HomeMy WebLinkAboutContract 54223-CO2 CSC No.54223-CO2
FO RT W"a-r H City of Fort Worth
Change Order Request
Project Name:1 Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 56019/07004301001480 NTP N/A City Proj.No.: 100995
Project Description: Construction of a new Sanitary Sewer Lift Station for the Lake Ariingten Force Main Project
Contractor: Bar Constructors Inc. Change Order# 0 Date: 1 8/27/2021
City Project Mgr.1 Pratima Poudyal City Inspector: I Nathan Gray
Phone Number: 817-392-6149 Phone Number: 817-392A961
Dept, Unit I Lift Station Unit II Water Alternate A-2 Totals Contract Time
(Calender days)
Original Contract Amount $9,422,126.00 $72,565.00 $583,002.00 $10,077,693.00 487
Extras to Date • 19,830.96 $0.00 $0.00 -$19,830.96 92
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $9,402,295.04 $72,565.00 $583,002.00 $10,057,862.04 579
Amount of Proposed Change Order •$11,978.95 $0.00 $0.00 411,978,95 0
Revised Contract Amount $9,390,316.09 $72,565.00 $583,002.00 $10,045,883.09 579
Original Funds Available for Change Orders $201,554.00 $0.00 $0.00 $201,554.00
Remaining Funds Available for this CO $221,384.96 $0.00 $0.00 $221,384,96
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT -0.32%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $12,597,116.25
JUSTIFICATION(REASONS)FOR CHANGE ORD
City of Fort Worth Water Depertment Plant Operations conducted two separate Radio Frequency PATH studies and each confirmed that the
designed tower height of 60 ft.above ground level was well in excess of the proper radio link needs at the Lake Arlington Lift Station location.
The PATH study determined that a much shorter tower of only 20 ft.above ground level would be required.Change Order No.2 provides for
the following to accomodate the design change from the tower to the antenna:
.Removal of 60 ft.lattice style tower,the tower foundation and all appurtenances.
.Addition of 20 ft.pole style antenna to be mounted on the electrical building and all required appurtenances.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an c,ccord and_at sfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's company Name Contractor Name r;ontcaor 5 nature Darr:
Bar Constructors Inc. Mike Ayers
Inspector Date Prokct Mavaget. Date
9/15/21 0 zC1 1202
Director(Water Deptf Date Construction r Da
T. S• Sep 21,2021Mai
Date Assistant City Manaw Date-
Sep 24,2021Ha 5 Sep 27,2021
Council Action if Required)
M&C Number r NIA M&C Date Approved OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 56019/0700430/001480 DOE No. N/A City Proj. No.: 100995
Project Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Description
Contractor Bar Constructors Inc. Change Order: 0 Date: 8/27/2021
City Project Mgr. Pratima Poudyal City Inspector r Nathan Gray
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
43 20'Pole Antenna&Appurtenances Unit I Lift Station 1.00 EA $1,763.13 $1,763.13
Unit I Lift Station $1,763.13
Unit II Water
Alternate A-2
Page 1 of 3 Additions Sub Total $1,763.13
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 56019/0700430/001480 DOE No. N/A City Proj. No.: 100995
Project Description Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractor Bar Constructors Inc. Change Order: � Date 8/27/2021
City Project Mgr. I Pratima Poudyal City Inspector: EEEray
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
9999,0017 Instrumentation,SCADA",Antenna Tower(Deduct 60' Unit I Lift Station 0.054 EA $256,000.00 $13,742.08
33 lattice style tower,the tower foundation and all appurtenances)
Unit I Lift Station $13,742.08
Unit II Water
Alternate A-2
Page 2 of 3 Deletions Sub Total 1$13,742.08
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 3 of 3
Contract Co►nnliame Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration ofthis contract,including
ensuring all performance andrep orting requirements.
Signature
Pratinia Poudyal, P.E.
Name of Employee
Project Manager
Title
ATTEST:
��
000000000.4_ �
Ronald Gonzales ��0 °op��
Acting City Secretary �o °
0vo °=d
°oo o°4��
Y� 000000000
oo a
SEX Asap