HomeMy WebLinkAbout(0042) M&C 21-0695City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/14/21 M&C FILE NUMBER: M&C 21-0695
LOG NAME: 20TEMPORARY CLOSURE OF CHURCHILL ROAD
SUBJECT
(CD 2) Authorize the Temporary Closure of Churchill Road from White Settlement Road to Rockwood Road from August 23, 2021 to October 15,
2021 for Construction Activities
RECOMMENDATION:
It is recommended that the City Council authorize the temporary closure of Churchill Road from White Settlement Road to Rockwood Road from
August 23, 2021 to October 15, 2021 for construction activities.
DISCUSSION:
The City of Fort Worth Transportation and Public Works Department (TPW) requests the temporary closure of Churchill Road from White
Settlement Road to Rockwood Road for protection of the public. Construction is currently limiting Churchill Road to one lane, visibility is restricted
due to the levee, and the bore pits are too large to be safely covered by steel plates. All of these factors necessitate a closure in the interest of
public safety. Churchill Road has been temporarily closed since August 6, 2021 to protect the public and to provide a safe working environment for
the contractor. Traffic control plans for this project have been previously accepted.
A Form 1295 is not required because: This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that approval of this recommendation will have no material effect on City funds.
Submitted for City Manager's Office by. Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Tanya Brooks 7861
Expedited