HomeMy WebLinkAbout(0007) IR 20-10512 - Monthly Development ReportINFORMAL REPORT TO CITY COUNCIL MEMBERS No. 20-10512
To the Mayor and Members of the City Council November 17, 2020
Page 1 of 5
SUBJECT: Monthly Development Activity Report
#z rn
Y@7'a
This Informal Report is in response to the City Council's request to receive a monthly update on
development activity within the City and the measures staff are using to improve the development
process. Staff also generates a monthly report to keep the Council informed of the volume of
development activity, process improvements and staff's performance in implementing changes and
improving the delivery of plan review and permits. This activity report consists of metrics associated
with building permits, infrastructure, stormwater development, and water development plan review.
It provides updates on continuous development process improvement efforts. The monthly
Development Activity report is attached for your use and information.
October 2020 Highlights
Building Permits
• Total commercial valuation (including remodels and additions) for October 2020 was $153
million compared to:
o $613 million in September 2020, down 75%
o $421 million in October 2019, down 64%
• In October 2020, 53 new commercial permits were issued compared to:
0 84 new commercial permits issued in September 2020, down 37%
0 100 new commercial permits issued in October 2019, down 47%
• In October 2020, 44 new commercial permit applications were received.
• In October 2020, 662 new single-family permits were issued compared to:
0 732 new single-family permits issued in September 2020, down 10%
0 326 new single-family permits issued in October 2019, up 103%
• In October 2020, 784 new single-family residential applications were received.
• In October 2020, 715 new commercial and new single-family permits were issued.
Development Support Services
• The Overall Customer Service Satisfaction was 74.36% for either Very Positive or Somewhat
Positive for October 2020, slightly up from 73.63% in September 2020.
• Chart A shows survey responses for October 2020.
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
To the Mayor and Members of the City Council
pRTE}A,I
rn SUBJECT: Monthly Development Activity Report
r
1ev3
How would you rate the quality of your customer service experience?
Chart A
MOMS 72.84%
70.00%62.82%
60.00%
50.00%
40.00%
30.00%
20.00%
13.78%
11.54%
8.97%
11.54%
10.00%
.6■
3.11%
,
5
3.55%
0.00%
m
Sim
Very Positive
Somewhat Positive
Neutral
Somewhat Negative
Very Negative
*October 2020 survey results
■City of Fort Worth Customers
■SurveyMonkey Global Benchmark
No. 20-10512
November 17, 2020
Page 2 of 5
• Chart B shows commercial vs residential survey responses for October 2020.
Overall, how would you rate the quality of your customer service experience?
Chart B
sa.0crA
72.84%
7a.00%
68.09%
6a.0CrA
4.84%
5a.0crA
4a.0CrA
3a.0crA
2a.0a%
13.78%
12.90%
ia.OXA
10. 64%'
a.00%
Very Positive
Somewhat Positive
* October 2020 survey results
9.68% 12.90%
8.51% .71% 10.64% 9.66%
. � ,' 3.11% 2.13%, 3.55%
Neutral Somewhat Negttve Very Negative
City of Fart Worth Customers (Commercial)
■ City of Fort Worth Customers (Residential)
SurveyMonkey Global Benchmark
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 20-10512
To the Mayor and Members of the City Council November 17, 2020
Page 3 of 5
SUBJECT: Monthly Development Activity Report
r Yn
rer�
• In October 2020, a total of 100% of 4 customers surveyed thought that our Inspections team
was Extremely Helpful or Very Helpful, steady with 100% of 5 customers surveyed reported in
September 2020.
X-Team Buildina Plan Review
•�1 -
X-Team Applications
Conferences Completed
Building Permits Issued
January
10
11
17
February
11
10
24
March
6
1
27
April
3
0
2
May
9
0
10
June
1
0
13
July
7
0
9
August
8
2
8
September
11
1
26
October
16
1
17
YTD 2020 TOTAL:
82
26
153
CY 2019 TOTAL:
88
70 1
106
G ROSS:
170
96 1
259
• As of October 31st, there are 50 pending X-Team building permits.
Building Plan Review
• On October 31st, 2020 review times were as follows:
Days to first review Commercial Plans Actual 5 Days Goal 7 Days
Days to first review Residential Plans Actual 1 Days Goal 7 Days
• All departmental reviews time to first comment were as follows:
Commercial Plans 6 Days
Residential Plans 5 Days
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 20-10512
To the Mayor and Members of the City Council November 17, 2020
Page 4 of 5
SUBJECT: Monthly Development Activity Report
r Yn
rer�
New Commercial Building Permits
BPI Project
May 2017 - Apr. 2018
Annual Report
CY 2019
Annual Report
CY 2020 thru Oct.
Current Month
Oct-20
Total Time: from opened date to issued permit
96 days
64 days
114 days
152 days
City Time
63 days
31 days
33 days
28 days
Customer Time
33 days
33 days
81 days
124 days
Average Time to First Review
38 days
15 days
13 days
10 days
Total Number of Permits
60
76
79
7
New
Residential
Building Permits
Annual Report
CY 2019
Annual Report
CY 2020 thru Oct.
Current Month
Oct-20
Total Time: from opened date to issued permit
31 days
34 days
31 days
City Time
19 days
13 days
11 days
Customer Time
12 days
22 days
20 days
Average Time to First Review
11 days
8 days
7 days
Total Number of Permits
394
415
33
*Data is reported in average business days and excludes the miscellaneous permits that are included in the building
plan review section above. Miscellaneous permits are as follows: pools, spas, retaining walls, foundations,
temporary construction, and fences. Additionally, the data excluded X-Team applications, walk-in permits and third -
party review permits.
CY 2020 thru October 2020:
• City time for new commercial building permits issued thru the month of October 2020 was 33
days compared to:
0 63 days in the BPI Project, down 14 days
0 31 days in the CY 2019 Annual Report, up 2 days
• Average time to complete first review for new commercial building permits issued thru the
month of October 2020 was 13 days compared to-
* 38 days in the BPI Project, down 25 days
0 15 days in the CY 2019 Annual Report, down 2 days
• City time for new residential building permits during thru the month of October 2020 was 13
days compared to 19 days in the CY 2019 Annual Report, down 6 days.
• Average time to complete first review for new residential building permits thru the month of
October 2020 was 8 days compared to 11 days in the CY 2019 Annual Report, down 3 days.
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 20-10512
To the Mayor and Members of the City Council November 17, 2020
Page 5 of 5
SUBJECT: Monthly Development Activity Report
#Z rn
Y@7'a
Plat/ Infrastructure Plan Review
• Infrastructure Plan Review Center (IPRC) reviewed 100% of the plans submitted within the
14-day goal timeframe in the month of October 2020.
• In October 2020,13 CFA applications were received, compared to 15 in September 2020,
down 13%
• In October 2020, 54 Plat applications were received, compared to 46 in September 2020, up
17%
Resaonse to COVID-19 Pandemic
• All required applications/permits continue to be available online. Staff continues to work on
streamlining and adding permit processes online.
• Development Services continues to hold virtual Board and Commission meetings. This will
continue to provide a high level of transparency for City business while encouraging public
participation and engagement.
• Development Services is working to launch an interactive web tool, Open Counter, to help the
public navigate zoning districts and building permit processes. There will be three modules:
zoning, residential, and commercial. Each module will walk the citizen/developer through a
series of interactive questioning that will lead to a printed permit guide for commercial or
residential projects.
o Staff completed testing of the Zoning Module on October 29t", and is coordinating Zoning
Module testing with members of DAC. November 20th is the projected date to approve
the Zoning Module. The Residential and Commercial Modules implementation has
started and is still on schedule to be conducted in December and January. The software
is still scheduled to "Go Live" in February 2021.
Please contact D.J. Harrell, Development Services Director, at 817-392-8032 or
Dalton. Harrell(o)_fortworthtexas.gov if you have any questions, concerns or comments.
David Cooke
City Manager
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
FORTWORTH.
Development
Activity Report
I NSI DE THIS EDITION
%.J `I I V 0 E R LVIr. V
BUILDING PERMITS....................................................2-7
INFRASTRUCTURE....................................................8-11
STORMWATER........................................................12-13
WATER..............................................................................14
DEVELOPMENT PROCESS IMPROVEMENTS ........ 15
New Single Family Permits
800
700
600
—
500
400
I
300
I
200
100
Ilid
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
De(
2016
204
151
290
379
277
435
323
262
268
281
239
341
■ 2017
268
326
594
391
475
497
412
419
317
248
567
341
■ 2018
583
492
428
479
440
288
319
567
543
545
581
452.
■ 2019
396
415
468
500
388
385
417
504
491
326
328
55�
■ 2020
575
526
612
504
505
482
612
626
732
662
All data is in calendar year
New Commercial Permits
250
200
150
1
100
50 ILI'
0 - —
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
12016 92 82 72 80 67 166 105 103 82 90 104 75
■ 2017 106 71 100 99 77 76 83 116 62 96 51 54
■ 2018 94 70 74 101 81 70 52 76 38 142 60 37
■ 2019 66 142 90 65 141 79 80 45 84 100 135 181
■ 2020 126 120 139 128 69 221 81 84 84 53
All data is in calendar year
Development Activity Report
Building Permit Comparison
16000
14,717 14,573
14000 12,853 13,467 13,632
12000 10,576 11,131 11,320
9,963
10000 9,955 9,817
8000
6000
4000
2000
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Multi -Family Permits 486 450 409 349 376 349 803 487 421 451 517
■ Residential Permits 7136 7101 6927 8115 8471 8792 9522 10562 11687 11523 11560
■ Commercial Permits 2341 2404 2481 2112 2284 2179 2528 2418 2609 2599 1555
All data is in calendar year
Total Commercial Valuation
$800
$700 —
$600 —
$500 —
o $400
$300
$200
$100
$0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
■ 2016 $79
$164
$491
$167
$75
$182
$164
$185
$85
$111
$205
■ 2017 $209
$727
$249
$118
$518
$198
$134
$203
$282
$144
$193
■ 2018 $650
$126
$165
$266
$158
$257
$91
$255
$62
$177
$156
■ 2019 $103
$208
$230
$98
$311
$269
$221
$121
$392
$421
$588
■ 2020 $214
$440
$262
$258
$119
$220
$188
$130
$613
$153
All data is in calendar year
L 3rd
Million'
Million
F,
r C!
■
Dec
$101
$125
$103
$242
Development Activity Report
New Commercial Permits Valuation
$800
$700
$600
N $500
0
$400
$300 r
$200
$10
$010 hi 10
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov De(
■ 2016 $57 $131 $307 $99 $14 $148 $117 $135 $62 $80 $141 $63
■ 2017 $131 $702 $218 $87 $355 $152 $73 $175 $215 $114 $97 $74
■ 2018 $616 $99 $112 $223 $122 $213 $39 $154 $25 $113 $128 $66
■ 2019 $2 $193 $201 $51 $246 $234 $162 $40 $339 $383 $477 $141
■ 2020 $167 $282 $204 $155 $36 $134 $147 $81 $514 $102
All data is in calendar year
* excludes additions and remodels
Permit Valuation Comparison
Category
Current Month
Prev. Month
Difference Prev.
M-M Year
Difference Y-Y
%
Pill.
Dec..,,
New SF
-70
336
5175 5,836
662
732
326
113 %
Permits
-10%
103 %
New SF
-$9,891,114
$56,162,224
$937,688,297
$1,024,606,041
$118,616,644
$128,507,758
$62,454,420
Value
-8%
90 %
109%
New Comm
-31
-47
1208
1105
53
84
100
91 %
Permits
-37%
-47%
New Comm
-$411,895,781
-$280,916,602
$2,537,698,790
$1,823,002,508
$102,039,261
$513,935,042
$382,955,863
Value
-80%
-73%
72%
Development Activity Report
Large Commercial Projects
October Large Commercial Projects
Address Council District Project Name Work Description
Valuation
NEW COMMERCIAL APARTMENT COMPLEX, BUILDING 1 & 2, 387 UNITS, FIRE AREA A-D,
5232 TRINITY RIVER TRL
19
STILLWATER CRYSTAL SPRINGS
COURTYARD, CLUBHOUSE, FITNESS CENTER, LEASING OFFICE, PARKING GARAGE &
$44,253,817
SKYLOUNGE
4500 W ILMA LN
5
VILLAGE CREEK WATER RECLAMATION FACILITY
NEW CONSTRUCTION, GRIT REMOVAL IMPROVEMENTS, GRIT SEPARATION UNITS, GRIT
$25,000,000
SLURRY CONVEYANCE
OUTDOOR ENTERGY STORAGE YARD, 38 ENCLOSURES TO HOUSE BATTERIES FOR
9400 ASPHALT DR
7
CHISOLM GRID
GRID, UG ELECTRICAL, TWO TRANSFORMERS & TWO SW ITCHGEARS, OUTDOOR
$17,004,740
ELECTRICAL SUBSTATION, WITH UG ELECTRICAL, FOUNDATIONS, STRUCTURAL STEEL,
HV AND MV EQUIPMENT
3000 S NORWOOD DR
5
BELL ROC EXPANSION
ADDITION TO EXISTING INDUSTRIAL PARK NEW BAYS & RAMPS, CONCRETE, SEWER,
$10,100,000
ELECTRICAL
5100 W ILLIE ST
5
YOUNG MEN'S LEADERSHIP ACADEMY
REMODEL OF ENTIRE CLASSROOM BUILDING
$10,000,000
7650 WILL ROGERS BLVD
8
BEN E. KEITH COMPANY
RENOVATIONS TO DRY COOLER AND FREEZER STORAGE, ROOF REMODEL, FIRE
$6,600,000
PROTECTIONS
6401 NORTHWEST LOOP 820 FWY
7
HAMPTON INN & SUITES
NEW CONSTRUCTION OF A 5 STORY 85 UNIT HOTEL
$6,000,000
6201 SOUTH FWY
8
ALCON FWN MANUFACTURING
REMODEL OF PRODUCTION AREA IN EXISTING BUILDING
$5,333,021
1591 RIP JOHNSON DR
7
RICHARDSON BASS BUILDING AT WILL ROGERS
ROOF REPLACEMENT
$2,700,000
MEMORIAL CENTER
13501 PARK VISTA BLVD
7
MCKESSON PARK VISTA- BIOLOGICS
INTERIOR RENOVATIONS TO EXISTING SUITE ON THE FIRST FLOOR, NEW CEILINGS,
$2,500,000
LIGHTING, PARTITIIONS, DOORS, FLOORING & MEP MODIFICATIONS
8600 CURRENCY DR
2
GODDARD SCHOL
NEW SCHOOL CONSTRUCTION FOR EARLY CHILDHOOD DEVELOPMENT
$1,900,000
4625 SAINT AMAND CIR
3
KEEHAN DERMATOLOGY CLINIC
NEW CONSTRUCTION OF A MEDICAL OFFICE BUILDING
$1,792,980
2401 PETTY PL
7
AMERCARE ROYAL
REMODEL ADDING 3,392 BAYS OF PALLET RACKING AND 49 BAYS OF DEEP PUSH BACK
$1 480,175
RACKS FOR WAREHOUSE STORAGE.
464 BAILEY AVE
7
TEXAS BANK AND TRUST
TENANT FINISH OUT, NEW WALLS, NEW PLUMBING, ELECTRICAL, DUCTWORK AND
$1,300,000
FINISHES
6454 BRENTWOOD STAIR RD
4
FORT WORTH COMMUNITY CREDIT UNION
REMODEL OF EXISTING CREDIT UNION
$1,131,852
4541 W BAILEY BOSWELL RD
7
BURGER KING
NEW CONSTRUCTION OF A FAST FOOD RESTAURANT
$1,100,000
Development Activity Report
CY 20 Q3 New Commercial Permits Heat Map
Legend
CY 20 43 New Commercial Permits Per Sq Mile
OO-1
=1-2
=2-3
=3-4
aCFW CITY LIMIT
0 New Comm Building Permits Jul 20 - Sep 20
Development Activity Report
2
CY 20 Q3 New Residential Permits Heat Map
.±
o
Ly
`;
• r
n q*
n . •
F
•
•
•
I'
r Legend
P I CY 20 Q3 New Residential Permits Per Sq Mile
• 0-5
5-10
10-15
�15-20
�20-25
O CFW CITY LIMIT
. New Res Building Permits Jul 20 - Sep 20
Development Activity Report
INFRASTRUCTURE jj
PRC Overview
Cycle Complete
52
52
52
44
Total Projects
170
148
181
132
Avg. Project Total Per Cycle
3.27
2.85
3.48
3.00
Total Accepted Projects
156
139
143
1 108
Plan Rev. & Ret w/n 14 days
95%
98%
94%
1 99%
*All data is in calendar year
IPRC Quarterly Details
Cycles
13
14
13
14
4
Total Projects
41
36
35
50
6
Avg. Projects Total Per Cycle
3.15
2.57
2.70
3.57
1.50
Total Avg. Accepted Projects Per Cycle
3.10
2.20
1.54
2.43
3.00
Plan Rev. & Ret w/n 14 days
100%
1 100%
100%
94%
100%
*All data is in calendar year
Development Activity Report
CFA Project Overview
$40.0
$35.0
$30.0
$25.0
G
° $20.0
$15.0
$10.0 {
$5.0
$0.0-
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
2017 $20.8 $20.0 $18.3 $9.2 $11.3 $12.4 $18.0 $35.2 $34.7 $24.0 $11.2 $24.0
■2018 $5.9 $24.2 $13.8 $14.5 $9.9 $23.0 $17.0 $19.8 $16.3 $16.9 $7.1 $17.0
■2019 $19.4 $10.4 $25.6 $36.4 $5.7 $18.4 $23.9 $35.0 $8.3 $14.4 $3.8 $1.5
■2020 $8.0 $6.0 $17.4 $6.0 $12.0 $9.0 $16.1 $15.0 $12.6 $13.5
2018 Total $185.4 M
All data is in calendar year
Public Infrastructure Residential Projects
$35.0
$30.0
$25.0
$20.0
0
0
$15.0
$10.0
$5.0
$0.0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
2017
$7.6
$14.3
$12.7
$5.8
$0.9
$11.6
$17.6
$29.6
■2018
$4.7
$22.2
$11.8
$12.4
$3.4
$14.3
$14.6
$17.9
■2019
$14.0
$7.1
$21.4
$24.4
$3.7
$14.5
$21.0
$23.4
■2020
$7.1
$0.9
$7.6
$5.3
$7.5
$6.7
$13.8
$13.0
2018 Total $122.2 M
2019 Total $150.5 M
-J
All data is in calendar year
r
Sep
Oct
Nov
Dec
$13.2
$15.0
$4.4
$12.0
$11.2
$4.5
$1.3
$3.8
$4.5
$12.9
$2.7
$0.9
$8.8
$7.3
20 Total $78.0 M
Development Activity Report
Public Infrastructure Commercial Projects
$14.0
$12.0
$10.0
$8.0
0
$6.0
$4.0
$2.0
L61
$
Jan
Feb
Mar
2017
$9.2
$3.5
$5.3
■ 2018
$0.9
$0.9
$0.8
■ 2019
$3.7
$0.8
$3.3
2020
$0.1
$0.5
$3.3
2018 Total $36.8 M
All data is in calendar year
Apr
$2.1
$2.0
$7.5
$0.31
May
Jun
Jul
Aug
Sep
Oct
Nov
$1.9
$0.6
$0.2
$2.8
$11.2
$1.0
$6.3
$3.1
$1.5
$0.8
$0.7
$4.7
$6.0
$4.7
$0.8
$2.3
$2.9
$4.0
$3.2
$1.5
$0.1
$1.0
$2.3
$0.8
$1.4
$0.1
$0.1
Public Infrastructure Industrial Projects
Dec
$12.0
$10.7
$6.0
$5.0
$4.0
G
$3.0
$2.0
$1.0
$
Jan Feb Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
2017 $4.0 $- $-
$-
$-
$-
$-
$0.3
$-
$-
$-
$-
■ 2018 $- $- $-
$-
$-
$0.1
$-
$0.2
$3.6
$-
$-
$-
■2019 $- $- $-
$-
$-
$1.2
$-
$-
$0.5
$-
$0.9
$0.5
■2020 $0.4 $3.6 $3.4
$-
$3.5
$-
$1.6
$-
$3.3
$5.4
2018 Total $3.9 M
All data is in calendar year
Development Activity Report
Public Infrastructure Multi -Family Projects
$8.0
$7.0
$6.0
$5.0
N
0
° $4.0
$3.0
$2.0
Jan
Feb
Mar Apr
May
Jun
Jul
Aug
■ 2017
$-
$-
$- $1.19
$-
$0.32
$0.21
$-
2018
$0.24
$0.13
$- $-
$3.33
$5.24
$1.57
$0.05
■ 2019
$0.70
$-
$0.88 $4.40
$1.21
$0.26
$-
$7.18
■ 2020
$0.11
$0.93
$0.70 $0.39
$-
$-
$-
$0.46
2.01
All data is in calendar year
Public Infrastructure Institutional Projects
Sep
Oct
Nov
Dec
$-
$-
$-
$0.21
$0.40
$-
$-
$2.63
$0.28
$0.78
2020 Total
$8.00
$7.00
$6.00
$5.00
N
0
$4.00
$3.00
$2.00
Jan Feb
Mar
Apr
May Jun Jul
Aug
Sep
Oct
Nov
Dec
■ 2017
$- $2.25
$-
$0.17
$- $- $-
$2.46
$-
$7.00
$0.51
$0.12
02018
$0.06 $0.92
$1.18
$0.11
$- $1.92 $0.10
$0.91
$-
$2.65
$1.13
$-
■ 2019
$0.98 $2.60
$-
$0.13
$- $0.15 $-
$0.43
$-
$-
$-
$-
■ 2020
$0.60 $-
$2.40
$-
$- $- $-
$0.24
$0.06
$-
2018 Total $Irm
2019
2020 Total
All data is in calendar year
Development Activity Report
Stormwater Review Performance
Stormwater- - Performance
Avg. Review Time (days)
7.1
6.8
7.2
-. 20
6.2
Oct 20
6.4
Num. Review Completed
1,567
838
110
93
110
% completed in 10 business days or less
92.0
97.7
97.2
98.9
97.2
Avg. PiSWM Review Iterations (City)
2.6
3.3
0.0
0.0
0.0
Avg. FiSWM Review Iterations (City)
3.1
4.5
4.7
4.0
3.0
Avg. IPRC Review Iterations (City)
3.2
2.4
1.9
2.6
2.8
Avg. SWMP Review Iterations (City)*
1.6
2.5
3.7
7.0
3.6
Avg. Drainage Studies Iterations (City)*
0.0
2.1
2.6
2.5
2.9
Overall Customer Satisfaction Rating (1-5 scale)
4.6
4.7
4.0
5.0
5.0
Num. of Surveys Taken
64
33
2
2
4
* New item tracked as a result of HB 3167
New Stormwater Submissions
IN
70 -
60
50
40 +�
30
20
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2018 41 42 54 48 76 71 42 48 47 54 65 42
■ 2019 42 38 57 48 20 38 45 43 28 11 21 40
■ 2020 47 36 34 41 35 34 37 29 30 33
All data is in calendar year
Development Activity Report
Stormwater Pipeline Snapshot
250
200
150
100
50
Reviews in process Reviews with City
May '20 223 28
■ June '20 117 36
July '20 127 45
Aug '20 107 27
■ Sep' '20 102 23
■ Oct' '20 108 26
250
200
150
100
50
■��
0
Avg. age of Reviews with City (Days)
Avg. age of Reviews with Developer
(Days)
May'20
4
209
-qJune'20
3
45
July'20
4
45
Aug'20
4
49
■ Sep' '20
3
57
Oct' '20
5
24
Development Activity Report
Newly Submitted Water/Sewer Studies
Water-
Newly Submitted Water Studies
6
10
8
-.
6
9
Water Studies Approved *
9
5
9
8
7
Total Submittals & Resubmittals
18
14
25
21
19
Avg. Water Study Cycle
Sewer
Newly Submitted Sewer Studies
2
9
2.8
9
2.8
10
2.6
-.
6
2.7
•
9
Sewer Studies Approved *
11
5
10
14
3
Total Submittals & Resubmittals
23
18
31
39
9
Avg. Sewer Study Cycle
2.1
3.6
3.1
2.8
3
* A study can be submitted multiple times prior to the reported month before being approved
Submitted Water/Sewer Studies
Water
Water Study Reviews in Process
-0
10
16
A.0
15
-.0
14
16
Water Study Reviews in Process with City
4
6
6
2
6
Water Study Reviews in Process with Owner
6
10
9
12
10
Avg. Water Study Reviews in Process with City (Days)
6.7
6.7
7.5
6.7
9.2
Avg. Water Study Review in Process with Owner (Days)
Sewer
Sewer Study Reviews in Process
12
-
12
5.4
17
4.3
17
2.3
-.
10
14.3
•
16
Sewer Study Reviews in Process with City
3
4
7
2
8
Sewer Study Reviews in Process with Owner
9
13
10
8
8
Avg. Sewer Study Reviews in Process with City (Days)
5.9
5.9
7.8
6.7
6.6
Avg. Sewer Study Review in Process with Owner (Days)
16.5
3.4
4.2
6.4
3.1
Development Activity Report
As of October 2020
n=.k
Department/Staff Assigned
Status
Staff worked with consultant on the consolidated
reports and an updated report was provided to
Create shared database for CFAs, IPRC, inspections
staff for review. Staff received updated HB
and closeout for developer -led infrastructure projects.
Development Services, TPW, ITS
Consolidated report from consultant on
10/14/2020, and staff provided response to
consultant on 10/29/2020.
Open Counter (I in progress)
Department/Staff Assigned
Ir
Status
Coordinating Zoning Module testing with
members of DAC. Completed staff testing of the
Zoning Module on October 29th. November
Implement the Open Counter software that will improve
Development Services, ITS, Water, Fire, TPW,
20th is the projected date to approve the Zoning
the developer permitting experience and process in
Neighborhood Services
Module. The Residential and Commercial
the City
Modules implementation has started and is still
on schedule to be conducted in December and
January. The software is still scheduled to "Go
inprogress)
Live" in February 2021.
Task
Permitting Review (1
Department/Staff Assigned
Status
Several videos are uploaded on the
Complete lean process evaluation for commercial
Development Services webpage and can be
building permits.
DS - Allison Gray, Rochell Thompson, D.J. Harrell
found here
https://fortworthtexas.gov/developmentservice
Development
Process Tree (1 in progress)
s/permits/how-to-apply-online/
Task
Department/Staff Assi ned
Status
To update and publish the process trees for each of our
alliance partners that have had changes in their
respective process as a result of H.B. 3167. This will
Staff is updating the process trees on the new
allow for citizens to have a clear, transparent and
Development Services, Water, and TPW
web page and continuing to update as needed
predictable review process for each of the review
with any new process changes.
submittal process.
Parks
and Recreation Department (I in progress)
Department/Staff Assigned
To streamline and improve the PARD
Quarterly meeting is anticipated to be held go
Dedication/Conversion Policy by improving process
P&D, PARD & TPW
over the improvements made since DAC
flows and decreasing total processing time.
Tarrant
County Interlocal Agreement in
presentation.
Task
(1 progress)
Department/Staff Assigned
Status
Tarrant County expressed that the organization
Update the 2008 Inter Local Agreement with Tarrant
would rather wait until they update their
County regarding plat approval jurisdiction in the City
subdivision ordinance before resuming
of fort Worth's ETJ.
Development Services, TPW, and Legal
discussions about updating the ILA and interim
ETJ regulations. City staff is working on a
comprehensive document that lays out
guidelines for developing in the ETJ.
School
Task
Site Development Guide(l in progress)
Department/Staff Assigned
Status
To provide ISDs, Charter Schools, and Private Schools
with a guide to developing a school site in the City of
Fort Worth. The guide will offer directions and insight
Development Services, Fire, Water, TPW, and
Project lead completed the second draft and has
for new school constructions, expansions/additions,
Neighborhood Services
submitted to staff for review and revisions.
and remodels.
Water
& Sewer Department (I in
Task
progress)
Department/Staff Assigned
status
Completed lean process improvement evaluation for
Configuration requirements has been delivered
misc. projects. After discussing results with
management, the process improvement has been
Water Dept. - Lawrence Hamilton and Homer
to ITS. ITS will begin to develop design and
expanded to include payment process for misc.
Garza
implementation configuration schedule.
projects.
Development Activity Report
15
D.J. Harrell, Director
Development Services Department
817-392-8032
Dalton.Harrell@fortworthtexas.gov
Building Permits
Allison Gray, Assistant Director
Development Services Department
Development Building Division
817-392-8030
Allison.Gray@fortworthtexas.gov
Infrastructure
Victor Tornero, IPRC Engineering Manager
Development Services Department
Infrastructure Development Division
817-392-7830
Victor.Tornero@fortworthtexas.gov
Stormwater
Tyson Thompson, Assistant Director
Development Services Department
Infrastructure Development Division
817-392-2120
Tyson.Thompson@fortworthtexas.gov
Water
Chris Harder, Director
Water Department
817-392-5020
Christopher.Harder@fortworthtexas.gov
Development Activity Report 16