ir� Construction Allowance Request
ProjectNamel 2018 CIP Year 2,Contract 4 City Sec# 1 54691
Client Project#(s)l 101451
Project Water,Sanitary Sewer,Storm Water improvements followed by Paving Improvement on several streets In CD2
Description
Contractor Woody Contracting CA#F---T---] Datel 10115/2021
City Project Mgr.1 Maged Zak! City Inspectorl Tamara Vaughn
UNIT or DEPT Water Sewer TPW SW Totals Contract Time
CD
Original Contract Amount $2,192,478.60 $515,998.10 $3,771,541.00 $114,267. 0 — 6,594,285.30 540
Extras to Date $2,580.00 $2,580.00
Credits to Date
Current Contract Amount $2,195,058.60 $515,998.10 $3,771,541.00 $114,267.60 $6,596,865.30 540
Amount of Proposed Allocation To.00 o.o0 $3,274.40 $4,800.00 8 074.40
Original Allowance Available to Allocation $100,000.00 $30,000.00 $150,000.00 $20,000.00 300 000.00 540
Allowance Funds Previously Allocated $16,000.00 $7,000.00 $23,000.00
Revised Allowance Balance $84,000.00 $23,000.00 $146,725.60 $15,200.00 $268,925.60
JUSTIFICATION(REASONS)FOR CONSTRUCTION ALLOWANCE
This constriction allowance is required to to pay the contractor for reforming of curb and gutter forms that needed to be removed and adjusted to work with the ROW
elevation on Lincoln Ave between STA 13+50 to STA 15+50 and to add new bid items to remove and install 5'curb inlet on Houston street that were not in the original bid
items.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and
satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Construction
Allowance Request. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and
administration of this contract,including ensuring all performance and reporting requirements.
Contractors Company Name Contractor(Name) Contract Signature Date ;
Woody Contracting Troy Woody
Inspector/Inspection Supervsor Date Project and Contract Compliance Manager Date
Nov 1,2021 ���,�.��� Nov 1,2021
Program Manager Date Senior Capital Project Officer Date
. -! Nov 2,2021 lanC7tu M- Nov 3,2021
Assistant Director(Dept) Date Director,Contracting Department(Dept) Date
L.auuvn v✓vriv Nov 4,2021
Nov 4,2021
Assistant City Attomey Date Assistant City Manager Date
Nov 4,2021 ,Z7zha$;�y� Nov 4,2021
ATTEST:
A,O 00000000
Ronald Gonzales,Asst City Secretary o° o w
0
0�o oor�t�
000 0 0
0 0* d
0
o° o �
°OO°°°°o°° a OFFICIAL RECORD
�1 ��EXPS-oAp
CITY SECRETARY
FT. WORTH, TX
Construction Allowance SUMMARY
Page 1 of 4
FORTWORTH.> City of Fort Worth
Construction Allowance Additions
Project Name 2018 CIP Year 2,Contract 4 City Sec#
Client Project# 1 101451
Contractorl Woody Contracting PM Maged Zak! inspectorl Tamara Vaughn
Construction Allowance Submittal# 0 Date
ADDITIONS
ITEM DESCRIPTION DEPT city Unit Unit Cost Total
Unit 3-78 Reforming Curb and Gutter TPW 1.00000000 EA 3,2 44.40 $3,274.40
ni - Remove 5'uurb inlet
rn --ZT-5'Gurb Inlet
Water $0.00
Sewer $0.00
TPW $3,274.40
SW $4,800.00
Total Additions 6707 . 0
Construction Allowance Additions
Page 2 of 4
FORT WORTH. City of Fort Worth
Construction Allowance Value
Project Name 2 118 CIP Year 2,Contract 4 City Sec#
Client Project# 1 101451
Contractor Woody Contracting PMJ Maged Zaki 7 Inspector Tamara Vaughn
Construction Allowance Submittal# 0 Date
CONSTRUCTION ALLOWANCE VALUE BEING USED
ITEM DESCRIPTION Qty Unit Unit Cost Total
77 Unit 3-Constrcution Allowance 0.02 LS $150,000.00 $3,274.40
19 Unit 4-Constrcution Allowance 0.24 LS $20,000.00 $4.800.00
Note to Preparer. Delete example information in cells and add the CONSTRUCTION ALLOWANCE contract
bid item number being used,description,UNIT or DEPT,Qty,Unit and Unit Cost in the lines above.Three
lines are provided for those cases when up to 3 different Construction Allowance types are being impacted.In
most cases only one Construction Allowance type will be impacted.Delete these instructions from the form.
Construction Allowance Value
3of4
MISBE for this Construction Allowance Request
MISBE Sub Type of Service Amount for this CAR
Total $0.00
Previous Construction Allowance Requests
CAR# DATE AMOUNT
Total $0.00
Construction Allowance MSBE Data
Page 4 of 4
Contract Compliance Manager:
By signing,I acknowledge that I am the person
responsible for the monitoring and
administration of this contract,including
ensuring all performance and reporting
requirements.
Maged Zald
Project Manager.
Signature:
Email: Michelle.Hadley-McGhee@fortworthtexas.gov