HomeMy WebLinkAboutOrdinance 25125-09-2021ORDINANCE NO. 25125-09-2021
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER BOND 2020A FUND IN
THE AMOUNT OF $192,773.00, BY DECREASING ESTIMATED
RECEIPTS AND APPROPRIATIONS IN THE UNSPECIFIED PROJECT
(CITY PROJECT NO. UNSPEC), AND INCREASING ESTIMATED
RECEIPTS AND APPROPRIATIONS IN THE CFA BUCKET
PROGRAMMABLE PROJECT (CITY PROJECT NO. P00001) BY THE
SAME AMOUNT, FOR THE PURPOSE OF FUNDING THE COMMUNITY
FACILITIES AGREEMENT—TAVOLO PARK PHASE 4 PROJECT (CITY
PROJECT NO. 102748); PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND
PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT
WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-
2021 in the Budget of the City Manager, there shall also be adjusted estimated receipts and
appropriations in the Water and Sewer Bond 2020A Fund in the amount of $192,773.00, by
decreasing estimated receipts and appropriations in the Unspecified project (City Project No.
UNSPEC), and increasing estimated receipts and appropriations in the CFA Bucket programmable
project (City Project No. P00001) by the same amount, for the purpose of funding the Community
Facilities Agreement-Tavolo Park Phase 4 project (City Project No. 102748).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative
or void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall
in no way impair the remaining portions, sections, or parts of sections of this ordinance, which said
remaining provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance
are in direct conflict with such other ordinances and appropriations, in which instance said
conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Richard A. McCracken
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: September 28, 2021
CITY SECRETARY
-nkQs2•40.:b
Ronald P. Gonzales
Acting City Secretary
LOCATION MAP
(NOT TO E
CONNECT TO EX.
8" WATER LINE
(CITY PROJECT
NO. 100549)
0
CONNECT TO EX.
8" WATER LINE
(CITY PROJECT
NO. 101565)
NORTH
CONNECT TO EX.
24" WATER LINE
(CITY PROJECT
NO. 101565)
300TAVOLO, PHASE 4
GRAPHIC SCALE
CPN 102748
DATE: JUNE 2021
5 I 6
PONDVIEW L
2 3
ANE 4 I
30 29 28
.„,
WINTERBLOOM WAY
1 2 34 5\j_Jj9 10 11
31 30 29
261 271 26
BRYANT IRV N ROAD
OWNER:
12 13 14
-11,11,11,11,11,11
LU
LU
CO
LU
0
Cr
LLi
/
I
LEGEND
PROPOSED GATE VALVE
EXISTING GATE VALVE
PROPOSED FIRE HYDRANT
EXISTING FIRE HYDRANT
NOTE: ALL PROPOSED WATER LINES
ARE 8" UNLESS OTHERWISE NOTED.
EXHIBIT A - WATER
PE LOTON
PATE RANCH SINGLE FAMILY, LP
10210 N CENTRAL EXPY, SUITE 300
DALLAS, TX 75231
PHONE: 972-385-4100
iffir LAND SOLUTIONS
11000 FRISCO STREET
SUITE 400
FRISCO, TX 75033
PHONE: 469-213-1800
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/28/21 M&C FILE NUMBER: M&C 21-0766
LOG NAME: 60TAVOLO PARK PH4 241NCH WATERLINE
SUBJECT
(CD 6) Authorize Execution of a Community Facilities Agreement with Pate Ranch Single Family LP with City Participation in an Amount Not to
Exceed $169,710.70 for Oversizing an 8 Inch Water Main to a 24 Inch Water Main South of Altamesa Boulevard and East of Bryant Irvin Road
to Serve Tavolo Park Phase 4 and Anticipated Future Growth in West Fort Worth and Adopt Attached Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a community facilities agreement with Pate Ranch Single Family LP with City participation in an amount not to exceed
$169,710.70 for oversizing an eight -inch water main to a twenty -four -inch water main south of Altamesa Boulevard and east of Bryant Irvin
Road to serve Tavolo Park Phase 4 and anticipated future growth in west Fort Worth; and
2. Adopt the attached appropriation ordinance adjusting receipts and appropriations in the Water and Sewer Bond 2020A Fund, in the amount
of $192,773.00, by decreasing receipts and appropriations in the Unspecified project (City Project No. UNSPEC) and increasing receipts
and appropriations in the Community Facilities Agreement Bucket programmable project (City Project No.P00001) by the same amount, for
the purpose of funding the Community Facilities Agreement —Tavolo Park Phase 4 project (City Project No.102748).
DISCUSSION:
Pate Ranch Single Family LP (Developer) is constructing Tavolo Park Phase 4 (Development) south of Altamesa Boulevard and east of
Bryant Irvin Road. The Water Department would like to cost participate to oversize approximately 1,200 linear feet of 8-inch water main to a 24-
inch water main. The Tavolo Park Phase 4 project is assigned City Project No. 102748 and Accela System Record IPRC20-0064.
In accordance with Chapter 212, Subchapter C of the Texas Local Government Code, the City's participation in the contract is exempt from
competitive bidding requirements because the contract is for oversizing public improvements being constructed by the Developer, the Developer
will execute a performance bond to cover the total project cost, including all of the City's cost participation, and the City's cost participation will be
determined in accordance with the City's community facilities agreement (CFA) unit price ordinance. The City's cost participation in the
construction and oversizing of the water mains is estimated to be in an amount not to exceed $169,710.70 as shown in the table below. Payments
to the Developer are estimated to be $153,745.79 for construction costs, $8,265.00 for design services, and $3,074.92 for material testing. The
remaining City participation in the estimated amount of $4,625.00 will cover the City's portion of inspection fees, administrative material testing
fees, and water lab testing fees.
A. 24" WL Construction
1. Water
2. Sewer
3. Water Contingency 15%
4. Paving
5. Street Lights
6. Storm Drains
B. Inspections & Testing
Developer City Cost
Cost
Total Cost
$934,190.91 $153,745.79$1,087,936.70
$671,334.75
$0.00
$1,845,013.00
$271,608.00
$0.00
$0.00
$23,061.87
$0.00
$0.00
$0.00
$671,334.75
$23,061.87
$1,845,013.00
$271,608.00
$0.00
1. Construction Inspection
Fee
2. Admin Material Testing
Fee
3. Water Lab Fee
4. Material Testing Cost
Contingency
C. Design Services Cost
$81,250.00 $3,250.00 $84,500.00
$30,037.00 $1,225.00 $31,262.00
$3,240.00 $150.00 $3,390.00
$0.00 $3,074.92 $3,074.92
$0.00 $8,265.00 $8,265.00
Total Project Cost $3,836,673.66 $192,772.58 $4,029,446.24
*Numbers will be rounded up for accounting purposes.
The reimbursement of the participation, excluding inspection and material testing fees, is not a lump -sum amount and may be less than the stated
amount depending upon the actual quantities and unit prices from the Notice of Final Completion package, commonly referred to as the Green
Sheet package. Funding for the Community Facility Agreement (CFA)-Tavolo Park Phase 4 project as depicted in the table below:
Fund
Existing
Appropriations
Additional
Appropriations
Project Total*
Water & Sewer Bond
$0.00
2020A-Fund 56017
$192,773.00 $192,773.00
'Project Total
$0.00 $192,773.00 $192,773.00
*Numbers rounded for presentation purposes.
Business Equity Division: Offerors are strongly encouraged to comply with the intent of the City's Business Diversity Enterprise Ordinance to
utilized Minority Business Enterprises or Small Business Enterprises on the City -funded portion of the Community Facilities Agreement.
This development is located in Council District 6.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified - All Funds project within the Water & Sewer Bond 2020A
Fund and upon approval of the above recommendation and adoption of the attached appropriation ordinance, funds will be available in the Water
& Sewer Bond 2020A Fund for the CFA Bucket programmable project to support the approval of the above recommendation and execution of the
agreement. Prior to an expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted for Citv Manaaer's Office bv: Dana Burghdoff 8018