DATE: 12/17/19 M&C FILE NUMBER: M&C 19-0411
LOG NAME: 20HMAC SURFACE OVERLAY 2019-6
SUBJECT
Authorize Execution of a Contract with Peachtree Construction, Ltd., in the Amount of $1,079,975.00 for Hot Mix Asphaltic Concrete, HMAC
(2019-6) Surface Overlay along Various Streets (COUNCIL DISTRICTS 2 and 9)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of a contract with Peachtree Construction, Ltd., in the Amount of $1,079,975.00 for
Hot Mix Asphaltic Concrete, HMAC (2019-6) Surface Overlay along various street sections identified in the attached location map (City Project
No. 102098).
DISCUSSION:
In the Fiscal Year 2019 Pay -Go Contract Street Maintenance Program, various types of street maintenance are grouped into specific contract
packages. This contract provides Pulverization and Overlay (POL) which is a process that reuses the existing pavement and base material, along
with an added treatment material, to reclaim the roadway structural integrity. After establishing the new base, new asphalt pavement will be placed
on the approximately 1.44 lane miles along various street sections identified below:
Street Name
Street Limits
Block Number
CD
Mapsco
Grand Avenue - West
Denver Avenue
Northside Drive
1200 - 1299
2
62P
Grand Avenue - West
Lagonda Avenue
Northside Drive
1201 - 1299
2
62T
West Magnolia Avenue -
5th Avenue
West Allen Avenue
1300 - 1699
9
76M
Hemphill Street - College
Page Street
Avenue
700 -999
9
76V
Elizabeth
College Avenue - South
Boulevard
Adams Street
1000 - 1095
9
76V
Construction for this project is expected to start approximately January 2020 and to be completed by approximately October 2020. Upon
completion of the project there will be no anticipated impact on the general fund operating budget.
This project was advertised for bid on September 12, 2019 and September 19, 2019 in the Fort Worth Star -Telegram. On October 10, 2019, the
following bids were received:
Bidders Amount
Peachtree Construction, Ltd. $1,079,975.00
Texas Bit - Texas Materials Group $1,109,931.15
M/WBE OFFICE — Peachtree Construction, Ltd. is in compliance with the City's BIDE Ordinance by committing to 6% MBE participation and
documenting good faith effort. Peachtree Construction, Ltd. identified several subcontracting and supplier opportunities. However, the firms
contacted in the areas identified did not respond or did not submit the lowest bids. The City's MBE goal on this project is 13%.
The City reserves the right to increase or decrease quantities of individual pay items within the contract provided that the total contract amount
remains within plus or minus 25 percent of the contract award.
This project is located in COUNCIL DISTRICTS 2 and 9.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendation and award of the contract, funds are available in the current
capital budget, as appropriated, in the General Capital Projects Fund, Project 102098. Prior to any expenditure being incurred, the Transportation
& Public Works has the responsibility to validate the availability of funds.
Submitted for City Manager's Office by. Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Monte Hall 8662