HomeMy WebLinkAbout5. Update on 2014 and 2018 Bond ProgramUpdate on
2014 and 2018 Bond Programs
Presented to City Council
April 13, 2021
1
2
2014 Bond Program
Status Update
$219.7M
$31.4M
$12.7M
$9.3M
$1.5M
$15.1M
$2.4M
0 50 100 150 200 250
Prop 1:
Streets
Prop 2:
Parks
Prop 3:
Library
Prop 4:
Fire
Prop 5:
Court
Prop 6:
Facilities
Prop 7:
Animal Care
Millions
2014 Bond Program: Total Approved Funds = $292,121,100
75%
11%
4%
3%1%
5%
1%
3
$181.8M
$28.7M $35.8M
$37.9M
$2.8M $5.1M
$0
$50
$100
$150
$200
$250
Prop 1: Streets Prop 2: Parks Props 3-7: FacilitiesMillions
Committed Uncommitted
2014 Bond Program: Total Approved Funds = $292,121,100
$246.3M,
84%
$45.7M,
16%
4
Project
Total Project
Funds
April 2021
% Complete
May 2022
Projection
Como Community Center -Replacement $12,388,644 100%100%
Eugene McCray Community Center -Expansion $1,877,605 100%100%
Handley-Meadowbrook Community Center -Expansion $2,698,417 100%100%
Reby Cary Library (Eastside) -New $5,497,725 82%100%
Golden Triangle Library (Far North) -New $8,927,894 100%100%
Fire Station 42 (Spinks Airport) -New $5,398,468 100%100%
Fire Station 43 (Far West, Walsh) -New $6,200,000 11%80%
Municipal Court Facility -Renovation $2,650,000 100%100%
North Service Center -New $31,397,260 100%100%
Municipal Vehicle Maintenance Facility -New $8,042,818 100%100%
Second Animal Care and Control Design -New $1,303,000 100%100%
Silcox Animal Care and Control Facility -Expansion $1,303,900 100%100%
2014 Bond Program –Facility Project Status
5
6
Project Bond Funds
April 2021
% Complete
May 2022
Projection
Athletic Field Development $4,350,000 90%100%
Community Park Improvements $5,407,000 100%100%
Heritage Park Redevelopment $1,500,000 0%30%
McLeland Tennis Center $550,000 100%100%
Nature Center Levee $350,000 100%100%
Park Erosion Repair and Control $2,525,000 100%100%
Park Roads and Parking Lots $1,317,450 100%100%
Park Security Lighting $420,000 100%100%
Playgrounds $2,600,000 100%100%
Reserve Park Development $550,000 100%100%
Rockwood Golf Course $2,000,000 100%100%
Walks and Trails $1,900,000 100%100%
2014 Bond Program –Park Project Status
Remaining 2014 Bond Projects
2014 Bond Program –Street Project Status
8
2018 Bond Program
Status Update
$261.6M
$84.2M
$9.9M
$12.0M
$13.8M
$18.1M
0 50 100 150 200 250 300
Prop A:
Streets
Prop B:
Parks
Prop C:
Library
Prop D:
Fire
Prop E:
Animal Care
Prop F:
Police
Millions
2018 Bond Program: Total Approved Funds = $399,500,000
65%
21%
2%3%3%
5%
9
$123.8M
$39.1M
$17.7M
$137.8M
$45.0M
$36.0M
$0
$50
$100
$150
$200
$250
$300
Prop A: Streets Prop B: Parks Prop C-F: FacilitiesMillions
Committed Uncommitted
2018 Bond Program: Total Approved Funds = $399,500,000
$180.6M
45%$218.8M
55%
10
2018 Bond Program -Debt Issuance
Purpose
Amount
Authorized
Amount
Previously
Issued
2021 Amount
Being Issued
Unissued
Balance
Streets & Mobility Infrastructure $261,630,080 $105,000,000 $49,400,000 $107,230,185
Parks & Recreation 84,180,600 26,000,000 20,000,000 38,180,600
Library 9,868,500 --9,868,500
Fire Safety 11,975,820 4,000,000 -7,975,820
Animal Care and Shelter Facility 13,770,000 -13,770,000 -
Police Facility 18,075,000 15,000,000 -3,075,000
$399,500,000 $150,000,000 $83,170,000 $166,330,000
11
Fiscal
Year Completed/Plan
2019 $30,000,000
2020 $120,000,000
2021 $83,170,000
2022 $83,165,000
2023 $83,165,000
Totals $399,500,000
Project
Total Project
Funds
April 2021
% Complete
May 2022
Projection
Northwest Community Center -New $11,820,000 5%60%
Diamond Hill Community Center -Replacement $10,900,000 15%70%
Northside Community Center -Renovation $5,100,000 10%100%
Sycamore Community Center -Renovation $2,710,000 5%100%
Thomas Place Community Center -Acquisition $1,000,000 100%100%
Rockwood Clubhouse & Maint. Facility -Replacement $7,710,000 85%100%
Park Maintenance Facility –James Ave -Replacement $21,100,000 90%100%
Far Southwest Library -New $9,675,000 2%60%
Fire Station 26 (South Hulen) -Replacement $5,341,000 10%90%
Fire Station 45 (Harmon Road, near Hwy 287) -New $6,400,000 18%100%
North Animal Care and Shelter Facility -New $14,803,000 92%100%
South Police Station -New $17,720,000 16%85%
2018 Bond Program –Facility Project Status
12
Completed
14 Projects
Construction 10
Projects
Completed
2 Projects
Construction
6 Projects
Design
15 Projects
Planning
1 Projects
April 2021 Status
13
May 2022 Status
2018 Bond Program –Park Project Status
14
Project Funding Amount Projected
May 2022 Status
Community Parks
Alliance Community Park $3,000,000 Completed
Chisholm Trail Park $2,500,000 Completed
North Park $2,000,000 Completed
North Z Boaz $2,000,000 Construction
Marine Creek Ranch $3,000,000 Construction
Riverside Park $2,000,000 Completed
Neighborhood Parks
Deer Meadow $500,000 Completed
Kingsridge $600,000 Construction
Marine Creek Lake $500,000 Construction
McPherson Park $500,000 Completed
Parkwood East $300,000 Construction
Trail Lake Estates $450,000 Construction
Tim Watson $500,000 Construction
Vineyards at Heritage $410,000 Construction
2018 –Community Parks and Neighborhood Parks
Chisholm Trail Park –Skate Park
Alliance Park –Soccer Fields
15
Project Funding Amount Projected
May 2022 Status
Walks and Trails $7,500,000 Construction
Park Land Acquisition $3,500,000 Completed
Fort Worth Zoo -Utility
Infrastructure $1,339,000 Completed
Playground Equipment $750,000 Completed
Athletic Field Lighting $3,000,000 Completed
Erosion Repair and Control, and
Dam Restoration $661,000 Completed
Candleridge Park –Erosion Control
North Park –Playground Concept
2018 –Other Park Categories
2018 Bond Program –Street Project Status
16
2018 –Arterial Street Project Status
Projects Less Than 50% Complete by May 2022
17
2018 –Neighborhood Street Project Status
Projects Less Than 50% Complete by May 2022
(CD3)
(CD5)
(CD7)18
2018 –Mobility Infrastructure Project Status
•Intersections (Named Projects)
•Sidewalks/Bicycle Lanes
•Railroad Crossings
•Streetlights
•Traffic Signals
•Neighborhood/School Safety
•Bridge Rehabilitation
19
20
2018 –Intersection Project Status
Projects Less Than 50% Complete by May 2022
(TXDOT)
(TXDOT)
(TXDOT)
(TXDOT)
(TXDOT)
Street Program Challenges and Opportunities
2018 Bond Strategy and Challenges 2022 Bond Strategy
21
Design Phase
•Jump Start funds allocated primarily for feasibility and
scoping, not design initiation
•Projects scoped for interim improvements to provide
partial capacity or connectivity improvements that
were outpaced by development
•Specific infrastructure improvements, like
roundabouts, were specified prior to design
•Implemented limited alternative delivery methods,
such as Construction Manager At Risk (CMAR), in
addition to traditional Design-Bid-Build
Design Phase
•Begin design on select projects prior to
bond issuance
•Reduce design amendments by scoping
projects to full MTP
•Determine specific infrastructure
improvements through design process
•Continue using CMAR and utilize Design-
Build if appropriate
•Incentivize design consultants to expedite
design and hold accountable through
liquidated damages
Street Program Challenges and Opportunities (cont.)
22
Right of Way Acquisition Phase
•ROW acquisition started at 60%design phase
Utility Relocation Phase
•Utility relocation coordination started at 60%design
phase
•Limited City staff resources for utility coordination
•Limited City staff capability to verify utility relocation
Right of Way Acquisition Phase
•Begin ROW acquisition at 30% design phase
•Incorporate 2018 actual timelines for ROW
acquisition into future schedules
•Address ROW risk management in project
selection criteria
Utility Relocation Phase
•Begin utility coordination at 30%design
phase
•Incorporate utility relocation coordination
and verification into consultant contracts
2018 Bond Strategy and Challenges 2022 Bond Strategy
23
Questions?