HomeMy WebLinkAbout(0047) CP 101459 - Rock Creek Brewer Blvd CO#1 Executed.pdfDEVELOPER -AWARDED -PROJECT CHANGE ORDER PROJECT NAME: Rock Creek Ranch/Tarleton State University Brewer Boulevard CHANGE CONTRACT: CS#50944 Pavin , Drainage, and Street Lights) ORDER No: CFA # 2017-102 CITY PARTICIPATION: I YES CITY PROJECT # 101459 DOE # N/A WATER PROJECT # N/A 1 SEWER PROJECT # N/A FILE # K-2588 INSPECTOR: Julius McLaudn Phone No: 817-392-8306 PROJECT MANAGER: Debbie Willhelm, PE Phone No: 817-392-2481 CONTRACT UNIT: CS#50944 WATER SEWER PAVING DRAINAGE STREET LIGHTS B SIGNS CONTRACT Developer Cost City Co., Developer Cost City Cost Developer Cost yYM SUB CTR. LP Developer Cost TSU (Walton) City Cost PID Cost Developer Cost yyM SUB CTR, LP Developer Cost TSU (Walton) City Cost PID Cost Developer Cost yyM SUB CTR, LP Developer Co TSU (Walsl ton) City Cost PID Cost DAYS ORIGINAL CONTRACT $0.00 $0.00 $0.00 $0.00 $288,905.02 $220,566.88 $1,725,805.60 $1,161,728.50 $93,051.56 $123,156.07 $830,344.51 $648,663.86 $34,039.35 $30,794.97 $228,658.16 $162,197.52 240 EXTRAS TO DATE CREDITS TO DATE CONTRACT TO DATE $0.00 $0.00 $0.00 $0.00 $288,905.02 $220,566.88 $1,725,805.60 $1,161,728.50 $93,051.56 $123,156.07 $830,344.51 $648,663.86 $34,039.35 $30,794.97 $228,658.16 $162,197.52 240 AMOUNT OF PROP. CHANGE ORDER $0.00 $0.00 $0.00 $0.00 $4,249.2 $12,116.73 $72,115.40 $63,818.99 $0.00 $0.00 $0.00 $0.00 $1,449.64 $0.00 $2,830.36 $0.00 11 REVISED CONTRACT AMOUNT $0.00 $0.00 $0.00 1 $0.00 $293,154.21 $232,683.61 $1,797,921.00 $1,225,547A9 $93,051.58 $123,156.07 $830,344.51 $648,663.86 $35,488.99 $30,794.97 $231,488.52 $162,197.52 251 TOTAL REVISED CONTRACT AMOUNT PER UNIT $0.00 $0.00 $3,549,306.32 $1,695,216.00 $459,970.00 REVISED COST SHARE Dev. Cost: $808,329.41 Ity Cost: $2,859,754.03 PID Cost: $2,036,408.87 TOTAL REVISED CONTRACT $5,704,492.32 You are directed to make the followina chances in the contract documents: PAY ITEM# CITY BID ITEM# QUANTITY UNIT PAVING ITEMS ITEM DESCRIPTION UNIT PRICE TOTAL 3211.04 (1) 7 348.402 Ton Hydrated Lime Material $160.00 $55.744.32 3305.0111 (2) 79 -21 EA Valve Box Adjustment also includes hydrants) $100.00 ($2.100.00) 3305.0101 (2) 82 8 EA Fire Hydrant Stem Extension $2,750.00 $22.000.00 3305.0114 (2) 83 14 EA Manhole Adjustment, Major w/Cover 60"Vault $3,404.00 $47.656.00 3305.0114 (2) 84 8 EA Manhole Adjustment, Maor w/Cover 72"Vautt $3,625.00 $29.000.00 SUBTOTAL PAVING $152.300.32 PAY ITEM# CITY BID ITEM# QUANTITY UNIT STREET LIGHT ITEMS ITEM DESCRIPTION UNIT PRICE TOTAL 2605.3015 (3) 34 58 LF 2- CONDT PVC SCH 80 T $8.00 S464.00 3441.3302 (3) 37 1 EA Rdwy Ilium Foundation TY 3, 5, 6, and 8 $1,250.00 $1.250.00 3441.3342 (3) 38 1 EA Rdwy Ilium TY 19 Pole Powder Coat Black $2,450.00 $2,450.00 3441.3404 (3) 39 58 LF 2-2-2-4 Qyadplex Alum Else Conductor $2.00 $116.00 SUBTOTAL STREET LIGHTS $4.280.00 Participation Percentages: Developer City PID NOTES: (1) Quantity Inside PID = 269.992, Quantity Outside PID = 78.410 Total Change Order: $156,580.32 Inside PID 8.67% 45.665% 45.665% (2) Quantity Inside PID Non-PID 33.87% 66.13% 0% (3) Quantity Outside PID REASONS FOR CHANGE ORDER 1. Revised lime treated sucrade quantities based on lime series performed by aeotech. Lime % increased from 7% to 8%. 2. Deleted 21 minor valve box adiustments and revised to separate bid items for fire hvdrants, 60" vaults, and 72" vaults adjustments. 3. Chanced light pole #14 from a since pole with two light fixtures to two light poles with single light fixtures to avoid water line conflict in median. 4. An additional 11 calendar days have been requested for this chance order. PID AND TPW DEPARTMENT PARTICIPATION FUNDS INVOLVED IN THIS CONTRACT Developer's Share increased by: $17.815.57 City Participation increased by: $74.945.76 PID Participation increased by., $63.818.99 RECOMMENDED: APPROVED: (Consulting Engineer) (Developer) Goodwin and Marshall, Inc. Walton Development 8 Management 7X LLC Ada e� ,Ae By: Ma By.',on Name: Matt Baacke, PE Name: Title: Project Engineer Title: APPROVAL RECOMMENDED: APPROVED: (CFW - Sponsoring Department) (CFW - Assistant City Manager) c ('T0,1�0, r,00�I0, By: sr okeiM+vs ovs� SwSI/r By., Steve Cooke Name: Name: Director, Transportation and Public Works Title: Title: RECOMMENDED: (CFW -Contract Compliance Manager) M&C Number: M&C Date Approved: .¢�st By: o�s� Debbie J. Wi Rhelm Name: Title: Project Manager APPROVED: (Contractor) Jackson Construction, Ltd. BY: c,.ar z�i Name: Carmen Estep Title: Office Manager APPROVED AS TO FORM AND LEGALITY: (CFW - Assistant City Attorney) Ri 1asx2 d M,r a k BY:m-MI 111i Name: Richard A. McCracken Title: Sr. Assistant City Attorney " Contract Compliance Manager (Project Manager): By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. There are City Funds associated with this Contract