HomeMy WebLinkAboutOrdinance 25020-08-2021 ORDINANCE NO.25020-08-2021
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER&SEWER CAPITAL PROJECTS FUND IN
THE AMOUNT OF$376,495.00,TRANSFERRED FROM AVAILABLE FUNDS IN
THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING THE
CITYWIDE WASTEWATER COLLECTION SYSTEM FLOW MONITIORING
PROJECT (CITY PROJECT NO. 100854); PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-2021 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
&Sewer Capital Projects Fund in the amount of$376,495.00,transferred from available funds in the Water
and Sewer Fund,for the purpose of funding the Citywide Wastewater Collection System Flow Monitoring
project(City Project No. 100854).
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: ACTING CITY SECRETARY
Mack(Sep 3,202111:34 CDT)
g,Y
Douglas W.Black Ronald P.Gonzales
Sr.Assistant City Attorney Acting City Secretary
ED
ADOPTED AND EFFECTIVE:August 24,2021
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 08/24/21 M&C FILE NUMBER: M&C 21-0623
LOG NAME: 60CITYWIDE WW METER RENEWAL NO.2-ADS/HACH AND AMEND2 RJN FUNDI
SUBJECT
(ALL)Adopt the Attached Appropriation Ordinance in the Amount of$376,495.00 to Fund Amendment No.2 to an Engineering Agreement with
RJN Group, Inc, in the Amount Up To$96,895.00,the Second Renewal to a Professional Services Agreement with Hach Company in the Amount
of$132,000.00,and the Second Renewal to a Professional Services Agreement with ADS,LLC in the Amount of$147,600.00 for the Citywide
Wastewater Collection System Flow Metering Project
RECOMMENDATION:
It is recommended that the City Council adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water
&Sewer Capital Projects Fund in the amount of$376,495.00,transferred from available funds within the Water&Sewer Fund for the Citywide
Wastewater Collection System Flow Monitoring project(City Project No. 100854).
DISCUSSION:
On April 3,2017,a professional services agreement in the amount of$95,000.00,Mayor&Council Communication(M&C C-28142),was
administratively authorized with RJN Group,Inc.,for Citywide Wastewater Collection System Flow Metering project(City Secretary No.48947)to
prepare to monitor wastewater flows within the wastewater collection system.The agreement was subsequently revised by Amendment No. 1 in
the amount of$49,700.00 on June 18,2019(M&C C-29152)that provided for assisting staff with planning new meter sites,meter site
investigations,and oversight and review of vendor installations.
This appropriation includes funding for the RJN Amendment No.2 and renewals of the Hach Company and ADS,LLC contracts as described
below:
Amendment No.2 provides continuing professional services work that includes assisting staff with planning new meter sites,meter site
investigations,and oversight/review of vendor installations and construction services. RJN Group,Inc.proposes to provide these services for a
fee not to exceed$96,895.00. Staff considers the proposed fees to be fair and reasonable for the scope of services proposed.
On June 5,2018,(M&C P-12204),the City Council authorized a professional services agreement with Hach Company(Hach)in the amount of
$326,000.00(City Secretary Contract No.51038)and ADS,LLC(ADS)in the amount of$356,560.00(City Secretary Contract No.51017)for the
Citywide Wastewater Collection System Flow Metering project.The project is to monitor wastewater flows within the wastewater collection system
with portable flow metering devices allowing the Water Department to collect data to direct maintenance activities.Both contracts were awarded
for an initial two-year term plus three one-year renewal options.
On June 18,2019,(M&C C-29152),City Council authorized Amendment No.1 with Hach in the amount of$114,000.00 for installation of an
additional five meters on Sanitary Sewer Mains Big Fossil 54-inch M-402A and the parallel relief main,West Fork Mains including the 90-inch M-
2808 and 90-inch M-338B and the existing 48-inch M-285 and provided for a twelve(12)month monitoring period for the new meters,roughly
aligning with the second year of overall monitoring.
On June 16,2020,(M&C 20-0394),the City Council authorized funding for the first renewals in the amounts of$132,000.00 with Hach
(administratively executed September 23,2020[City Secretary No.51038-R1])and$147,600.00 with ADS(administratively authorized
September 1,2020(City Secretary No.51017-R1)).
The City of Fort Worth,ADS and Hach,now desire to exercise the 2nd renewal of their respective contracts in the same amounts as the first
renewals.
Professional services for Citywide Wastewater Collection System Flow Metering project is one component of the overall project that includes the
purchase and installation of temporary meters. This project will impact the Water Department Operating Budget due to the on-going maintenance
and calibration requirements of the installed meters. These costs will be incorporated into future Water Department Operating Budgets.
Funding for the Citywide Wastewater Collection System Flow Monitoring are as depicted in the table below:
r Existing Additional
Fund ( Project Total*
Appropriations ,Appropriations
Water Capital j
Projects Fund $115,000.00 $0.00 $115,000.00
59601
W&S Capital �� --�
�56002ts Fund $1,125,860.00 1376,495.00ij$4,502,355.00
Project Total J $1,240860.001 $376,495.00$1,617,355_00J
*Numbers rounded for presentation purposes.
Business Equity:A waiver of the goal for MBE/SBE subcontracting requirements was requested by the Purchasing Division and approved by the
MWBE Office in,accordance with the MWWBE or BDE Ordinance,because the purchase of goods or services is from sources where
subcontracting or supplier opportunities are negligible.
This project is citywide and affects ALL COUNCIL DISTRICTS.
A Form 1295 is not required because:This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current operating budget of the Water&Sewer Fund and upon approval of the
above recommendation and adoption of the attached appropriation ordinance,funds will be available in the W&S Capital Projects Fund for the
Citywide WWC Sys Flow Metering Monitoring project. Prior to any expenditure being incurred,the Water Department has the responsibility of
verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: John Kasavich 8480