HomeMy WebLinkAbout(0012) M&C 21-0226City of Fort Worth,
Mayor and
DATE: 04/06/21
Texas
Council Communication
LOG NAME: 17PID11 MIDYEARFY21
SUBJECT
M&C FILE NUMBER: M&C 21-0226
(CD 2) Adopt Attached Resolution Amending the Fiscal Year 2020-2021 Budget and Five -Year Service Plan for Public Improvement District 11 -
Stockyards and Adopt Attached Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached resolution approving the revised Fiscal Year 2020-2021 Budget and Five -Year Service Plan for Public Improvement
District 11 — Stockyards to reflect amendments associated with a mid -year review; and
2. Adopt the attached appropriation ordinance increasing receipts and appropriations in the Fort Worth Public Improvement District 11 —
Stockyards Fund in the amount of $49,000.00 in Fiscal Year 2020-2021, from available unreserved fund balance.
DISCUSSION:
The City of Fort Worth Department of Economic Development administers the City's Public Improvement Districts (PIDs) in accordance with
Chapter 372 of the Texas Local Government Code. The City's Operating PID Policy outlines the need to proactively work with the PID managers to
oversee the services being provided by the PIDs and their associated financial positions. Staff, along with the contracted PID management
companies, have conducted mid -year reviews of the Public Improvement District 11 - Stockyards (Stockyards PID) Annual Budget (Budget) and
recommend the following adjustments.
The City contracts with Stockyards Preservation Foundation of Fort Worth, Inc. (Foundation) to manage the Stockyards PID. The Foundation has
identified the need to increase the Budget by $49,000.00 to cover expenses associated with Litter Abatement & Maintenance and Capital
Improvements for improvements made to light poles and signage.
Revenue adjustments:
Line Items
Previously
Recommended
Amended
to be
Approved FY21
Mid -Year
FY21 Budget
Adjusted
Budget Item
Adjustment
Item
PID
Assessments
$193,097.00
$0.00
$193,097.00
Use of Fund
Balance
$60,361.00
$49,000.00
$109,361.00
Totals
$253,458.00
$49,000.00
$302,458.00
Expenditure adjustments:
Previously
Recommended
Amended
Line Items to
be Adjusted
Approved FY21
Mid -Year
FY21 Budget
Budget Item
Adjustment
Item
Litter
Abatement &
$36,000.00
$49,000.00
$85,000.00
Maintenance
Public Events
1 $70,638.001
($15,000.00)
$55,638.00
Capital
Improvements
$10,000.00
$15,000.00
$25,000.00
Totals
$116,638.001
$49,000.00
$165,638.00
Staff supports the Foundation's recommended mid -year budget adjustments. All other previously approved line items not mentioned above remain
the same. Upon approval of the above recommendations, the total budgeted expenses for Fiscal Year 2020-2021 will be $302,458.00. This mid-
year budget adjustment will decrease the unaudited, unassigned fund balance by a total of $49,000.00. The revised Budget and Five -Year Service
Plan will take effect upon approval by City Council. The City and Stockyards Preservation of Fort Worth, Inc. will amend the existing management
contract to reflect the mid -year adjustment (City Secretary Contract No. 54863). The proposed changes to the Stockyards PID Budget will
maintain compliance with reserve requirements.
The Stockyards PID is located in COUNCIL DISTRICT 2.
A Form 1295 is not required because: This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds
will be available in the current operating budget, as appropriated, in the FWPID #11 - Stockyards Fund. Prior to any expenditure being incurred,
the Economic Development Department has the responsibility to validate the availability of funds.
Submitted for City Manager's Office by. Jay Chapa 5804
Originating Business Unit Head: Robert Sturns 2663
Additional Information Contact: Crystal Hinojosa 7808