HomeMy WebLinkAboutOrdinance 25152-10-2021ORDINANCE NO. 25152-10-2021
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE STORMWATER CAPITAL PROJECTS FUND BY
INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE 2018
BOND STREET RECONSTRUCTION CONTRACT 15 PROJECT (CITY
PROJECT NO. 101476) IN THE AMOUNT OF $40,000.00, AND DECREASING
ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE DRAINAGE
IMPROVEMENTS PROGRAMMABLE PROJECT (CITY PROJECT NO. P00043)
BY THE SAME AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING
AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-2021 in the
Budget of the City Manager, there shall also be adjusted estimated receipts and appropriations in the
Stormwater Capital Projects Fund by increasing estimated receipts and appropriations in the 2018 Bond
Street Reconstruction Contract 15 project (City Project No. 101476) in the amount of $40,000.00, and
decreasing estimated receipts and appropriations in the Drainage Improvements Programmable project
(City Project No. P00043) by the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas W Black
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: October 12, 2021
CITY SECRETARY
Ronald P. Gonzales
Acting City Secretary
MAYOR AND COUNCIL COMMUNICATION MAP
602018CIPY2C15CO2-TEXASBIT
4 T
'V6h 4,�'minnu
Ijlvl 0,00110,000000
IAII
100010000i00010000 000
'VIS�,llii�
RIIA'I01r,
'lll IYIpIV"...,IIN
w„ „ VIC K ERY,BLVD III
4 �'w' Wlly
FORTWORTFI
oho
iIII�I�VW
y;, .�
000
10011 1I111I
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 10/12/21
LOG NAME: 602018CIPY2C15CO2-TEXASBIT
SUBJECT
M&C FILE NUMBER: M&C 21-0800
(CD 8) Authorize Execution of Change Order No. 2 in the Amount of $392,607.72 and the Addition of 35 Calendar Days to a Contract with Texas
Materials Group dba Texas Bit, for Combined Street Paving Improvements, Storm Drain and Water and Sanitary Sewer Main Replacements for
2018 Bond Street Reconstruction Contract 15 Project, for a Revised Contact Amount of $7,966,449.74 and Adopt Attached Appropriation
Ordinances
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No. 2 in the amount of $392,607.72 and the addition of 35 calendar days to City Secretary Contract
No. 54278 with Texas Materials Group dba Texas Bit, for combined street paving improvements, storm drain and water and sanitary sewer
main replacements for 2018 Bond Street Reconstruction Contract 15 project for a revised contract amount of $7,966,449.74;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $114,411.00 transferred from available funds within the Water and Sewer Fund, for the purpose of funding the 2018 Bond
Street Reconstruction Contract 15 project (City Project No. 101476);
3. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Stormwater Capital Projects fund by
increasing appropriations in the 2018 Bond Street Reconstruction Contract 15 project (City Project No. 101476) in the amount of
$40,000.00 and decreasing estimated receipts and appropriations in the Drainage Improvements programmable project (City Project No.
P00043) by the same amount; and
4. Adopt the attached appropriation ordinance adjusting appropriations in the 2018 Bond Program Fund by increasing appropriations in the
2018 Bond Street Reconstruction Contract 15 project in the amount of $329,808.00 and decreasing appropriations in the Street
Construction/Recon/Rehab programmable project (City Project No. PB0001) by the same amount.
DISCUSSION:
On June 23, 2020, Mayor and Council Communication (M&C) 20-0456, City Council authorized a contract with Texas Materials Group dba Texas
Bit, in the amount of $7,543,467.02 for the combined street paving improvements, storm drain and water and sanitary sewer main replacements
for 2018 Bond Street Reconstruction Contract 15 Project. The contract was subsequently revised by Change Order No. 1 in the amount of
$30,375.00 administratively authorized March 2, 2021 that provided for imported fill material to replace unsuitable trench material.
Due to failure of the concrete base on Essex Street, it is necessary to change the proposed paving procedure subsequent to water and sewer
replacement from mill and overlay to pulverize and overlay. Change Order No. 2 will provide the necessary pay items to allow for the change in
procedure. The change order will also provide pay item quantities for additional pavement repair beyond the trench width for the water and storm
drain lines that are being installed as part of this project. Additional pay items will also be provided to realign a portion of the 4'x3' storm drain box
culvert that during construction was determined to directly conflict with a previously unknown fiber optics communication cable.
The staff has reviewed and verified the quantities for the additional work under this Change Order No. 2. Additionally, to complete this work, staff
recommends that the contract time be extended by 35 calendar days. Staff recommends use of the remaining project funds and contingency in
2018 Bond Program - Fund 34018 to fund the paving portion of this change order.
This change order will have no impact of the Transportation and Public Works or on the Water Departments' annual operating budget.
Appropriations for the combined street paving improvements, storm drain and water and sanitary sewer main replacements for 2018 Bond Street
Reconstruction Contract 15 Project will consist of the following:
Fund
Existing
Appropriations
Additional
Appropriations
Project Total*
2018 Bond
Program - Fund
34018
$4,873,832.00
$0.00$4,873,832.00
Storm Water
Capital Projects
Fund - 52002
Water & Sewer
Capital Projects -
Fund 56002 _._..
$282,500.00 $40,000.00
$4,792,889.00
$114,411.00
$322,500.00
$4,907,300.00
Project Total II $9,949,221.001 $154,411.00II$10,103,632.00II
* Numbers rounded for presentation purposes.
Funds for this project are included in the 2018 Bond Program. Available resources within the General Fund will be used to provide interim
financing until debt is issued. Once debt associated with the project is sold, bond proceeds will reimburse the General Fund in accordance with the
statement expressing Official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance No. 23209-
05-2018) and subsequent actions taken by the Mayor and Council.
Approval of Recommendation 4 would adjust appropriations between a programmable project and convert the 2018 Bond Street Reconstruction
Contract 15 into a static capital project. This action is needed as future funding for the 2018 Bond Street Reconstruction Contract 15 is anticipated
from other funding sources and the scope of the project differs from that of the current programmable project.
Business Equity: Texas Materials Group, Inc. dba Texas Bit agrees to maintain its initial MBE commitment of 15 percent that it made on the
original contract and extend and maintain that same MBE commitment of 15 percent to all prior change orders up to and inclusive of this Change
Order No. 2. Therefore Texas Materials Group, Inc. dba Texas Bit remains in compliance with the City's BDE Ordinance and attests to its
commitment by its signature on the acceptance of Previous MBE Commitment from executed by an authorized representative of its company.
This project is located in COUNCIL DISTRICT 8.
A Form 1295 is not required because: This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are available in the current operating budget in the Water & Sewer Fund and in the capital budget for
the Drainage Improvement Projects project within the Stormwater Capital Projects Fund and upon approval of the above recommendations and
adoption of the attached appropriation ordinances, funds will be available in the Stormwater Capital Projects Fund and W&S Capital Projects
Fund for the 2018 WSM-J-CIP Contract 15 project to support the approval of the above recommendations and execution of the change order to
the contract. Prior to an expenditure being incurred, the Transportation & Public Works and Water Departments have the responsibility of verifying
the availability of funds.
Submitted for Citv Manaaer's Office bv: Dana Burghdoff 8018
Oriainatina Business Unit Head:
Chris Harder 5020
Additional Information Contact: Pratima Poudyal 6149