Loading...
HomeMy WebLinkAbout(0125) M&C 20-0512City of Fort Worth, Mayor and Texas Council Communication DATE: 08/04/20 M&C FILE NUMBER: M&C 20-0512 LOG NAME: 60CROWLEY RELIEF M-325 PART 3 PER ACRE SUBJECT Adopt Ordinance to Establish the Sewer Per Acre Charge in the Amount of $4,076.89 Per Acre for the Crowley Relief Interceptor M-325 for Village Creek Basin Part 3 and to Establish the Basin Boundaries, Pursuant to Chapter 35, Water and Sewer, Article III, Division 3, Sections 35-81 through 35-86 of the City Code (ETJ and COUNCIL DISTRICT 6) RECOMMENDATION: It is recommended that the City Council adopt the attached ordinance to establish $4,076.89 per acre for the Crowley Relief Interceptor M-325 for Village Creek Basin Part 3 and to establish the basin boundaries for this per acre charge in accordance with Chapter 35, Water and Sewer, Article III, Division 3, Section 35-81 through 35-86 of the City Code. (City Project No. 100276) DISCUSSION: This Mayor and Council Communication is to authorize the establishment of a per acre charge for a 21-inch sewer main collector at the Crowley Relief Interceptor M-325 for Village Creek Basin Part 3 project (Crowley SS Relief Line - City Project No. 100276, City Secretary Contract No. 51954). This project will provide additional capacity to convey anticipated flows from proposed development within the Upper Village Creek Drainage Basin. The wastewater collection main is 8,355 linear feet of 21-inch diameter wastewater pipe which will serve a calculated basin area of 986.99 acres. The establishment of this per acre charge will allow the City to recapture costs associated with the capital investment in wastewater collection mains. The qualified costs used to establish this per acre charge is based on the Amended Agreement to City Secretary Contract No. 49305 for Wastewater Service between the City of Crowley and the City of Fort Worth. The qualified costs are outlined below: Design $581,864.31 Easements $85,592.81 Construction Cost Part 3 (21-inch) $3,356,390.03 Total $4,023,847.15 The net acreage of the calculated sewer basin is 986.99 acres, which is depicted on the drainage map attached to this communication. By dividing the costs above by the number of acres in the sewer basin, the per -acre charge for the Crowley Relief Interceptor M-325 for Village Creek Basin Part 3 is $4,076.89 per acre. There is no restriction to the time period for the reimbursement to the Fort Worth Water Department. A per acre charge shall be assessed on each acre within the calculated sewer basin area served by a sewer approach main or by a sewer main constructed under a city initiated project, without exclusion or reduction. The wastewater collection main is located in the City's Extraterritorial Jurisdiction and Council District 6. A Form 1295 is not required because: This M&C does not request approval of a contract with a business entity. FISCAL INFORMATION / CERTIFICATION: The Director of Finance certifies that upon approval of the above recommendation and establishment of the charge, funds will be deposited into the Water & Sewer Fund. The Water Department (and Financial Management Services) is responsible for the collection and deposit of funds due to the City. Submitted for City Manager's Office by: Dana Burghdoff 8018 Originating Business Unit Head: Chris Harder 5020 Additional Information Contact: Wade Goodman 7139 Matt Kusnir 8219