(CD 2) Authorize Execution of Developer Funding Agreement with Victory @ Basswood, LLC in the Amount of $172,000.00 for Construction of
Drainage Improvements Along Farm to Market Road 156; Authorize Execution of an Advanced Funding Agreement with Texas Department of
Transportation in the Amount of $171,550.00 for Constructing the Drainage Improvements; and Adopt Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Developer Funding Agreement with Victory at Basswood, LLC in the Amount of $172,000.00 for construction of
drainage improvements along Farm to Market Road 156;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Developer Contribution Fund in the
amount of $172,000.00, from developer contributions, for the purpose of funding the Victory @ Basswood FM156 project (City Project No.
103115); and
3. Authorize execution of an Advanced Funding Agreement with Texas Department of Transportation in the amount of $171,550.00
for constructing the drainage improvements (City Project Number: 103115).
DISCUSSION:
In May 2019, Victory @ Basswood, Limited Liability Company (LLC) expressed an interest in upsizing planned drainage improvements along the
eastern side of Farm to Market Road 156 to serve the future needs of their development.
Victory @ Basswood, LLC evaluated the hydraulics to determine the necessary increase in the Texas Department of Transportation's planned
drainage system to support the needs of the proposed development. The drainage system project upsizes approximately 1,250 linear feet of
storm drainage system from 24 inch reinforced concrete pipe to 4 foot by 2 foot reinforced concrete box. The Texas Department of Transportation
constructed the upsize storm drainage improvement as requested to support the future development. The cost for the upsize drainage
improvements was $171,550.00.
This Mayor and Council Communiction is to authorize the execution of a Developers Agreement between Victory @ Basswood, LLC and the City
of Fort Worth for the City of Fort Worth to accept funds in the amount of $172,000.00 from Victory @ Basswood, LLC and the execution of a
funding agreement between the City of Fort Worth and Texas Department of Transportation to transfer $171,550.00 to Texas Department of
Transportation for constructing of the drainage improvements. The remaining amount of $450.00 is for city staff costs to execute these two
agreements.
The Victory @ Basswood, LLC drainage improvements along Farm to Market Road 156 is located within COUNCIL DISTRICT 2.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations, execution of the funding agreements and adoption of the
attached appropriation ordinance, funds will be deposited into the Developer Contribution Fund for the Victory @ Basswood FM156 Drainage
project and available as appropriated to support the approval of the above recommendations and execution of the funding agreement with the
Texas Department of Transportation. The Transportation and Public Works Department (and Financial Management Services) are responsible for
the collection and deposit of funds due to the City of Fort Worth. Prior to an expense being incurred, the Transportation and Public Works
Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office b� Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Monty Hall 8662