O c - �
� �
w o ,��,
P �
� �
� O
N � w
N N N N A N N N A N N A A
m �
�. o
f�i, ^ c
A W A A N A m A
m
� N
J O
N A A O �
O o m O m m m m N N O w OJ In W A W -
D �
o � o �
A cm N v� O
n �
a ti,
3 Z
' O
A A N N A
-1 N
�
�=
u, o �
� A N m O�i N N W
� _ _ " " _ _ _ _ p � N �r �
A A V N O
A W A A � N O
i
fn b+ � � N
o m
A A N
N Z G
o d
A A �
A� N N m N �
[Jii O� � � � A A A W fil
m
m
0 0 0 o v� o m o o u� �n o 0 0 0 0 0
-i
�
<
�
il
N A A
� N >
-i
O
� m
o x
u
o N O� J A O
" _ _ " _ _ N _ . _ » �
(Ji� O�i fn W �n A o A
-i
0 oN o 0 00 0 00 0 olnm o0 o w o o cn o 00
N
m �
N A N N O�i N A � N m A� W p
A� m A A A U � � � � �� A v O� A N �
C)
0
3
m
A
3 W
� �
�
O
�
�C
C
�
N
N
Q
�
G
m
C
i11
�
�%
�
ill �
�
� N
v�
3
x �
N �
� G
a�
� �
O N
C p
S
�
N
�
Q
�
�
'I
N
N
�
N
N
0
�
N
7
D �
� �
= O
O
cm
� o
W "�'
m�
� d
� Q
Oy
�3
m
Z ;:
�an
3 m �
o�o
� 3 T
_ � �
���
r �
m -i
Q o
mmN
m�
O (/1
o�
N �
u
� �nD"w x
IV o
Z
an �o��Tm�� �
-- o,�v000-,�v3 m
_ � � _ o � = Q
(/1 � � � ? m
zN � —
� °i Z D d
- � = fn O
- N z � x
- C o
N
m
0
c�
�
o �
w o ,��„
A l
3 �p
� o
m �
�. o
' y� �'o � r
�
P �
m
�q "i
n
� �
w D �
0
A �y O
0
� D �
a ti,
3 Z
- O
_ W
A
1 N
�
C� =
o � v
P
~ O
A
�
� � � N
� W
� m
fJ
� z -
� �
A � »
W m
m
�
�
a
o'
a
m =N 1»
-i
O
w o m
�
-1
x
N
N C
1
O
M fA Hi
n
3
�
3 W
S�
� �
N
O
C
SC
C
N
N
N
o:
m
G
m
m
d
m
a
�
0
'm p
�
m N
� �.
7
� �
N �
� G
a�
� �
o N
C O
SC
G
N
N
Q
�
�
�
N
N
3
�
�
0
7
�
v
�
D �
� �
� �
= O
om
C --�
.I1 O
W "�'
ma
� ni
0 4
O �'
�S
fD
Z ;:
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
South Westside V Elevated Storage Tank and South Westside V Transmission Main
City Project No. 103428
No changes to the Standard Agreement
City of Fort Worth, Texas
Attachment C
PMO Release Date: 05.19.2010
Page I of 1
FORT WORTH
ATTACHMENT "D"
PROJECT SCHEDULE
A. ENGINEER Project Schedule Development
ENGINEER shall prepare a project schedule for the services to be provided in fulfilling
the requirements of the Agreement and encompassing the Scope of Work defined in
Attachment A to the Agreement.
ENGINEER shall prepare and maintain project schedule throughout the life of the project
as defined in the Agreement in compliance with the City's Specification 00 31 15 entitled
Engineer Project Schedule.
ENGINEER's project schedule will follow the Critical Path Methodology (CPM) for
planned sequencing of the work activity and timing of the work.
B. Schedule "Tier" Selection
City has identified three "Tier" levels for project schedules as defined in City's
Specification 00 31 15, to align with the size and complexity of the project as a basis for
schedule development. City's Project Manager will determine the "Tier" level for the
ENGINEER's project schedule as part of the negotiation of the Agreement.
C. Project Baseline Schedule
ENGINEER will produce an initial project schedule and submit as a"baseline" for review
and acceptance by City's Project Manager as defined in City's Specification 00 31 15
which will be referred to as the Project Baseline Schedule. Updates to the baseline
schedule follow the requirements of City's Specification 00 31 15.
D. Project Progress Schedule
ENGINEER will provide to the City, monthly updates to their project schedule indicating
progress of the Work in compliance with the requirements of City's Specification 00 31
15 and said schedule will be referred to as the Project Progress Schedule.
E. Master Project Schedule
City will develop and maintain a master project schedule for the overall project.
ENGINEER's project baseline and progress schedule submittals will be an integral part
of the development and updating process of City's Master Project Schedule.
City of Fort Worth, Texas
Attachment D
Revision Date: 07202018
Page 1 of 1
Attachment E
,
30
i
'-s;�,
�, o-
PROPOSEDELEVATED
STORAGE TANK
pLEDO_,RD
�z
WEST FWY
�.: � 't� .
��
�
�y
.20
IH=20
PROPOSED WATER
TRANSMISSION MAIN
��
FUTURE WS4/WS5
BOOSTER STATION
3MG GROUND
STORAGE TANK
ALEp�� f
�_RD �
�
L�
���''�'t�R�r
Source! Esri, D'igitalGlobe, GeoEye, Ear�t
DS, US'DA, USGS, AeroGR�1D„ IGN, and 1
,�
� '�
�;
�
C.
� .�
��
�'.
'Z'
C�'
,_,
Q
Geographics; CNES/A�ir6us
S User Coromun, ity
Attachiiient F
Certificate of Insurailce
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/22/21 M&C FILE NUMBER: M&C 21-0474
LOG NAME: 60SWSV EST AND TRANSMISSION MAIN-HALFF
SUBJECT
(CD 3) Authorize Execution of an Engineering Agreement with Halff Associates, Inc. for $1,291,838.00 for Design of the South Westside V
Elevated Storage Tank and Water Transmission Main, Provide for Project Costs for a Total Project Amount of $1,698,798.00, Adopt Attached
Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt, and Adopt Attached Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an Engineering Agreement with Halff Associates, Inc. in the amount of $1,291,838.00 for the South Westside V
Elevated Storage Tank and Water Transmission Main;
2. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds from future debt for the South Westside V
Elevated Storage Tank and Water Transmission Main; and
3. Adopt the attached appropriation ordinance adjusting appropriations in the Water and Sewer Commercial Paper Fund by increasing
appropriations in the amount of $1,698,798.00 in the South Westside V Elevated Storage Tank and Water Transmission Main Project (City
Project No. 103428) and decreasing appropriations in the Unspecified project (City Project No. UNSPEC) by the same amount.
DISCUSSION:
This Mayor and Council Communication is to authorize the preparation of plans and specifications for the construction of South Westside V
Elevated Storage Tank (EST) and Water Transmission Main.
Growth within west Fort Worth and its Extra Territorial Jurisdiction requires continuous improvements to the water distribution system in order to
provide and maintain reliable water service to existing and proposed developments within the Westside pressure planes. This EST will provide
additional storage capacity in the South Westside V Pressure Plane while Water Transmission will pump/provide the needed water to the tank.
The proposed scope of services include site selection and feasibility studies, field surveys, design for the transmission main, design survey,
environmental permitting, easement preparation, subsurface utility engineering and geotechnical investigation.
Halff Associates, Inc. proposes to provide all the necessary design and construction administration services for a fee of $1,291,838.00. Staff
considers the proposed fee to be fair and reasonable for the scope of services proposed.
In addition to the contract amount, $406,960.00 is required for project management, real property acquisitions and utility coordination. This project
will have no impact on the Water Department Operating Budget when complete.
Appropriations for the South Westside V Elevated Storage Tank and Water Transmission Main are as depicted below:
Fund Existing
Appropriations
Additional
Appropriations Project Total*
W&S Commercial
Paper Fund 56020 $0.00 $1,698,798.00 $1,698,798.00
Project Total $0.00 $1,698,798.00 $1,698,798.00
*Numbers rounded for presentation purposes.
This project is anticipated to be included in a future revenue bond issue for the Water & Sewer Fund. Available cash within the Water and Sewer
portfolio and the City's portfolio along with the appropriation authority authorized under the callable Commercial Paper Program (CP) will be used
to provide interim financing for this project until debt is issued. Once debt associated with this project is sold, bond proceeds will be used to
reimburse the Water and Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution. Under federal law,
debt must be issued within approximately three years in order for these expenses to be reimbursable. Adoption of the attached resolution does not
obligate the City to sell bonds, but preserves the ability to reimburse itself from tax-exempt bond proceeds.
Business Equity: Halff Associates, Inc. is in compliance with the City's Business Equity Ordinance by committing to 10 percent participation on this
project. The City's Business Equity goal on this project is 10 percent.
The project is located in COUNCIL DISTRICT 3.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the UNSPEC project within the W&S Commercial Paper Fund and upon
approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Commercial
Paper Fund for the WS V EST and Transmission Main project to support the approval of the above recommendations and execution of the
engineering agreement. Prior to an expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head:Chris Harder 5020
Additional Information Contact:Russell Redder 4970
Expedited
60SWSV EST AND TRANSMISSION MAIN-HALFF FID Table
Rec #Fund Dept #Account Project
ID
Activity Budget
Year
CF 2 Program Amount Purpose Xfer
2&3)56020 0600430 UNSPEC UNSPEC 2021 ($1,698,798.00)
2&3)56020 0600430 103428 001430 2021 $1,698,798.00
Rec #Fund Dept #Account Project
ID
Activity Budget
Year
CF 2 Program Amount Purpose Xfer
Rec #Fund Dept #Account Project
ID
Activity Budget
Year
CF 2 Program Amount Purpose Xfer
2&3)56020 0600430 5110101 103428 001430 9999 $242,400.00 Staff Costs
2&3)56020 0600430 5540101 103428 001430 9999 $4,000.00 Public Outreach
1 56020 0600430 5330500 103428 001430 9999 $1,291,838.00 To pay Engineering Company
2&3)56020 0600430 5110101 103428 001440 9999 $40,000.00 Land Acquisition
2&3)56020 0600430 5330500 103428 001440 9999 $5,000.00 Land Acquisition
2&3)56020 0600430 5710010 103428 001440 9999 $50,000.00 Land Acquisition
2&3)56020 0600430 5740010 103428 001440 9999 $5,000.00 Land Acquisition
2&3)56020 0600430 5310350 103428 001470 9999 $4,000.00 Utility Coordination
2&3)56020 0600430 5330500 103428 001484 9999 $40,400.00 Soil Lab Consultant
2&3)56020 0600430 5310350 103428 001484 9999 $16,160.00 Soil Lab TPW Staff Cost
FIDs (Budget)
FIDs (Actual)
FIDs (REVENUE or EXPENSE - No KK or GL Entries Needed)