HomeMy WebLinkAboutContract 43132-A1 CITY SECRETARY
AMENDMENT No.1 CONTRACT NO.
TO CITY SECRETARY CONTRACT No. 43132
WHEREAS, the City of Fort worth (CITY) and Jacob's Engineering
Group, Inc. , (ENGINEER) made and entered into City Secretary Contract No.
43132, (the CONTRACT) which was administratively authorized on the 18th
day of_ April, 2012 in the amount of $ 49, 981 .00; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Security Improvements at Alliance Airport, CPM 1978; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee .
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated October 31 , 2012, a
copy of which is attached hereto and incorporated herein. The cost to
City for the additional design services to be performed by Engineer
totals $39,837. 00.
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $89,818. 00.
3 .
All other provisions of the Contract, which are not expressly
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012 OFFICIAL RECORD
Page 1af2
CITY SECRETARY
PO4 :2` IN FT WORTH, TX
� ��
amended herein, shall remain in full force and effect .
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth ENGINEER
Jacobs Engineering Group, -Tnr.
Fernando Costa Scott Bussell
Assistant City Manager Operations Manager
DATE: j DATE: - ?0. j
APPROVAL RECOMMENDED:
--
?
Z7,
Bill Welstead
Director, Aviation Department
APPROVED AS TO FORM AND LEGALITY: M&C:
Date :
Douglas W. Black
Assistant City Attorney
4P Coll
000 %0
ATTEST: a 0�fi
Q�
V'O Ck
�q a
Mar J. �� ►
City Secretary " '
City of Fart Worth
Professional Services Agreement Amendment Template
P gCl Official Release 8/1/2012 ������
Pa e 2 of EOFFICIAL Y SECRETARY
I FT
FTS WORTH,TX
JACOBS i r i E1t itl`slf oel,,
F u 0 Worth,TX 7G 102 USA
1 817 735,5000 Fax 1817 159,14E
October 31, 2012
Tim Ward
President
Alliance Air Services
2221 Alliance Blvd. Suite 100
Fort Worth,Texas 76127-4300
R6: Request for Additional Design Funds for the AOA Security Fence and Vehicular Gate Replacements
and CCTV Upgrades
This is a request for your consideration for additional funds for the referenced project.A few scope
changes as described below have resulted in Jacobs incurring costs beyond the original contract value. In
addition Jacobs has been requested to coordinate with contractors, revise the construction documents
and re-bid the documents.
The additional amount requested for the design and rebid is$39,837.The amount requested for design
is$27,678.The effort to coordinate with Contractors,revise the construction documents and re-bid the
documents is$12,159. Both of these items are described in detail below.
On January 23,2012 a scope and estimate of construction cost was provided to Jacobs,via Dallas
Security Systems(DSS),This estimate of construction cost of$323,003 included both fence and security
improvements. Based on this information and a subsequent site visit,Jacobs'developed a scope and fee
for design and construction phase services.
Jacobs'original design fee of$28,362 for these services was approximately 8.8%of anticipated
construction costs. Percent of construction cost is one of the quality checks utilized in fee development
and 8.8%is within the industry standard for a project with a construction estimate under$500,000.
Bidding and Construction Phase Services constituted the remaining$21,619 of the contract.
During the design phase,a few revisions to the current scope were incorporated into the construction
documents including:
A change to all pan-tilt-Zoom(PT2)cameras
+ The addition of a PTZ camera at the FBO Building
0 Adding bid alternates to the plans and specifications
Additional factors that resulted in an increased effort by Jacobs:
Scope was based on vendors providing Information to Jacobs for the development of
performance specifications, actual effort required full specification development.
• Scope was based on Dallas Security Systems providing CADD drawings,which could easily be
incorporated into the construction documents.DSS only provided product catalog sheets and
approximate costs of materials.
The need to develop a traffic lane closure for the work along Westport Parkway was not
anticipated.
Upon the completion of the design phase services,Jacobs prepared an initial estimate for construction
of$599,994,an 86%increase relative to the original estimate.As outlined below, both fencing and
electrical items are nearly double the cost provided by DSS.As described previously, percent of
construction provides a range that a typical engineering design fee should fall within. Based on the
actual engineer's estimate of$599,994,Jacobs original design fee of$28,362 is 4.7%of construction
which is not within industry standard for this site of a project.The revised fee of$56,040 is 9.3%of
construction cost,more in line with industry standards.
DESCRIPTION DSS ESTIMATE JACOBS ESTIMATE DIFFERENCE
Pre Construction Items $151,940 $15,940
Taxes $721,922 -$22,923
Fencing Items $149,741 $285,800 $136,059
Electrical Security 150 340 $298,25 4 147 914
Total $323,003 $599,994 $276,991
A secondary item for consideration is Jacobs has been requested to coordinate with the contractors and
evaluate potential unknowns in the design documents that may be causing inflated prices to cover
contractor risk. It is anticipated that this effort will result in construction document changes.After these
revisions have been made to the construction documents,Jacobs will re-bid the construction
documents.
The effort to coordinate with contractors, revise the construction documents and re-bid the documents
is anticipated to be$12,159 as described in detail below:
$3,80S for contractor coordination
$3,805 for construction document revisions
4 549 for Bid Phase Services
$12,159
DESCRIPTION ORIGINAL FEE ADDITIONAL FEE TOTAL FEE
Design $28,771 $27,678 $55,449
Bid Phase $4,549 $0 $40,549
Rebid $0 $120159 $12,159
Construction Phase 16 661 so 16 661
Total $49,981 $39.837 $89,818
In summary,Jacobs is requesting additional funding in the amount of$39,837; $27,678 for the
additional design effort and$12,159 for the requested effort to coordinate with Contractors, revise the
construction documents and re-bid the documents.
Thank you for your consideration of this request.
Sincerely,
Je Peterman, P.E.