Project Name: Contract 2019 WSM-C City Sec No.: 1 54517
Project No.(s): 59601-0600430-001780,59607-0700430-001780 DOE No. N/A City Proj.No.: 102170
Water/Sewer replacements and pavement rehabilitation on NW 27th St.,Azle Ave.,Columbus Ave.,Westwood Ave.,
Project Description: Sunset Ln.,and Loving Ave.
Contractor: Jackson Construction,Ltd. Change Order# Date: 1 8/19/2021
City Project Mgr. Leon Wilson-- City Inspector: I Jesse Reed
Phone Number: 817-392-2387 Phone Number: 817-392-8362
Contract Time
Dept. Water Sewer Paving Totals (Calender days)
Original Contract Amount $4,366,241.50 $144,414.50 $4,510,656.00 500
Extras to Date $6.11 $599,815.00 $264,943.50 $864,764.61 175
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $4,366,247.61 $744,229.50 $264,943.50 $5,375,420.61 675
Amount of Proposed Change Order $0.00 $14,415.00 $0.00 $14,415.00
Revised Contract Amount $4,366,247.61 $758,644.50 $264,943.50 $5,389,835.61 675
Original Funds Available for Change Orders $130,987.50 $14,441.00 $0.00 $145,428.50
Remaining Funds Available for this CO $130,981.39 $14,441.00 $145,422.39
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 19.49%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $5,638,320.00
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No.3 will provide for the following items that are necessary on the project:
•Re-lay M-161 wih DIP(w/Protecto 401)from 3+00 to 4+20 including 4 services to allow for a segment of project sewer main to run manhole
to manhole.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's company Name Contractor Name Contractor Si na re Date
Jackson Construction,Ltd. Carmen Estep 08/19/2021
Inspector Date l Project Mana er Date
-2/ �Zj
Director Water pet Date Construction Supervisor Water Dept Date
T . Aug 24,2021 �� a+1-- rr�ri�-T
a,rsmpn.,a,d.,(Ag 24,zon oam CDT)
Assistant City Attorne Date Assistant Ci Manager Date
ug 27,2021
Oil Aug 26,2021 Borghd.ff(Aog27,2o ,.
vela 1 Au 2
Council Action If Required) OFFICIAL RECORD
M&C Number F_ N/A M&C Date Approved
CITY SECRETARY
FT. WORTH, TX
F(oRT City of Fort Worth
Change Order Additions
Project Name Contract 20191NSM-C City Sec No.: 54517
Project No.(s): 59601-0600430-001780 59607-0700430-001780 DOE No. N/A City Proj.No.: 102170
Project Water/Sewer replacements and pavement rehabilitation on NW 27th St.,Azle Ave.,Columbus Ave.,Westwood Ave.,
Description Sunset Ln.,and Loving Ave.
Contractor Jackson Construction Ltd. Change Order:= Date: 8/19/2021
City Project Mgr. Leon Wilson City Inspector Fiesse Reed
ADDITIONS
ITEM =7170 DEPT Qty Unit Unit Cost Total
35 Re-lay M-161 with DIP(w/protecto 401)from 3+00 to 4+20 incl.services Sewer 1.00 LS $24,415.00 $24,415.00
Water
Sewer $24,415.00
Paving
rage i of 1 Additions Sub Total $24,415.00
FCC RT WC3 RT H City of Fort Worth
Change Order Deletions
Project Name I Contract 2019 WSM-C City Sec No.: 54517
Project No.(s): F 59601-0600430-001780,59607-0700430-001780 DOE No. N/A City Proj. No.: 1 102170
Project Description Water/Sewer replacements and pavement rehabilitation on NW 27th St.,Azle Ave.,Columbus Ave.,Westwood
Ave.,Sunset Ln and Loving Ave.
Contractor Jackson Construction, Ltd. Change Order: EE Date 8/19/2021
City Project Mgr. I Leon Wilson City Inspector: Jesse Reed
DELETIONS
ITEM DESCRIPTION DEPT Qty JUnit Unit Cost Total
30 Sewer Allowance Sewer 1.00 LS $10,000.00 $10,000.00
Water
Sewer $10,000.00
Paving
Page 1 of 1 Deletions Sub Total 1$10,000.00
NIMBE Breakdown for this Change Order
MWBE Sub Type.of Service Amount for this CO
Total $0.00
--j
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 1 of 1
i
I
i
Contract Compliance Manager
By signing Z acknowledge that t am the person responsible
)
for the monitoring and administration of this contract,including
enstuing all performance and reporting requirements. j
Signature i
I
_Leon Wilson, Jr.
Name of Employee
I
Project Manager
Title
�� P. CiUf7zGLCES LO�,o
oo nn�.� OATTEST: 10000 4
9,►0
Ronald P.Gonzales( ug 27,202112:19 CDT) ^O O �1
000
Ronald Gonzales *o o.*�d ,) '
o °
Acting City Secretary �� °°O °°0000
`� I
• I
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
i
• I