Report to City Council
6 Month Progress
October 1, 2020 to March 31, 2021
Patrick Newman, CEO
2 of 24
Purpose of Presentation
2 of 24
3 of 24Purpose of Presentation
Provide a Six Month Progress Report on the Botanical Research
Institute of Texas managing the Botanic Garden, per Management
Agreement approved May 19, 2020, M&C 20-0347 (10/1/2020 fully
implemented)
Revenue and Participation
Programs
Master Plan Process
Capital Development Programs (2020 Tax Notes; 2022 Bond)
4 of 24
Revenue and Participation
4 of 24
5 of 24Key Metrics
Management Agreement Benchmarks:
•Growth in Attendance vs. City Fiscal Year 2020
•Minimum of 10% of total admission are free or reduced cost
•Growth in non-City funding versus City Fiscal Year 2020
•Increased participation in education, events, and volunteer programs vs. City
Fiscal Year 2020
6 of 24
74,796
99,237
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
FY 20 Oct-Mar Fy 21 Oct-Mar
Total ## of Guests
Botanic Garden Admission Year Over Year
FY 21 Forecast # guests
200,000
33% increase from
FY 20 to FY 21
7 of 24Botanic Garden Admission Year Over Year
FY 21 Forecast Revenue
$1,645,719
49% increase from
FY 20 to FY 21
8 of 24Accessibility & Reduced Admission: FY 2021
0
5000
10000
15000
October November December January February March Total
TOTAL Attendance: 99,237
TOTAL Free & Reduced: 9797
FY 21 to date = ~ 10%
9797
3620
395707
171117451619
Funding Streams vs. City Subsidy
•Subsidy has
decreased 6%
compared to FY
2020
•Largest difference
is increased
admission
•City contributions
fell as % of total
budget despite
increase in City
funding
59%
6%4%
8%
0%
23%
53%
7%
2%
6%3%
29%
0%
10%
20%
30%
40%
50%
60%
70%
City Subsidy Gift Shop Donations &
Foundations
Rentals Membership Admission
FY 20 compared with FY 21 Earned Revenue
+ Subsidy
FY20 FY21
9 of 24
10 of 24
Programs
10 of 24
11 of 24Class Attendance: October –March
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
FY 2018 FY 2019 FY 2020 FY 2021
Children & Families ES MS/HS Higher Ed Educators Community Ed
12 of 24
Capital Development
Programs
12 of 24
13 of 24Master Plan
Comprehensive study of joint campus and programs
Coordinates with campus-wide strategic plan to determine:
•Joint mission and vision
•Programmatic goals
•Feasibility
•Physical facilities
Two nationally recognized teams specializing in public garden/museum development under
consideration to facilitate that effort
Studio Outside –Dallas
Ten Eyck Landscape Architects -Austin
14 of 24Master Plan Steering Committee
Dennis Shingleton –
Chair
Bob Byers –Vice Chair
Ennis Anderson
John Avila
Ed Bass
Billy Brentlinger
Steve Brauer
Dana Burghdoff
Ralph Emerson
Leticia Esparza
Tracy Friday
Peter Fritsch
Craig Hamilton
Judy Koslow
LA Moncrief
Debbie Morrison
Patrick Newman
Elaine Petrus
Debbie Reynolds
Terry Siegel
Dan Villegas
Harvey Yamagata
Jing Yang
Richard Zavala
15 of 24FY 2020 Tax Note Program
Addresses $4.3MM of the $17 MM in City deferred maintenance obligations
4 projects and $253K in design work substantially complete
Project management split to expedite project completion
•PMD managing renovations/replacements of vertical improvements
•PARD & FWBG|BRIT managing utility and landscape projects
16 of 24Status: FY 2020 Tax Notes
$-
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
$3,500,000
Encumbered Expensed Unappropriated Funds
remaining
Change Since Q4
As of May 18, 2021
$327K
$751K
$3,222K
$297K
17 of 24FY 2020 Tax Notes –COMPLETED*
Design Fees $ 253,257
IT Upgrades $ 367,000
South Restrooms $ 33,068
Conservation Greenhouse Repairs $ 72,487
Fuller Garden Paving
Other Costs Remaining Projects
$ 62,463
$ 289,832
TOTAL completed $ 1,078,107 *Includes only Tax Notes
18 of 24
IT Upgrades -
$367,000
L: Boring machine
running to
connect to BG
R: First run from
ATT to BRIT
building
18 of 24
19 of 24
South
Restrooms -
$33,068
Fuller Garden
Paving -$62,463
19 of 24
20 of 24
Conservation Greenhouse
Repairs -$72,487
21 of 24FY 2020 Tax Notes –Remaining funds as of 5/18
Managed by BG/BRIT*Managed by PMD
Old Garden Rd Renovation $ 1,021,156 Moncrief Garden Center $ 209,010
Hill Arbor $ 15 Restaurant/Rock Springs $ 50,468
Rose Garden Fountains $ 195,179 Rose Shelter Stabilization $ 99,753
South Vista Drainage $ 432,240 Greenhouse Replacement $ 928,720
Full Moon Bridge $ 32,226
Site Amenities $ 94,080
Southwest Quadrant $ 366,230
TOTAL $2,141,126 TOTAL $1,287,951
*Includes Tax Notes and PayG
22 of 242022 Bond Request
Continues program to address $17MM in deferred maintenance
Focuses on infrastructure and related projects that do not present opportunities for significant private fund raising
while master plan is underway
Public funding $4.6MM, Private funding $3.575MM
Key elements:
•Improvements to education facilities and collections housing
•Pedestrian/guest service improvements
•Consolidation of operations
•Utilities/infrastructure
•Site preparation for Children’s Garden
•Professional services
23 of 242022 Bond Request Summary*
*Does not include private funds included in total project costs
PROJECT ESTIMATED COST
Professional Services $150,000
Infrastructure $274,000
Event/Guest Services $1,390,000
Facility Repair/Replacement $2,786,000
TOTAL $4,600,000
24 of 24
Questions?