HomeMy WebLinkAboutContract 54099-CO2 CSC No.54099-CO2 FORT WORTH; City of Fort Worth Change Order Request ProjeclName VCWRF Grit Removal Facility CitySecN 54099 Client Project 11(s) Village Creek Water Reclamation Facility(VCWRF)Grit Removal Facility(CPN 100075) Project Description The project consist of a new Grit Facility with 8 slacked tray vordex grit removal units,structural modifications to existing Headwork Facility,modilicataions to Odor Control Biofiller System,and Electrical/HVAC/Plumbinglyard Piping Contractor Crescent Constructors,Inc. Change Order 41 2 Dale 9/27/2021 City Project Mgr. Fadda Gode ya,P E City Inspector Kevin Sideboltom (FNI) Dept. Water Department Contract Time Totals (CD) Original Contract Amount 25,797,000.00 25,797,000.00 730 Extras to Date $19,965.00 $19,965.00 0 Credits to Date $0.00 0 Pending Change Orders(n M&C Process) $0.00 0 Contract Cost to Dale $25,816,965.00 $25,816,965.00 730 Amount of Proposed Change Order $77,630.00 $77,630.00 0 Revised Contract Amount $25,894,595.00 25,894,695.00 730 Original Funds Available for Change Orders $332,463.00 $332,463.00 Remaining Funds Available for this CO $312.498.00 $312,498.00 Additional Funding(f necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.38% MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $32,246,250.00 JUSTIFICATION(REASONS)FOR CHANGE ORDER - Change Order No 02 provides for the following: Increasing two(2)HVAC Units sizes for the Integrated Power Assembly(IPA)for pre-fabricated electrical building from 3,5 ton to 6 tons to provide full redundancy. The installation of Rotork Actuators(for eight 156'x 30",two 96'x 96'gales,total of 10 gates)in lieu of Limilorque actuators,which are provided per VCWRF staff request. Addition costs to allow for the reroute of an 184nch drain line[hat is in conflict with multiple existing utilities. Credit for the reduction of the Odor Control fan size from 28,600 cfm to 13,000 cfm. Staff concurs with the contractors price proposal,however denies the contractor's request for 14 additional calendar days an the change order. it is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money)for all costs arising out of,or incidental to,the above Change Order.The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's Company Name Contractor(Name) / Coon ctSignature Date Crescent Constructors,Inc. Ryan Glanz 3 Z l Inspectorlhspection Supervisor Date Project and Contract Complian anger Date Kevin Sidebottom,FNI 1 1/2/21 Program Manager Date Senior Capital Project Officer Date Farida Goderya 1114/2021 Assistant Director(Dept) Date Director,Contracting Department(Dept) Date Tony Sholola 0 A J o 4- ChrisHarde4���o41�d/' Nov 5,2021 Assistant CI Atlomey Date Assistant City Manager Date Nov 5,2021 Dan Burghdoff � Nov 9,2021 Council Action(If required) M&C Number n/a M&C Dale Approved n/a OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WORTH City of Fort Worth If-- Change Order Additions Project Name VCWRF Grit Removal Facility City Sec# 54099 Client Project# Village Creek Water Reclamation Facility(VCWRF)Grit Removal Facility(CPN 100075) Contractor Crescent Constructors,Inc. PM Farida Goderya,PE Inspector Change Order Submittal# 0 Dale 9/27/2021 ADDITIONS ITEM DESCRIPTION DEPT ty U nit Unit Cost Total Unit Size Increase aler epartment 2 PCM-003Rolork Actuators Water Department 1.00000000 LS 34,100.00 PCM-005 Utility Conflict and Reroute of Proposed 18'D PVC Water Department 1.06000000-Ls 51,000.00 5, Odor Control FaMoMic-attons Water-Department Water Department $77,630.00 Sub Total Additions 77,630.00 Change Order Additions Page 2 of 2 Contract Compliance Manager By signing I acknowledge that I am the person responsible forthe monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Farida Goderya, PhD, PE Name of Employee Senior Project Manager Title IFORr ATTEST: "/•o P ° °�'�� �v o ° _ 0 � Ronald Gonzales d °o ° ICY°o°000°° a Acting City Secretary �� EXpSoad OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX 2560 Technology Drive#400 Plano, TX 75074 CONTRACT MODIFICATION REQUEST: CMR-02 PROJECT: VILLAGE CREEK GRIT FACILITY DATE: 03/08/21 PROJECT NO. 100075 ATTENTION: CITY OF FORT WORTH 1000 THROCKMORTON STREET FORT WORTH, TX 76102 ATTN: FARIDA GODERYA Attention: The following change in contract on this project is proposed: A breakdown of cost SHALL be attached. YVark shall not commence until authorized by the OYVNER. Description of the Proposed Change & Clarifications Pricing for the following The Submittal review comments in 23.2 noted increasing the IPA Building 2 EA HVAC Units to 6 ton units. Below are the costs to increase the 2 EA 3.5 Ton HVAC units to 2 EA 6 Ton HVAC units TOTAL AMOUNT $ 6,530 Ryan Glanz Crescent All work shall be in accordance with the terms, stipulations, and conditions of the original Contract Documents. If the work herein provided for is Approved by Change Order, the time of completion will be: Increased By 0 Calendar Days Decreased Unchanged ❑X ACCEPTED Amy Robinson 3/25/2021 Date ❑ REJECTED CDM Smith 2560 Technology Drive 4400 Plano, TX 75074 CONTRACT MODIFICATION REQUEST: PCM-03rev01 PROJECT: VILLAGE CREEK GRIT FACILITY DATE: 04/08l21 PROJECT NO. 100075 ATTENTION: CITY OF FORT WORTH 1000 THROCKMORTON STREET FORT WORTH, TX 76102 ATTN: FARIDA GODERYA Attention: The following change in contract on this project is proposed: A breakdown of cost SHALL be attached. Work shall not commence until authorized by the OWNER. Description of the Proposed Change & Clarifications Pricing for the following PCM-03: Slide Gates and Ball Valves Actuator Options: (A) Slide Gates Actuators: (1) Provide Rotork Actuators = $ 34,100 (Down from $42,100) (B) Ball Valve Actuators: (1) Change Auma to Rotork Actuators =_= No Additional Charge TOTAL AMOUNT See Above Ryan Glanz Crescent All work shall be in accordance with the terms, stipulations, and conditions of the original Contract Documents. If the work herein provided for is Approved by Change Order,the time of completion will be: Increased By 0 Calendar Days Decreased Unchanged ® ACCEPTED Amy Robinson 4/20/2021 CDM Smith Inc. Date ❑ REJECTED 2560 Technology Drive#400 Plano, TX 75074 CONTRACT MODIFICATION REQUEST: PCM-05 PROJECT: VILLAGE CREEK GRIT FACILITY DATE: 07/06/21 PROJECT NO. 100075 ATTENTION: CITY OF FORT WORTH 1000 THROCKMORTON STREET FORT WORTH, TX 76102 ATTN: FARIDA GODERYA Attention: The following change in contract on this project is proposed: A breakdown of cost SHALL be attached. Work shall not commence until authorized by the 0PVNER. Description of the Proposed Change & Clarifications Pricing for the following (1) Reroute of 18" D-PVC line due to multiple existing utility conflicts in orignal align (PCM-05) (A) Utlity investigation SUE work to provide info for revised PCM-05 routing = $15,000 (5 Day) (B) Concrete Demo additional MH and new 18" D-PVC alignment = $10,000 (2 Day) (C) Install new 48" Fiberglass Manhole & Cast in place base/invert = $22,000 (5 Day) (D) 7" Concrete Pavement Replacement for new 18" D-PVC alignment = $ 6,000 (3 Day) TOTAL AMOUNT $ 51,000 Ryan Glanz Crescent All work shall be in accordance with the terms, stipulations, and conditions of the original Contract Documents. If the work herein provided for is Approved by Change Order, the time of completion will be: Time Extension of 14 days, Denied Increased By 14 Calendar Days Farida Goderya. 9/27/21 Decreased Unchanged El ACCEPTED City of Fort Worth Date ❑ REJECTED 2560 Technology Drive#400 Plano, TX 75074 CONTRACT MODIFICATION REQUEST: PCM-04rev01 PROJECT: VILLAGE CREEK GRIT FACILITY DATE: 04/28/21 PROJECT NO. 100075 ATTENTION: CITY OF FORT WORTH 1000 THROCKMORTON STREET FORT WORTH, TX 76102 ATTN: FARIDA GODERYA Attention: The following change in contract on this project is proposed: A breakdown of cost SHALL be attached. Work shall not commence until authorized by the OWNER. Description of the Proposed Change & Clarifications Pricing for the following CDM PCM-004 To reduce the sizing of FAN-200-04 & 200-05, odor control ductwork connections, and electrical items. (1) Fan Size Reduction --- Credit of$5,400.00 Perry Fiberglass Base Bid Pricing was for a 13,000 CFM Fan (See attached) (2) Odor Control Ductwork Mods --- Credit of$ 2,300.00 (3) Electrical Mods --- Credit of$ 6,300.00 TOTAL AMOUNT 1 $ (14,000) Ryan Glanz Crescent All work shall be in accordance with the terms, stipulations, and conditions of the original Contract Documents. If the work herein provided for is Approved by Change Order,the time of completion will be: Increased By 0 Calendar Days Decreased Unchanged � ACCEPTED City of Fort Worth Date ❑ REJECTED