HomeMy WebLinkAbout(0067) M&C 21-0538City of Fort Worth,
Mayor and
DATE: 08/03/21
Texas
Council Communication
LOG NAME: 60SSRC118-AZB
SUBJECT
M&C FILE NUMBER: M&C 21-0538
(CD 9) Authorize Execution of an Engineering Agreement with Arredondo, Zepeda & Brunz, LLC, in the Amount of $302,590.50 for the Sanitary
Sewer Rehabilitation, Contract 118 Project and Adopt Attached Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an engineering agreement with Arredondo, Zepeda & Brunz, LLC, in the amount of $302,590.50, for Sanitary Sewer
Rehabilitation, Contract 118 project; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $537,405.00, transferred from available funds within the Water and Sewer Fund, for the purpose of funding the Sanitary
Sewer Rehabilitation, Contract 118 project (City Project No. 102789).
DISCUSSION:
This Mayor and Council Communication (M&C) is to authorize execution of an engineering agreement with Arredondo, Zepeda & Brunz, LLC, in
the amount of $302,590.50, for Sanitary Sewer Rehabilitation, Contract 118 project for the preparation of plans and specifications for sanitary
sewer and water main replacements on the following streets, alleys and easements:
Scope
Street
From
To
of
Work
150 feet East of the Stanley
Easement East of
feet
Stanley Avenue
Avenue/Glenco Terrace
Sou
South
Sewer
intersection
150 feet East and 660 feet
Easement South of
South of the Stanley
290 feet
Sewer
Stanley Avenue
Avenue/Glenco Terrace
West
intersection
Easement between
540 feet
Warner Road and
Glenco Terrace
South
Sewer
Stanley Avenue
Easement West of
600 feet
Glenco Terrace
Sewer
Warner Road
South
350 feet South and 300 feet
Easement North of
West of the Ward
450 feet
Sewer
Park Hill Drive
Parkway/Warner Road
West
intersection
300 feet South and 280 feet
Easement South of
West of the Ward
50 feet
Sewer
Ward Parkway
Parkway/Warner Road
North
intersection
Alley between
430 feet
Leuda Street and
Tennessee Avenue
East
Sewer
Terrell Avenue
100 feet East of the 6th
350 feet
Devitt Street
Avenue/Devitt Street
V1/est
Sewer
intersection
Alley between
800 feet
Willing Avenue and
Devitt Street
South
Sewer
Ryan Avenue
Easement between
410 feet
5th Avenue and
Biddison Street
South
Sewer
Baldwin Street
Easement between
Baldwin Street and
Henderson Street
Biddison Street
420 feet
South
Sewer
Baldwin Street
IBiddison Street
Ripy Street
Water
Henderson Str
IBiddison Street
Ripy Street
Water
340 feet
200 feet West of the Odessa
Benbrook
Avenue/Benbrook Boulevard
West then
Sewer
Boulevard
intersection
North 130
feet
Easement East of
Benbrook
Lamesa Place
Sewer
Odessa Avenue
Boulevard
Easement Lamesa
Place and
Odessa Avenue
500 feet
Sewer
Benbrook
East
Boulevard
Easement South of
Forest
Sandage Avenue
Sewer
Park Hill Drive
Drive
Forest Street/McPherson
100 feet
McPherson Avenue
Sewer
Street intersection
West
Alley between
140 feet
McCart Avenue and
eson Avenue
South
Sewer
Sandage Avenue
Alley between
900 feet
Forest Park
Bowie Street
North then
Sewer
Boulevard and
150 feet
McCart Avenue
West
Alley between
150 feet
McCart Avenue and
Cantley Street
North
Sewer
Sandage Avenue
Easement North of
550 feet
McCart Avenue
Sewer
Cantley Street
West
In addition to the contract amount, $234,814.50 (Water: $42,500.79; Sewer: $192,313.71) is required for project management, real property
acquisition, utility coordination, and material testing. This project will have no impact on the Water Department's operating budget when
completed. The sewer component of the project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
Appropriations for Sanitary Sewer Replacement, Contract 118, are as depicted below:
Fund
W&S Capital Projects
- Fund 56002
Existing IFAdditional
Appropriations 11
$0.00
Appropriations
$537,405.00
Project
Total*
$537,405.00
Project Total 11
$0.001
$537,405.00
$537,405.00
*Numbers rounded for presentation purposes.
Business Equity: Arredondo, Zepeda & Brunz, LLC is in compliance with the City's BIDE Ordinance by committing to 36% SBE participation on
this project. The City's SBE goal on this project is 10%..
The project is located in COUNCIL DISTRICT 9.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund, and upon approval of the above recommendation
and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the SS Rehab, Contract 118
project to support the approval of the above recommendations and execution of the engineering agreement. Prior to any expenditure being
incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office b� Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Suby Varughese 7803