HomeMy WebLinkAbout(0004) IR 10307 - Monthly Development Activity Report June -JulyINFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 10307
PRTEot
c e�cw?.e
1@7'3
To the Mayor and Members of the City Council
August 20, 2019
Page 1 of 6
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
This Informal Report is in response to the City Council's request to receive a monthly update on
development activity within the City and the measures staff are using to improve the development
process. Staff also generates a monthly report to keep the Council informed of the volume of
development activity, process improvements and staff's performance in implementing changes
and improving the delivery of plan review and permits. This activity report consists of metrics
associated with building permits, infrastructure, stormwater development, and water development
plan review. It provides updates on continuous development process improvement efforts. The
monthly Development Activity report is attached for your use and information.
June/July 2019 Highlights
Building Permits
• In July 2019, 417 new single-family permits were issued compared to:
o 385 new single-family permits issued in June 2019, up 8%
0 319 new single-family permits issued in July 2018, up 31 %
• In July 2019, 80 new commercial permits were issued compared to:
o 79 new commercial permits issued in June 2019, up 1 %
o 52 new commercial permits issued in July 2018, up 54%
• Total commercial valuation (including remodels and additions) for July 2019 was $221
million compared to-
* $269 million in June 2019, down 18%
o $91 million in July 2018, up 143%
• In June 2019, 385 new single-family permits were issued compared to:
0 388 new single-family permits issued in May 2019, down .7%
0 288 new single-family permits issued in June 2018, up 34%
• In June 2019, 79 new commercial permits were issued compared to:
0 141 new commercial permits issued in May 2019, down 44%
0 70 new commercial permits issued in June 2018, up 13%
• Total commercial valuation (including remodels and additions) for June 2019 was $269
million compared to:
o $311 million in May 2019, down 14%
o $257 million in June 2018, up 5%
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 10307
PRTEot
c e�cw?.e
1@70L
To the Mayor and Members of the City Council August 20, 2019
Page 2 of 6
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
Customer Service
• Overall customer service satisfaction was 86% Very Positive or Somewhat Positive for
July 2019, down from 88% in June 2019.
• Chart A shows June survey responses
How would you rate the quality of your customer
service experience? ChartA
80.00% 73.20❑/❑ 71.57❑/❑
70.00% M M
60.00%
50.00%
40.00%
30.00%
20.00%
14.4311/❑ 15.13❑/❑
0. 00%
Very Positive
Somewhat
Positive
■ City of Fort Worth Customers
x June 2019 survey results
6.87% 5.15%
4.12❑/❑ 3.33% 3.09❑/❑ 3.09❑/❑
� m � fi fi fi
Neutral Somewhat Very Negative
Negative
■ SurveyMonkey Global Benchmark
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 10307
To the Mayor and Members of the City Council August 20, 2019
Page 3 of 6
i
r
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
rt rA
re�a
• Chart B shows June commercial vs residential survey responses
How would you rate the quality of your customer
service experience? ChartB
90.00%
80.00%
70.00% 68.33°/°
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0. 00%
81.08%
71 57%
Very Positive
16.67% 1I).81 °/015.13% 6.87°/°
° 2.70 /° 5.00% 5.41 °/° ° 5.00°/° 0.00% 3.09%
I° ++
Somewhat Neutral Somewhat Very Negative
Positive N egtive
■ City of Fort Worth Customers (Commercial)
■ City of Fort Worth Customers (Residential)
'June 2019 survey results SurveyMcnkey Global Benchmark
• Chart C shows July survey responses
How would you rate the quality of your customer
service experience? ChartC
90.00%
79.12°/°
80.00%
71.57%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
15.13%
10.00%
6.5911/°
6.87°I°
5.49R° /
4.40% 3.33R° 4.40% 3.09°/o
Very Positive Somewhat
Neutral
Somewhat Very Negative
Positive
Negative
■ City of Fort Worth Customers
■ SurveyMonkey
Global Benchmark
x July 2019
survey results
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 10307
To the Mayor and Members of the City Council August 20, 2019
Page 4 of 6
i
r
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
r�rA
re�a
• Chart D shows July commercial vs residential survey responses
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20 00%
1&00%
0.00%
How would you rate the quality of your customer
service experience? ChartD
80.00%
78.0011/o 71.57%
6.00%
2.50% 15.13%
7.50%
3.33%
0
7.50 /o
10.0f
4 %/
1 .500/0
2.00%:3.09%
Very Positive
Somewhat
Neutral
Somewhat
Very Negative
Positive
N egtive
x July 2019 survey results
■ City of Fort Worth Customers (Commercial)
■ City of Fort Worth Customers (Residential)
SurveyMonkey Global Benchmark
• A total of 89% of our customers surveyed thought that our Inspections team was
extremely helpful or very helpful in July 2019 compared to 88% in June 2019.
X-Team Buildina Plan Review
-
X-Team Applications
Conferences Completed
Building Permits Pending
Building Permits Issued
March
5
1
O
0
April
9
6
0
2
May
14
7
0
14
June
12
16
8
15
July
14
9
23
30
TOTAL:
1 54
39
31
61
• The above 2019 X-Team chart displays a comprehensive comparison of all X-Team
activity from March to July 2019. Though the X-Team was active in January and
February, the team did not have applications but processed regular plans. However,
the X-Team was fielding inquiries regarding the process and but began receiving
applications in March. X-Team Applications are a count of accepted and completed
application received for that month. Conferences Completed is the number of X-Team
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 10307
PRTEot
c e�cw?.e
1@7'3
To the Mayor and Members of the City Council
August 20, 2019
Page 5 of 6
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
meetings held within that month. Building Permits Pending are permits that require
corrections or are in plan review that is based off the date of the last status change.
For example, an applicant's X-Team meeting was held in May and as a result, the
plans required corrections, but the applicant submits a corrected plan set in June.
Building Permits Issued falls within the month that the permit issuance was recorded.
An applicant could have submitted an application in March, conducted the conference
in April, but the building permits were not approved until May due to addressing plan
revisions. The X-Team Applications, Conferences Completed, and Building Permits
Issued are fixed numerals because they are date based. Building Permits Issued data
is fluid and will always be shifting because it is dependent on the date of status change
for the permit.
Building Plan Review
On August 6, 2019, building code plan review times for first review were as follows:
Commercial Plans Actual 7 days Goal 7 days
Residential Plans Actual 10 days Goal 7 days
All departmental review times for first review were as follows:
Commercial Plans 14 days
Residential Plans 14 days
Infrastructure Plan Review
Infrastructure Plan Review Center (IPRC) reviewed 93% of the plans submitted within
the 14-day goal timeframe in July 2019.
• Infrastructure Plan Review Center (IPRC) reviewed 96% of the plans submitted within
the 14-day goal timeframe in June 2019.
• Staff continues to monitor the implementation of phase two of the Accela Automation
shared database.
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 10307
To the Mayor and Members of the City Council August 20, 2019
Page 6 of 6
i
r
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
r�rA
re�a
Development Process Improvements
Commercial Permitting Lean Review: The Executive Management and DAC subcommittee
members of the NCBP process improvement project team met on August 7th to discuss
the controls and implementation phase of the process improvement exercise. The
particulars of the implementation of these improvements will be laid out and the final report
will be released to the public for review.
Please contact Randle Harwood, Planning and Development Director, at 817-392-6101 or
Randle.Harwood@fortworthtexas.gov if you have any questions, concerns or comments.
David Cooke
City Manager
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
FORTWORTH.
Development
Activity Report
I NSI DE THIS EDITION
JVLT LV17
BUILDING PERMITS....................................................2-7
INFRASTRUCTURE....................................................8-11
STORMWATER........................................................12-13
WATER..............................................................................14
DEVELOPMENT PROCESS IMPROVEMENTS ........ 15
New Single Family Permits
700
600
500
400
300
200
100
0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
■ 2015
323
318
308
405
326
304
300
243
237
274
169
226
,j2016
204
151
290
379
277
435
323
262
268
281
239
341
■ 2017
268
326
594
391
475
497
412
419
317
248
567
341
■ 2018
583
492
428
479
440
288
319
567
543
545
581
454
sa2019
396
415
468
500
388
385
417
All data is in calendar year
2nd Qtr
20181
• Qtr
2019
'
New Commercial Permits
180
160
140
-
—
120
100
80
_
—
60
40
20
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
* 2015
62
56
60
105
47
84
65
74
117
86
51
76
* 2016
92
82
72
80
67
166
105
103
82
90
104
75
■ 2017
106
71
100
99
77
76
83
116
62
96
51
54
■ 2018
94
70
74
101
81
70
52
76
38
142
60
37
02019
66
142
90
65
141
79
80
All data is in calendar year
2nd
Qtr 2018•
Qtr
2019Increase
Development Activity Report
Building Permit Comparison
35000
30000
25000
20000
15000
10000
5000
0
2009 20L0 20L1 2012 2013 2014 2015 20L6 2017 2018 YTD
■ Multi -Family Permits 384 486 450 409 349 376 349 803 487 42 L 2 L0
■Residential Permits 7066 7136 7101 6927 8115 8471 6792 9522 10562 11687 6610
■ Commercial Permits 2285 2341 2404 2481 2112 2284 2179 2528 2418 2609 1502
■ Grand Total 9735 9963 9955 9817 10576 11131 11320 12853 13467 14717 8322
All data is in calendaryear
Total Commercial Valuation
$800
$700
$600
$500
o $400
$300
$200 111. . I , Ihil 11',
La�
$0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
■ 2015
$24
$158
$239
$74
$58
$157
$91
$177
$243
$371
$111
$63
■ 2016
$79
$164
$491
$167
$75
$182
$164
$185
$85
$111
$205
$101
■ 2017
$209
$727
$249
$118
$518
$198
$134
$203
$282
$144
$193
$125
■ 2018
$650
$L26
$165
$266
$158
$257
$91
$255
$62
$177
$156
$103
■ 2019
$103
$208
$230
$98
$311
$269
$22L
All data is in calendaryear
Development Activity Report
New Commercial Valuation
0
$700
$600
$500
$400
$300
$200
$100
$0
Jan
■ 2015
$10
■ 2016
$57
■2017
$131
■ 2018
$616
■ 2019
$71
All data is in
calen6
Feb
Mar
Apr
May
Jun
Jul
$86
$140
$59
$28
$97
$40
$131
$307
$99
$14
$148
$117
$702
$218
$87
$355
$152
$73
$99
$112
$223
$122
$213
$39
$193
$201
$51
$246
$234
$162
* excludes additions and remodels
Monthly Valuation Comparison
Aug
Sep
Oct
Nov
$127
$210
$329
$82
$135
$62
$80
$141
$175
$215
$114
$97
$154
$25
$113
$128
as
Dec
$30
$63
$74
$66
Current Month
Prev. Month
M-M
Year
%
DecCategory
,
New SF
32
100
5719 2969
417
385
317
52%
Permits
8%
32%
New SF
$16,971,784
$27,130,998
$970,351,567
$545,327,370
$85,491,843
$68,520,059
$58,360,845
Value
25%
46%
56%
New Comm
1
28
895
663
80
79
52
74%
Permits
1%
54%
New Comm
-$71,790,740
$123,107,070
$1,910,313,426
$1,157,722,793
$161,956,312
$233,747,052
$38,849,242
61%
Value
-31%
317%
Development Activity Report
Large Commercial Projects
July Large Commercial Projects
Address Project Name Work Desc Valuation
CENTREPORT II - BLDGS 1A, B & C, 2 A & B, 3, 4, &
14265 FAA BLVD
351 UNIT MULTIFAMILY DEVELOPMENT
$36,370,000
5A,B&C
1976 TEXAN DR
NWISD AQUATICS CENTER
NEW AQUATICS CENTER FOR NWISD
$30,000,000
NOLAN CATHOLIC HIGH SCHOOL- IDEA BUILDING
NEW ENGINEERING AND VISUAL ARTS CLASSROOMS AND
4501 BRIDGE ST
$22,000,000
AND NATATORIUM
NATATORIUM
2942 S RIVERSIDE DR
SIERRA VISTA SENIOR LIVING
NEW SENIOR LIVING DEVELOPMENT/ PHASED CONSTRUCTION
$18,000,000
PHASE II CONSTRUCTION FOR NEW 200 ROOM HOTEL AND MEETING
2333 MULE ALLEY DR
HOTEL DROVER
$17,000,000
SPACE
MATERIAL HANDLING EQUIPMENT ADDITION TO NEW DISTRIBUTION
7151 JACK NEWELL BLVD S
KNAPP INC
$9,697,187
CENTER TO INCLUDE ASRS AND CONVEYING SYSTEMS
3400 POST OAK BLVD
PLATINUM SELF STORAGE
4 STORY CONTROLLED CLIMATE SELF STORAGE FACILITY
$8,000,000
CLASSROOM RENOVATIONS WITH RESTROOMS/ HVAC/ PLUMBING
2211 MC KINLEY AVE
NORTH SIDE HIGH SCHOOL
$4,000,000
AND TECHNOLOGY UPGRADES
1753 CHAPLIN DR
CTDI PHASE II
CHANGE OF USE FROM WAREHOUSE TO OFFICE BUILDING
$3,800,714
9701 HARMON RD
USMD ALLIANCE & FORT WORTH SW
FINSIH OUT OF MEDICAL OFFICE BUILDING
$3,067,500
133 NURSERY UN
NURSERY LANE OFFICE BUILDING
NEW OFFICE BUILDING
$2,953,000
RENOVATION OF WORSHIP CENTER/ FIRE ALARMS/ SPRINKLERS
5801 NORTH FWY
NORTH FORT WORTH BAPTIST CHURCH
$2,539,200
AND REPLACE WINDOWS
REMODEL OFFICE SPACE AND CLEAN ROOM FACILITY IN EXISTING
6201 SOUTH FWY
ALCON - GDD PILOT FACILITY AND LAB ASPEX
$2,343,508
BUILDING
4865 BRIARHAVEN RD
FORT WORTH IS
FOUNDATION PERMIT ONLY FOR NEW FWISD SCHOOL
$2,200,000
REMODEL OFFICE BUILDING/ RESTROOMS AND MANUFACTURING
1301 NORTHEAST LOOP 820 FWY
XPRESSDOCS
$1,997,000
SPACE
6224 SANDSHELL DR
KEYSTONE FELLOWSHIP
NEW COMMERCIAL CHURCH
$1,900,000
9439 N BEACH ST
HERITAGE GLEN LOT
NEW OFFICE BUILDING
$1,900,000
1700 MONTGOMERY ST
BARBER OPTICAL
OPHTHALMOLOGY BUILDING (TILT WALL)
$1,650,000
INTERIOR FINISH OUT WITH HOSPITATLITY BAR; BREAKROOM AND
122 E EXCHANGE AVE, SUITE# 420
APHA
$1,500,000
CONFERENCE ROOMS
3700 HIGHWAY 114
RAISING CAINS
NEW GRADING/ PAVING/ LANDSCAPING/ UTILITIES AND BUILDING
$1,500,000
INTERIOR FINISH OUT WITH HOSPITALITY BAR/ BREAK ROOM AND
9100 NW HIGHWAY 287
MARQUIS GROUP
$1,400,000
CONFERENCE ROOMS
5000 SOUTHWEST BLVD
RIDGLEA PRESPYTERIAN CHURCH
INTERIOR AND EXTERIOR REMODEL
$1,368,596
6856 BLUE MOUND RD
BRAKES PLUS
NEW COMMERCIAL BUILDING/ AUTOMOTIVE REPAIR FACILITY
$1,000,000
Development Activity Report
CY 19 Q2 New Commercial Permits Heat Map
Development Activity Report
CY 19 Q2 New Residential Permits Heat Map
7,% I
o
�JCO O •r
amp O I
a
Legend
CY 19 Q 2 New Residential Permits
Per Sq Mile
00-5
05 - 10
=10-15
=15-20
=20 - 25
• New Res. Building Permits
Development Activity Report
PRC Overview
IPRC Overview Report 20167
Cycle Complete 52
W 20170—L.
52
2018 -1-
52
2019
31
Total Projects 157
170
148
99
Avg. Project Total Per Cycle 3.02
3.27
2.85
3.19
Total Accepted Projects 138
156
139
71
Plan Rev. & Ret w/n 14 days 93%
95%
98%
93%
*All data is in calendar year
IPRC Quarterly Details
Cycles
•- 2018
13
• 1 2019
13
Q2 2019
13
Q3 2019
5
Total Projects
35
38
45
16
Avg. Projects Total Per Cycle
2.70
2.92
3.46
3.20
Total Avg. Accepted Projects Per Cycle
2.151
2.081
2.31
2.80
Plan Rev. & Ret w/n 14 days
100 %
9 7 %
87 %
94 %
*All data is in calendar year
Development Activity Report
CFA Project Overview
$40.0
$35.0 -
$30.0
$25.0
N
0
o $20.0
$15.0
$10.0
$5.0
$0.0
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
:
■ 2017 $20.8 $20.0 $18.3 $9.2 $11.3 $12.4 $18.0 $35.2 $34.7 $24.0 $11.2 $24.0
I■2018 $5.9 $24.2 $13.8 $14.5 $9.9 $23.0 $17.0 $19.8 $16.3 $16.9 $7.1 $17.0
■ 2019 $19.4 $10.4 $25.6 $36.4 $5.7 $16.4 $23.9
39.2 M 2018 Total $185.4 M 2019 Total $ 139.8 M
All data is in calendaryear
Public Infrastructure Residential Projects
$35.0
$30.0
$25.0
$20.0
0
$15.0
$10.0
$5.0
$0 0 J i i k L
Jan Feb Mar
Apr
2017 $7.6 $14.3 $12.7
$5.8
d 2018 $4.7 $22.2 $11.8
$12.4
2019 $14.0 $7.1 $21.4
$24.4
l 2017 Total $144.7 M
All data is in calendaryear
May
Jun
Jul Aug Sep Oct
$0.9
$11.6
$17.6 $29.6 $13.2 $15.0
$3.4
$14.3
$14.6 $17.9 $11.2 $4.5
$3.7
$14.5
$21.0
2018 Total $122.2 M 201
L_
Nov
$4.4 $12.0
$1.3 $3.8
Development Activity Report
Public Infrastructure Commercial Projects
$14.0
$12.0
$10.0
$ 8.0
C
O
2 $6.0
$ 4.0
$ 2.0
$ I,,L_�
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■2017 $9.2 $3.5 $5.3 $2.1 $1.9 $0.6 $0.2 $2.8 $11.2 $1.0 $6.3 $12.0
02018 $0.9 $0.9 $0.8 $2.0 $3.1 $1.5 $0.8 $0.7 $4.7 $6.0 $4.7 $10.7
■ 2019 $3.7 $0.8 $3.3 $7.5 $0.8 $2.3 $2.9
EME06E] 2018 Ral $21.3 M
All data is in calendar year
Public Infrastructure Industrial Projects
$4.5
$4.0
$3.5
$3.0
Mq
C $2.5
0
$2.0
$1.5
$1.0
$0.5
Is
$-
Jan Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct Nov Dec
■ 2017 $4.0 $-
$-
$-
$-
$-
$-
$0.3
$-
$- $- $-
■ 2018 $- $-
$-
$-
$-
$C.1
$-
$0.2
$3.6
$- $- $-
■2019 $- $-
$-
$-
$-
$1.2
$-
2017 Total $4.3 M
2018
Total
$3.9 M
2019 Total $1.2 M
All data is in calendar year
Development Activity Report
Public Infrastructure Multi -Family Projects
$6.00
$5.00
$1.00
III
I
"J.Jw
Jan Feb
Mar
Apr May
Aug Sep Oct Nov Dec
A 2017 $- $-
$-
$1.19 $- $0.32 $0.21
$- $- $- $- $0.21
■ 2018 $0.24 $0.13
$-
$- $3.33 $5.24 $1.57
$0.05 $0.40 $- $- $2.63
■2019 $0.70 $-
$0.88
$4.40 $1.21 $0.26 $-
2017 Total $ 1.9 M
2018 Total $13.6 M
All data is in calendaryear
Public Infrastructure Institutional Projects
$8.00
$7.00
$6.00
$5.00
$4.00
$3.00
$2.00
Jan Feb
Mar
Apr
■ 2017 $- $2.25
$-
$0.17
12018 $0.06 $0.92
$1.18
$0.11
■ 2019 $0.98 $2.60
$-
$C.13
2017 Total $12.5 M
A22 data is in calendaryear
Im _
1
May
Jun Jul
Aug
$-
$- $-
$2.46
$-
$1.92 $0.10
$0.91
$-
$0.15 $-
2018 Total $9.0 M
4
Sep Oct Nov
$- $7.00 $0.51
$- $2.65 $1.13
C2019 Total $3.9 M
Dec
S0.1=
Development Activity Report
Stormwater Review Performance
StormwaterReview Performance
Avg. Review Time (days)
;
8.1
7.5
6.3
Num. Review Completed
1,693
979
130
% completed in 10 business days or less
85.1
88.4
100.0
Avg. PiSWM Review Iterations (City)
2.2
2.5
2.3
Avg. FiSWM Review Iterations (City)
3.0
3.2
3.7
Avg. IPRC Review Iterations (City)
3.1
3.2
3.1
Overall Customer Satisfaction Rating (1-5 scale)
4.6
4.5
4.0
Num. of Surveys Taken
1 32
40
6
New Stormwater Submissions
80
70
60
50
40
30
20
10 d h
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2018 41 42 54 48 76 71 42 48 47 54 66 42
2019 42 38 57 48 20 38 45
All data is in calendaryear
Development Activity Report
Stormwater Pipeline Snapshot
350
300
250
200
150
100
50
0
Feb '19
Mar'19
■ Apr'19
■ May ' 19
■ Jun ' 19
■Jul'19
Reviews in process
294
287
298
307
283
278
MI MMMP
Reviews with City
66
58
60
59
38
41
140
120
100
80
60
40
20
0
Avg. age of Reviews with City
Avg. age of Reviews with
(Days}
Developer (Days)
Feb '19
4.8
100.4
Mar'19
3.6
104.7
■ Apr'19
4.6
112.7
■ May ' 19
4.8
115.3
■ Jun ' 19
4.3
99.2
■ Jul ' 19
5.9
113.5
Development Activity Report
Newly Submitted Water/Sewer Studies
Water
Newly Submitted Water Studies
5
.,
11
5
7
11
Water Studies Approved *
7
8
5
3
8
Total Submittals & Resubmittals
13
15
9
6
19
Avg. Water Study Cycle
Sewer
Newly Submitted Sewer Studies
1.9
6
1.9
.,
9
1.8
4
2
1 8
2.4
8
Sewer Studies Approved *
9
8
6
4
8
Total Submittals & Resubmittals
18
14
11
5
16
Avg. Sewer Study Cycle
1 2
1.8
1.8
1.3
1 2
* A study can be submitted multiple times prior to the reported month before being approved
Submitted Water/Sewer Studies
WaterMar'19.,
Water Study Reviews in Process
3
5
6
10
12
Water Study Reviews in Process with City
1
0
2
4
7
Water Study Reviews in Process with Owner
2
5
4
6
5
Avg. Water Study Reviews in Process with City (Days)
1 7.1
1 4.6
1 5.0
1 9.3
1 15.6
Avg. Water Study Review in Process with Owner (Days)
Sewer
Sewer Study Reviews in Process
1.6
5
1.11
,,
6
3.0
5
11.0
9
30.1
8
Sewer Study Reviews in Process with City
0
0
2
3
5
Sewer Study Reviews in Process with Owner
5
6
3
6
3
Avg. Sewer Study Reviews in Process with City (Days)
5.7
4.5
6.5
11.3
14.5
Avg. Sewer Study Review in Process with Owner (Days)
1.7
1.0
26.0
1.0
26.5
Development Activity Report
As of Tulv 2019
The three databases were migrated into Accela on
shared database for CFAs, IPRC, inspections and April 27th and moved to production on May 1st.
it for developer -led infrastructure projects. P&D, TPW, ITS Staff continues to work with the consultant to
ensure that as issues arise they are corrected
during the warranty period.
departmental Staff and the DAC sub -committee will P&D - D.J.taff is reviewing H.B. 3167 and its full impact on
elopment uss developing guidelines for infill dev.J. Harrell, Arty Wheaton -Rodriguez &Mary Elliot Fort Worth. Currently, we are not able to provide
update Subdivision Ordinance standarc I I more details at this time.
The Executive Management and DAC
subcommittee members of the NCBP process
improvement project team met on August 7th to
e lean process evaluation for commercial P&D -Allison Cray, Rochell Thompson, D.J. Harrell, Douglas discuss the controls and implementation phase of
permits. Bailey the process improvement exercise. The
particulars of the implementation of these
improvements will be laid out and the final report
will be released to DAC for review.
ileted lean process improvement evaluation for
projects. After discussing results with
3ement, the process improvement has been
ided to include payment process for misc. projects.
The Water Department will be beginning
conversations with the City's IT Department
Dept. - Sheree Collins, Martin Phillips & Tim Schwartz regarding the feasibility of utilizing Accela for
miscellaneous projects. We will keep DAC
updated as we progress.
Development Activity Report
D.J. Harrell
Assistant Director
Planning & Development Department
817-392-8032
Dalton.Harrel I@FortWorthTexas.Gov
Building Permits
Allison Gray, Assistant Director
Planning & Development Department
Development Division
817-392-8030
AlIison.Gray@FortWorthTexas.Gov
Infrastructure
Victor Tornero, Acting Program Manager
Transportation & Public Works Department
Infrastructure Plan Review Center
817-392-7830
Victor.Tornero@FortWorthTexas.Gov
Stormwater
Tyson Thompson, Development Services Manager
Transportation & Public Works Department
Stormwater Management Division
817-392-2120
Tyson.Thompson@FortWorthTexas.Gov
Water
Chris Harder, Director
Water Department
Engineering & Regulatory Compliance Division
817-392-5020
Christopher.Harder@FortWorthTexas.Gov
Development Activity Report 16