HomeMy WebLinkAbout(0009) IR 20-10442 - Super Majority Minority Area Project UpdatesINFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 20-10442
PRTEA(, To the Mayor and Members of the City Council June 23, 2020
°ew?%
Page 1 of 1
SUBJECT: SUPER MAJORITY MINORITY AREA PROJECT UPDATES
The purpose of this informal report is to provide an update on the status of TPW projects
conducted in the Super Majority Minority Areas of Fort Worth. (S-MMAs). The attached document
provides greater detail of work performed between FY17 and FY20, and includes street
rehabilitation, sidewalks, streetlights, traffic signs and signals, pavement markings, and storm
water improvements. S-MMAs are generally defined as census blocks that have a minority
population of 75% or greater.
Approximately 33% of the City's transportation assets are located within S-MMAs, but more than
50% of the underperforming assets and assets in poor condition are located within these areas.
Funding needs remain great if improvements are to be significant enough to truly impact
conditions in these neighborhoods. Funding sources for project work have included over $3
million in improvements approved by the City Council in the FY20 budget, funding from the 2014
and 2018 bond programs, as well as funding for select projects from the storm water enterprise
fund.
Major areas of focus include sidewalks, where over 80% of the sidewalks in poor condition are
located in S-MMAs, and street lighting, which has a direct correlation to complaints and public
safety in communities. All projects are prioritized based on safety, need, asset condition, equity,
and access to services in coordination with the Active Transportation Plan, the Vision Zero
planning efforts underway, and our Safe Routes to School and Transit programs. Projects and
investments from the Storm Water Division often can be larger projects with broader areas of
impact. As feasibility analyses of these projects help determine which ones can be undertaken
and completed, safety, risk mitigation and equity are all considered as part of the process.
For any questions on the report, please contact William Johnson, Director of Transportation and
Public Works at 817-392-7801.
David Cooke
City Manager
Attachment
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
Super Majority Minority Area
Project Status Updates
Transportation and Public Works
William Johnson, Director
hInP iR ?n?n
Purpose
• Provide update on status of TPW projects in the S-MMA
• Street Rehabilitation and Reconstruction
• Sidewalks
• Capital
• ADA, Sidewalk Gap, Sidewalk Repair
• Safe Routes to School
• Streetlights
• Traffic Signals
• Traffic Signs
• Pavement Markings
• Stormwater Improvements
• Answer questions and receive comments
Super Majority Minority Area (S-MMA)
• The S-MMA is defined as
those census block groups
that have a 75% or higher
minority population.
• The boundary of the
S-MMA was established by
the Race and Culture Task
force created in 2017.
Super M ajorie} M inorit} Areas
3
TPW Asset Summary
Asset Type
CFW
SMMA
Percent
Pavement (Lane Miles)
71986
21872
36%
Signalized Intersections
921
275
30%
Signs
128,230
45,790
36%
Streetlights
60,594
19,673
32%
Sidewalks (Miles)
21620
780
30%
Drainage Pipes (Miles)
993.99
318.47
32%
Storm drain inlets
27,550
8,882
32%
FY20 Improvement Package Summary
Work Performed in
Percent Spent
Additional
Project
Funding
SMMA
in SMMA
Information
Pavement
Management -
$500,000
1.8 Lane Miles
63%
Slide 8
Reclamation
Sidewalks
$742,870
8,924 Linear Feet
71%
Slides 14, 15
98 Knockdowns
Street Lighting
$500,000
Repaired;
88%
Slides 18, 19
Maintenance
301 LED Conversions
Pavement Markings
$1,398,000
41 Schools*
46%
Slide 24
Street Rehabilitation
and Reconstruction
Projects
FY17 - FY20
Pay -Go FY17 to Current
2018 Bond Projects
2014 Bond Projects
City Streets
Major Streets
Super Majority Minority Areas
Fort Worth City Limit
nn:: 5.5 3 4.5
Miles E)
S-MMA Pavement Network
• The Pavement Condition Index (PCI) scores the network from 0
to 100. Poor condition streets have a score below 50.
• There are 7,986 Lane Miles Citywide and 681 in poor condition.
• The S-MMA has 2,872 or 36% of the City's total Lane Miles.
• Of the 2,872 lane miles, 342 or 12% are in poor condition.
50% of the City's poor condition roadways are in the Super MMA
FY20 Improvement Package:
Pavement Reclamation
• Allocation: $500,000
• Locations:
• Park Vista Circle from Kroger Dr to Kroger Dr — Complete
• North Commerce Street from NE 21St to NE 23rd — Complete*
• Seth Barwise Street from longhorn In to WJ Boaz - June 2020
Scheduled Completion*
• 2.8 Total Lane Miles
• Pavement reclamation work performed in-house
100
90
80
70
60
W
J
50
W
Q 40
J
NEI
wk
C
■ INSIDE S-MMA
■ OUTSIDE S-MMA
LANE MILES REHABILITATED OR RECONSTRUCTED BY FISCAL YEAR
FY 2017
69.2
76.14
FY 2018
42.2
92.1
FY 2019
35.17
70.29
NJ
FY 2020
14.64
23.83
4
DOLLARS SPENT FOR ROADWAY RECONSTRUCTION AND REHABILITATION
$45, 000, 000.00
$40, 000, 000.00
$35,000,000.00
$30,000,000.00
$25,000,000.00
$20,000,000.00
$15, 000, 000.00
$10, 000, 000.00
$5,000,000.00
INSIDE S-MMA
OUTSIDE S-MMA
FY 2017
$30,853,782.41
$38,459,027.42
FY 2018
$25,708,355.36
$26,112,531.51
FY 2019
$17,690,278.18
$18,455,949.94
FY 2020
$7,536,804.25
$11,027,391.90
S-MMA Sidewalk Network
• The Active Transportation
finding missing sidewalks,
sidewalk needs.
Plan analyzed the City's sidewalk network
poor condition sidewalks and high priority
• The S-MMA has 58% of the City's total 3,740 miles of missing
sidewalk
• 140 miles of high priority missing sidewalks are in the MMA, the cost
of construction is estimated at $135M
The S-MMA has 50°0 of the existing City sidewalks but 81 °o of the
poor condition sidewalks
Capital Sidewalk Projects
FY17 —
FY20
Sidewalk Construction
Major Streets
City Streets
Super Majority
Minority Areas
0 0.5 1 2 3 4
Miles
12
30,000
25,000
20,000
10,000
5,000
U
• sd
CAPITAL SIDEWALK PROJECTS CONSTRUCTED IN S-MMA
FY 2017
18,729
24,339
Other 3,586 23,972
FY 2019
5,728
FY 2020
6,602
FY 20 Improvement Package: ADA, Sidewalk Gap, and
Sidewalk Repair
• Allocation: $742,870
• FY 2020 is the first year that Transportation Management received funding to
address sidewalk gaps and ADA needs.
The Active Transportation Plan was used to identify sidewalk gap projects for
implementation.
10,129 linear feet of sidewalks are planned for implementation in FY 2020
Approximately 88% sidewalks are planned in SMMA's.
1,324 linear feet of sidewalks constructed to date
Approximately 74% of sidewalks constructed to date are in SMMA's
FY 20 Improvement
Package: ADA, Sidewalk
Gap, and Sidewalk Repair
Continued
- 11324 LF of sidewalks gaps constructed
(74% in SMMA's)
- 11119 LF of sidewalks repaired/replaced
( 86% in SMMA's)
0 Now Sidewalk - Complete
New Sidewalk - Planned
9 Sidewalk Repairs
— Major stroets
City Streets
ikiiiiiiiiiiiiiiii Super Majority
Minority Areas
4 1 2 4 B 8
M Iles
15
Safe Routes to School (SRTS) Sidewalk Projects
• Seven SRTS projects are being implemented in the 2018 Bond, and their
scope includes sidewalks, pavement markings, and pedestrian signage.
• The total cost for implementation is $12M.
• Six out of the seven schools are located in SMMA's.
• Approximately 65,069 linear feet of sidewalks will be constructed.
• Approximately 59,324 linear feet of sidewalks will be constructed in
SM MA's.
• All SRTS projects are at 90% design and construction is anticipated to begin
in early 2021.
Safe Routes to Schoo
(SRTS) Sidewalk
Projects
2018 Bond
School Campus
Major Streets
City Streets
' Super Majority
Minority Areas
0 1 2 4 6 8
Miles
'iU 1
WA Turner Q
Dmentary Soh of
Diarnond.Hill�
Elernenti ry Schaal
M Lphillips� e
:lementary School—
E M Daggett
Elementary School
L F
Elementary School
CC:ry
oss
. I Elemen#School
0'
Streetlights Projects
69,000 lights citywide
Program/Project Work inside Work outside Total Citywide % of Work in
SMMA SMMA SMMAs
Maintenance
(August 2018 to date)
4,489
15,134
19,623
23%
FY18 PayGo
(completed projects)
9
66
75
12%
FY19 PayGo
(completed projects)
6
2
8
0
75/0
FY20 PayGo
(planned projects,
54
139
193
28%
FY20 Improvement Package)"
Stop Six/Amanda
320
320
100%
LED Pilot
3,087
368
31455
89%
Ash Crescent
93
-
93
100%
Northside
536
-
536
100%
Rosemont (planned)
40
10
50
80%
2018 Bond (planned)
21235
31689
51924
38%
Total
8,634
15,719
24,353
35%
Streetlight PayGo
Maintenance
Projects
FY18 — FY20
0 PayGo Streetlight Maint.
City Streets
Major Streets
Super Majority
Minority Areas
Q , 2 4 6 8
Miles
LED Conversion
Project
2018 Bond
O Streetlights e
City Streets
Major Streets
QLED Conversion
Target Areas
Super Majority
Minority Areas
0 0.5 1 2 3 4
Miles
Traffic Signal Projects
892 signals citywide
Program/Project
Work inside
Work outside
Total Citywide
% of Work in SMMAs
SMMA
SMMA
Maintenance
(June 2019* to date)
1,104
31321
41425
25%
Signal Retiming
(Oct 2017 to date)
181
308
489
37%
Signal Upgrades -
Completed
42
86
128
33%
(Oct 2017 to date)
Signal Upgrades —
In Progress/ Planned
10
19
29
34%
Tota 1
52
105
157
33
Traffic Signals:
Retiming, Upgrades and
New Construction
FY17 — FY 20
Q Retiming Program
Q Upgrades & Modifications
(� New Signal
Major Streets
City Streets
Super Majority
Minority Areas
0 1.5 3 5 9
Miles
22
Traffic Sign Projects
130,000 total signs citywide
Program/Project
Work inside
SM MA
Work outside
SM MA
Total Citywide % of Work in SMMAs
Maintenance — Signs
Repaired/Replaced
11732
41545
61277 28%
(August 2018* to date)
FY20 PayGo Vision Zero —
Signs Repaired/Replaced
1,710
21295
41005 43%
(planned)
Total
31442
61840
10,282 33%
Pavement Markings Projects
8.7 million linear feet of pavement markings citywide
Program/Project
Work inside
SMMA
Work outside
SMMA
Total Citywide
% of Work in
SMMAs
FY18 PayGo -Linear Feet
94,812
1291513
2241325
42%
FY18 PayGo - Crosswalks
2,922
129
31051
96%
FY19 PayGo
284,001
2511064
5351065
53%
FY19 PayGo - Crosswalks
4,330
11233
51563
78%
FY20 PayGo —Linear Feet o
(in progress/ planned)* 578,146 470,714 1,048,860 55/
FY20 PayGo - Vision 19 846 58 108 77 954 25%
Zero crosswalks (planned)* '
Total 984,057 910,761 1,894,818 52% 1
*FY20 Improvement Package Funding
Stormwater Completed
Projects
FY 17 - FY 20
Weather Stations/ High Water Warning System
Completed Stormwater Projects
Major Streets
Minor Streets
Super Majority
Minority Areas
0 2 4 S
Miles
990009000
,000,000
710001000
90009000
4-1
590009000
490009000
0
90009000
,000,000
110001000
I
t rmwarter Projects Investment FY1 -FY2
FY 2017
FY 2018
FY 2019
FY 0
■ Inside SM MA 5555,955
195679325
1155 , 4
6059795
■ Outside SMMA 517211518
613301787
813561742
516771247
26
Stormwater Work in SMMAs
• Capital improvement benefits
• 173 properties with mitigated flood risk
• 151200 average daily vehicle trips on roads with mitigated flood risk
• City Floodrisk Areas (CFRA) policy
• Floodprone areas not reflected on FEMA floodplain maps
• 13 CFRAs intersect SMMAs
• 378 acres of SMMAs in CFRAs
• New communication and regulation in CFRAs provide higher protection from
floodrisk
• 2 new weather stations in SMMAs for enhanced ability to provide
early flood warning notifications
Questions: