HomeMy WebLinkAboutContract 53958-FP1 City Secretary 53958 -FP1
Contract No.
FORTWORTH, Date Received Sep 21,2021
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Tradition Central Phase 1 B
City Project No.: 102509
Improvement Type(s): Water ❑x Sewer ❑x
Original Contract Price: $1,702,626.00
Amount of Approved Change Order(s):
Revised Contract Amount.-
Total Cost of Work Complete: $1,702,626.00
':f2- ins- Sep 20, 2021
JeremiA Patton TSep 20,202111:58 CDT)
Contractor Date
Project Manager
Title
Conatser Construction
Company Name
Sep 20, 2021
Tinner(Sep 20,202112:42 C,
Project Inspector Date
Ya�pA.'� p-C-- Sep 20, 2021
Yog Patel,I,P.E.(Sep 20,202114:02 CDT)
Project Manager Date
W�11 Sep 20, 2021
CFA Manager Date
Oana 24L( hdoAc Sep 20, 2021
Dana Burghdoff(5ep 20,202116:58 CDT)
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Tradition Central Phase 1 B
City Project No.: 102509
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Pipe Report: ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 220 WD Days Charged: 226
Work Start Date: 6/15/2020 Work Complete Date: 6/16/2021
Completed number of Soil Lab Test: 801
Completed number of Water Test: 26
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name TRADITION CENTRAL PHASE IB
Contract Limits
Project Type WATER&SEWER
City Project Numbers 102509
DOE Number 2509
Estimate Number 1 Payment Number 1 For Period Ending 9/14/2021
WD
City Secretary Contract Number Contract Time 22#11)
Contract Date Days Charged to Date 226
Project Manager NA Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors OWEN / SAMANIEGO
Wednesday,September 15,2021 Page 1 of 5
City Project Numbers 102509 DOE Number 2509
Contract Name TRADITION CENTRAL PHASE 1B Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 9/14/2021
Project Funding
WATER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
------- ----------------------------------
1 8"PVC WATER PIPE 7942 LF $38.00 $301,796.00 7942 $301,796.00
2 12"PVC WATER PIPE 1396 LF $62.00 $86,552.00 1396 $86,552.00
3 TRENCH SAFETY WATER 9338 LF $1.00 $9,338.00 9338 $9,338.00
4 8"WATERLINE LOWERING 15 EA $2,500.00 $37,500.00 15 $37,500.00
5 12"WATERLINE LOWERING 4 EA $3,500.00 $14,000.00 4 $14,000.00
6 DUCTILE IRON WATER FITTINGS 2.1 TN $5,500.00 $11,550.00 2.1 $11,550.00
W/RESTRAINT
7 STD FIRE HYDRANT ASSEMBLY W/6"GATE 9 EA $4,500.00 $40,500.00 9 $40,500.00
VALVE&BOX
8 8"GATE VALVE 19 EA $1,250.00 $23,750.00 19 $23,750.00
9 12"GATE VALVE 1 EA $2,400.00 $2,400.00 1 $2,400.00
10 CONNECTION TO EXISTING 4"-12"WATER 8 EA $1,200.00 $9,600,00 8 $9,600.00
MAIN
11 4"12"PRESSURE PLUG 2 EA $1,000.00 $2,000.00 2 $2,000.00
12 1"WATER SERVICE 270 EA $1,000.00 $270,000.00 270 $270,000.00
13 1"DOMESTIC SERVICE 1 EA $1,200.00 $1,200.00 1 $1,200.00
14 1"IRRIGATION SERVICE I EA $1,200.00 $1,200.00 1 $1,200.00
----------------------------------------
Sub-Total of Previous Unit $811,386.00 $811,386.00
SEWER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8"SEWER PIPE 5718 LF $52.00 $297,336.00 5718 $297,336.00
2 8"SEWER PIPE CSS BACKFILL 468 LF $62.00 $29,016.00 468 $29,016.00
3 12"SEWER 1320 LF $76.00 $100,320.00 1320 $100,320.00
4 12"SEWER PIPE CSS BACKFILL 100 LF $96.00 $9,600.00 100 $9,600.00
5 TRENCH SAFETY 7606 LF $2.00 $15,212.00 7606 $15,212.00
6 POST CCTV INSPECTION 7606 LF $3.50 $26,621.00 7606 $26,621.00
7 8"SEWER PIPE STEEL CASING 20 LF $160.00 $3,200.00 20 $3,200.00
8 4'MANHOLE 34 EA $4,800.00 $163,200.00 34 $163,200.00
9 MANHOLE VACUUM TESTING 34 EA $150.00 $5,100.00 34 $5,100.00
10 4'EXTRA DEPTH MANHOLE 143 VF $195.00 $27,885.00 143 $27,885.00
Wednesday,September 15,2021 Page 2 of 5
City Project Numbers 102509 DOE Number 2509
Contract Name TRADITION CENTRAL PHASE 1B Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 9/14/2021
Project Funding
11 TRENCH WATER STOPS 21 EA $250.00 $5,250.00 21 $5,250.00
12 4"SEWER SERVICE 272 EA $750.00 $204,000.00 272 $204,000.00
13 4"-12"PRESSURE PLUG 3 EA $1,000.00 $3,000.00 3 $3,000.00
14 CONNECTION TO EXISTING4"-12"SEWER 1 EA $1,500.00 $1,500.00 1 $1,500.00
--------------------------------------
Sub-Total of Previous Unit $891,240.00 $891,240.00
--------------------------------------
Wednesday,September 15,2021 Page 3 of 5
City Project Numbers 102509 DOE Number 2509
Contract Name TRADITION CENTRAL PHASE 1B Estimate Number I
Contract Limits Payment Number I
Project Type WATER&SEWER For Period Ending 9/14/2021
Project Funding
Contract Information Summary
Original Contract Amount $1,702,626.00
Ctian;3e Orders
Total Contract Price $1,702,626.00
Total Cost of Work Completed $1,702,626.00
Less %Retained $0.00
Net Earned $1,702,626.00
Earned This Period $1,702,626.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $1,702,626.00
Wednesday,September 15,2021 Page 4 of 5
City Project Numbers 102509 DOE Number 2509
Contract Name TRADITION CENTRAL PHASE IB Estimate Number I
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 9/14/2021
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors OWEN / SAMANIEGO Contract Date
Contractor CONATSER CONSTRUCTION TxLP Contract Time 220 WD
5327 WICHITA ST Days Charged to Date 226 WD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $1,702,626.00
Less %Retained $0.00
Net Earned $1,702,626.00
Earned This Period $1,702,626.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $1,702,626.00
Wednesday,September 15,2021 Page 5 of 5
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Tradition Central Phase I
PROJECT NUMBER: 102509
DOE NUMBER: N/A
WATER
PIPE LAID SIZE TYPE OF PIPE LF
8" PVC 7942
12" PVC 1396
FIRE HYDRANTS: 9 VALVES(16"OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES:
NEW SERVICES: 272( V) COPPER
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
8" SDR-26 PVC 6186
1211 SDR-26 PVC 1420
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES:
NEW SERVICES: 272(4") SDR 26 PVC
TRANSPORTATION AND PUBLIC WORKS
FORTWORTHO
TRANSPORTATION AND PUBLIC WORKS
September 14,2021
Conatser Construction TX,L.P
5327 Wichita st.
Fort Worth TX 76119
RE: Acceptance Letter
Project Name:Tradition Central Phase 1B
Project Type:01,02, 03,04,06
City Project No.: 102509
To Whom It May Concern:
On May 10, 2021 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on June 16,2021. The final inspection and
the corrected punch list items indicate that the work meets the City of Fort Worth specifications and is
therefore accepted by the City. The warranty period will start on June 16, 2021,which is the date of the
punch list completion and will extend of two (2)years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2443.
Sincerely,
Yzre�P�teG,
Yog Patel,I,P.E.(Sep 20,202114:02 CDT)
Yogesh Patel, Project Manager
Cc: Eric Tinner, Inspector
Wade Miller, Inspection Supervisor
Ariel Duarte,Senior Inspector
Victor Tornero, Program Manager
Goodwin Marshall, Consultant
Conatser Construction,Contractor
Hines Interests LP, Developer
File
E-Mail:
Douglas W.Wiersig, P.E., PhD., Director,TPW Wendy Chi-Babulal, P.E.,Water
Richard Martinez,Assistant Director,TPW Tony Sholola, P.E.,Water
Marisa Conlin,Traffic Engineering Richard Zavala, Director, PARD
Allen Hall,Superintendent,TPW David Creek,Assistant Director, PARD
John Robert Carman, P.E., Director,Water
Chris Harder, P.E., Assistant Director,Water
Rev.9/15/16
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatser Management Group, Inc.,
general partner of Conatser Construction TX, LP, known to me to be a credible person, who
being by me duly sworn, upon his oath deposed and said:
That all persons, firms, associations, corporations or other organizations furnishing
labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth, has
been paid in full; and
That there are no claims pending for personal injury and/or property damages;
On Contract described as:
TRADITION, CENTRAL PHASE 1B
WATER, SANITARY SEWER, STORM DRAIN,
PAVING AND STREET LIGHT IMPROVEMENTS
DOE#: N/A
CFA PRJ #: 19-0150
CITY PROJCT #:N/A
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TX, LP
//,-Z—
h
Brock Huggins
Subscribed and sworn to before me this 16''day of July, 202
GIANUL1S Notary Public in Tarrant County, Texas
Y aoB, BER�NA State of Texas
o; o Public,
Not2rym F,cpires 0911912023
*`• 'yF com ID 1026977-3
1z �q�� Notary
No.BI-7280j-el
POWER OF ATTORNEY
BERKLEY INSURANCE COMPANY
WILMINGTON,DELAWARE
NOTICE: The warning found elsewhere in this Power of Attorney affects the validity thereof. Please review carefully.
KNOW ALL MEN BY THESE PRESENTS, that BERKLEY INSURANCE COMPANY (the "Company"), a corporation duly
organized and existing under the laws of the State of Delaware,having its principal office in Greenwich,CT,has made,constituted
and appointed, and does by these presents make, constitute and appoint: Ricardo J. Reyna;Don E. Cornell; Sophinie Hunter;
Robbi Morales;Kelly A. Westbrook; Tina McEwan; Joshua A. Saunders, or Tonie Petranek of Aon Risk Services Southwest,
Ina of Dallas, TX its true and lawful Attorney-in-Fact, to sign its name as surety only as delineated below and to execute, seal,
acknowledge and deliver any and all bonds and undertakings,with the exception of Financial Guaranty Insurance, providing that
no single obligation shall exceed Fifty Million and 00/100 U.S.Dollars(U.S.$50,000,000.00),to the same extent as if such bonds
had been duly executed and acknowledged by the regularly elected officers of the Company at its principal office in their own
proper persons.
This Power of Attorney shall be construed and enforced in accordance with, and governed by,the laws of the State of Delaware,
without giving effect to the principles of conflicts of laws thereof This Power of Attorney is granted pursuant to the following
resolutions which were duly and validly adopted at a meeting of the Board of Directors of the Company held on January 25,2010:
RESOLVED, that, with respect to the Surety business written by Berkley Surety, the Chairman of the Board, Chief
Executive Officer, President or any Vice President of the Company, in conjunction with the Secretary or any Assistant
Secretary are hereby authorized to execute powers of attorney authorizing and qualifying the attorney-in-fact named therein
to execute bonds, undertakings, recognizances, or other suretyship obligations on behalf of the Company, and to affix the
corporate seal of the Company to powers of attorney executed pursuant hereto; and said officers may remove any such
attorney-in-fact and revoke any power of attorney previously granted;and further
RESOLVED,that such power of attorney limits the acts of those named therein to the bonds, undertakings, recognizances,
or other suretyship obligations specifically named therein, and they have no authority to bind the Company except in the
manner and to the extent therein stated;and further
RESOLVED,that such power of attorney revokes all previous powers issued on behalf of the attorney-in-fact named; and
further
RESOLVED,that the signature of any authorized officer and the seal of the Company may be affixed by facsimile to any
power of attorney or certification thereof authorizing the execution and delivery of any bond, undertaking, recognizance, or
other suretyship obligation of the Company;and such signature and seal when so used shall have the same force and effect as
though manually affixed. The Company may continue to use for the purposes herein stated the facsimile signature of any
person or persons who shall have been such officer or officers of the Company, notwithstanding the fact that they may have
ceased to be such at the time when such instruments shall be issued.
IN WITNESS WHEREOF,the Company has caused these presents to..be signed and attested by its appropriate officers and its
corporate seal hereunto affixed this end day of .tune 2020
,uRaN E Attest: Berkl Insurance Company
51'.'�I, i By By r
.
derman Je after
1975
�enwA Executive Vice President&Secretary ` .Se ce resident
STATE OF CONNECTICUT)
) ss:
COUIr"TY OF FAIRFIELD )
Sworn to before me,a Rotary Public in the State of Connecticut,this end day of June 2020 ,by Ira S.Lederman
and Jelfrey M. Hafter who are sworn to me to be the Executive Vice President Secretary, and t w Senior Vice President,
respectively,of Berkley Insurance Company. NOTARY PURI'icy
�V CO,Fy 0,2�` . otary Public,State of Connecticut
CERTIFICATE
I,the undersigned,Assistant Secretary of BERKLEY INSURANCE COMPANY,DO HEREBY CERTIFY that the foregoing is a
true,correct and complete copy of the original Power of Attorney;that said Power of Attorney has not been revoked or rescinded
anal-that-tlw authority of the Attorney-in-Fact set forth therein, who executed the bond or undertaking to which this Power of
IRAfy
ched,is in full force and affect as of this date.
�nder my hand and seal of the Company,this 15th day of J111y s 2021
m 1975 Y
41AWAQ`�' ••r Vincent P,1'OCtJ
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
CONTRACTOR ❑
TO FINAL PAYMENT SURETY ❑
Conforms with the American institute of OTHER
Architects,AIA Document G707
Bond No 0230485
PROJECT:
(name, address)Tradition, Central Phase I
Fort Worth,TX
TO (Owner)
HT HWY 114 DEVELOPMENT LP&CITY OF FORT ARCHITECT'S PROJECT NO: CFA20-0003
WORTH CONTRACT FOR:
2200 Ross Avenue,Sujite 420OW Water,Sanitary Sewer,Paving,Street Lights and Drainage
Improvements for Tradition,Central Phase 1 B
Dallas TX 75201 J CONTRACT DATE:
CONTRACTOR:CONATSER CONSTRUCTION TX, L.P.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above,the
(here insert name and address of Surety Company)
BERKLEY INSURANCE COMPANY
475 Steamboat Road
Greenwich CT 06830 , SURETY COMPANY
on bond of (here insert name and address of Contractor)
CONATSER CONSTRUCTION TX, L.P.
5327 Wichita St.
Fort Worth TX 76119-6035 , CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to (here insert name and address of Owner)
HT HWY 114 DEVELOPMENT LP&CITY OF FORT WORTH
2200 Ross Avenue, Sujite 420OW
Dallas TX 75201 , OWNER,
as set forth in the said Surety Company's bond.
IN WITNESS,WHEREOF,
the Surety Company has hereunto set its hand this 15th day of July,2021
BERKLEY INSURANCE COMPANY
Surety Company
Attest:
(Seal): Signature of Authorized Representative
Ro bi Morales Attorne -in-Fact
Title
NOTE: This form is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,
Current Edition
ONE PAGE
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
CONTRACTOR ❑
TO FINAL PAYMENT SURETY ❑
Conforms with the American institute of OTHER
Architects,AIA Document G707
Bond No 0230485
PROJECT:
(name, address)Tradition, Central Phase I
Fort Worth,TX
TO (Owner)
HT HWY 114 DEVELOPMENT LP&CITY OF FORT ARCHITECT'S PROJECT NO: CFA20-0003
WORTH CONTRACT FOR:
2200 Ross Avenue,Sujite 420OW Water,Sanitary Sewer,Paving,Street Lights and Drainage
Improvements for Tradition,Central Phase 1 B
Dallas TX 75201 J CONTRACT DATE:
CONTRACTOR:CONATSER CONSTRUCTION TX, L.P.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above,the
(here insert name and address of Surety Company)
BERKLEY INSURANCE COMPANY
475 Steamboat Road
Greenwich CT 06830 , SURETY COMPANY
on bond of (here insert name and address of Contractor)
CONATSER CONSTRUCTION TX, L.P.
5327 Wichita St.
Fort Worth TX 76119-6035 , CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to (here insert name and address of Owner)
HT HWY 114 DEVELOPMENT LP&CITY OF FORT WORTH
2200 Ross Avenue, Sujite 420OW
Dallas TX 75201 , OWNER,
as set forth in the said Surety Company's bond.
IN WITNESS,WHEREOF,
the Surety Company has hereunto set its hand this 15th day of July,2021
BERKLEY INSURANCE COMPANY
Surety Company
Attest:
(Seal): Signature of Authorized Representative
Ro bi Morales Attorne -in-Fact
Title
NOTE: This form is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,
Current Edition
ONE PAGE