HomeMy WebLinkAboutOrdinance 24982-08-2021 ORDINANCE NO.24982-08-2021
AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE 2018 BOND
PROGRAM FUND IN THE AMOUNT OF $250,000.00 BY INCREASING
APPROPRIATIONS IN THE EAST 4TH STREET-EAST 1ST STREET ON-STREET
BIKE LANE PROJECT (CITY PROJECT NO. 102601), AND BY DECREASING
APPROPRIATIONS IN THE SIDEWALKSBICYCLE LANES PROGRAMMABLE
PROJECT(CITY PROJECT NO.PB0002)BY THE SAME AMOUNT;PROVIDING
FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE
OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-2021 in the
Budget of the City Manager, there shall also be adjusted appropriations in the 2018 Bond Program-Fund in
the amount of$250,000.00, by increasing appropriations in the East 4`h Street-East I"Street On-Street Bike
Lane project (City Project No. 102601), and by decreasing appropriations in the SidewalksBicycle Lanes
programmable project(City Project No. PB0002)by the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections, or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
��'P
Mack(Sep 1,202111:51 CDT)
Douglas W Black Ronald P. Gonzales,Acting
Sr.Assistant City Attorney
O� IFOR7-
l20
ADOPTED AND EFFECTIVE: August 10,2021
*
�LXAS
SAN
Iff
,yam,-
it
OP
41
UP
� r
r ,
eA 1ST S
} T 4TH'ST i }
�r • � r
' r
. v
.44
ta r* 1• 1 — F
_ y -
. •11
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 08/10/21 M&C FILE NUMBER: M&C 21-0549
LOG NAME: 2021 EAST 4TH/1 ST STREET ON STREET BIKE LANE APPROPRIATION
SUBJECT
(CD 4 and CD 8)Adopt Attached Appropriation Ordinance to Provide Additional Funding for the East 4th Street and East 1 st Street Improvement
Project in the Amount of$250,000.00 for the East 4th Street-East 1 st Street On-Street Bike Lane Construction Services and City Staff Costs and
Amend the Fiscal Years 2021-2025 Capital Improvement Program(2018 Bond Program)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance adjusting appropriations in the 2018 Bond Program Fund in the amount of$250,000.00 by
increasing appropriations in the East 4th Street-East 1 st Street On-Street Bike Lane project(City Project No.102601),and by decreasing
appropriations in the Sidewalks/Bicycle Lanes programmable project(City Project No. PB0002)by the same amount;and
2. Amend the Fiscal Years 2021-2025 Capital Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication(M&C)is to authorize an additional$250,000.00 for construction services and City staff
costs associated with the East 4th Street-East 1 st Street On-Street Bike Lane project(City Project No. 102601).The East 4th Street-East 1 st
Street project provides for the construction of new separated bicycle lanes,bicycle and pedestrian signalization, bicycle and pedestrian counters
and related intersection improvements along the project corridor.The additional funds will come from the 2018 Bond Program Fund.
The table below summarizes past appropriations by source,the additional funding and estimated total cost of the project at completion:
East 4th Street-East 1st Street On-Street Bike Lane(CPN102601)
Fund Existing Additional funding from PB0002 Project Funding
Funding Project Total
2014 Bond- $23,200.00
34014 $0.00 $23,200.00
2018 Bond- $701,800.00
34018 $250,000.00 $951,800.00
Total $975,000.00
Funding for this project was included in the Fiscal Years(FY)2021-2025 Capital Improvement Program in the amount of$725,000.00.Additional
funding in the amount of$250,000.00 is needed for construction services and City staff costs.The action in this M&C will amend the FY2021-2025
Capital Improvement Program as approved in connection with Ordinance 24446-09-2020.
This project is included in the 2018 Bond Program. Available resources within the General Fund will be used to provide interim financing until debt
is issued. Once debt associated with the project is sold, bond proceeds will reimburse the General Fund in accordance with the statement
expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election(Ordinance No.23209-05-2018)
and subsequent actions taken by the Mayor and Council.
The above mentioned project is located in COUNCIL DISTRICTS 4 and 8.
A Form 1295 is not required because:This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Sidewalks/Bicycle Lanes programmable project within the 2018
Bond Program Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be
available in the 2018 Bond Program Fund for the EAth St&E.1 st St. Improvemt project.Prior to an expenditure being incurred,the Transportation
and Public Works Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office: Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Monty Hall 8662