HomeMy WebLinkAboutContract 55143-CO1 CSC No.55143-COl
FORT WORTH. City of Fort Worth
Change Order Request
Project Name 2021 CONCRETE RESTORATION CONTRACT 2 City Sec# 55143
Client Project#(s) 102861
Project Description The Repair and Reconstruction of Failed Concrete Pavement at Various Locations in the City.
Contractor OMEGA CONTRACTING INC Change Order# 1 Date 8/31/2021
City Project Mgr. Iretomiwa Otuyelu City Inspector Steve Johnson
Dept. TPW Contract Time
Totals (CD)
Original Contract Amount $849,817.75 $849,817.75 180
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $849,817.75 $849,817.75 180
Amount of Proposed Change Order $85,218.75 $85,218.75 40
Revised Contract Amount $935,036.50 $935,036.50 220
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $85,218.75 $85,218.75
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 10.03%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,062,272.19
JUSTIFICATION(REASONS)FOR CHANGE ORDER
This Change Order is to add the amount of$85,218.75 and 40 calendar days to the Construction Contract#55143.
During the course of construction at the intersection of Saratoga Downs Way&Grandstand Way,unsuitable soil was exposed requiring the need to excavate and remediate
the subgrade to a depth of 3 1/2 feet.The creation of new items is needed to address the changed conditions and the level of effort required to stabilize the soil as stated in
the geotechnical report.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
JOEntracWs Company Namell rontractor(Name)0 MContract Signature Date
OMEGA CONTRACTING INC Daniel Garcia =7Sep 13,2021
Inspector/Inspection Super v Date Project and Contract Compliance Manager Date
Sep 13,2021 �s Sep 14,2021
Date ject Officer Date
Sep 14,2021 'h Sep 14,2021
rss�santor(Dept) Date Director,Contracting Department(Dept) Date
L P,r— Sep 15,2021 .W,*-9J— Sep 15,2021
Assistant City Attorney Date ity Manager Date
Sep 15,2021 Sep 15,2021
Council Action(if required)
M&C Number M&C Date Approved 0
ATTEST:?
Ronald P.Gonzales,Acting City Secretary �bF FORT t14a
o°°00000°oo
O�O���
P=°
Ao
o d OFFICIAL RECORD
add a� 000 oo
CITY SECRETARY
nRanaa° FT.WORTH,TX
FoaT WORTH City of Fort Worth
Change Order Additions
Project Name 2021 CONCRETE RESTORATION CONTRACT 2 City Sec# 55143
Client Project# 102861
Contractor OMEGA CONTRACTING INC PM Iretomiwa Otuyelu Inspector Steve Johnson
Change Order Submittal# �9� Date 8/31/2021
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
EXCAVATE&HAUL MATERIALS TO ADDITONAL DEPTH( . -DEPTH) TPW CY
BACKFILL USING ONLY FLEXBASE TO ADDITONAL DEPTH TPW 615.000000ou CY
3 3"STONE AT BOTTOM OF BASE CUT TPW 700.00000000 SY $15.56
TPW $85,218.75
Sub Total Additions $85,218.75
Change Order Additions Page 2 of 5
FORTAVORTH City of Fort Worth
—Y� Change Order Deletions
Project Name 2021 CONCRETE RESTORATION CONTRACT 2 City Sec# 55143
Client Project# 102861
Contractor OMEGA CONTRACTING INC PM Iretomiwa Otuyelu Inspector Steve Johnson
Change Order Submittal# Date 831/2021
ULLLIIUNS
ty Unit Unit Cost I ota
TPW $0.00
Sub Total Deletions
Change Order Deletions Page 3 of 5
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
From: Otuyelu,Iretomiwa S
To: Munoz,Filoaonio
Cc: Daniel Garcia
Subject: CPN102861 Change Order
Date: Thursday,September 9,2021 9:13:41 AM
Attachments: Outlook-Fort Worth.ona
CPN102861 C01(Saratoga Downs Way).xlsm
Good morning, Filo
Please find attached the change order for the above-mentioned project.
Daniel Garcia is the Contractor; email: gdarcia@azteca
It is important that we expedite this Change Order routing as we have been at this location for
over a month now and the residents are getting fed up.
Please let me know if you have any questions, thanks.
Iretomiwa S. Otuyelu E.I.T.
Graduate Engineer
City of Fort Worth
Transportation and Public Work Department
817.392.6747
City of Fort Worth — Working together to build a strong community.