HomeMy WebLinkAboutContract 52902-CO1 CSC No.52902-COI
FORT WORTH City of Fort Worth
��_ Change Order Request
Project Name:[_Churchill Road Water and Sanitary Sewer Improvements City Sec No.: 52902
Project No.(s):l 56017-0600430/0700430-001780 1 DOE No. N/A City Proj.No.: 100888
Installation of Water and Sanitary Sewer Improvements on Churchill Rd between White Settlement Rd and River Oaks
Project Description: Blvd.
Contractor: Flow-Line Construction, Inc. Change Order# 0 Date: 8/23/2021
City Project Mgr.1 Lawrence Hamilton City Inspector: I Carmen Drake
Phone Number: 817-392-2626 Phone Number: 817-392-8347
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $6,522,745.00 $1,614,210.00 $8,136,955.00 720
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $6,522,745.00 $1,614,210.00 $8,136,955.00 720
Amount of Proposed Change Order $0.00 $22,705.70 $22,705.70 047
Revised Contract Amount $6,522,745.00 $1,636,915.70 $8,159,660.70 767
Original Funds Available for Change Orders $130,455.00 $48,426.00 $178,881.00
Remaining Funds Available for this CO $130,455.00 $48,426.00 $178,881.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.28%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $10,171,193.75
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No. 1 provides for the following:
• The installation of special levee backfill material as required by the USACOE at a levee crossing on the project.
• 6-inch sewer pipe for the reroute of sewer mains away from the levee crossing.
• The relocation of a sewer manhole from the levee crossing as required by the USACOE.
• Additional storm water pollution prevention.
• The reroute of a 4-inch service at 800 Churchill Road from two lots.
Staff recommends the addition of 47 calendar days for the change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
In full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name = 11 conA Signature Dat
Flow-Line Construction, Inc. Eduardo Hernandez Q Z
Ins eot r, Date Project Manager Date
Nrector Water D4tr, Date Construction supervisor Water Dept) Date
Aug31,2021 „� i�,�vio�i.�nto,L -77,9
Chnso herH r DT
Assistant City Attorney Date Assistant City Manager Date
Sep 3,2021 a s 9 �f Sep 3 2021
Council Action If Required
M&C Number NIA M&C Date Approved FNTA
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
Ft>n r Wt>wr H City of Fort Worth
Change Order Additions
Project Name Churchill Road Water and Sanitary Sewer Improvements City Sec No.: 1 52902
Project No.(s): 56017-0600430/0700430-001780 DOE No. N/A City Proj.No.: 100888
Project Installation of Water and Sanitary Sewer Improvements on Churchill Rd between White Settlement Rd and River Oaks
Description Blvd.
Contractor Flow-Line Construction,Inc. Change Order:= Date: 8/23/2021
City Project Mgr. Lawrence Hamilton City Inspector Carmen Drake
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
2 8"Sewer Pipe PVC(SDR 26) Sewer 23.00 LF $65.00 $1,495.00
5 Construction Staking Sewer 0.08690 LS $40,000.00 $3,476.00
9 Remove 4'Sewer Manhole Sewer 1.00 EA $1,000.00 $1,000.00
11 SWPPP>=1 ACRE Sewer 0.06 LS $50,000.00 $3,050.00
22 Trench Safety Sewer 23.00 LF $2.00 $46.00
28 4'Extra Depth Manhole Sewer 2.00 VF $215.00 $430.00
39 6"Sewer Pipe PVC(SDR 26)w/fittings and connections to existing Sewer 77.00 LF $117.83 $9,072.91
40 6"Sanitary Sewer Two-Way Cleanout Sewer 2.00 EA $3,173.67 $6,347.34
41 4'Drop Manhole Relocation(out of levee) Sewer 1.00 EA $8,000.00 $8,000.00
42 Grout/Abandon Existing 6"PVC Sewer pipe(in levee) Sewer 5.00 CY J$300.00 $1,500.00
43 Import and Install Special Levee Backfill,Haul of Surplus Dirt(289 CY) Sewer 289.00 CY J$142.63 $41,220.07
44 Re-Route of 4"Sewer Service at 800 Churchill Rd. Sewer 1.00 LS $3,118.38 $3,118.38
Water
Sewer $78,705.70
Page 1 of i Additions Sub Total $78,705.70
FOR-T WORTH City of Fort Worth
Change Order Deletions
Project Name Churchill Road Water and Sanitary Sewer Improvements City Sec No.: 52902
Project No.(s): 56017-0600430/0700430-001780 DOE No. ERKI City Proj.No.: 100888
Project Description Installation of Water and Sanitary Sewer Improvements on Churchill Rd between White Settlement Rd and River
Oaks Blvd,
Contractor Flow-Line Construction, Inc. Change Order: M Date 8/23/2021
City Project Mgr. Lawrence Hamilton City Inspector: Carmen Drake
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
33 Sewer Construction Allowance Sewer 0.80 LS $70,000.00 $56,000.00
Water
Sewer $56,000.00
Page 1 of 1 IDeletions Sub Total 1$56,000.00
MIWBE Breakdown for this Change Order
Total
Previous Change Orders
Co MOM . , ._ AMOAT
Total = = $Q 00
Page 1 of 1
Contract Compliance Manager
By signing I acknowledge that I am the poison responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
J /V of y-fi 1�?�_{'� j 011u t,c L _
Signature
�G 0 cam( {�11J
Name of Employee
1'WAtSIONdI by,41Nf(r
Title
ATTEST: I�F°F°0000.0 �
° °
=
dvg°°°°°°°°°°° od
Ronald Gonzales P� b
Acting City Secretary aa�nEXAso4p