HomeMy WebLinkAboutContract 54357-PM1PROJECT MANUAL
FOR
THE CONSTRUCTION OF
EVERMAN OFFSITE WASTEWATER EXTENSION
City Project No. 102550
IPRC No. 20-0011
FID No. 30114-0200431-102550-E07685
X-26335
Betsy Price David Cooke
Mayor City Manager
Christopher P. Harder, P.E.
Director, Water Department
David Johnson
Transportation and Public Works Department
Prepared for
The City of Fort Worth
PACHECO KOCH CONSULTING ENGINEERS, INC.
4060 BRYANT IRVIN ROAD
FORT WORTH, TX 76109
TX REG. ENGINEERING FIRM F-469
TX REG. SURVEYING FIRM LS-10008000
09/16/2020
CSC No. 54357-PM1
00 00 10
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised March 20, 2020
SECTION 00 00 10
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions Last Revised
00 11 13 Invitation to Bidders 03/20/2020
00 21 13 Instructions to Bidders 03/20/2020
00 41 00 Bid Form 04/02/2014
00 42 43 Proposal Form Unit Price 05/22/2019
00 43 13 Bid Bond 04/02/2014
00 45 11 Bidders Prequalification’s 04/02/2014
00 45 12 Prequalification Statement 09/01/2015
00 45 13 Bidder Prequalification Application 03/09/2020
00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014
00 45 40 Minority Business Enterprise Goal 08/21/2018
00 52 43 Agreement 06/16/2016
00 61 25 Certificate of Insurance 07/01/2011
00 62 13 Performance Bond 01/31/2012
00 62 14 Payment Bond 01/31/2012
00 62 19 Maintenance Bond 01/31/2012
00 72 00 General Conditions 11/15/2017
00 73 00 Supplementary Conditions 07/01/2011
00 73 10 Standard City Conditions of the Construction Contract for Developer
Awarded Projects 01/10/2013
Division 01 - General Requirements Last Revised
01 11 00 Summary of Work 12/20/2012
01 25 00 Substitution Procedures 08/30/2013
01 31 19 Preconstruction Meeting 08/30/2013
01 31 20 Project Meetings 07/01/2011
01 32 33 Preconstruction Video 08/30/2013
01 33 00 Submittals 08/30/2013
01 35 13 Special Project Procedures 08/30/2013
01 45 23 Testing and Inspection Services 03/20/2020
01 50 00 Temporary Facilities and Controls 07/01/2011
01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011
01 57 13 Storm Water Pollution Prevention Plan 07/01/2011
01 60 00 Product Requirements 03/20/2020
01 66 00 Product Storage and Handling Requirements 04/07/2014
01 70 00 Mobilization and Remobilization 04/07/2014
01 71 23 Construction Staking 04/07/2014
01 74 23 Cleaning 04/07/2014
01 77 19 Closeout Requirements 04/07/2014
01 78 23 Operation and Maintenance Data 04/07/2014
01 78 39 Project Record Documents 04/07/2014
00 00 10
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised March 20, 2020
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project’s Contract Documents
NONE
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City’s website at:
https://apps.fortworthtexas.gov/ProjectResources/
Division 02 - Existing Conditions Last Revised
02 41 13 Selective Site Demolition 12/20/2012
02 41 14 Utility Removal/Abandonment 12/20/2012
02 41 15 Paving Removal 02/02/2016
Division 03 - Concrete
03 30 00 Cast-In-Place Concrete 12/20/2012
03 34 13 Controlled Low Strength Material (CLSM)12/20/2012
03 34 16 Concrete Base Material for Trench Repair 12/20/2012
03 80 00 Modifications to Existing Concrete Structures 12/20/2012
Division 26 - Electrical
26 05 00 Common Work Results for Electrical 11/22/2013
26 05 10 Demolition for Electrical Systems 12/20/2012
26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012
26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011
26 05 50 Communications Multi-Duct Conduit 02/26/2016
Division 31 - Earthwork
31 10 00 Site Clearing 12/20/2012
31 23 16 Unclassified Excavation 01/28/2013
31 23 23 Borrow 01/28/2013
31 24 00 Embankments 01/28/2013
31 25 00 Erosion and Sediment Control 12/20/2012
31 36 00 Gabions 12/20/2012
31 37 00 Riprap 12/20/2012
Division 32 - Exterior Improvements
32 01 17 Permanent Asphalt Paving Repair 12/20/2012
32 01 18 Temporary Asphalt Paving Repair 12/20/2012
32 01 29 Concrete Paving Repair 12/20/2012
32 11 23 Flexible Base Courses 12/20/2012
32 11 29 Lime Treated Base Courses 12/20/2012
32 11 33 Cement Treated Base Courses 12/20/2012
32 11 37 Liquid Treated Soil Stabilizer 08/21/2015
32 12 16 Asphalt Paving 12/20/2012
32 12 73 Asphalt Paving Crack Sealants 12/20/2012
32 13 13 Concrete Paving 12/20/2012
00 00 10
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised March 20, 2020
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018
32 13 73 Concrete Paving Joint Sealants 12/20/2012
32 14 16 Brick Unit Paving 12/20/2012
32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016
32 17 23 Pavement Markings 11/22/2013
32 17 25 Curb Address Painting 11/04/2013
32 31 13 Chain Fences and Gates 12/20/2012
32 31 26 Wire Fences and Gates 12/20/2012
32 31 29 Wood Fences and Gates 12/20/2012
32 32 13 Cast-in-Place Concrete Retaining Walls 06/05/2018
32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012
32 92 13 Hydro-Mulching, Seeding, and Sodding 12/20/2012
32 93 43 Trees and Shrubs 12/20/2012
Division 33 - Utilities
33 01 30 Sewer and Manhole Testing 12/20/2012
33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016
33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012
33 04 10 Joint Bonding and Electrical Isolation 12/20/2012
33 04 11 Corrosion Control Test Stations 12/20/2012
33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012
33 04 30 Temporary Water Services 07/01/2011
33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013
33 04 50 Cleaning of Sewer Mains 12/20/2012
33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016
33 05 12 Water Line Lowering 12/20/2012
33 05 13 Frame, Cover and Grade Rings – Cast Iron 01/22/2016
33 05 13.10 Frame, Cover and Grade Rings – Composite 01/22/2016
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
Grade 12/20/2012
33 05 16 Concrete Water Vaults 12/20/2012
33 05 17 Concrete Collars 12/20/2012
33 05 20 Auger Boring 12/20/2012
33 05 21 Tunnel Liner Plate 12/20/2012
33 05 22 Steel Casing Pipe 12/20/2012
33 05 23 Hand Tunneling 12/20/2012
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013
33 05 26 Utility Markers/Locators 12/20/2012
33 05 30 Location of Existing Utilities 12/20/2012
33 11 05 Bolts, Nuts, and Gaskets 12/20/2012
33 11 10 Ductile Iron Pipe 12/20/2012
33 11 11 Ductile Iron Fittings 12/20/2012
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018
33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12/20/2012
33 11 14 Buried Steel Pipe and Fittings 12/20/2012
33 12 10 Water Services 1-inch to 2-inch 02/14/2017
33 12 11 Large Water Meters 12/20/2012
33 12 20 Resilient Seated Gate Valve 12/20/2012
33 12 21 AWWA Rubber-Seated Butterfly Valves 12/20/2012
00 00 10
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised March 20, 2020
33 12 25 Connection to Existing Water Mains 02/06/2013
33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012
33 12 40 Fire Hydrants 01/03/2014
33 12 50 Water Sample Stations 12/20/2012
33 12 60 Standard Blow-off Valve Assembly 06/19/2013
33 31 12 Cured in Place Pipe (CIPP)12/20/2012
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012
33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer
Pipe 12/20/2012
33 31 22 Sanitary Sewer Slip Lining 12/20/2012
33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012
33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012
33 39 10 Cast-in-Place Concrete Manholes 12/20/2012
33 39 20 Precast Concrete Manholes 12/20/2012
33 39 30 Fiberglass Manholes 12/20/2012
33 39 40 Wastewater Access Chamber (WAC)12/20/2012
33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011
33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012
33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015
33 46 00 Subdrainage 12/20/2012
33 46 01 Slotted Storm Drains 07/01/2011
33 46 02 Trench Drains 07/01/2011
33 49 10 Cast-in-Place Manholes and Junction Boxes 12/20/2012
33 49 20 Curb and Drop Inlets 12/20/2012
33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011
Division 34 - Transportation
34 41 10 Traffic Signals 10/12/2015
34 41 10.01 Attachment A – Controller Cabinet 12/18/2015
34 41 10.02 Attachment B – Controller Specification 02/2012
34 41 10.03 Attachment C – Software Specification 01/2012
34 41 11 Temporary Traffic Signals 11/22/2013
34 41 13 Removing Traffic Signals 12/20/2012
34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013
34 41 16 Pedestrian Hybrid Signal 11/22/2013
34 41 20 Roadway Illumination Assemblies 12/20/2012
34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015
34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015
34 41 20.03 Residential LED Roadway Luminaires 06/15/2015
34 41 30 Aluminum Signs 11/12/2013
34 41 50 Single-Mode Fiber Optic Cable 02/26/2016
34 71 13 Traffic Control 11/22/2013
00 00 10
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 5 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised March 20, 2020
Appendix
GC-4.01 Availability of Lands
GC-4.02 Subsurface and Physical Conditions
GC-4.04 Underground Facilities
GC-4.06 Hazardous Environmental Condition at Site
GC-6.06.D Minority and Women Owned Business Enterprise Compliance
GC-6.07 Wage Rates
GC-6.09 Permits and Utilities
GC-6.24 Nondiscrimination
GR-01 60 00 Product Requirements
END OF SECTION
ao �z a�
DAP-BN �ROI'OSAL
PaSx 2 of]
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
CI"I Y OF PORi NORiH
STANDilliD CONS'1'RUCTION SI'ECR�'ICATfON DOCUAIENiS -DEVELOPGRA\YeVtDLD PROIGCSS
Poem Vcrsion ivlay 22, 2019 0042 J3_Hid Proposel_�AY
UNIT PRICE BID Bidder's Application
Kyle Marsh
oo�s iz
UAP �2EQUALIfiCAT10N STATEMEN f
Page I of I
S�CTION 00 45 12
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize For the major work type(s) listed. In the "Major Work
Tvoe" box provide the comolete maior work tvne and actual descriotion as uiovided by the Water
Denartment for water and sewer and TPW for oavine
BIDDER:
Wright Construction Co.,Inc.
601 W. Wall St.
Grapevine, Texas 76051
DATE: �
�ND Or SECTION
CIttOF FORi WORTH
STAN�AR�CONSiRUCTIONPREQUNL�FIUTIONSiATEMENT—DEVELOPEPNWAROE�Pf(OIECiS 000512 Piequalification5ta[ement2015 DAP
Fo�m Version Se�[embe� 1, 2�35 — —
The undersigned liereby certifies that the contracfors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
004526-1
1
2
3
CONTftACfOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Page 1 of 2
SECTION 00 45 26
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
4 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it
5 provides worl<er's compensation insurance coverage for all of its employees employed on City
6 Project No. 102550. Contractor further certifies that, pursuant to Texas Labor Code, Section
7 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with
8 worker's compensation coverage.
F�
10 CONTRACTOR:
11
12
13
14
15
16
17
18
19
20
Z1
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Wright Construction Co., Inc.
Company
601 W. Wall St.
Address
Grapevine Texas 76051
City/State/Zip
THE STATE OF TEXAS §
COUNTY OF TARRANT §
Kyle Marsh
By:
. _�
(Please Pri
/
Signature:
Title:
(Please Print)
BEFORE ME, the undersigned authority, on this day personally appeared
Kyle Marsh , known to me to be the person whose name is
subscribed to the foregoing instrument, and acknowledged to me that he/she executed the
same as the act and deed of President/ Wright Construction Co., Inc. for the purposes and
consideration therein expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this
J u ly 20 _
1����_ �= _'�
r oa � Deb C>onald on
�� � N 1 y P blic, Stal of Teras
"�; ��:;,*` Ccinm. E�cpires O1RA2o21
���w'F'c��i" NotarylD 11�J70986
a—�,-��-r�--.s ua-..»v�.
President
of
CITY OF FORT WORTH EVERMANOFFSITEWASTEWATER EA7ENSION
STANDARD CONSTRUCTION SPEqFICAT10N DOCUMENTS 102550
Revised April 2, 2014
0o as ze - z
CONTRACTOR COMPLIANCE WITH WORKERS COMPENSATION LAW
Page 2 of 2
.,t=_ =r"Q'�-s-
. z,z-_:�v==a;�
1 i� Deb Do�ald on
Z �� �� ���_ �o��ry public, Stale of Teras
( � t,� ,, C n m. f-XPires 011241?.021
3 '.i >>e _Fsr�� IaotarylU
11970966
� , <. . ����� �..
{.s::�:,'.;,..,��;��c �_
�� �� �
Notary Public in and for the State of Texas
4 END OF SECTION
qTYOF FORT WORTH
STANDARD CONSTRUCTION SPEqFICATION DO W MENTS
Revised April 2, 2014
EVERMAN OFFSITE WASTEWATER EX7ENSION
102550
oosza3-i
Developer Awarded Proiect Agreement
Page 1 ot 6
1
2
SECTION 00 52 43
AGREEMENT
3 THIS AGREEMENT, authorized on October 10, 2019 is made by and between the Developer,
4 TCRG Opportunity VII, LLC, authorized to do business in Texas ("Developer') , and Wright
S Construction Co., Inc, authorized to do business in Texas, acting by and through its duly
6 authorized representative, ("Contractor").
7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree
8 as follows:
9 Article 1. WORK
10 Contractor shall complete aIl Work as specified or indicated in the Contract Documents for the
il Project identified herein.
12 Article 2. PROJECT
13 The project for which the Work under the Contrect Documents may be the whole or only a part
14 is generally described as follows:
15 EVfRMAN OFFSITE WASTEWATER EMENSION
16 CPN 102550
17 Article 3. CONTRACT TIME
18 3.1 Time is of the essence.
19 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract
20 Documents are of the essence to this Contract.
21 3.2 Final Acceptance.
7-� The Work will be complete for final Acceptance within 90 working days after the date
23 when the Contract Time commences to run as provided in Paragraph 12.04 of the
24 Standard City Conditions of the Construction Contract for Developer Awarded Projects.
25 3.3 Liquidated damages
26 Contractor recognizes that time is of the essence of this Agreement and that Developer
Z7 will suffer financial loss if the Work is not completed within the times specified in
28 Paregraph 3.2 above, plus any extension thereof allowed in accordance with Article 10
29 of the Standard City Conditions of the Construction Contract for Developer Awarded
30 Projects. The Contractor also recognizes the delays, expense and difficulties involved in
CITV OF FORT WORTH EVERMANOFFSlTEWASTEWATfR EXTENSION
SfANDARD CONST0.URION SPECIFICATION DOCUMENTS—DEVELOPER AWARDE� PROIECTS 102550
Revised lune 16, 2016
005243-2
Developer Awarded Project Agreement
Page 2 of 6
31 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not
3Z completed on time. Accordingly, instead of requiring any such proof , Contractor agrees
33 that as liquidated damages for delay (but not as a penalty), Contractor shall pay
34 Developer Zero Dollars ($0.00) for each day that expires after the time specified in
35 Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of Acceptance.
36 Article 4. CONTRACT pRICE
37 Developer agrees to pay Contractor for performance of the Work in accordance with the
38 Contract Documents an amount in current funds of Three Hundred Ninetv-Five Thousand Nine
39 Hundred and Ninetv-Three Dollars ($ 395 993 00).
40 Article 5. CONTRACT DOCUMENTS
41 5.1 CONTENTS:
G2 A. The Contract Documents which comprise the entire agreement 6etween Developer
43 and Contractor concerning the Work consist of the following:
44 1. This Ag�eement.
45 2. Attachments to this Agreement:
46 a. Bid Form (As provided by Developer)
47 1) Proposal Form (DAP Version)
48 2j Prequalification Statement
49 3) State and Federal documentr (project specific)
50 b. Insurance ACORD Form(s)
51 c. Payment Bond (DAP Version)
52 d. Performance Bond (DAP Versionj
53 e. Maintenance Bond (DAP Version)
54 f. Power of Attorney for the Bonds
55 g. Worker's Compensation Affidavit
56 h. MBE and/or 58E Commitment Form (If required)
5? 3. Standard City General Conditions of the Construdion Contract for Developer
58 Awarded Projects.
59 4. Supplementary Conditions.
CITY OF FORT W ORTH EVEFMAN OFFS/TEWASTfWATER EXrEN510N
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPEft AWARDED PROIECTS 501550
Revised June 16, 2016
005243-3
Developer Awarded Project Agreement
Page 3 of 6
60 5. Specifications specifically made a part of the Contract Documents by attachment
61 or, if not attached, as incorporated by reference and described in the Table of
6z Contents of the ProjecYs Contract Documents.
63 6. Drawings.
64 7. qddenda.
65 8. Documentation submitted by Contractor prior to Notice of Award.
66 9. The following which may be delivered or issued after the Effective Date of the
67 Agreement and, if issued, 6ecome an incorporeted part of the Contract
68 Documents:
69 a. Notice to Proceed.
70 b. Field Orders.
�1 c. Change Orders.
�Z d. Letter of Final Acceptance.
73
74
Ct1V OF fORT WORTH EVEFMANOFFSfTEWASTEWATER EXTENSION
STANDARD CONSfkUCTION SPECIFICATION DOCUMENTS— DEVEIOPER AWAADED PROJECTS 702550
Revised lune 16, 2016
005243-4
Developer AWarded ProJect Agreement
Page 4 of 6
%$
76
77
78
79
80
�1
82
83
84
85
86
87
88
89
90
91
92
93
oq
95
96
97
98
99
100
101
102
103
104
105
106
Article 6. INDEMNIFICATION
6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
expense, the city, its officers, servants and employees, from and against any and all
clafms arising out of, or alleged to arise out of, the work and services to be performed by
the contractor, its officers, agents, employees, subcontractors, licenses or invitees under
this contrect. This indemnification orovision is soecificallv intended to ooerete and be
effective even if it is alleeed or oroven that all or some of the dama¢es beine sou¢ht
were caused. in whole or in oart bv anv act omission or necli¢ence of the ciri. This
indemnity provision is intended to include, without limitation, indemnity for costs,
expenses and legal fees incurred by the city in defending against such claims and causes
of actions.
6,2 Contrector covenants and agrees to indemnify and hold harmless, at its own expense,
the city, its officers, servants and employees, from and against any and all loss, damage
or destruction of property of the city, arising out of, or alleged to arise out of, the work
and services to be performed by the contractor, its officers, agents, employees,
subcontreaors, Iicensees or invitees under this contrect. This indemnification orovision
is soecificallv intended to ooerete and be effective even if it is alleeed or oroven that all
or some of the damaees bein¢ sou¢ht were caused in whole or in oart bv anv act
omission or ne¢li¢ence of the citv
Article 7. MIS�ELLANEOUS
7.1 Terms.
Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of
the Construction Contrect for Developer Awarded Projects.
7.2 Assignment of Contract.
This Agreement, including all of the Contract Documents may not be assigned by the
Contractor without the advanced express written consent of the Developer.
73 Successors and Assigns.
Developer and Contractor each binds itself, its partners, successors, assigns and legal
representatives to the other party hereto, in respect to alI covenants, agreements and
obligations contained in the Contract Documents.
CIiY OF FORT WORTH EVERMANOFFSIT£ WASiEWATfR EATENSlON
STANDARD CONS7ftURION SPECIFIC4TIDN DOCUMEN7S—DEVELOPERAWARDED PROJERS 107550
Revised June 16, 20i6
005243-5
Developer Awarded Pmject Agreemem
Page 5 of 6
�i�%
108
109
110
!11
7.4 Severability.
Any provision or part of the Contract Documents held to be unconstitutional, void or
unenforceable by a court of competent jurisdidion shall be deemed stricken, and all
remaining provisions shall continue to be valid and binding upon DEVELOPER and
CONTRACTOR.
112 7.5 Governing Law and Venue.
113 This Agreement, including all of the Contract Documents is performable in the State of
114 Texas. Venue shall 6e Tarrent County, Texas, or the United States District Court for the
115 Northern District of Texas, Fort Worth Division.
116
117 7.6 Authority to Sign.
118
119
120
121
122
123
124
125
Contrector shall attach evidence of authority to sign Agreement, if other than duly
authorized signatory of the Contractor.
IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple
counterparts.
This Agreement is effective as of the last date signed by the Parties ("Effective Date"�.
Contrector:
Wriqht
By:
(Signature)
Co,
Developer:
CITV OF FORT WOA7H EVfFMAN OFF5/7E WASTEWATfR FX7ENSION
STANDqRD CONSfRUQION SVEGfIfATIDN DOCUMEN75 — DEVELOPER AWAftDED PROIECTS 102550
Revised lune 16, 2016
TCRG Oppo=tunity VZI, LLC
005243-6
DeveloperAwarded ProJectAgreement
Page 6 of fi
126
Ryle Marsh
(Printed Name)
Title: president
CompanyName:�=iqne Conatruction Co,
INC
Address: 601 w wa11 st
City/State/Zip: Grapevine TX 76051
il/03/2020
Date
Robert L Patton, Jr
(Printed Name)
Title: t9anaqer
Companyname: TcxG opportunity vzi, LLC
Address: 5201 camp Powie slva �200
City/State/Zip: Fort worth Tx 76107
I1/03/2020
Date
CITY OF fORT WO1tTH EVERMAN OFFSITE WASTEWAiFR EXTENSION
STANDARO CONSTFtUC110N SPECIFICATIDN DOCUMEMS—DEVELOPER AWARDED PROJECTS IOI550
Revlsed June 16, 2016
Policy Number: C05G29737A
COMMERCIAL GENERAL LIABILITY
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
XTEND ENDORSEMENT FOR CONTRACTORS
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
GENERAL DESCRIPTION OF COVERAGE — This endorsement broadens coverage. However, coverage for any
injury, damage or medical e�enses described in any of the provisions of this endorsement may be excluded or
limited by another endorsement to this Coverage Part, and these coverage broadening provisions do not apply to
the extent that coverage is excluded or limited by such an endorsement. The following listing is a general
coverage description only. Read all the provisions of this endorsement and the rest of your policy carefully to
determine rights, duties, and what is and is not covered.
A. WholsAn Insured—Unnamed Subsidiaries
B. Blanket Additional Insured — Governmental
Entities — Permits Or Authorizations Relating To
Operations
C. Incidental Medical Malpractice
D. Blanket Waiver Of Subrogation
E. Contradual Liability—Railroads
F. Damage To Premises Rented To You
PROVISIONS a. An organization other than a partnership, joint
A. WHO IS AN INSURED — UNNAMED venture or limited liability company; or
SUBSIDIARIES b. A trust;
The following is added to SECTION II — WHO IS as indicated in its name or the documents that
AN INSURED: gavern its structure.
Any of your subsidiaries, other than a partnership, g, gLANKET ADDITIONAL INSURED —
joint venture or limited liability company, that is GOVERNMENTAL ENTITIES — PERMITS OR
not shown as a Named Insured in the AUTHORQATIONSRELATINGTOOPERATIONS
Declarations is a Named Insured if:
a. You are the sole owner of, or maintain an
ownership interest of more than 50 % in, such
subsidiary on the first day of the policy period;
and
b. Such subsidiary is not an insured under
similar otherinsurance.
No such subsidiary is an insured for "bodily injury'
or "property damage" that occurred, or "personal
and advertising injury" caused by an offense
committed:
a. Before you maintained an ownership interest
of more than 50 % in such subsidiary; or
The following is added to SECTION II — WHO IS
AN INSURED:
Any governmental entity that has issued a permit
or authorization with respect to operations
performed by you or on your behalf and that you
are required by any ordinance, law, building code
or written contract or agreement to include as an
additional insured on this Coverage Part is an
insured, but only with respect to liability for "bodily
injury", "property damage" or "personal and
advertising injury" arising out of such operations.
The insurance provided to such governmental
entity does not apply to:
b. After the date, if any, during the policy period a. Any "bodily injury', "property damage" or
that you no longer maintain an ownership "personal and advertising injury" arising out of
interest of more than 50 % in such subsidiary. operations performed for the governmental
For purposes of Paragraph 1. of Section II — Who entity; or
Is An Insured, each such subsidiary will be b. Any "bodily injury' or "property damage"
deemed to be designated in the Declarations as: included in the "products-completed
operations hazard".
CG D3 '� 6 02 19 Oo 2017 The Travelers Indemniry Company. All rights resen,ed. Page 1 of 3
Includes copyrigh[ed material o( Insurance Services Office, Ina, with its permission.
COMMERCIAL GENERAL LIABILITY
C. INCIDENTAL MEDICAL MALPRACTICE
1. The following replaces Paragraph b. of the
definition of "occurrence" in the
DEFINfTIONS Section:
b. An act or omission committed in providing
or failing to provide "incidental medical
services", first aid or "Good Samaritan
services" to a person, unless you are in
the business or occupation of providing
professional health care services.
2. The following replaces the last paragraph of
Paragraph 2.a.(1) of SECTION II — WHO IS
AN INSURED:
3.
4.
Unless you are in the business or occupation
of providing professional health care services,
Paragraphs (1)(a), (b), (c) and (d) above do
not apply to "bodily injury" arising out of
providing orfailing to provide:
(a) "Incidental medical services" by any of
your "employees" who is a nurse, nurse
assistant, emergency medical technician
or paramedic; or
(b) First aid or "Good Samaritan services" by
any of your "employees" or "volunteer
workers", other than an employed or
volunteer doctor. Any such "employees"
or "volunteer workers" providing or failing
to provide first aid or "Good Samaritan
services" during their work hours for you
will be deemed to be acting within the
scope of their employment by you or
performing duties related to the conduct
of your business.
The following replaces the last sentence of
Paragraph 5. of SECTION III — LIMITS OF
INSURANCE:
For the purposes of determining the
applicable Each Occurrence Limit, all related
acts or omissions committed in providing or
failing to provide "incidental medical
services", first aid or "Good Samaritan
services" to any one person will be deemed to
be one "occurrence".
The following exclusion is added to
Paragraph 2., Exclusions, of SECTION I—
COVERAGES — COVERAGE A — BODILY
INJURY AND PROPERTY DAMAGE
LIABILffY:
Sale Of Pharmaceuticals
"Bodily injury' or "property damage" arising
out of the violation of a penal statute or
ordinance relating to the sale of
pharmaceuticals committed by, or with the
knowledge or consent of, the insured.
5. The following is added to the DEFINI7'IONS
Section:
"Incidental medical services" means:
a. Medical, surgical, dental, laboratory, x-ray
or nursing service or treatment, advice or
instruction, or the related furnishing of
food or beverages; or
b. The furnishing or dispensing of drugs or
medical, dental, or surgical supplies or
appliances.
6. The following is added to Paragraph 4.b.,
Excess Insurance, of SECTION IV —
COMMERCIAL GENERAL LIABILITY
CONDffIONS:
This insurance is excess over any valid and
collectible other insurance, whether primary,
excess, contingent or on any other basis, that
is available to any of your "employees" for
"bodily injury" that arises out of providing or
failing to provide "incidental medical services"
to any person to the extent not subjed to
Paragraph 2.a.(1) of Section II — Who Is An
Insured.
D. BLANKET WAIVER OF SUBROGATION
The following is added to Paragraph 8., Transfer
Of Rights Of Recovery Against Others To Us,
of SECTION IV — COMMERCIAL GENERAL
LIABILffY CONDffIONS:
If the insured has agreed in a contract or
agreement to waive that insured's right of
recovery against any person or organization, we
waive our right of recovery against such person or
organization, but only for payments we make
because of:
a. "Bodily injury" or "property damage" that
occurs; or
b. "Personal and advertising injury" caused by
an offense that is committed;
subsequent to the execution of the contract or
agreement.
E. CONTRACTUALLIABILITY—RAILROADS
1. The following replaces Paragraph c. of the
definition of "insured contract" in the
DEFINfTIONS Section:
c. Any easement or license agreement;
Pa9B 2 of 3 OO 2017 The Travelers Indermity Company. All rights resen.Ed. CG D$ 'I B OZ 'I9
Includes copyrighted material of Insurance Services Office, Inc., with its permis�on.
COMMERCIAL GENERAL LIABILITY
l
2. Paragraph f.(1) of the defnition of "insured
contracY' in the DEFINITIONS Section is
deleted.
F. DAMAGE TO PREMISES RENTED TO YOU
The following replaces the definition of "premises
damage" in the DEFINITIONS Section:
"Premises damage" means "property damage" to:
a. Any premises while rented to you or
temporarily occupied by you with permission
of the owner; or
b. The contents of any premises while such
premises is rented to you, if you rent such
premises for a period of seven or fewer
consecutive days.
CG D3 16 02 19 OO 2017 The Travelers Indemnily Company. All rights reserved. P898 3 of 3
Includes copyrighted material of Insurance Services Office, Inc., wi[h its permisson.
Policy Number: C05G29737A
COMMERCIAL GENERAL LIABILITY
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
BLANKET ADDITIONAL INSURED - AUTOMATIC STATUS
IF REQUIRED BY WRITTEN CONTRACT (CONTRACTORS)
This endorsement modifies insurance provided underthe following:
COMMERCIAL GENERAL LIABILITYCOVERAGE PART
The following is added to SECTION II — WHO IS AN
INSURED:
Any person or organization that:
a. You agree in a written contract or agreement to
include as an additional insured on this Coverage
Part; and
b. Has not been added as an additional insured for
the same project by attachment of an endors�
ment under this Coverage Part which includes
such person or organization in the endorsemenYs
schedule;
is an insured, but:
a. Only with respect to liability for "bodily injury" or
"property damage" that occurs, or for "personal
injury' caused by an offense that is committed,
subsequent to the signing of that contract or
agreement and while that part of the contract or
agreement is in effect; and
b. Only as described in Paragraph (1), (2) or (3) be�
low, whichever applies:
(1) If the written contract or agreement specifical-
ly requires you to provide additional insured
coverage to that person or organization by
the use of:
(a) The Additional Insured — Owners, Les-
sees or Contractors —(Form B) endorse-
ment CG 20 10 11 85; or
(b) Either or both of the following: the Addi-
tional Insured — Owners, Lessees or Con-
tractors — Scheduled Person Or Organi-
zation endorsement CG 20 10 10 01, or
the Additional Insured — Owners, Lessees
or Contractors — Completed Operations
endorsement CG 20 37 10 01;
(a) The Additional Insured — Owners, Les-
sees or Contractors — Scheduled Person
or Organization endorsement CG 20 10
07 04 or CG 20 10 04 13, the Additional
Insured — Owners, Lessees or Contrac-
tors — Completed Operations endorse-
ment CG 20 37 07 04 or CG 20 37 04 13,
or both of such endorsements with either
of those edition dates; or
(b) Either or both of the following: the Addi-
tional Insured — Owners, Lessees or Con-
tractors — Scheduled Person Or Organi-
zation endorsement CG 20 10, or the Ad-
ditional Insured — Owners, Lessees or
Contractors — Completed Operations en-
dorsement CG 20 37, without an edition
date of such endorsement specified;
the person or organization is an additional in-
sured only if the injury or damage is caused,
in whole or in part, by acts or omissions of
you or your subcontractor in the performance
of "your work" to which the written contract or
agreement applies; or
(3) If neither Paragraph (1) nor (2) above applies:
(a) The person or organization is an addi-
tional insured only if, and to the eMent
that, the injury or damage is caused by
ac[s or omissions of you or your subcon-
tractor in the performance of "your work"
to which the written contract or agree-
mentapplies; and
(b) Such person or organization does not
qualify as an additional insured with re-
spect to the independent acts or omis-
sions of such person or organization.
the person or organization is an additional in- The insurance provided to such additional insured is
sured only if the injury or damage arises out subject to the following provisions:
of "your work" to which the written contract or a. If the Limits of Insurance of this Coverage Part
agreement applies; shown in the Declarations exceed the minimum
(2) If the written contract or agreement specifical- limits required by the written contract or agree-
ly requires you to provide additional insured ment, the insurance provided to the additional in-
coverage to that person or organization by sured will be limited to such minimum required
the use of: limits. For the purposes of determining whether
CG D6 04 02 19 �O 2017 The Travelers Indemnity Company. All rights reserved. Page 1 of 2
COMMERCIAL GENERAL LIABILITY
b.
c.
this limitation applies, the minimum limits required
by the written contract or agreement will be con-
sidered to include the minimum limits of any Um-
brella or Excess liability coverage required for the
additional insured by that written contract or
agreement. This provision will not increase the
limits of insurance described in Section III — Limits
Oflnsurance.
The insurance provided to such additional insured
does not apply to:
(1) Any "bodily injury', "property damage" or
"personal injury" arising out of the providing,
or failure to provide, any professional archi-
tectural, engineering or surveying services,
including:
(a) The preparing, approving, or failing to
prepare or approve, maps, shop draw-
ings, opinions, reports, surveys, field ory
ders or change orders, or the preparing,
approving, or failing to prepare or ap-
prove, drawings and specifcations; and
(b) Supervisory, inspection, architectural or
engineering ac[ivities.
(2) Any "bodily injury' or "property damage"
caused by "your work" and included in the
"products-completed operations hazard" un-
less the written contract or agreement specifi-
cally requires you to provide such coverage
for that additional insured during the policy
period.
The additional insured must comply with the fol-
lowing duties:
(1) Give us written notice as soon as practicable
of an "occurrence" or an offense which may
result in a claim. To the extent possible, such
notice should include:
(a) How, when and where the "occurrence"
or offense took place;
(b) The names and addresses of any injured
persons and witnesses; and
(c) The nature and location of any injury or
damage arising out of the "occurrence" or
offense.
(2) If a claim is made or "suiY' is brought against
the additional insured:
(a) Immediately record the specifics of the
claim or "suiY' and the date received; and
(b) Notify us as soon as practicable and see
to it that we receive written notice of the
claim or "suiY' as soon as practicable.
(3) Immediately send us copies of all legal pa-
pers received in connection with the claim or
"suiY', cooperate with us in the investigation
or settlement of the claim or defense against
the "suiY', and otherwise comply with all policy
conditions.
(4) Tender the defense and indemnity of any
claim or "suiY' to any provider of other insur-
ance which would cover such additional in-
sured for a loss we cover. However, this con-
dition does not affect whether the insurance
provided to such additional insured is primary
to other insurance available to such additional
insured which coversthat person or organiza-
tion as a named insured as described in Par-
agraph 4., Other Insurance, of Section N—
Commercial General Liability Conditions.
Page 2 of 2 OO 2017 The Travelers IndemnityCompany. All rights reser�.ed. CG DB O4 OZ 'I J
COMMERCIAL GENERAL LIABILITY
POLICY NUMBER: Co5G29737A
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY
DESIGNATED PROJECT(S)
GENERAL AGGREGATE LIMIT
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIA8ILITY COVERAGE PART
SCHEDULE
Designated Project(s):
EACH "PROJECT" FOR WHICH YOU HAVE AGREED, IN
A WRITTEN CONTRACT WHICH IS IN EFFCCT DURING
THIS POLICY PEAIOD, TO PROVIDE A SEPARATE
GENERAL AGGREGATE LIMIT; PROVIDED THAT THE
CONTRACT IS SIGNED AND E}CECUTED BY YOU
BEFORE THE "BODILY INJURY" OR "PROPERTY
DAMAGE" OCCURS.
A. For all sums which lhe insured becomes legally
obligaled !o pay as damages caused by "occur-
rences" under COVERAGE A. (SECTION I), and
for all medical expenses caused by accidents un-
der COVERAGE C(SECTION I), which can be
attribuled only lo operalions at a single desig-
naled "projecC' shown in the Schedule above:
3,
Designated Project
General Aggregate�s):
GENERAL AGGREGATE
LIMIT SHOWN ON
DECLARATIONS.
Any paymenls made under COVERAGE A.
for damages or under COVERAGE C. for
medical expenses shall reduce lhe Desig-
nated Project General Aggregale Limit for
that designated "projecP'. Such payments
shall not reduce fhe General Aggregale Limit
shown in the Declarations nor shall they re-
duce any other Designated Project General
Aggregate Limit for any other designated
"projecC' shown in lhe Schedule above.
The limits shown in lhe Declarations for Each
Occurrence, Damage To Premises Rented
To You and Medical Expense continue to
apply. However, inslead of being subject to
the General Aggregale Limit shown in the
Declaretions, such limits will be subject to the
applicable Designated Project General Ag-
gregate Limit.
1. A separate Designated Project General Ag-
gregate Limit applies lo each designaled "pro-
jecC', and that limit is equal lo the amount of
the General Aggregale Limit shown in lhe 4.
Declaretions, unless separate �esignated
Project General Aggregate(s) are sched-
uled above.
2. The Designated Project General Aggregale
Limi[ is ihe most we will pay for the sum of all
damages under COVERAGE A., except
damages because of "bodily injury" or "prop-
erty damage" included in the "producls-
completed operations hazard", and for medi-
cal expenses under COVERAGE C, regard-
less of the number of:
a. Insureds;
�
c.
Claims made or "suits" brought; or
Persons or organizalions making claims
or bringin9 "suits". �
B. For all sums which ihe insured becomes legally
obligated to pay as damages caused by "occur-
rences" under COVERAGE A. (SECTION Ij, and
for all medical expenses caused by accidents un-
der COVERAGE C. (SECTION I), which cannot
be attribuled onry to operetions at a single desig-
natetl "project" shown in the Schedule above:
CG D2 11 01 04 Copyright, The Travelers Indemnity Company, 2004 Page 1 of Z
COMMERCIAL GENERAL LIABILITY
1. Any payments made under COVERAGE A.
for damages or under COVERAGE C. for
medical expenses shall reduce the amounl
available under the General Aggregate Limit
or the Products-Completed Operations Ag-
gregale Limit, whichever is applicable; and
2. Such payments shall not reduce any Desig-
nated Projecl General Aggregate Limit.
C. Parl 2. of SECTION III — LIMITS OF INSURANCE
is deleted and replaced by the following:
2. The General Aggregate Limil is lhe most we
will pay for the sum of:
a. Damages under Coverage B; and
b. Damages from "occurrences" under
COVERAGE A(SECTION I) and for all
medical expenses caused by accidenis
under COVERAGE C(SECTION I) which
cannol be attributed onty to operations at
a single designated "projecC' shown in the
SCHEDULE above.
D. When coverage for liability arising oul of the
"produds-completed operations hazard" is pro-
vided, any paymenis for damages because of
"bodily injury" or "properry damage" included in
lhe "products-completed operations hazard" will
reduce the Products-Completed Operations Ag-
gregate Limit, and not reduce the General Aggre-
gate Limil nor the Designated Projecl General
Aggregate Limit.
E. For lhe purposes of this endorsement the Defini-
tions Section is amended by lhe addition of lhe
following definiUon:
'ProjecC' means an area away from premises
owned by or rented to you al which you are per-
forming operations pursuant to a contract or
agreement. For the purposes of determining the
applicable aggregate limil of insurance, each
"projecC' that includes premises involving lhe
same or connecting lols, or premises whose con-
nection is interrupted only by a street, roadway,
watenvay or right-of-way of a railroad shall be
considered a single "project".
F. The provisions of SECTION III — LIMITS OF
INSURANCE nol otherwise modified by this en-
dorsement shall wntinue to appty as stipulaled.
Page 2 of 2 Copyright, The Travelers Indemniry Company, 2004 CG D2 11 01 04
POLICY NUMBER: C05G29737A
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
DESIGNATED ENTITY - NOTICE OF
CANCELLATION PROVIDED BY US
�
This endorsemenl modifies insurance provided under lhe following:
AlL COVERAGE PARTS INCLUDED IN THIS POLICY
SCHEDULE
CANCELLATION: Number of Days Notice of Cancellation: 30
PERSON OR
ORGANIZATION:
ANY PERSON OR ORGANIZATION TO WfIOM
CONTINUED ON IL TB 03
ADDRESS:
THE ADDRESS FOR THAT PERSON OR
CONTINUED ON IL T8 03
GRAPEVINE
TX
76051
PROVISIONS:
If we cancel this policy for any staWtorily permitted
reason ofher than nonpayment of premium, and a
number of days is shown for cancellalion in the
schedule above, we will mail notice of cancellation to
the person or organization shown in lhe schedule
IL T4 05 03 11 p 2011 The 7raveiars Indemnity Company. All righls reserved.
above. We will mail such nolice to the address shown
in lhe schedule above at least the number of days
shown for cancellalion in Ihe schedule above before
the effective dale of canceliation.
Page 1 of 1
BAOL932023
COMMERCIAL AUTO
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
BUSINESS AUTO EXTENSION ENDORSEMENT
This endorsement modifies insurance provided under the following:
BUSINESS AUTO COVERAGE FORM
GENERAL DESCRIPTION OF COVERAGE —This endorsement broadens coverage. However, coverage for any
injury, damage or medical expenses described in any of the provisions of this endorsement may be excluded or
limited by another endorsemenl to lhe Coverage Part, and these coverege broadening provisions do not apply to
the extent that coverage is excluded or limited by such an endorsemenl 7he following listing is a general cover-
age description oniy. Limitations and exclusions may apply to these coverages. Read all lhe provislons of this en-
dorsement and the rest of your policy carefully to determine rights, duties, and what is and is not covered.
A, BROAD FORM NAMED INSURED H. HIRED AUTO PHYSICAL DAMAGE — LOSS OF
B. BLANKET ADDITIONAL INSURED USE —INCREASED LIMIT
C. EMPLOYEE HIRED AUTO I. PHYSICAL DAMAGE — TRANSPORTATION
EXPENSES—INCREASED LIMIT
D. EMPLOYEES AS INSURED J, PERSONAL PROPERTY
E. SUPPLEMENTARY PAYMENTS — INCREASED K. AIRBAGS
LIMITS L. NOTICE AND KNOWLEDGE OF ACCIDENT OR
F. HIRED AUTO — LIMITED WORLDWIDE COV• LOSS
ERAGE — INDEMNITY BASIS M. BLANKET WAIVER OF SUBROGATION
G. WAIVER OF DEDUCTIBLE —GLA55 N. UNINTENTIONAL ERRORS OR OMIS510N5
PROVISIONS
A. BROAD FORM NAMED INSURED
The following is added to Paragraph A.1., Who Is
An Insured, of SECTION II —COVERED AUTOS
LIABILITY COVERAGE:
Any organization you newly acquire or form dur-
ing the policy period over which you maintain
50% or more ownership interest and that is not
separately insured for Business Auto Coverage.
Coverage under lhis provision Is afforded only un-
til the 180th day after you acquire or form the or-
ganization or the end of the policy period, which-
ever is earlier.
B, BLANKET ADDITIONAL INSURED
The following is added to Paragraph c. in A.1.,
Who Is An Insured, of SECTION II — COVERED
AUTOS LIABILITY COVERAGE:
Any person or organizatlon who Is requlred under
a wrillen coMracl or agreement between you and
that person or organizalfon, that is signed and
executed by you before the 'bodily inJury' or
"property damage' occurs and that Is in effect
during lhe policy period, to be named as an addi-
tional insured is an "insured" for Covered Autos
Liability Coverage, bul only for damages to which
lhis insurance applies and only to the extent that
person or organiZation qualifies as an 'insured'
under the Who Is An Insured provision contained
in Section II.
C. EMPLOYEE HIRED AUTO
1. The following Is added to Paragraph A.1.,
Who Is An Insured, of SECTION II — COV•
ERED AUTOS LIABILITY COVERAGE:
An 'employee" of yours is an "insured' while
operating an "auto" hired or rented under a
contract or agreement In an "employee's'
name, with your permission, while performing
duties related to the conduct of your busi-
ness.
2. The following replaces Paragraph b. in 8.5.,
O[her Insurance, of SECTION IV — BUSI•
NESS AUTO CONDITIONS:
h. For Hired Auto Physical Damage Cover-
age, the following are deemed lo be cov-
ered "autos" you own:
(1) Any covered "auto' you lease, hire,
rent or borrow; and
(2) Any covered "auto" hired or rented by
your'employee" under a contract in
an 'employee's' name, with your
CA T3 53 02 15 P) 2015 The 7ravNe.s Inoemnity Company. nll dgms reserved. Page 1 of 4
Inclutles copynghled matenal IX Insurance Services 01fice, Inc. wilh ils permission.
COMMERCIAL AUTO
permission, while perfonning duties
related to the conduct of your busi-
ness.
However, any "auto" that is leased, hired,
rented or borrowed with a driver is not a
covered 'auto".
D. EMPLOYEES AS INSURED
The (ollowing is added to Paragraph A.1., Who Is
An Insured, of SECTION II —COVERED AUTOS
LIABILITY COVERAGE:
Any "employee" of yours is an "insured" while us-
ing a covered "auto' you don't own, hire or borrow
In your business or your personal affairs.
E. SUPPLEMENTARY PAYMENTS —INCREASED
LIMITS
1. The (ollowing replaces Paragraph A.2,a.(2),
of SECTION II—COVERED AUTOS LIABIL-
ITY COVERAGE:
(2) Up to $3,000 for cost of bail bonds (In-
cluding bonds for related traffic law viola-
tions) required because of an 'accidenP'
we cover. W e do not have to (urnish
lhese bonds.
2. The following replaces Paragraph A,2.a.(4),
of SECTION II—COVERED AUTOS LIABIL-
ITY COVERAGE:
(4) All reasonable expenses incurred by the
'insured" at our request, including actual
loss of earnings up to $500 a day be-
cause of time off from work.
F. HIRED AUTO — LIMITED WORLDWIDE COV-
ERAGE — INDEMNITY BASIS
The following replaces Subparagraph (5) in Para-
graph B.7., Policy Perlod, Coverege Terrltory,
af SECTION IV — BUSINE55 AUTO CONDI-
TIONS:
(5) Anywhere in the world, except any country or
Jurisdiction while any trade sancllon, em-
bargo, or similar regulalion Imposed by the
United States of America applies to and pro-
hlbits the transaction of business wilh or
wilhin such country or jurisdiction, for Cov-
ered Autos Liability Coverage for any covered
'auto' that you lease, hire, rent or borrow
wlthout a driver for a period of 30 days or less
and that is not an "auto' you lease, hire, rent
or borrow from any of your "employees",
partners (if you are a partnership), members
(if you are a limited liability company) or
members of their households.
(a) Wlth respect lo any claim made or "suiC
brought outside the United States of
America, the territories and possessions
of the Unitetl States of America, Puerto
Rico and Canada:
(I) You mus� arrange to defend the "in-
sured" against, and investigate or set-
tle any such claim or 'suit" and keep
us advised of all proceedings and ac-
tions.
(II) Neither you nor any other involved
'insured' will make any settlement
without our consent.
(III) We may, at our discretion, participate
in defending the "insured" againsl, or
in the setllement of, any clalm or
"suit".
(Iv) We will relmburse the "Insured" for
sums that the "Insured" legally must
pay as damages because o( "bodily
injury" or'properry damage'to which
this insurance applies, lhat the "in-
sured' pays with our consent, but
only up to the limit described in Pa�a-
graph C., Limits Of Insurance, of
SECTION II — COVERE� AUTOS
LIABI�ITY COVERAGE.
(v) We will reimburse the "insured' for
the reasonable expenses Incurred
with our consent for your invesliga-
tion of such claims and your defense
of the "insured' againsi any such
"suit", but only up to and included
within the limil described in Para-
graph C., Limits Of Insurance, of
SECTION II — COVERED AUTOS
LIABILITY COVERAGE, and not In
addition to such limit. Our duty lo
make such payments ends when we
have used up the applicable limit o1
Insurance in payments for damages,
settlements or defense expenses.
(6) This insurance is ezcess over any valid
and colleclible other insurance available
lo the "insured" whether primary, excess,
contingentor on any other basis.
(c) This insurance Is not a substitute for re-
qulred or compulsory insurance In any
country outslde the United States, its ter-
ritories and possessions, Puerto Rico and
Canada.
Page 2 of 4 � 2015 The Travciars Indemnily Campany. All riBhts reserved. CA T3 51 02 15
Includes wpyri9hled malenai al Insurance Services Otli�, Inc. wiR� ils permission.
COMMERCIAL AUTO
You agree to malntaln ail requlred or
compulsory insurance In any such coun-
try up to the minimum limits requlred by
local law. Your failure to comply with
compulsory insurance requirements will
not Invalldate the coverage afforded by
this policy, but we will only be liable [o the
same extenl we would have been liable
had you complied with [he compulsory in-
surance requiremanls.
(d) It is understood lhat we are not an admit-
ted or authorized insurer outside the
United States of America, Its terrlrories
and possessions, Puerto Rico and Can-
ada. We assume no responsibility for the
furnlshing of certificates of insurance, or
for compliance in any way wilh the laws
of other countries �elating to insurance.
G. WAIVER OF DEDUCTIBLE —GLASS
The following is added lo Paragraph D., Deductl-
ble, of SECTION III — PHYSICAL DAMAGE
COVERAGE:
No deductible for a covered "aulo" wiil apply to
glass damage if the glass is repaired rather than
replaced.
H. HIRED AUTO PHYSICAL DAMAGE — LOSS OF
USE—INCREASED LIMIT
The following replaces the last sentence of Para-
graph A.4.b., Loss Of Use Expenses, of SEC-
TION III — PHYSICAL DAMAGE COVERAGE:
However, the most we will pay (or any ezpenses
for loss of use is $65 per day, to a maximum of
$750 for any one "accident".
I. PHYSICAL DAMAGE — TRANSPORTATION
EXPENSES — INCREASED LIMIT
The following replaces lhe first sentence In Para-
graph A,4,a., Transportatlon Expenses, of
SECTION III — PHYSICAL DAMAGE COVER-
AGE:
We will pay up to $50 per day to a maximum of
$1,500 for lemporary transportation expense in-
curred by you because of the total the(t of a cov-
ered "auto" of the private passenger type.
J. PERSONALPROPERTY
(2) In or on your covered "auto".
This coverage applies only in the evenl of a total
theft of your covered "auto".
No deductibles apply to this Personal Property
coverage.
K, AIRBAGS
The following is added to Paragraph B,3., Exclu•
slons, of SECTION III — PHYSICAL DAMAGE
COVERAGE:
Exclusion 3.a, does not apply to 'loss" to one or
more airbags In a covered'auto" you own that in-
flate due to a cause other than a cause of "loss"
sel forth In Paragraphs A.1.6, and A.1.c., but
only:
a. If that "auto" is a covered "aulo" for Compie-
hensive Coverage under this pollcy;
b. The airbags are not covered under any war-
ranly; and
c, The alrbags were not intentionally Inflated.
We wlll pay up to a maximum of $1,000 for any
one'loss'.
L. NOTICE AND KNOWLEDGE OF ACCI�ENT OR
LOSS
The following is added to Paragraph A.2.a., of
SECTION IV — BUSINESS AUTO CONDITIONS:
Your duty to give us or our authorized representa-
tive prompt notice of lhe 'accident" or 'loss" ap-
plies only when the 'accidenC or "loss' is known
to:
(a) You (if you are an individual);
(b) A partner (if you are a partnership);
(c) A member (if you are a limiled liability com-
pany);
(d) An execulive officer, director or insurance
manager (if you are a corporallon or other or-
ganization); or
(e) Any "employee' authorized by you to give no-
tice of the "accident" or "loss".
M. BLANKET WAIVER OF SUBROGATION
The following replaces Paragraph A.5.. Trans(er
Ot Rlghts Ot Recovery Agalnst Others To Us,
of SECTION IV — BUSINESS AUTO CONDI-
TIONS:
The following is added to Paragraph A.4., Cover- 5. Transfer Of Rlghts Of Recovery Agalnst
age Extenslons, of SECTION III — PHYSICAL Others To Us
DAMAGE COVERAGE: We waive any right of recovery we may have
Personal Property against any person or organization to the ex-
tent required of you by a written contrect
We will pay up [o $400 for'loss" to weanng ap- signed and exewled prior lo any "accidenC'
parel and other personal properry which is: or "loss", provided that the "accidenC or "loss'
(1) Owned by an "insured"; and arises out of operations contemplated by
CA T3 53 02 15 � 2�157he Travelen Indemnily Compeny. All tlgMs reservetl. Pege 3 O( 4
Includes mpynghletl male�ial ol Insurance Services Olfice, Inc. wiih its permissic.�.
COMMERCIAL AUTO
such wnlracL The waiver applles only lo lhe The unintentional omission of, or unintentional
person or organization designated In such error In, any information given by you shail not
conlracl. prejudice your rights under this insurance. How-
N. UNINTENTIONAL ERRORS OR OMISSIONS ever this provision does nol affect our right to col-
The following Is added lo Paragraph 8.2., Con- lect addilional premium or exercise our righl of
cealment, Mlsrepresentatlon, Or Fraud, of cancellation or non-renewal.
SECTION IV—BUSINE55 AUTO CONDITIONS:
\
Page 4 of 4 F9 20757he TravAers Intlemnlly Company. All righ�s reserved. CA T3 53 02 15
Includes copyrighletl malenal ul Insurance Services 011ice, Inc. wilh ils permissian.
�AOL932U23
COMMERCIAL AUTO
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
BLANKET ADDITIONAL INSURED - PRIMARY AND
NON-CONTRIBUTORY WITH OTHER INSURANCE
This endorsement modifies insurance provided under the following:
BUSINESS AUTO COVERAGE FORM
PROVISIONS
1. The following is added lo Paragraph A.t.c., Who
Is An Insured, of SECTION II — COVERED
AUTOS LIABILITY COVERAGE:
Any person or organization who is required under
a wrftten contract or agreement behveen you and
ihal person or organization, that is slgned and
executed by you before the "bodily injury" or
'property damage" occurs and that is in effect
during the policy period, to be named as an addl-
tional insured is an "Insured' for Covered Autos
Liabiliry Coverage, but only for damages to which
this insurance applies and only lo �he extent lhat
person or organization qualifies as an "insured"
under the Who Is An Insured provision contained
In SECTION II.
2. The following is added lo Paragraph B.S., Other
Insurance of SECTION IV — BUSINESS AUTO
CONDITIONS:
Regardless of the provisions of paragraph a. and
paragraph d, of this part5. O[her Insurance, this
insurance is primary ro and noncontributory with
applicable other Insurance under which an addl-
tional insured person or organization is the firsl
named insured when Ihe wrilten contract or
agreement between you and thal person or or-
ganization, that is signed and executed by you
before the "bodily InJury' or 'property damage"
occurs and that is in effect during the policy pe-
riod, requires this insurance to be primary and
non�oniributory.
CA T4 74 02 15 d� 2015 The TravNers Indemnity Cwnpany. All righls reserved. P89@ 1 Of 1
Includes copynghled malerial ol Insurance Survices Office, Ir�c. wilh i�s permissim.
POLICY NUMBER: BA0�,932023
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
DESIGNATED ENTITY - NOTICE OF
CANCELLATION PROVIDED BY US
This endorsemerit modifies insurance provided under the following:
ALL COVERAGE PARTS INCLUDED IN THIS POLICY
$CNEOULE
CANCELLATION:
Number of Days Notfce of Cancellation: 30
PERSON OR
ORGANIZATION: nm xrsa� o� oreanffiaia� m wnom Yo� heve aoreea m e�rm�� ��«aa mai �oiKe m�nc�iano� m i�ue ��cyw�u ua oi�en, cw o�N rc
l. vou seno us o wMlan rcqueatto ptavMe audt nolice, Indutlny the name ena eGdrtss W¢uc0 pBreon or orgeniraVon, aRer Ihe fmt named Insured redeVes nol�B
from us ot the cancellatlon ol thls pdky; and
2. We (aceiva auch wr¢b:n requzM at lees114 deys balo�e Iha beqinnl� d ihe eppf ble numbei d tlays shorin in this Scheaule.
ADDRESS: Tne eedress ra�me� Pe�s�� o� wDa���u�n ��u�caa in e�m wmta� r�quesu� ya, �o �s.
PROVISIONS:
If we cancel this policy for arry statutorily permitted
reason other than nonpayment of premium, and a
number of days is shown for cancellation in the
schedule above, we will mall in�lice of cancellation to
the person or organization shown in the schedule
above. We wlil mail such notice to the address shown
in the schedule above at leastthe number of days
shown for cancellation in the schedule above before
lhe effectNe qate oi canCellaqoll.
IL T4 05 03 11 � 2011 The Trevelers Indemnily Company. Ali nghts resarvetl. P890 'I Of "I
eX�1.SMutual°
WORKER$' COMPENSATION INSURANCE
WORKERS' COMPENSATION AND WC 42 03 04 B
EMPLOYERS LIABILITY POLICY Insured copy
TEXAS WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT
This endorsement applies only to the insurance provided by the policy because Texas is shown in item 3.A. of the
Information Page.
We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our
rightagainst the person or organization named in the Schedule, but this waiver applies only with respect to bodily injury
arising out of the operations described in the schedule where you are required by a written contract to obtain this waiver
from us.
This endorsement shall not operate directly or indirectly to benefit anyone not named in the Schedule.
The premium for this endorsement is shown in the Schedule.
Schedule
1. ( ) Specific Waiver
Name of person or organization
(X)Blanket Waiver
Any person or orpanization for whom the Named Insured has apreed by wriiten contract to furnish this waiver.
2. Operations: All Texas operations
3. Premium:
The premium charc�e for this endorsement shall be 2.00 percent of the premium devetoped on payroll in connection
with work performed for the above person(s) or organization(s) arising out of ihe operations described.
4. Advance Premium: Included, see Information Page
This endorsement changes the policy to which it is altached effective on Ihe inception date of the policy unless a different date is indicated below.
(The tollowing "attaching clause" need be compleled only when ihis endorsement is Issued subsequenl to preparation ot the policy.)
7his endorsement, effective on 11/29/19 at 12:01 a.m. standard time, forms a part oE
Poilcy no. 0002006571 of Texas Mulual Insuranca Company effective on 11/29/19
Issued to: WRIGHT CONSTRUCTION COMPANY INC
NCCI Carder Code: 2993�J
This is not a bill
r/� `�f�
Authorizetl representative
Nl21/19
PO Box 12058, Austin, TX 78711-2058
1 of 1 texasmutual.com �(800) 859-5995 � Fax (800) 359-0650 WC 42 03 04 B
eX�1�SMutua��
WORKERS' COMPENSA710N INSURANCE
WORKERS' CQMPENSATION AND WC 42 06 01
EMPLOYERS LIABILITY POLICY Insured copy
TEXAS NOTICE OF MATERIAL CHANGE ENDORSEMENT
This endorsement applies only to the insurance provided by the policy because Texas is shown in Item 3.A, of the
Information Page.
In the event of cancellation or other material change of the policy, we will mail advance notice to the person or
organization named in the Schedule. The number of days advance notice is shown in the Schedule.
This endorsement shalf not operate directly or indirectly to benefit anyone not named in the Schedule.
5chedule
1. Number of days advance notice:
2. Notice will be mailed to:
30
PER LIST ON FILE
This endorsement changes the policy to which it is attached eflective on ihe inceplion dale of ihe policy unless a differenf dale is indicated 6elow.
(The following "atlaching ctause" need 6e completed only when ibis endorsement is Issued subsequent to preparation of the policy.)
This endorsement, effective on 11l29/19 at 12:D7 a.m, standard time, forms a part oF:
Policy no. 0002006571 of Texas Mutuai Insurance Company effeclive on 11/29/19
Issued to: WRIGHT CONSTRUCTION COMPANY INC
NCCI Carrler Code: 29939
This is not a hill
�'� c``�"
Authorized representat(ve
11f21/19
PO Box 12058, Austin, TX 78711-2058
1 of 1 texasmu[ual.com �(800) 859-5995 � Fax (B00) 359-D650 WC 42 O6 01
Pollution Policy #0312-1244
11 /29/2019 to 11 /29/2020
4. Any person or organization with whom you agree to include as an insured in a written contract or
written agreement, but only with respect to bodily injury, property damage, environmental
damage or emergency response expense arising out of your work.
5. Any person or organization that has at least a 50 % controlling interest in you but only with respect to
bodily injury, property damage, environmental damage or emergency response expense
arising out of their financial control of you.
No person or organization is an insured with respect to the conduct of any current or past partnership,
joint venture or limited liability company that is not shown as a Named Insured in the Declarations.
SECTION III — EXCLUSIONS
This insurance does not apply to:
1. Contractual Liability
Bodily injury, property damage, environmental damage or emergency response expense for
which the insured is obligated to pay damages by reason of the assumption of liability in a contract or
agreement. This exclusion does not apply to liability for damages:
a. That the insured would have in the absence of the contract or agreement; or
b. Assumed in a contract or agreement that is an insured contract, provided the bodily injury,
property damage, environmental damage or emergency response expense occurs
subsequent to the execution of the contract or agreement. Solely for the purposes of liability
assumed in an insured contract, reasonable attorneys' fees and necessary litigation expenses
incurred by or for a party other than an insured are deemed to be damages because of bodily
injury, property damage, environmental damage or emergency response expense,
provided:
(1) Liability to such party for, or for the cost of, that party's defense has also been assumed in
the same insured contract and
(2) Such attorneys' fees and litigation expenses are for defense of that party against a civil or
alternative dispute resolution proceeding in which damages to which this insurance applies
are alleged.
2. Criminal Fines, Penalties and Assessments
Any criminal fines, criminal penalties or criminal assessments.
3. Damage to Conveyance
Property damage to any conveyance utilized during transportation. This exclusion does not apply
to claims made by third-party carriers for such property damage arising from the insured's
negligence.
4. Damage to Property
Property damage or environmental damage to:
a. Property you own, rent, or occupy including any costs or expenses incurred by you, or any other
person, organization or entity, for repair, replacement, enhancement, restoration or maintenance
ENV-CPL 00003 00 (02/12) Page 7 of 22
Includes copyrighted material of Insurance Services Offices, Inc. with its permission.
Pollution Policy #0312-1244
11/29/2019 to 11/29/2020
b. To sue us on this policy unless all of its terms have been fully complied with.
A person or organization may sue us to recover on an agreed settlement or on a final judgment
against an insured; but we will not be liable for damages that are not payable under the terms of this
policy or that are in excess of the applicable limit of insurance. An agreed settlement means a
settlement and release of liability signed by us, the insured and the claimant or the claimanYs legal
representative.
12. Other Insurance
If other valid and collectible insurance is available to the insured for a loss we cover under this policy,
our obligations are limited as follows:
a. Primary Insurance
This insurance is primary except when Paragraph b. below applies. If this insurance is primary,
our obligations are not affected unless any of the other insurance is also primary. Then, we will
share with all that other insurance by the method described in Paragraph b. below. However, in
the event that a written contract or written agreement requires this insurance to be primary for any
person or organization with whom you agreed to insure and such person or organization is an
insured under this policy, we will not seek contributions from any such other insurance issued to
such person or organization.
b. Method of Sharing
If all of the other insurance permits contribution by equal shares, we will also follow this method.
Under this approach, each insurer contributes equal amounts until it has paid its applicable limit
of insurance or none of the loss remains, whichever comes first.
If any of the other insurance does not permit contribution by equal shares, we will contribute by
limits. Under this method, each insurer's share is based on the ratio of its applicable limit of
insurance to the total applicable limits of insurance of all insurers.
c. Project Specific Insurance Policy
Notwithstanding Paragraphs a. and b. above, if a project covered under this policy is insured
under a policy specifcally purchased to apply to such project, this policy will apply excess of such
policy.
13. Premiums and Deductible
The first Named Insured shown in the Declarations:
a. Is responsible for the payment of all premiums;
b. Will be the payee for any return premiums we pay; and
c. Is responsible for the payment of all deductibles.
14. Representations
a. By accepting this policy, you agree:
ENV-CPL 00003 00 (02/12) Page 14 of 22
Includes copyrighted material of Insurance Services Offices, Inc. with its permission.
Pollution Policy #0312-1244
11/29/2019 to 11/29/2020
(1) The statements and information in any Application and/or Questionnaire and other
supplemental materials submitted to us are accurate and complete and are material to our
undenvriting of this policy;
(2) Those statements and the information provided are based upon representations you made to
us; and
(3) We have issued this policy in reliance upon your representations.
b. Misrepresentation, concealment, breach of a term or condition, or violation of any duty under this
policy by one insured shall not prejudice the interest of coverage for another insured under this
policy. Provided, however, that this condition shall not apply to any insured who is a parent,
subsidiary or affiliate of the first Named Insured.
15. Separation of Insureds
Except with respect to the Limits of Insurance, and any rights or duties specifically assigned in this
policy to the first Named Insured, this insurance applies:
a. As if each Named Insured were the only Named Insured; and
b. Separately to each insured against whom claim is made or suit is brought.
16. Service of Suit
In the event of our failure to pay any amount claimed to be due hereunder, we, at your request, will
submit to the jurisdiction of a court of competent jurisdiction within the United States. Nothing in this
condition constitutes or should be understood to constitute a waiver of our rights to commence an
action in any court of competent jurisdiction in the United States, to remove an action to a United
States District Court, or to seek transfer of a case to another court as permitted by the laws of the
United States or of any state in the United States. It is further agreed that service of process in such
suit may be made uPon counsel, Legal Department, Allied World Assurance Company (U.S.) Inc.,
199 Water Street, 24 h Floor, New York, NY 10038 or his or her representative, and that in any suit
instituted against us upon this policy, we will abide by the fnal decision of such court or of any
appellate court in the event of an appeal.
Further, pursuant to any statute of any state, territory, or district of the United States which makes
provision therefore, we hereby designate the Superintendent, Commissioner or Director of Insurance,
or other officer specified for that purpose in the statute, or his or her successors in office, as its true
and lawful agent upon whom may be served any lawful process in any action, suit, or proceeding
instituted by or on your behalf or any beneficiary hereunder arising out of this policy of insurance and
hereby designates the above named as the person to whom the said officer is authorized to mail such
process or a true copy thereof.
17. Transfer of Rights of Recovery Against Others to Us
If you have rights to recover all or part of any payment we have made under this policy, those rights
are transferred to us. You must do nothing after loss to impair them. At our request, you will bring
suit or transfer those rights to us and help us enforce them.
However, we waive our right(s) of recovery against any person or organization if and to the extenf you
have agreed to waive your right(s) of recovery against such person or organization in a written
contract signed by you prior to the first commencement of a pollution incident out of which the
claim or request for emergency response expense arises under Section I— Coverages, 1. Insuring
Agreement.
ENV-CPL 00003 00 (02/12) Page 15 of 22
Includes copyrighted material of Insurance Services Offices, Inc. with its permission.
Pollution Policy #0312-1244
11/29/2019 to 11/29/2020
Any recovery as a result of subrogation proceedings arising out of the payment of loss covered under
this policy shall accrue first to us to the extent of our payment under the policy, and then to you to the
extent of your deductible. Expenses incurred in such subrogation proceedings shall be apportioned
among the interested parties in the recovery in the proportion that each interested party's share in the
recovery bears to the total recovery.
18. Transfer of Your Rights and Duties Under This Policy
Your rights and duties under this policy may not be transferred without our written consent, which
shall not be unreasonably withheld, except in the case of death of an individual Named Insured.
If you die, your rights and duties will be transferred to your legal representative but only while
acting within the scope of duties as your legal representative. Until your legal representative is
appointed, anyone having proper temporary custody of your property will have your rights and
duties but only with respect to that property.
19. When We Do Not Renew
If we decide not to renew, we will mail or deliver to the first Named Insured shown in the Declarations
written notice of the nonrenewal not less than ninety (90) days before the expiration date. If notice is
mailed, proof of mailing will be sufficient proof of notice.
SECTION VI — DEFINITIONS
1. Auto means:
a. A land motor vehicle, trailer or semitrailer designed for travel on public roads, including any
attached machinery or equipment.
b. Any other land vehicle that is subject to a compulsory or financial responsibility law in the state
where it is licensed or principally garaged.
However, auto does not include mobile equipment.
2. Bodily injury means bodily injury, physical injury, sickness, building-related illness, mental anguish,
shock or emotional distress or disease sustained by a person, including death resulting from any of
these at any time. Bodily injury damages shall include monetary awards or settlements of
compensatory damages and where allowable by law, punitive, exemplary, or multiple damages, and
civil fines, penalties, or assessments for bodily injury.
3. Claim means a demand seeking a remedy and alleging liability or responsibility on the part of the
insured.
4. Clean-up costs means reasonable and necessary expenses, including restoration costs and legal
expenses incurred with our prior written consent, which consent shall not be unreasonably withheld or
delayed, to investigate, abate, contain, treat, remove, remediate, monitor, or dispose of soil,
surfacewater, groundwater or other contaminated media but only:
a. To the extent required by environmental laws;
b. For those costs that have been incurred by the government or any political subdivision of the
United States of America (including its territories and possessions), Puerto Rico and Canada or
by third parties; or
c. In the absence of a. above, to the extent recommended by an environmental professional.
ENV-CPL 00003 00 (02/12) Page 16 of 22
Includes copyrighted material of Insurance Services Offices, Inc. with its permission.
006219-1
MAINTENANCE BOND
Page 1 of 5
Bond STXC613109
1
2
3
4
5
6
7
8
9
10
11
12
SECTION 00 62 19
MAINTENANCE BOND
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we wright construction co., Inc , I<nown as
"Principal" herein and MerchaNs Bonding Company (MuWal) , a corporate surety
(sureties, if more than one) duly authorized to do business in the State of Texas, known as
"Surety" herein (whether one or more), are held and firmly bound unto the Developer, TCRG
Opportunity VII, LLC, authorized to do business in Texas ("Developer") and the City of Fort
13 Worth, a Texas municipal corporation ("City'), in the sum
Three Hundred Ninety five Thousand Nine Hundred NinetyThree
14 Of Dollars and No/100""•""""""""""•"•"•*•""""' Dollar5 ($ 395,993.00"*""*""'"""""'"` �,
15 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for payment
16
17
18
19
of which sum well and truly be made jointly unto the Developer and the City as dual obligees
and their successors, we bind ourselves, our heirs, executors, administrators, successors and
assigns, jointly and severally, firmly by these presents.
20 WHEREAS, Developer and City have entered into an Agreement for the construction of
21 community facilities in the City of Fort Worth by and through a Community Facilities Agreement,
22 CFA Number CFA20-0026; and
23 WHEREAS, the Principal has entered into a certain written contract with the Developer
24 awarded the 23rd day of Jo1Y , 20 ZJ which Contract is
25 hereby referred to and a made part hereof for all purposes as if fully set forth herein, to furnish
26 all materials, equipment labor and other accessories as defined by law, in the prosecution of the
27 Worl<, including any Work resulting from a duly authorized Change Order (collectively herein,
28 the "Work") as provided for in said Contract and designated as Everman Offsite Wastewater
29 Extension; and
CITY OF FORT WORTH EVERMAN OFFSITEWASTEWATEF EXTENSION
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROIKTS 102550
Revised January 31, 2012
006219-2
MAIMENANCE BOND
Page 2 of 5
E�
2 WHEREAS, Principal binds itself to use such materials and to so construct the Work in
3 accordance with the plans, specifications and Contract Documents that the Work is and will
4 remain free from defects in materials or workmanship for and during the period of two (2) years
5 after the date of Final Acceptance of the Work by the City ("Maintenance Period"�; and
0
7 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part upon
8 receiving notice from the Developer and/or City of the need thereof at any time within the
9 Maintenance Period.
10
11 NOW THEREFORE, the condition of this obligation is such that if Principal shall remedy
12 any defective Work, for which timely notice was provided by Developer or City, to a completion
13 satisfactory to the City, then this obligation shall become null and void; otherwise to remain in
14 full force and effect.
i67
16 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
17 noticed defective Work, it is agreed that the Developer or City may cause any and all such
18 defective Work to be repaired and/or reconstructed with all associated costs thereof being
19 borne by the Principal and the Surety under this Maintenance Bond; and
20
21 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
22 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
23 Worth Division; and
24
25 PROVIDED FURTHER, that this obligation shall be continuous in nature and successive
26 recoveries may be had hereon for successive breaches.
QTY OF FORT WORTH EVERMANOFFSITEWASTEWATER EMENSION
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS 102550
Revised lanuary 31, 2012
006219-3
MAIMENANCE BOND
Page 3 of 5
CITY OF FORT WORTH EVERMANOFFSITEWASTEWATER EXiEN510N
STANDARD CIN CONDITIONS — DEVELOPER AWARDED PROJECTS 302550
Revised lanuary 31, 2012
006219-4
MAIMENANCE80ND
Page 4 of 5
1 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
2 instrument by duly authorized agents and officers on this the 23rd day of
3 July 20 20
4
S
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
PRWCIPAL:
Wright Construclion Co., Inc.
Signature
ATTEST:
�� C�:__-.--
� I
(Principal)Secretary
Witness as to Principal
Name and Title
Address:
601 W. Wall Street
Grapevine, TX 76051
SU RETY:
Merohants Bontling Company (MuWal)
CITV OF FORT W ORTH EVEFMAN OFFSITE WASTEWATER EXTENSION
STANDARD CITV CONDITIONS - DEVELOPER AWARDED PROlECTS 102550
Revised January 31, 2012
006219-5
MAINTENANCE BOND
Page 5 of 5
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
�.tl
ATTEST:
NIA
(Surety)Secretary
Jennifer Clark, Allomey-In-Fact
Name and Title
Address:
ix�a:asz. �[[�:r.3
�es Moines, IA 503063498
�-•-J� �
Witness as to Surety Telephone Number: �ste) zaa-et�a
Elena Sells
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CI7Y OF FORT WORTH
STANDARD CITV CONDITIONS—DEVELOPER AWAR�E� PROJELTS
Revised January 31, 2012
EVERMAN OFFSITE WASiEWATER EMENSION
102550
MERCI-IANTS�
L�(J[VDiNG ���htPANY
IMPORTANT NOTICE
To obtain information or make a complaint:
You may contact your insurance agen4 at the telephone number provided by your insurance
agent.
You may call Merchants Bonding Company's toll-free telephone number for information or to
mal<e a complaint at:
1-800-678-8171
You may contact the Texas Department of Insurance to obtain information on companies,
coverages, rights or complaints at:
1-800-252-3439
You may write the Texas Department of Insurance at:
P. O. Box 149104
Austin, TX 78714-9104
Fax: (512) 475-1771
Web: http://wvuw.tdi.state.tx.us
E-mail: ConsumerProtection@tdi.state.tx.us
PREMIUM AND CLAIM DISPUTES: Should you have a dispute concerning your premium or
about a claim you should contact the agent first. If the dispute is not resolved, you may contact
the Texas Department of Insurance.
ATTACH THIS NOTICE TO YOUR POLICY: This notice is for information only and does not
become a part or condition of the attached document.
SUP 0032 TX (1/09)
23
MERCHA_NT��
60NDING COMPANY-•
POWER OF ATTORNEY
KnowAll Persons By These Presents, that MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC.,
both being corporations of lhe State of lowa (herein collectively called the "Companies") do hereby make, cons�ilule and appoint, individually,
Elena Sells; Jennifer Clark; Kathy Sells; Lanny Land; Steven W Lewis
iheir true and lawFul Attorney(s)-in-Fact, to sign its name as surety(ies) antl to execule, seal and acknowtedge any and all bonds, undertakings,
contracts antl olher wriften instruments in ihe naWre lhereof, on behalf of the Companies in their business of guaranteeing the fidelity
of persons, guaranleeing the performance of conUacfs and execuGng or guaranteeing bonds and undertakings requiretl or permifted in any
ac�ions or proceedings allowed 6y law.
This Powerof-Attomey is granted and is signed and sealed by facsimile under and by authority of the following By-Laws adoptetl by the Board
of Directors of Merchants Bonding Company (Mulual) on April 23, 2011 and amended Augus� 14, 2015 and adopted by the Board of Directors
of Merchants Nationel Bonding, Inc., on October 16, 2015.
"The Presiden�, Secretary, Treasurer, or any Assistant Treasurer or any Assistanf Secretary or any Vice Presidenl shall have power and aulhodty
to appoint Attorneys-in-Facl, and to aulhorize them to execule on behalf of the Company, and altach the seal of the Company ihereto, bontls and
undertakings, recognizances, contracts of intlemnily and other writings obligatory in the nature ihereof."
"The signaWre of any authorized officer and the seal of the Company may be affxed by facsimile or elecUonic irensmission to any Power of Attorney
or Certifcation thereof aulhorizing �he execution and delivery of any bontl, undertaking, recognizance, or other suretyship obligations of the
Company, and such signaWre and seal when so used shall have the same force and eRecl as �hough manually flxed:'
In connection with obligations in favor of Ihe Florida Department of Transportation oNy, it is agreed Ihal ihe power and au� hority hereby given to the
Attorney-in-Facl includes any and all consenls for ihe release of retained percentages and/or final estimates on engineering and construction
coNracts required by ihe State of Florida Departmen[ of Transportation. It is fully untlerstood lhat consenting lo the Slate ofFlorida Department
of Transporfafion making payment of lhe final estimate to �he Con�ractor and/or ifs assignee, shall not relieve this surety company of any of
its obligafions under its bond.
In conneclion wifh obliga�ions in favor of lhe Kenlucky Depadmenf of Highways only, it is agreed that the power and aufhority herehy given
to the Allorney-imFact cannot 6e modifed or revoked unless prior written personal notice of such intenl has been given to lhe Commissioner-
Deparimenf of Highways of ihe Commonweallh of Ken�ucky at least thitly (30) days prior to lhe modification or revocation.
In Witness Whereof, the Companies have caused ihis Ins�mment �o be signetl and sealed ihis 8th day of Apnl , 2020
,. �p\N� . CodjA ,
�•�O,.�PPOq •.9'.
, c� -9�;.2<:
:�:� o- o:
•Z:
' a'� 1933 ,-'c'
:y�'•. . c:'
•,b,��....... •��?:
MERCHANTS BONDING COMPANY (MUTUAL)
MERCHANTS NATIONAL BONDING, INC,
ey ��/ ��
j� �
Pres�dent
STATE OF IOWA """""� "�
COUNTY OF DALLAS ss.
On lhis 17th day of March 2020 , 6etore me appeared Larry Taylor, lo me personally known, who being by me duly sworn
ditl say that he is President of MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, WC.; and that the
seals affxed lo the foregoing instrument are the Corporate Seals of the Companies; and that the said insirument was signed and sealetl in behalf
of lhe Companies by authority of their respective Boards of Directors.
,�PR�A� S POLLY MASON .
o D Commission Number 750576 �� %,^ �0.,�p�-�
? ° °��° ° : My Commission Expires " � �
,oWP January07,2023 NotaryPu6lic
(Expiration of notary's commission
does rrot invalida�e this instrumenQ
I, Wlliam Warner, Jr., Secretary of MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC., do hereby
certify thal the above and foregoirg is a Irue and correcl copy of lhe POWER-OF-ATTORNEY execuled by said Companies, which is sfill in full
force and effect and has not been amended or revoked.
In Witness Whereof, � have hereunto set my hand and affixed the seal of the Companies on this 23rd day of July , 2020 .
..•��aPj1p�pA� 6+ % � O���PPO �'?'°q' 6��
, y. pR Rq y, .� 0 99 y�� l/.G�-�/ �✓ �J .
.i.;•u l�. �c, �•.<�
j2:2 _o_ p':,G: :�i2 -o- m•. L�,�'+!/7
:¢:— . ._. 0:3;
:= i ' Z' ' a' 1933 ; C: Secretary
; v., 2003 :; c�; • y'�. �,
,,y�; ;��,, :°y�;.. 1,�c:
. �•....�..�,� •W.... ;
POA 0018 (1/20)
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 – Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 – Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 – Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 – Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contractor’s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 – Contractor’s Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and “Or-Equals” ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 – Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 – City’s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on City’s Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 – City’s Observation Status During Construction ........................................................................... 27
8.01 City’s Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 – Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 – Completion .................................................................................................................................. 32
12.01 Contractor’s Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 – Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 – Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos—Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day – A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw – City’s on-line, electronic document management and collaboration system.
5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract—The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents—Those items that make up the contract and which must include the
Agreement, and it’s attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non-Resident Bidder
iii. Prequalification Statement
c. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l. Supplementary Conditions
m. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project’s Contract Documents
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor—The individual or entity with whom Developer has entered into the Agreement.
11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer – An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings—That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer—The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
16. Final Inspection – Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements—A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone—A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non-Participating Change Order—A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order—A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans – See definition of Drawings.
24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor’s plan to accomplish the Work within the Contract Time.
25. Project—The Work to be performed under the Contract Documents.
26. Project Representative—The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting – An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples—Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications—That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions – That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor—An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent – The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions—That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
41. Work—The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non-Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City’s written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or
the word “Supply,” or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 2 – PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City’s written interpretation or clarification.
ARTICLE 4 – BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor’s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. The certificate of insurance shall document the City, an as “Additional Insured” on all
liability policies.
2. The Contractor’s general liability insurance shall include a, “per project” or “per location”,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor’s obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage’s and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor’s insurance.
4.04 Contractor’s Insurance
A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers’ Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers’ compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor’s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U”
coverage’s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”,
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor’s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: ____________________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a “Right of Entry Agreement” with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor’s use of private and/or construction access roads crossing said railroad company’s
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor’s operations and work cross, occupy, or touch railroad property:
a. General Aggregate: _____________________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : _____________________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
NONE
NONE
NONE
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad company’s right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company’s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company’s property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor’s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor’s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City’s written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or “or-equal” item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an “or-equal” item, in which
case review and approval of the proposed item may, in City’s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City’s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor’s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or
“or-equal” at Contractor’s expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City’s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
X
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City’s determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
X
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor’s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor’s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City’s safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any,
with which City’s employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor’s designated safety representative at the Site.
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City’s review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City’s Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City’s review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City’s review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor’s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor’s warranty and guarantee.
B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor’s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor’s obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor’s responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional’s written approval when
submitted to City.
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City’s
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 6 – OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City’s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City’s employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor’s Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor’s Work except for latent defects in the work provided by others.
ARTICLE 7 – CITY’S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City’s Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor’s failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7.03 Compliance with Safety Program
While at the Site, City’s employees and representatives shall comply with the specific applicable
requirements of Contractor’s safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City’s Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City’s representative during construction are
set forth in the Contract Documents.
A. City’s Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor’s executed Work. Based on
information obtained during such visits and observations, City’s Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City’s Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City’s Project Representative’s visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City’s Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City’s Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City’s Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City’s written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 – CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor’s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to
perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City’s special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor’s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City’s written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor’s obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor’s services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants,
employees, and City’s other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City’s rights and remedies under this
Paragraph 11.09.
ARTICLE 12 – COMPLETION
12.01 Contractor’s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor’s
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 – SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 – MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
01 11 00 - 1
DAP SUMMARY OF WORK
Page 1 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects 102500
Revised December 20, 2012
1 SECTION 01 11 00
2 SUMMARY OF WORK
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Summary of Work to be performed in accordance with the Contract Documents
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
11 2. Division 1 - General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Work Covered by Contract Documents
19 1. Work is to include furnishing all labor, materials, and equipment, and performing
20 all Work necessary for this construction project as detailed in the Drawings and
21 Specifications.
22 B. Subsidiary Work
23 1. Any and all Work specifically governed by documentary requirements for the
24 project, such as conditions imposed by the Drawings or Contract Documents in
25 which no specific item for bid has been provided for in the Proposal and the item is
26 not a typical unit bid item included on the standard bid item list, then the item shall
27 be considered as a subsidiary item of Work, the cost of which shall be included in
28 the price bid in the Proposal for various bid items.
29 C. Use of Premises
30 1. Coordinate uses of premises under direction of the City.
31 2. Assume full responsibility for protection and safekeeping of materials and
32 equipment stored on the Site.
33 3. Use and occupy only portions of the public streets and alleys, or other public places
34 or other rights-of-way as provided for in the ordinances of the City, as shown in the
35 Contract Documents, or as may be specifically authorized in writing by the City.
36 a. A reasonable amount of tools, materials, and equipment for construction
37 purposes may be stored in such space, but no more than is necessary to avoid
38 delay in the construction operations.
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects 102500
Revised December 20, 2012
1 b. Excavated and waste materials shall be stored in such a way as not to interfere
2 with the use of spaces that may be designated to be left free and unobstructed
3 and so as not to inconvenience occupants of adjacent property.
4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such
5 manner as not to interfere with the operation of the railroad.
6 1) All Work shall be in accordance with railroad requirements set forth in
7 Division 0 as well as the railroad permit.
8 D. Work within Easements
9 1. Do not enter upon private property for any purpose without having previously
10 obtained permission from the owner of such property.
11 2. Do not store equipment or material on private property unless and until the
12 specified approval of the property owner has been secured in writing by the
13 Contractor and a copy furnished to the City.
14 3. Unless specifically provided otherwise, clear all rights-of-way or easements of
15 obstructions which must be removed to make possible proper prosecution of the
16 Work as a part of the project construction operations.
17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
18 lawns, fences, culverts, curbing, and all other types of structures or improvements,
19 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
20 appurtenances thereof, including the construction of temporary fences and to all
21 other public or private property adjacent to the Work.
22 5. Notify the proper representatives of the owners or occupants of the public or private
23 lands of interest in lands which might be affected by the Work.
24 a. Such notice shall be made at least 48 hours in advance of the beginning of the
25 Work.
26 b. Notices shall be applicable to both public and private utility companies and any
27 corporation, company, individual, or other, either as owners or occupants,
28 whose land or interest in land might be affected by the Work.
29 c. Be responsible for all damage or injury to property of any character resulting
30 from any act, omission, neglect, or misconduct in the manner or method or
31 execution of the Work, or at any time due to defective work, material, or
32 equipment.
33 6. Fence
34 a. Restore all fences encountered and removed during construction of the Project
35 to the original or a better than original condition.
36 b. Erect temporary fencing in place of the fencing removed whenever the Work is
37 not in progress and when the site is vacated overnight, and/or at all times to
38 provide site security.
39 c. The cost for all fence work within easements, including removal, temporary
40 closures and replacement, shall be subsidiary to the various items bid in the
41 project proposal, unless a bid item is specifically provided in the proposal.
01 11 00 - 3
DAP SUMMARY OF WORK
Page 3 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects 102500
Revised December 20, 2012
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 SECTION 01 31 19
2 PRECONSTRUCTION MEETING
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to
7 clarify construction contract administration procedures
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. No construction schedule required unless requested by the City.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 – General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Work associated with this Item is considered subsidiary to the various items bid.
16 No separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19 A. Coordination
20 1. Attend preconstruction meeting.
21 2. Representatives of Contractor, subcontractors and suppliers attending meetings
22 shall be qualified and authorized to act on behalf of the entity each represents.
23 3. Meeting administered by City may be tape recorded.
24 a. If recorded, tapes will be used to prepare minutes and retained by City for
25 future reference.
26 B. Preconstruction Meeting
27 1. A preconstruction meeting will be held within 14 days after the delivery of the
28 distribution package to the City.
29 a. The meeting will be scheduled and administered by the City.
30 2. The Project Representative will preside at the meeting, prepare the notes of the
31 meeting and distribute copies of same to all participants who so request by fully
32 completing the attendance form to be circulated at the beginning of the meeting.
33 3. Attendance shall include:
34 a. Developer and Consultant
35 b. Contractor's project manager
36 c. Contractor's superintendent
37 d. Any subcontractor or supplier representatives whom the Contractor may desire
38 to invite or the City may request
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 e. Other City representatives
2 f. Others as appropriate
3 4. Preliminary Agenda may include:
4 a. Introduction of Project Personnel
5 b. General Description of Project
6 c. Status of right-of-way, utility clearances, easements or other pertinent permits
7 d. Contractor’s work plan and schedule
8 e. Contract Time
9 f. Notice to Proceed
10 g. Construction Staking
11 h. Progress Payments
12 i. Extra Work and Change Order Procedures
13 j. Field Orders
14 k. Disposal Site Letter for Waste Material
15 l. Insurance Renewals
16 m. Payroll Certification
17 n. Material Certifications and Quality Control Testing
18 o. Public Safety and Convenience
19 p. Documentation of Pre-Construction Conditions
20 q. Weekend Work Notification
21 r. Legal Holidays
22 s. Trench Safety Plans
23 t. Confined Space Entry Standards
24 u. Coordination with the City’s representative for operations of existing water
25 systems
26 v. Storm Water Pollution Prevention Plan
27 w. Coordination with other Contractors
28 x. Early Warning System
29 y. Contractor Evaluation
30 z. Special Conditions applicable to the project
31 aa. Damages Claims
32 bb. Submittal Procedures
33 cc. Substitution Procedures
34 dd. Correspondence Routing
35 ee. Record Drawings
36 ff. Temporary construction facilities
37 gg. MBE/SBE procedures
38 hh. Final Acceptance
39 ii. Final Payment
40 jj. Questions or Comments
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 SECTION 01 33 00
2 DAP SUBMITTALS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. General methods and requirements of submissions applicable to the following
7 Work-related submittals:
8 a. Shop Drawings
9 b. Product Data (including Standard Product List submittals)
10 c. Samples
11 d. Mock Ups
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 – General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. CoordinationY
01 33 00 - 2
DAP SUBMITTALS
Page 2 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 1. Notify the City in writing, at the time of submittal, of any deviations in the
2 submittals from the requirements of the Contract Documents.
3 2. Coordination of Submittal Times
4 a. Prepare, prioritize and transmit each submittal sufficiently in advance of
5 performing the related Work or other applicable activities, or within the time
6 specified in the individual Work Sections, of the Specifications.
7 b. Contractor is responsible such that the installation will not be delayed by
8 processing times including, but not limited to:
9 a) Disapproval and resubmittal (if required)
10 b) Coordination with other submittals
11 c) Testing
12 d) Purchasing
13 e) Fabrication
14 f) Delivery
15 g) Similar sequenced activities
16 c. No extension of time will be authorized because of the Contractor's failure to
17 transmit submittals sufficiently in advance of the Work.
18 d. Make submittals promptly in accordance with approved schedule, and in such
19 sequence as to cause no delay in the Work or in the work of any other
20 contractor.
21 B. Submittal Numbering
22 1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
23 reference identification numbering system in the following manner:
24 a. Use the first 6 digits of the applicable Specification Section Number.
25 b. For the next 2 digits number use numbers 01-99 to sequentially number each
26 initial separate item or drawing submitted under each specific Section
27 number.
28 c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
29 A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
30 submittal number would be as follows:
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1
2 03 30 00-08-B
3
4 1) 03 30 00 is the Specification Section for Concrete
5 2) 08 is the eighth initial submittal under this Specification Section
6 3) B is the third submission (second resubmission) of that particular shop
7 drawing
8 C. Contractor Certification
9 1. Review shop drawings, product data and samples, including those by
10 subcontractors, prior to submission to determine and verify the following:
11 a. Field measurements
12 b. Field construction criteria
13 c. Catalog numbers and similar data
14 d. Conformance with the Contract Documents
15 2. Provide each shop drawing, sample and product data submitted by the Contractor
16 with a Certification Statement affixed including:
17 a. The Contractor's Company name
18 b. Signature of submittal reviewer
19 c. Certification Statement
20 1) “By this submittal, I hereby represent that I have determined and verified
21 field measurements, field construction criteria, materials, dimensions,
22 catalog numbers and similar data and I have checked and coordinated
23 each item with other applicable approved shop drawings."
24 D. Submittal Format
25 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.
26 2. Bind shop drawings and product data sheets together.
27 3. Order
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 a. Cover Sheet
2 1) Description of Packet
3 2) Contractor Certification
4 b. List of items / Table of Contents
5 c. Product Data /Shop Drawings/Samples /Calculations
6 E. Submittal Content
7 1. The date of submission and the dates of any previous submissions
8 2. The Project title and number
9 3. Contractor identification
10 4. The names of:
11 a. Contractor
12 b. Supplier
13 c. Manufacturer
14 5. Identification of the product, with the Specification Section number, page and
15 paragraph(s)
16 6. Field dimensions, clearly identified as such
17 7. Relation to adjacent or critical features of the Work or materials
18 8. Applicable standards, such as ASTM or Federal Specification numbers
19 9. Identification by highlighting of deviations from Contract Documents
20 10. Identification by highlighting of revisions on resubmittals
21 11. An 8-inch x 3-inch blank space for Contractor and City stamps
22 F. Shop Drawings
23 1. As specified in individual Work Sections includes, but is not necessarily limited to:
24 a. Custom-prepared data such as fabrication and erection/installation (working)
25 drawings
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 b. Scheduled information
2 c. Setting diagrams
3 d. Actual shopwork manufacturing instructions
4 e. Custom templates
5 f. Special wiring diagrams
6 g. Coordination drawings
7 h. Individual system or equipment inspection and test reports including:
8 1) Performance curves and certifications
9 i. As applicable to the Work
10 2. Details
11 a. Relation of the various parts to the main members and lines of the structure
12 b. Where correct fabrication of the Work depends upon field measurements
13 1) Provide such measurements and note on the drawings prior to submitting
14 for approval.
15 G. Product Data
16 1. For submittals of product data for products included on the City’s Standard
17 Product List, clearly identify each item selected for use on the Project.
18 2. For submittals of product data for products not included on the City’s Standard
19 Product List, submittal data may include, but is not necessarily limited to:
20 a. Standard prepared data for manufactured products (sometimes referred to as
21 catalog data)
22 1) Such as the manufacturer's product specification and installation
23 instructions
24 2) Availability of colors and patterns
25 3) Manufacturer's printed statements of compliances and applicability
26 4) Roughing-in diagrams and templates
27 5) Catalog cuts
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 6) Product photographs
2 7) Standard wiring diagrams
3 8) Printed performance curves and operational-range diagrams
4 9) Production or quality control inspection and test reports and certifications
5 10) Mill reports
6 11) Product operating and maintenance instructions and recommended
7 spare-parts listing and printed product warranties
8 12) As applicable to the Work
9 H. Samples
10 1. As specified in individual Sections, include, but are not necessarily limited to:
11 a. Physical examples of the Work such as:
12 1) Sections of manufactured or fabricated Work
13 2) Small cuts or containers of materials
14 3) Complete units of repetitively used products color/texture/pattern
15 swatches and range sets
16 4) Specimens for coordination of visual effect
17 5) Graphic symbols and units of Work to be used by the City for independent
18 inspection and testing, as applicable to the Work
19 I. Do not start Work requiring a shop drawing, sample or product data nor any material
20 to be fabricated or installed prior to the approval or qualified approval of such item.
21 1. Fabrication performed, materials purchased or on-site construction accomplished
22 which does not conform to approved shop drawings and data is at the Contractor's
23 risk.
24 2. The City will not be liable for any expense or delay due to corrections or remedies
25 required to accomplish conformity.
26 3. Complete project Work, materials, fabrication, and installations in conformance
27 with approved shop drawings, applicable samples, and product data.
28 J. Submittal Distribution
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 1. Electronic Distribution
2 a. Confirm development of Project directory for electronic submittals to be
3 uploaded to City’s Buzzsaw site, or another external FTP site approved by the
4 City.
5 b. Shop Drawings
6 1) Upload submittal to designated project directory and notify appropriate
7 City representatives via email of submittal posting.
8 2) Hard Copies
9 a) 3 copies for all submittals
10 b) If Contractor requires more than 1 hard copy of Shop Drawings
11 returned, Contractor shall submit more than the number of copies
12 listed above.
13 c. Product Data
14 1) Upload submittal to designated project directory and notify appropriate
15 City representatives via email of submittal posting.
16 2) Hard Copies
17 a) 3 copies for all submittals
18 d. Samples
19 1) Distributed to the Project Representative
20 2. Hard Copy Distribution (if required in lieu of electronic distribution)
21 a. Shop Drawings
22 1) Distributed to the City
23 2) Copies
24 a) 8 copies for mechanical submittals
25 b) 7 copies for all other submittals
26 c) If Contractor requires more than 3 copies of Shop Drawings returned,
27 Contractor shall submit more than the number of copies listed above.
28 b. Product Data
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 1) Distributed to the City
2 2) Copies
3 a) 4 copies
4 c. Samples
5 1) Distributed to the Project Representative
6 2) Copies
7 a) Submit the number stated in the respective Specification Sections.
8 3. Distribute reproductions of approved shop drawings and copies of approved
9 product data and samples, where required, to the job site file and elsewhere as
10 directed by the City.
11 a. Provide number of copies as directed by the City but not exceeding the
12 number previously specified.
13 K. Submittal Review
14 1. The review of shop drawings, data and samples will be for general conformance
15 with the design concept and Contract Documents. This is not to be construed as:
16 a. Permitting any departure from the Contract requirements
17 b. Relieving the Contractor of responsibility for any errors, including details,
18 dimensions, and materials
19 c. Approving departures from details furnished by the City, except as otherwise
20 provided herein
21 2. The review and approval of shop drawings, samples or product data by the City
22 does not relieve the Contractor from his/her responsibility with regard to the
23 fulfillment of the terms of the Contract.
24 a. All risks of error and omission are assumed by the Contractor, and the City will
25 have no responsibility therefore.
26 3. The Contractor remains responsible for details and accuracy, for coordinating the
27 Work with all other associated work and trades, for selecting fabrication
28 processes, for techniques of assembly and for performing Work in a safe manner.
01 33 00 - 9
DAP SUBMITTALS
Page 9 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 4. If the shop drawings, data or samples as submitted describe variations and show a
2 departure from the Contract requirements which City finds to be in the interest of
3 the City and to be so minor as not to involve a change in Contract Price or time for
4 performance, the City may return the reviewed drawings without noting an
5 exception.
6 5. Submittals will be returned to the Contractor under 1 of the following codes:
7 a. Code 1
8 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
9 comments on the submittal.
10 a) When returned under this code the Contractor may release the
11 equipment and/or material for manufacture.
12 b. Code 2
13 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the
14 notations and comments IS NOT required by the Contractor.
15 a) The Contractor may release the equipment or material for
16 manufacture; however, all notations and comments must be
17 incorporated into the final product.
18 c. Code 3
19 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned
20 when notations and comments are extensive enough to require a
21 resubmittal of the package.
22 a) The Contractor may release the equipment or material for
23 manufacture; however, all notations and comments must be
24 incorporated into the final product.
25 b) This resubmittal is to address all comments, omissions and
26 non-conforming items that were noted.
27 c) Resubmittal is to be received by the City within 15 Calendar Days of
28 the date of the City's transmittal requiring the resubmittal.
29 d. Code 4
30 1) "NOT APPROVED" is assigned when the submittal does not meet the intent
31 of the Contract Documents.
01 33 00 - 10
DAP SUBMITTALS
Page 10 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 a) The Contractor must resubmit the entire package revised to bring the
2 submittal into conformance.
3 b) It may be necessary to resubmit using a different
4 manufacturer/vendor to meet the Contract Documents.
5 6. Resubmittals
6 a. Handled in the same manner as first submittals
7 1) Corrections other than requested by the City
8 2) Marked with revision triangle or other similar method
9 a) At Contractor’s risk if not marked
10 b. Submittals for each item will be reviewed no more than twice at the City’s
11 expense.
12 1) All subsequent reviews will be performed at times convenient to the City
13 and at the Contractor's expense, based on the City's or City
14 Representative’s then prevailing rates.
15 2) Provide Contractor reimbursement to the City within 30 Calendar Days for
16 all such fees invoiced by the City.
17 c. The need for more than 1 resubmission or any other delay in obtaining City's
18 review of submittals, will not entitle the Contractor to an extension of
19 Contract Time.
20 7. Partial Submittals
21 a. City reserves the right to not review submittals deemed partial, at the City’s
22 discretion.
23 b. Submittals deemed by the City to be not complete will be returned to the
24 Contractor, and will be considered "Not Approved" until resubmitted.
25 c. The City may at its option provide a list or mark the submittal directing the
26 Contractor to the areas that are incomplete.
27 8. If the Contractor considers any correction indicated on the shop drawings to
28 constitute a change to the Contract Documents, then written notice must be
29 provided thereof to the Developer at least 7 Calendar Days prior to release for
30 manufacture.
01 33 00 - 11
DAP SUBMITTALS
Page 11 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 9. When the shop drawings have been completed to the satisfaction of the City, the
2 Contractor may carry out the construction in accordance therewith and no further
3 changes therein except upon written instructions from the City.
4 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
5 following receipt of submittal by the City.
6 L. Mock ups
7 1. Mock Up units as specified in individual Sections, include, but are not necessarily
8 limited to, complete units of the standard of acceptance for that type of Work to
9 be used on the Project. Remove at the completion of the Work or when directed.
10 M. Qualifications
11 1. If specifically required in other Sections of these Specifications, submit a P.E.
12 Certification for each item required.
13 N. Request for Information (RFI)
14 1. Contractor Request for additional information
15 a. Clarification or interpretation of the contract documents
16 b. When the Contractor believes there is a conflict between Contract Documents
17 c. When the Contractor believes there is a conflict between the Drawings and
18 Specifications
19 1) Identify the conflict and request clarification
20 2. Sufficient information shall be attached to permit a written response without
21 further information.
22
23
24
25
26 1.5 SUBMITTALS [NOT USED]
01 33 00 - 12
DAP SUBMITTALS
Page 12 of 12
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August 30, 2013
1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
2 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
4 1.9 QUALITY ASSURANCE [NOT USED]
5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
6 1.11 FIELD [SITE] CONDITIONS [NOT USED]
7 1.12 WARRANTY [NOT USED]
8 PART 2 - PRODUCTS [NOT USED]
9 PART 3 - EXECUTION [NOT USED]
10 END OF SECTION
11
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
12
01 35 13 - 1
DAP SPECIAL PROJECT PROCEDURES
Page 1 of 7
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August, 30, 2013
1 SECTION 01 35 13
2 SPECIAL PROJECT PROCEDURES
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedures for special project circumstances that includes, but is not limited to:
7 a. Coordination with the Texas Department of Transportation
8 b. Work near High Voltage Lines
9 c. Confined Space Entry Program
10 d. Air Pollution Watch Days
11 e. Use of Explosives, Drop Weight, Etc.
12 f. Water Department Notification
13 g. Public Notification Prior to Beginning Construction
14 h. Coordination with United States Army Corps of Engineers
15 i. Coordination within Railroad permits areas
16 j. Dust Control
17 k. Employee Parking
18 B. Deviations from this City of Fort Worth Standard Specification
19 1. None.
20 C. Related Specification Sections include, but are not necessarily limited to:
21 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
22 2. Division 1 – General Requirements
23 3. Section 33 12 25 – Connection to Existing Water Mains
24
25 1.2 REFERENCES
26 A. Reference Standards
27 1. Reference standards cited in this Specification refer to the current reference
28 standard published at the time of the latest revision date logged at the end of this
29 Specification, unless a date is specifically cited.
30 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752.
31 High Voltage Overhead Lines.
32 3. North Central Texas Council of Governments (NCTCOG) – Clean Construction
33 Specification
34 1.3 ADMINISTRATIVE REQUIREMENTS
35 A. Coordination with the Texas Department of Transportation
36 1. When work in the right-of-way which is under the jurisdiction of the Texas
37 Department of Transportation (TxDOT):
38 a. Notify the Texas Department of Transportation prior to commencing any work
39 therein in accordance with the provisions of the permit
01 35 13 - 2
DAP SPECIAL PROJECT PROCEDURES
Page 2 of 7
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August, 30, 2013
1 b. All work performed in the TxDOT right-of-way shall be performed in
2 compliance with and subject to approval from the Texas Department of
3 Transportation
4 B. Work near High Voltage Lines
5 1. Regulatory Requirements
6 a. All Work near High Voltage Lines (more than 600 volts measured between
7 conductors or between a conductor and the ground) shall be in accordance with
8 Health and Safety Code, Title 9, Subtitle A, Chapter 752.
9 2. Warning sign
10 a. Provide sign of sufficient size meeting all OSHA requirements.
11 3. Equipment operating within 10 feet of high voltage lines will require the following
12 safety features
13 a. Insulating cage-type of guard about the boom or arm
14 b. Insulator links on the lift hook connections for back hoes or dippers
15 c. Equipment must meet the safety requirements as set forth by OSHA and the
16 safety requirements of the owner of the high voltage lines
17 4. Work within 6 feet of high voltage electric lines
18 a. Notification shall be given to:
19 1) The power company (example: ONCOR)
20 a) Maintain an accurate log of all such calls to power company and record
21 action taken in each case.
22 b. Coordination with power company
23 1) After notification coordinate with the power company to:
24 a) Erect temporary mechanical barriers, de-energize the lines, or raise or
25 lower the lines
26 c. No personnel may work within 6 feet of a high voltage line before the above
27 requirements have been met.
28 C. Confined Space Entry Program
29 1. Provide and follow approved Confined Space Entry Program in accordance with
30 OSHA requirements.
31 2. Confined Spaces include:
32 a. Manholes
33 b. All other confined spaces in accordance with OSHA’s Permit Required for
34 Confined Spaces
35 D. Use of Explosives, Drop Weight, Etc.
36 1. When Contract Documents permit on the project the following will apply:
37 a. Public Notification
38 1) Submit notice to City and proof of adequate insurance coverage, 24 hours
39 prior to commencing.
40 2) Minimum 24 hour public notification in accordance with Section 01 31 13
41 E. Water Department Coordination
42 1. During the construction of this project, it will be necessary to deactivate, for a
43 period of time, existing lines. The Contractor shall be required to coordinate with
44 the Water Department to determine the best times for deactivating and activating
45 those lines.
01 35 13 - 3
DAP SPECIAL PROJECT PROCEDURES
Page 3 of 7
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August, 30, 2013
1 2. Coordinate any event that will require connecting to or the operation of an existing
2 City water line system with the City’s representative.
3 a. Coordination shall be in accordance with Section 33 12 25.
4 b. If needed, obtain a hydrant water meter from the Water Department for use
5 during the life of named project.
6 c. In the event that a water valve on an existing live system be turned off and on
7 to accommodate the construction of the project is required, coordinate this
8 activity through the appropriate City representative.
9 1) Do not operate water line valves of existing water system.
10 a) Failure to comply will render the Contractor in violation of Texas Penal
11 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor
12 will be prosecuted to the full extent of the law.
13 b) In addition, the Contractor will assume all liabilities and
14 responsibilities as a result of these actions.
15 F. Public Notification Prior to Beginning Construction
16 1. Prior to beginning construction on any block in the project, on a block by block
17 basis, prepare and deliver a notice or flyer of the pending construction to the front
18 door of each residence or business that will be impacted by construction. The notice
19 shall be prepared as follows:
20 a. Post notice or flyer 7 days prior to beginning any construction activity on each
21 block in the project area.
22 1) Prepare flyer on the Contractor’s letterhead and include the following
23 information:
24 a) Name of Project
25 b) City Project No (CPN)
26 c) Scope of Project (i.e. type of construction activity)
27 d) Actual construction duration within the block
28 e) Name of the contractor’s foreman and phone number
29 f) Name of the City’s inspector and phone number
30 g) City’s after-hours phone number
31 2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit
32 A.
33 3) Submit schedule showing the construction start and finish time for each
34 block of the project to the inspector.
35 4) Deliver flyer to the City Inspector for review prior to distribution.
36 b. No construction will be allowed to begin on any block until the flyer is
37 delivered to all residents of the block.
38 G. Public Notification of Temporary Water Service Interruption during Construction
39 1. In the event it becomes necessary to temporarily shut down water service to
40 residents or businesses during construction, prepare and deliver a notice or flyer of
41 the pending interruption to the front door of each affected resident.
42 2. Prepared notice as follows:
43 a. The notification or flyer shall be posted 24 hours prior to the temporary
44 interruption.
45 b. Prepare flyer on the contractor’s letterhead and include the following
46 information:
47 1) Name of the project
48 2) City Project Number
01 35 13 - 4
DAP SPECIAL PROJECT PROCEDURES
Page 4 of 7
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August, 30, 2013
1 3) Date of the interruption of service
2 4) Period the interruption will take place
3 5) Name of the contractor’s foreman and phone number
4 6) Name of the City’s inspector and phone number
5 c. A sample of the temporary water service interruption notification is attached as
6 Exhibit B.
7 d. Deliver a copy of the temporary interruption notification to the City inspector
8 for review prior to being distributed.
9 e. No interruption of water service can occur until the flyer has been delivered to
10 all affected residents and businesses.
11 f. Electronic versions of the sample flyers can be obtained from the Project
12 Construction Inspector.
13 H. Coordination with United States Army Corps of Engineers (USACE)
14 1. At locations in the Project where construction activities occur in areas where
15 USACE permits are required, meet all requirements set forth in each designated
16 permit.
17 I. Coordination within Railroad Permit Areas
18 1. At locations in the project where construction activities occur in areas where
19 railroad permits are required, meet all requirements set forth in each designated
20 railroad permit. This includes, but is not limited to, provisions for:
21 a. Flagmen
22 b. Inspectors
23 c. Safety training
24 d. Additional insurance
25 e. Insurance certificates
26 f. Other employees required to protect the right-of-way and property of the
27 Railroad Company from damage arising out of and/or from the construction of
28 the project. Proper utility clearance procedures shall be used in accordance
29 with the permit guidelines.
30 2. Obtain any supplemental information needed to comply with the railroad’s
31 requirements.
32 J. Dust Control
33 1. Use acceptable measures to control dust at the Site.
34 a. If water is used to control dust, capture and properly dispose of waste water.
35 b. If wet saw cutting is performed, capture and properly dispose of slurry.
36 K. Employee Parking
37 1. Provide parking for employees at locations approved by the City.
01 35 13 - 5
DAP SPECIAL PROJECT PROCEDURES
Page 5 of 7
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August, 30, 2013
1 1.4 SUBMITTALS [NOT USED]
2 1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.6 CLOSEOUT SUBMITTALS [NOT USED]
4 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.8 QUALITY ASSURANCE [NOT USED]
6 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.10 FIELD [SITE] CONDITIONS [NOT USED]
8 1.11 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
1.3.B – Added requirement of compliance with Health and Safety Code, Title 9.
Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
01 35 13 - 6
DAP SPECIAL PROJECT PROCEDURES
Page 6 of 7
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August, 30, 2013
1 EXHIBIT A
2 (To be printed on Contractor’s Letterhead)
3
4
5
6 Date:
7
8 CPN No.:
9 Project Name:
10 Mapsco Location:
11 Limits of Construction:
12
13
14
15
16
17 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
18 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
19 PROPERTY.
20
21 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE
22 OF THIS NOTICE.
23
24 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER
25 ISSUE, PLEASE CALL:
26
27
28 Mr. <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.>
29
30 OR
31
32 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.>
33
34 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306
35
36 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL
01 35 13 - 7
DAP SPECIAL PROJECT PROCEDURES
Page 7 of 7
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised August, 30, 2013
1 EXHIBIT B
2
3
4
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to the City’s document management system, or another form of
distribution approved by the City.
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City’s Project Representative
4. Provide City’s Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded
through the City’s document management system.
01 50 00 - 1
DAP TEMPORARY FACILITIES AND CONTROLS
Page 1 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised JULY 1, 2011
1 SECTION 01 50 00
2 TEMPORARY FACILITIES AND CONTROLS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provide temporary facilities and controls needed for the Work including, but not
7 necessarily limited to:
8 a. Temporary utilities
9 b. Sanitary facilities
10 c. Storage Sheds and Buildings
11 d. Dust control
12 e. Temporary fencing of the construction site
13 B. Deviations from this City of Fort Worth Standard Specification
14 1. None.
15 C. Related Specification Sections include, but are not necessarily limited to:
16 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
17 2. Division 1 – General Requirements
18 1.2 PRICE AND PAYMENT PROCEDURES
19 A. Measurement and Payment
20 1. Work associated with this Item is considered subsidiary to the various Items bid.
21 No separate payment will be allowed for this Item.
22 1.3 REFERENCES [NOT USED]
23 1.4 ADMINISTRATIVE REQUIREMENTS
24 A. Temporary Utilities
25 1. Obtaining Temporary Service
26 a. Make arrangements with utility service companies for temporary services.
27 b. Abide by rules and regulations of utility service companies or authorities
28 having jurisdiction.
29 c. Be responsible for utility service costs until Work is approved for Final
30 Acceptance.
31 1) Included are fuel, power, light, heat and other utility services necessary for
32 execution, completion, testing and initial operation of Work.
33 2. Water
34 a. Contractor to provide water required for and in connection with Work to be
35 performed and for specified tests of piping, equipment, devices or other use as
36 required for the completion of the Work.
37 b. Provide and maintain adequate supply of potable water for domestic
38 consumption by Contractor personnel and City’s Project Representatives.
39 c. Coordination
40 1) Contact City 1 week before water for construction is desired
01 50 00 - 2
DAP TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised JULY 1, 2011
1 d. Contractor Payment for Construction Water
2 1) Obtain construction water meter from City for payment as billed by City’s
3 established rates.
4 3. Electricity and Lighting
5 a. Provide and pay for electric powered service as required for Work, including
6 testing of Work.
7 1) Provide power for lighting, operation of equipment, or other use.
8 b. Electric power service includes temporary power service or generator to
9 maintain operations during scheduled shutdown.
10 4. Telephone
11 a. Provide emergency telephone service at Site for use by Contractor personnel
12 and others performing work or furnishing services at Site.
13 5. Temporary Heat and Ventilation
14 a. Provide temporary heat as necessary for protection or completion of Work.
15 b. Provide temporary heat and ventilation to assure safe working conditions.
16 B. Sanitary Facilities
17 1. Provide and maintain sanitary facilities for persons on Site.
18 a. Comply with regulations of State and local departments of health.
19 2. Enforce use of sanitary facilities by construction personnel at job site.
20 a. Enclose and anchor sanitary facilities.
21 b. No discharge will be allowed from these facilities.
22 c. Collect and store sewage and waste so as not to cause nuisance or health
23 problem.
24 d. Haul sewage and waste off-site at no less than weekly intervals and properly
25 dispose in accordance with applicable regulation.
26 3. Locate facilities near Work Site and keep clean and maintained throughout Project.
27 4. Remove facilities at completion of Project
28 C. Storage Sheds and Buildings
29 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor
30 above ground level for materials and equipment susceptible to weather damage.
31 2. Storage of materials not susceptible to weather damage may be on blocks off
32 ground.
33 3. Store materials in a neat and orderly manner.
34 a. Place materials and equipment to permit easy access for identification,
35 inspection and inventory.
36 4. Equip building with lockable doors and lighting, and provide electrical service for
37 equipment space heaters and heating or ventilation as necessary to provide storage
38 environments acceptable to specified manufacturers.
39 5. Fill and grade site for temporary structures to provide drainage away from
40 temporary and existing buildings.
41 6. Remove building from site prior to Final Acceptance.
42 D. Temporary Fencing
43 1. Provide and maintain for the duration or construction when required in contract
44 documents
45 E. Dust Control
01 50 00 - 3
DAP TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised JULY 1, 2011
1 1. Contractor is responsible for maintaining dust control through the duration of the
2 project.
3 a. Contractor remains on-call at all times
4 b. Must respond in a timely manner
5 F. Temporary Protection of Construction
6 1. Contractor or subcontractors are responsible for protecting Work from damage due
7 to weather.
8 1.5 SUBMITTALS [NOT USED]
9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
10 1.7 CLOSEOUT SUBMITTALS [NOT USED]
11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
12 1.9 QUALITY ASSURANCE [NOT USED]
13 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
14 1.11 FIELD [SITE] CONDITIONS [NOT USED]
15 1.12 WARRANTY [NOT USED]
16 PART 2 - PRODUCTS [NOT USED]
17 PART 3 - EXECUTION [NOT USED]
18 3.1 INSTALLERS [NOT USED]
19 3.2 EXAMINATION [NOT USED]
20 3.3 PREPARATION [NOT USED]
21 3.4 INSTALLATION
22 A. Temporary Facilities
23 1. Maintain all temporary facilities for duration of construction activities as needed.
24 3.5 [REPAIR] / [RESTORATION]
25 3.6 RE-INSTALLATION
26 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
27 3.8 SYSTEM STARTUP [NOT USED]
28 3.9 ADJUSTING [NOT USED]
29 3.10 CLEANING [NOT USED]
30 3.11 CLOSEOUT ACTIVITIES
31 A. Temporary Facilities
01 50 00 - 4
DAP TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised JULY 1, 2011
1 1. Remove all temporary facilities and restore area after completion of the Work, to a
2 condition equal to or better than prior to start of Work.
3 3.12 PROTECTION [NOT USED]
4 3.13 MAINTENANCE [NOT USED]
5 3.14 ATTACHMENTS [NOT USED]
6 END OF SECTION
7
Revision Log
DATE NAME SUMMARY OF CHANGE
8
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised July 1, 2011
1 SECTION 01 55 26
2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Administrative procedures for:
7 a. Street Use Permit
8 b. Modification of approved traffic control
9 c. Removal of Street Signs
10 B. Deviations from this City of Fort Worth Standard Specification
11 1. None.
12 C. Related Specification Sections include, but are not necessarily limited to:
13 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
14 2. Division 1 – General Requirements
15 3. Section 34 71 13 – Traffic Control
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES
21 A. Reference Standards
22 1. Reference standards cited in this specification refer to the current reference standard
23 published at the time of the latest revision date logged at the end of this
24 specification, unless a date is specifically cited.
25 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Traffic Control
28 1. General
29 a. When traffic control plans are included in the Drawings, provide Traffic
30 Control in accordance with Drawings and Section 34 71 13.
31 b. When traffic control plans are not included in the Drawings, prepare traffic
32 control plans in accordance with Section 34 71 13 and submit to City for
33 review.
34 1) Allow minimum 10 working days for review of proposed Traffic Control.
35 B. Street Use Permit
36 1. Prior to installation of Traffic Control, a City Street Use Permit is required.
37 a. To obtain Street Use Permit, submit Traffic Control Plans to City
38 Transportation and Public Works Department.
01 55 26 - 2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised July 1, 2011
1 1) Allow a minimum of 5 working days for permit review.
2 2) Contractor’s responsibility to coordinate review of Traffic Control plans for
3 Street Use Permit, such that construction is not delayed.
4 C. Modification to Approved Traffic Control
5 1. Prior to installation traffic control:
6 a. Submit revised traffic control plans to City Department Transportation and
7 Public Works Department.
8 1) Revise Traffic Control plans in accordance with Section 34 71 13.
9 2) Allow minimum 5 working days for review of revised Traffic Control.
10 3) It is the Contractor’s responsibility to coordinate review of Traffic Control
11 plans for Street Use Permit, such that construction is not delayed.
12 D. Removal of Street Sign
13 1. If it is determined that a street sign must be removed for construction, then contact
14 City Transportation and Public Works Department, Signs and Markings Division to
15 remove the sign.
16 E. Temporary Signage
17 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
18 requirements of the latest edition of the Texas Manual on Uniform Traffic Control
19 Devices (MUTCD).
20 2. Install temporary sign before the removal of permanent sign.
21 3. When construction is complete, to the extent that the permanent sign can be
22 reinstalled, contact the City Transportation and Public Works Department, Signs
23 and Markings Division, to reinstall the permanent sign.
24 F. Traffic Control Standards
25 1. Traffic Control Standards can be found on the City’s Buzzsaw website.
26 1.5 SUBMITTALS [NOT USED]
27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
28 1.7 CLOSEOUT SUBMITTALS [NOT USED]
29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
30 1.9 QUALITY ASSURANCE [NOT USED]
31 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
32 1.11 FIELD [SITE] CONDITIONS [NOT USED]
33 1.12 WARRANTY [NOT USED]
34 PART 2 - PRODUCTS [NOT USED]
35 PART 3 - EXECUTION [NOT USED]
36 END OF SECTION
01 55 26 - 3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised July 1, 2011
1
Revision Log
DATE NAME SUMMARY OF CHANGE
2
01 57 13 - 1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised July 1, 2011
1 SECTION 01 57 13
2 STORM WATER POLLUTION PREVENTION
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Procedures for Storm Water Pollution Prevention Plans
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the
11 Contract
12 2. Division 1 – General Requirements
13 3. Section 31 25 00 – Erosion and Sediment Control
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Construction Activities resulting in less than 1 acre of disturbance
17 a. Work associated with this Item is considered subsidiary to the various Items
18 bid. No separate payment will be allowed for this Item.
19 2. Construction Activities resulting in greater than 1 acre of disturbance
20 a. Measurement and Payment shall be in accordance with Section 31 25 00.
21 1.3 REFERENCES
22 A. Abbreviations and Acronyms
23 1. Notice of Intent: NOI
24 2. Notice of Termination: NOT
25 3. Storm Water Pollution Prevention Plan: SWPPP
26 4. Texas Commission on Environmental Quality: TCEQ
27 5. Notice of Change: NOC
28 A. Reference Standards
29 1. Reference standards cited in this Specification refer to the current reference
30 standard published at the time of the latest revision date logged at the end of this
31 Specification, unless a date is specifically cited.
32 2. Integrated Storm Management (iSWM) Technical Manual for Construction
33 Controls
34 1.4 ADMINISTRATIVE REQUIREMENTS
35 A. General
36 1. Contractor is responsible for resolution and payment of any fines issued associated
37 with compliance to Stormwater Pollution Prevention Plan.
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised July 1, 2011
1 B. Construction Activities resulting in:
2 1. Less than 1 acre of disturbance
3 a. Provide erosion and sediment control in accordance with Section 31 25 00 and
4 Drawings.
5 2. 1 to less than 5 acres of disturbance
6 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
7 Permit is required
8 b. Complete SWPPP in accordance with TCEQ requirements
9 1) TCEQ Small Construction Site Notice Required under general permit
10 TXR150000
11 a) Sign and post at job site
12 b) Prior to Preconstruction Meeting, send 1 copy to City Department of
13 Transportation and Public Works, Environmental Division, (817) 392-
14 6088.
15 2) Provide erosion and sediment control in accordance with:
16 a) Section 31 25 00
17 b) The Drawings
18 c) TXR150000 General Permit
19 d) SWPPP
20 e) TCEQ requirements
21 3. 5 acres or more of Disturbance
22 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
23 Permit is required
24 b. Complete SWPPP in accordance with TCEQ requirements
25 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
26 a) Sign and post at job site
27 b) Send copy to City Department of Transportation and Public Works,
28 Environmental Division, (817) 392-6088.
29 2) TCEQ Notice of Change required if making changes or updates to NOI
30 3) Provide erosion and sediment control in accordance with:
31 a) Section 31 25 00
32 b) The Drawings
33 c) TXR150000 General Permit
34 d) SWPPP
35 e) TCEQ requirements
36 4) Once the project has been completed and all the closeout requirements of
37 TCEQ have been met a TCEQ Notice of Termination can be submitted.
38 a) Send copy to City Department of Transportation and Public Works,
39 Environmental Division, (817) 392-6088.
40 1.5 SUBMITTALS
41 A. SWPPP
42 1. Submit in accordance with Section 01 33 00, except as stated herein.
43 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
44 as follows:
45 1) 1 copy to the City Project Manager
46 a) City Project Manager will forward to the City Department of
47 Transportation and Public Works, Environmental Division for review
01 57 13 - 3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised July 1, 2011
1 B. Modified SWPPP
2 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
3 in accordance with Section 01 33 00.
4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
5 1.7 CLOSEOUT SUBMITTALS [NOT USED]
6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
7 1.9 QUALITY ASSURANCE [NOT USED]
8 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
9 1.11 FIELD [SITE] CONDITIONS [NOT USED]
10 1.12 WARRANTY [NOT USED]
11 PART 2 - PRODUCTS [NOT USED]
12 PART 3 - EXECUTION [NOT USED]
13 END OF SECTION
14
Revision Log
DATE NAME SUMMARY OF CHANGE
15
01 60 00
DAP PRODUCT REQUIREMENTS
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
SECTION 01 60 00
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A list of City approved products for use is available through the City’s website at:
https://apps.fortworthtexas.gov/ProjectResources/ and following the directory
path: 02 - Construction Documents\Standard Products List
A. Only products specifically included on City’s Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
B. Any specific product requirements in the Contract Documents supersede similar
products included on the City’s Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City’s Standard Product List.
C. Although a specific product is included on City’s Standard Product List, not all
products from that manufacturer are approved for use, including but not limited to, that
manufacturer’s standard product.
D. See Section 01 33 00 for submittal requirements of Product Data included on City’s
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
01 60 00
DAP PRODUCT REQUIREMENTS
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City’s Standard Product List
4/7/2014 M.Domenech Revised for DAP application
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City’s website.
01 66 00 - 1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 SECTION 01 66 00
2 PRODUCT STORAGE AND HANDLING REQUIREMENTS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Scheduling of product delivery
7 2. Packaging of products for delivery
8 3. Protection of products against damage from:
9 a. Handling
10 b. Exposure to elements or harsh environments
11 B. Deviations from this City of Fort Worth Standard Specification
12 1. None.
13 C. Related Specification Sections include, but are not necessarily limited to:
14 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
15 2. Division 1 – General Requirements
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES [NOT USED]
21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
22 1.5 SUBMITTALS [NOT USED]
23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
24 1.7 CLOSEOUT SUBMITTALS [NOT USED]
25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
26 1.9 QUALITY ASSURANCE [NOT USED]
27 1.10 DELIVERY AND HANDLING
28 A. Delivery Requirements
29 1. Schedule delivery of products or equipment as required to allow timely installation
30 and to avoid prolonged storage.
31 2. Provide appropriate personnel and equipment to receive deliveries.
32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site
33 for personnel or equipment to receive the delivery.
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 4. Deliver products or equipment in manufacturer's original unbroken cartons or other
2 containers designed and constructed to protect the contents from physical or
3 environmental damage.
4 5. Clearly and fully mark and identify as to manufacturer, item and installation
5 location.
6 6. Provide manufacturer's instructions for storage and handling.
7 B. Handling Requirements
8 1. Handle products or equipment in accordance with these Contract Documents and
9 manufacturer’s recommendations and instructions.
10 C. Storage Requirements
11 1. Store materials in accordance with manufacturer’s recommendations and
12 requirements of these Specifications.
13 2. Make necessary provisions for safe storage of materials and equipment.
14 a. Place loose soil materials and materials to be incorporated into Work to prevent
15 damage to any part of Work or existing facilities and to maintain free access at
16 all times to all parts of Work and to utility service company installations in
17 vicinity of Work.
18 3. Keep materials and equipment neatly and compactly stored in locations that will
19 cause minimum inconvenience to other contractors, public travel, adjoining owners,
20 tenants and occupants.
21 a. Arrange storage to provide easy access for inspection.
22 4. Restrict storage to areas available on construction site for storage of material and
23 equipment as shown on Drawings, or approved by City’s Project Representative.
24 5. Provide off-site storage and protection when on-site storage is not adequate.
25 a. Provide addresses of and access to off-site storage locations for inspection by
26 City’s Project Representative.
27 6. Do not use lawns, grass plots or other private property for storage purposes without
28 written permission of owner or other person in possession or control of premises.
29 7. Store in manufacturers’ unopened containers.
30 8. Neatly, safely and compactly stack materials delivered and stored along line of
31 Work to avoid inconvenience and damage to property owners and general public
32 and maintain at least 3 feet from fire hydrant.
33 9. Keep public and private driveways and street crossings open.
34 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
35 satisfaction of City’s Project Representative.
36 a. Total length which materials may be distributed along route of construction at
37 one time is 1,000 linear feet, unless otherwise approved in writing by City’s
38 Project Representative.
01 66 00 - 3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8 3.4 ERECTION [NOT USED]
9 3.5 REPAIR / RESTORATION [NOT USED]
10 3.6 RE-INSTALLATION [NOT USED]
11 3.7 FIELD [OR] SITE QUALITY CONTROL
12 A. Tests and Inspections
13 1. Inspect all products or equipment delivered to the site prior to unloading.
14 B. Non-Conforming Work
15 1. Reject all products or equipment that are damaged, used or in any other way
16 unsatisfactory for use on the project.
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION
22 A. Protect all products or equipment in accordance with manufacturer's written directions.
23 B. Store products or equipment in location to avoid physical damage to items while in
24 storage.
25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by
26 the manufacturer.
27 3.13 MAINTENANCE [NOT USED]
28 3.14 ATTACHMENTS [NOT USED]
29 END OF SECTION
30
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
1
01 70 00 - 1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
SECTION 01 70 00
MOBILIZATION AND REMOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Mobilization and Demobilization
a. Mobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
to the Site
2) Establishment of necessary general facilities for the Contractor’s operation
at the Site
3) Premiums paid for performance and payment bonds
4) Transportation of Contractor’s personnel, equipment, and operating supplies
to another location within the designated Site
5) Relocation of necessary general facilities for the Contractor’s operation
from 1 location to another location on the Site.
b. Demobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
away from the Site including disassembly
2) Site Clean-up
3) Removal of all buildings and/or other facilities assembled at the Site for this
Contract
c. Mobilization and Demobilization do not include activities for specific items of
work that are for which payment is provided elsewhere in the contract.
2. Remobilization
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
1) Demobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as designated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designated in the Contract Documents
2) Remobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site necessary to resume the Work.
3) No Payments will be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
c) Lost profits
3. Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
4060 BRYANT IRVIN SEWER IMPROVEMENTS
102551
01 70 00 - 2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
1) Mobilization shall consist of the activities and cost on a Work Order basis
necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site for the issued Work Order.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site for the issued Work Order
2) Demobilization shall consist of the activities and cost necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly for each issued Work
Order
b) Site Clean-up for each issued Work Order
c) Removal of all buildings or other facilities assembled at the Site for
each Work Oder
b. Mobilization and Demobilization do not include activities for specific items of
work for which payment is provided elsewhere in the contract.
4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
a. A Mobilization for Miscellaneous Projects when directed by the City and the
mobilization occurs within 24 hours of the issuance of the Work Order.
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Mobilization and Demobilization
a. Measure
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and materials furnished in accordance with this Item
are subsidiary to the various Items bid and no other compensation will be
allowed.
2. Remobilization for suspension of Work as specifically required in the Contract
Documents
a. Measurement
1) Measurement for this Item shall be per each remobilization performed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Specified Remobilization” in accordance with Contract
Documents.
c. The price shall include:
1) Demobilization as described in Section 1.1.A.2.a.1)
2) Remobilization as described in Section 1.1.A.2.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
4060 BRYANT IRVIN SEWER IMPROVEMENTS
102551
1) Measured by lump sum.
2) Demobilization shall be considered subsidiary to the various bid items.
01 70 00 - 3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
3. Remobilization for suspension of Work as required by City
a. Measurement and Payment
1) This shall be submitted as a Contract Claim in accordance with Article 10
of Section 00 72 00.
2) No payments will be made for standby, idle time, or lost profits associated
with this Item.
4. Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Mobilization” in accordance with Contract
Documents. Demobilization shall be considered subsidiary to mobilization
and shall not be paid for separately.
c. The price shall include:
1) Mobilization as described in Section 1.1.A.3.a.1)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Emergency Mobilization” in accordance with
Contract Documents. Demobilization shall be considered subsidiary to
mobilization and shall not be paid for separately.
c. The price shall include
1) Mobilization as described in Section 1.1.A.4.a)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
4060 BRYANT IRVIN SEWER IMPROVEMENTS
102551
01 70 00 - 4
DAP MOBILIZATION AND REMOBILIZATION
Page 4 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
4060 BRYANT IRVIN SEWER IMPROVEMENTS
102551
01 74 23 - 1
DAP CLEANING
Page 1 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 SECTION 01 74 23
2 CLEANING
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Intermediate and final cleaning for Work not including special cleaning of closed
7 systems specified elsewhere
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 – General Requirements
13 3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Work associated with this Item is considered subsidiary to the various Items bid.
17 No separate payment will be allowed for this Item.
18 1.3 REFERENCES [NOT USED]
19 1.4 ADMINISTRATIVE REQUIREMENTS
20 A. Scheduling
21 1. Schedule cleaning operations so that dust and other contaminants disturbed by
22 cleaning process will not fall on newly painted surfaces.
23 2. Schedule final cleaning upon completion of Work and immediately prior to final
24 inspection.
25 1.5 SUBMITTALS [NOT USED]
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE [NOT USED]
30 1.10 STORAGE, AND HANDLING
31 A. Storage and Handling Requirements
32 1. Store cleaning products and cleaning wastes in containers specifically designed for
33 those materials.
01 74 23 - 2
DAP CLEANING
Page 2 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS
4 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
5 2.2 MATERIALS
6 A. Cleaning Agents
7 1. Compatible with surface being cleaned
8 2. New and uncontaminated
9 3. For manufactured surfaces
10 a. Material recommended by manufacturer
11 2.3 ACCESSORIES [NOT USED]
12 2.4 SOURCE QUALITY CONTROL [NOT USED]
13 PART 3 - EXECUTION
14 3.1 INSTALLERS [NOT USED]
15 3.2 EXAMINATION [NOT USED]
16 3.3 PREPARATION [NOT USED]
17 3.4 APPLICATION [NOT USED]
18 3.5 REPAIR / RESTORATION [NOT USED]
19 3.6 RE-INSTALLATION [NOT USED]
20 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
21 3.8 SYSTEM STARTUP [NOT USED]
22 3.9 ADJUSTING [NOT USED]
23 3.10 CLEANING
24 A. General
25 1. Prevent accumulation of wastes that create hazardous conditions.
26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of
27 governing authorities.
28 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
29 storm or sanitary drains or sewers.
30 4. Dispose of degradable debris at an approved solid waste disposal site.
31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
32 alternate manner approved by City and regulatory agencies.
01 74 23 - 3
DAP CLEANING
Page 3 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 6. Handle materials in a controlled manner with as few handlings as possible.
2 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
3 this project.
4 8. Remove all signs of temporary construction and activities incidental to construction
5 of required permanent Work.
6 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
7 have the cleaning completed at the expense of the Contractor.
8 10. Do not burn on-site.
9 B. Intermediate Cleaning during Construction
10 1. Keep Work areas clean so as not to hinder health, safety or convenience of
11 personnel in existing facility operations.
12 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
13 3. Confine construction debris daily in strategically located container(s):
14 a. Cover to prevent blowing by wind
15 b. Store debris away from construction or operational activities
16 c. Haul from site at a minimum of once per week
17 4. Vacuum clean interior areas when ready to receive finish painting.
18 a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance.
19 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
20 may become airborne or transported by flowing water during the storm.
21 C. Exterior (Site or Right of Way) Final Cleaning
22 1. Remove trash and debris containers from site.
23 a. Re-seed areas disturbed by location of trash and debris containers in accordance
24 with Section 32 92 13.
25 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
26 that may hinder or disrupt the flow of traffic along the roadway.
27 3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
28 junction boxes and inlets.
29 4. If no longer required for maintenance of erosion facilities, and upon approval by
30 City, remove erosion control from site.
31 5. Clean signs, lights, signals, etc.
32 3.11 CLOSEOUT ACTIVITIES [NOT USED]
33 3.12 PROTECTION [NOT USED]
34 3.13 MAINTENANCE [NOT USED]
35 3.14 ATTACHMENTS [NOT USED]
36
37
38
39
40
01 74 23 - 4
DAP CLEANING
Page 4 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 END OF SECTION
2
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
3
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 SECTION 01 77 19
2 CLOSEOUT REQUIREMENTS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedure for closing out a contract
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 – General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Guarantees, Bonds and Affidavits
19 1. No application for final payment will be accepted until all guarantees, bonds,
20 certificates, licenses and affidavits required for Work or equipment as specified are
21 satisfactorily filed with the City.
22 B. Release of Liens or Claims
23 1. No application for final payment will be accepted until satisfactory evidence of
24 release of liens has been submitted to the City.
25 1.5 SUBMITTALS
26 A. Submit all required documentation to City’s Project Representative.
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 1.6 INFORMATIONAL SUBMITTALS [NOT USED]
2 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8 3.4 CLOSEOUT PROCEDURE
9 A. Prior to requesting Final Inspection, submit:
10 1. Project Record Documents in accordance with Section 01 78 39
11 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
12 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
13 01 74 23.
14 C. Final Inspection
15 1. After final cleaning, provide notice to the City Project Representative that the Work
16 is completed.
17 a. The City will make an initial Final Inspection with the Contractor present.
18 b. Upon completion of this inspection, the City will notify the Contractor, in
19 writing within 10 business days, of any particulars in which this inspection
20 reveals that the Work is defective or incomplete.
21 2. Upon receiving written notice from the City, immediately undertake the Work
22 required to remedy deficiencies and complete the Work to the satisfaction of the
23 City.
24 3. Upon completion of Work associated with the items listed in the City's written
25 notice, inform the City, that the required Work has been completed. Upon receipt
26 of this notice, the City, in the presence of the Contractor, will make a subsequent
27 Final Inspection of the project.
28 4. Provide all special accessories required to place each item of equipment in full
29 operation. These special accessory items include, but are not limited to:
30 a. Specified spare parts
31 b. Adequate oil and grease as required for the first lubrication of the equipment
32 c. Initial fill up of all chemical tanks and fuel tanks
33 d. Light bulbs
34 e. Fuses
35 f. Vault keys
36 g. Handwheels
37 h. Other expendable items as required for initial start-up and operation of all
38 equipment
39 D. Notice of Project Completion
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 1. Once the City Project Representative finds the Work subsequent to Final Inspection
2 to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
3 E. Supporting Documentation
4 1. Coordinate with the City Project Representative to complete the following
5 additional forms:
6 a. Final Payment Request
7 b. Statement of Contract Time
8 c. Affidavit of Payment and Release of Liens
9 d. Consent of Surety to Final Payment
10 e. Pipe Report (if required)
11 f. Contractor’s Evaluation of City
12 g. Performance Evaluation of Contractor
13 F. Letter of Final Acceptance
14 1. Upon review and acceptance of Notice of Project Completion and Supporting
15 Documentation, in accordance with General Conditions, City will issue Letter of
16 Final Acceptance and release the Final Payment Request for payment.
17 3.5 REPAIR / RESTORATION [NOT USED]
18 3.6 RE-INSTALLATION [NOT USED]
19 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
20 3.8 SYSTEM STARTUP [NOT USED]
21 3.9 ADJUSTING [NOT USED]
22 3.10 CLEANING [NOT USED]
23 3.11 CLOSEOUT ACTIVITIES [NOT USED]
24 3.12 PROTECTION [NOT USED]
25 3.13 MAINTENANCE [NOT USED]
26 3.14 ATTACHMENTS [NOT USED]
27 END OF SECTION
28
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
29
01 78 23 - 1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 SECTION 01 78 23
2 OPERATION AND MAINTENANCE DATA
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Product data and related information appropriate for City's maintenance and
7 operation of products furnished under Contract
8 2. Such products may include, but are not limited to:
9 a. Traffic Controllers
10 b. Irrigation Controllers (to be operated by the City)
11 c. Butterfly Valves
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 – General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Schedule
24 1. Submit manuals in final form to the City within 30 calendar days of product
25 shipment to the project site.
26 1.5 SUBMITTALS
27 A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
28 approved by the City prior to delivery.
29 1.6 INFORMATIONAL SUBMITTALS
30 A. Submittal Form
31 1. Prepare data in form of an instructional manual for use by City personnel.
32 2. Format
33 a. Size: 8 ½ inches x 11 inches
34 b. Paper
35 1) 40 pound minimum, white, for typed pages
36 2) Holes reinforced with plastic, cloth or metal
37 c. Text: Manufacturer’s printed data, or neatly typewritten
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 d. Drawings
2 1) Provide reinforced punched binder tab, bind in with text
3 2) Reduce larger drawings and fold to size of text pages.
4 e. Provide fly-leaf for each separate product, or each piece of operating
5 equipment.
6 1) Provide typed description of product, and major component parts of
7 equipment.
8 2) Provide indexed tabs.
9 f. Cover
10 1) Identify each volume with typed or printed title "OPERATING AND
11 MAINTENANCE INSTRUCTIONS".
12 2) List:
13 a) Title of Project
14 b) Identity of separate structure as applicable
15 c) Identity of general subject matter covered in the manual
16 3. Binders
17 a. Commercial quality 3-ring binders with durable and cleanable plastic covers
18 b. When multiple binders are used, correlate the data into related consistent
19 groupings.
20 4. If available, provide an electronic form of the O&M Manual.
21 B. Manual Content
22 1. Neatly typewritten table of contents for each volume, arranged in systematic order
23 a. Contractor, name of responsible principal, address and telephone number
24 b. A list of each product required to be included, indexed to content of the volume
25 c. List, with each product:
26 1) The name, address and telephone number of the subcontractor or installer
27 2) A list of each product required to be included, indexed to content of the
28 volume
29 3) Identify area of responsibility of each
30 4) Local source of supply for parts and replacement
31 d. Identify each product by product name and other identifying symbols as set
32 forth in Contract Documents.
33 2. Product Data
34 a. Include only those sheets which are pertinent to the specific product.
35 b. Annotate each sheet to:
36 1) Clearly identify specific product or part installed
37 2) Clearly identify data applicable to installation
38 3) Delete references to inapplicable information
39 3. Drawings
40 a. Supplement product data with drawings as necessary to clearly illustrate:
41 1) Relations of component parts of equipment and systems
42 2) Control and flow diagrams
43 b. Coordinate drawings with information in Project Record Documents to assure
44 correct illustration of completed installation.
45 c. Do not use Project Record Drawings as maintenance drawings.
46 4. Written text, as required to supplement product data for the particular installation:
47 a. Organize in consistent format under separate headings for different procedures.
48 b. Provide logical sequence of instructions of each procedure.
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 5. Copy of each warranty, bond and service contract issued
2 a. Provide information sheet for City personnel giving:
3 1) Proper procedures in event of failure
4 2) Instances which might affect validity of warranties or bonds
5 C. Manual for Materials and Finishes
6 1. Submit 5 copies of complete manual in final form.
7 2. Content, for architectural products, applied materials and finishes:
8 a. Manufacturer's data, giving full information on products
9 1) Catalog number, size, composition
10 2) Color and texture designations
11 3) Information required for reordering special manufactured products
12 b. Instructions for care and maintenance
13 1) Manufacturer's recommendation for types of cleaning agents and methods
14 2) Cautions against cleaning agents and methods which are detrimental to
15 product
16 3) Recommended schedule for cleaning and maintenance
17 3. Content, for moisture protection and weather exposure products:
18 a. Manufacturer's data, giving full information on products
19 1) Applicable standards
20 2) Chemical composition
21 3) Details of installation
22 b. Instructions for inspection, maintenance and repair
23 D. Manual for Equipment and Systems
24 1. Submit 5 copies of complete manual in final form.
25 2. Content, for each unit of equipment and system, as appropriate:
26 a. Description of unit and component parts
27 1) Function, normal operating characteristics and limiting conditions
28 2) Performance curves, engineering data and tests
29 3) Complete nomenclature and commercial number of replaceable parts
30 b. Operating procedures
31 1) Start-up, break-in, routine and normal operating instructions
32 2) Regulation, control, stopping, shut-down and emergency instructions
33 3) Summer and winter operating instructions
34 4) Special operating instructions
35 c. Maintenance procedures
36 1) Routine operations
37 2) Guide to "trouble shooting"
38 3) Disassembly, repair and reassembly
39 4) Alignment, adjusting and checking
40 d. Servicing and lubrication schedule
41 1) List of lubricants required
42 e. Manufacturer's printed operating and maintenance instructions
43 f. Description of sequence of operation by control manufacturer
44 1) Predicted life of parts subject to wear
45 2) Items recommended to be stocked as spare parts
46 g. As installed control diagrams by controls manufacturer
47 h. Each contractor's coordination drawings
48 1) As installed color coded piping diagrams
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 i. Charts of valve tag numbers, with location and function of each valve
2 j. List of original manufacturer's spare parts, manufacturer's current prices, and
3 recommended quantities to be maintained in storage
4 k. Other data as required under pertinent Sections of Specifications
5 3. Content, for each electric and electronic system, as appropriate:
6 a. Description of system and component parts
7 1) Function, normal operating characteristics, and limiting conditions
8 2) Performance curves, engineering data and tests
9 3) Complete nomenclature and commercial number of replaceable parts
10 b. Circuit directories of panelboards
11 1) Electrical service
12 2) Controls
13 3) Communications
14 c. As installed color coded wiring diagrams
15 d. Operating procedures
16 1) Routine and normal operating instructions
17 2) Sequences required
18 3) Special operating instructions
19 e. Maintenance procedures
20 1) Routine operations
21 2) Guide to "trouble shooting"
22 3) Disassembly, repair and reassembly
23 4) Adjustment and checking
24 f. Manufacturer's printed operating and maintenance instructions
25 g. List of original manufacturer's spare parts, manufacturer's current prices, and
26 recommended quantities to be maintained in storage
27 h. Other data as required under pertinent Sections of Specifications
28 4. Prepare and include additional data when the need for such data becomes apparent
29 during instruction of City's personnel.
30 1.7 CLOSEOUT SUBMITTALS [NOT USED]
31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
32 1.9 QUALITY ASSURANCE
33 A. Provide operation and maintenance data by personnel with the following criteria:
34 1. Trained and experienced in maintenance and operation of described products
35 2. Skilled as technical writer to the extent required to communicate essential data
36 3. Skilled as draftsman competent to prepare required drawings
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
2 1.11 FIELD [SITE] CONDITIONS [NOT USED]
3 1.12 WARRANTY [NOT USED]
4 PART 2 - PRODUCTS [NOT USED]
5 PART 3 - EXECUTION [NOT USED]
6 END OF SECTION
7
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 – title of section removed
4/7/2014 M.Domenech Revised for DAP Application
8
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 SECTION 01 78 39
2 PROJECT RECORD DOCUMENTS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Work associated with the documenting the project and recording changes to project
7 documents, including:
8 a. Record Drawings
9 b. Water Meter Service Reports
10 c. Sanitary Sewer Service Reports
11 d. Large Water Meter Reports
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 – General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
23 1.5 SUBMITTALS
24 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
25 City’s Project Representative.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE
30 A. Accuracy of Records
31 1. Thoroughly coordinate changes within the Record Documents, making adequate
32 and proper entries on each page of Specifications and each sheet of Drawings and
33 other Documents where such entry is required to show the change properly.
34 2. Accuracy of records shall be such that future search for items shown in the Contract
35 Documents may rely reasonably on information obtained from the approved Project
36 Record Documents.
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 3. To facilitate accuracy of records, make entries within 24 hours after receipt of
2 information that the change has occurred.
3 4. Provide factual information regarding all aspects of the Work, both concealed and
4 visible, to enable future modification of the Work to proceed without lengthy and
5 expensive site measurement, investigation and examination.
6 1.10 STORAGE AND HANDLING
7 A. Storage and Handling Requirements
8 1. Maintain the job set of Record Documents completely protected from deterioration
9 and from loss and damage until completion of the Work and transfer of all recorded
10 data to the final Project Record Documents.
11 2. In the event of loss of recorded data, use means necessary to again secure the data
12 to the City's approval.
13 a. In such case, provide replacements to the standards originally required by the
14 Contract Documents.
15 1.11 FIELD [SITE] CONDITIONS [NOT USED]
16 1.12 WARRANTY [NOT USED]
17 PART 2 - PRODUCTS
18 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED]
19 2.2 RECORD DOCUMENTS
20 A. Job set
21 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
22 charge to the Contractor, 1 complete set of all Documents comprising the Contract.
23 B. Final Record Documents
24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide
25 the City 1 complete set of all Final Record Drawings in the Contract.
26 2.3 ACCESSORIES [NOT USED]
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
28 PART 3 - EXECUTION
29 3.1 INSTALLERS [NOT USED]
30 3.2 EXAMINATION [NOT USED]
31 3.3 PREPARATION [NOT USED]
32 3.4 MAINTENANCE DOCUMENTS
33 A. Maintenance of Job Set
34 1. Immediately upon receipt of the job set, identify each of the Documents with the
35 title, "RECORD DOCUMENTS - JOB SET".
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 2. Preservation
2 a. Considering the Contract completion time, the probable number of occasions
3 upon which the job set must be taken out for new entries and for examination,
4 and the conditions under which these activities will be performed, devise a
5 suitable method for protecting the job set.
6 b. Do not use the job set for any purpose except entry of new data and for review
7 by the City, until start of transfer of data to final Project Record Documents.
8 c. Maintain the job set at the site of work.
9 3. Coordination with Construction Survey
10 a. At a minimum clearly mark any deviations from Contract Documents
11 associated with installation of the infrastructure.
12 4. Making entries on Drawings
13 a. Record any deviations from Contract Documents.
14 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
15 change by graphic line and note as required.
16 c. Date all entries.
17 d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
18 e. In the event of overlapping changes, use different colors for the overlapping
19 changes.
20 5. Conversion of schematic layouts
21 a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
22 ducts, and similar items, are shown schematically and are not intended to
23 portray precise physical layout.
24 1) Final physical arrangement is determined by the Contractor, subject to the
25 City's approval.
26 2) However, design of future modifications of the facility may require
27 accurate information as to the final physical layout of items which are
28 shown only schematically on the Drawings.
29 b. Show on the job set of Record Drawings, by dimension accurate to within 1
30 inch, the centerline of each run of items.
31 1) Final physical arrangement is determined by the Contractor, subject to the
32 City's approval.
33 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
34 ceiling plenum", "exposed", and the like).
35 3) Make all identification sufficiently descriptive that it may be related
36 reliably to the Specifications.
37 c. The City may waive the requirements for conversion of schematic layouts
38 where, in the City's judgment, conversion serves no useful purpose. However,
39 do not rely upon waivers being issued except as specifically issued in writing
40 by the City.
41 B. Final Project Record Documents
42 1. Transfer of data to Drawings
43 a. Carefully transfer change data shown on the job set of Record Drawings to the
44 corresponding final documents, coordinating the changes as required.
45 b. Clearly indicate at each affected detail and other Drawing a full description of
46 changes made during construction, and the actual location of items.
47 c. Call attention to each entry by drawing a "cloud" around the area or areas
48 affected.
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
CITY OF FORT WORTH EVERMAN OFFSITE WASTEWATER EXTENSION
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102550
Revised April 7, 2014
1 d. Make changes neatly, consistently and with the proper media to assure
2 longevity and clear reproduction.
3 2. Transfer of data to other Documents
4 a. If the Documents, other than Drawings, have been kept clean during progress of
5 the Work, and if entries thereon have been orderly to the approval of the City,
6 the job set of those Documents, other than Drawings, will be accepted as final
7 Record Documents.
8 b. If any such Document is not so approved by the City, secure a new copy of that
9 Document from the City at the City's usual charge for reproduction and
10 handling, and carefully transfer the change data to the new copy to the approval
11 of the City.
12 3.5 REPAIR / RESTORATION [NOT USED]
13 3.6 RE-INSTALLATION [NOT USED]
14 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
15 3.8 SYSTEM STARTUP [NOT USED]
16 3.9 ADJUSTING [NOT USED]
17 3.10 CLEANING [NOT USED]
18 3.11 CLOSEOUT ACTIVITIES [NOT USED]
19 3.12 PROTECTION [NOT USED]
20 3.13 MAINTENANCE [NOT USED]
21 3.14 ATTACHMENTS [NOT USED]
22 END OF SECTION
23
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
24
EXHIBIT “A”
SEWER FACILITY EASEMENT
Part of Lot 2, Block 2 Oak Grove Park First Filing
and part of TCRG Opportunity VII, LLC tracts
Jesse B. Renfro Survey, Abstract No. 1273
and the Jesse Teague Survey, Abstract No. 1546,
City of Fort Worth, Tarrant County, Texas
Page 1 of 2
DESCRIPTION of a 2.198 acre (95,745 square feet) tract of land located in the Jesse B. Renfro Survey,
Abstract No. 1273 and the Jesse Teague Survey, Abstract No. 1546, City of Fort Worth, Tarrant County,
Texas; said tract being a part of Lot 2, Block 2, Oak Grove Park First Filing, an addition to the city of Fort
Worth according to the plat recorded in Volume 388-113, Page 1 of the Plat Records of Tarrant County,
Texas; said tract also being a part of that tract of land described as 35.887 acres in Special Warranty Deed
to TCRG Opportunity VII, LLC recorded in Instrument No. D219207868, a part of that tract of land described
as 34.010 acres in Special Warranty Deed to TCRG Opportunity VII, LLC recorded in Instrument No.
D216176075 and a part of that tract of land described as 68.828 in Special Cash Warranty Deed to TCRG
Opportunity VII, LLC recorded in Instrument No. D216175390 all of the said Official Public Records; said
2.198 acre (95,745 square feet) parcel being more particularly described as follows (bearing system for this
survey is based on the Texas Coordinate System of 1983 (2011 adjustment), North Central Zone 4202,
based on observations made on July 31, 2019 with a combined scale factor of 1.00012):
COMMENCING, at a 1/2-inch iron rod found at the southwest corner of said 35.887 acre tract; said point
being the southeast corner of that tract of land described in Special Warranty Deed to Hickman Family
Limited Partnership recorded in Instrument No. D204401636 of the said Official Public Records and being
in the north line of that tract of land described as 271.95 acres in Limited Warranty Deed to Hillwood/South
Fort Worth, LTD. recorded in Volume 9409, Page 1397 of the Deed Records of Tarrant County, Texas;
THENCE, North 89 degrees, 25 minutes, 30 seconds East, with the south line of said 35.887 acre
tract and the north line of said Hillwood/South Fort Worth, LTD tract, a distance of 730.42 feet to
the POINT OF BEGINNING;
THENCE, North 00 degrees, 32 minutes, 29 seconds West, departing said south line of the 35.887 acre
tract and the said north line of the Hillwood/South Fort Worth, LTD tract, a distance of 121.56 feet to a point
for corner;
THENCE, North 44 degrees, 27 minutes, 31 seconds East, a distance of 10.61 feet to a point for corner;
THENCE, North 00 degrees, 32 minutes, 29 seconds West, a distance of 437.85 feet to a point for corner;
THENCE, North 66 degrees, 35 minutes, 39 seconds West, a distance of 793.23 feet to a point for corner;
THENCE, North 00 degrees, 41 minutes, 28 seconds West, at a distance of 29.60 feet passing the north
line of said 35.877 acre tract and the south line of said 34.010 acre tract, continuing in all a total distance
of 1,106.39 feet to a point for corner;
THENCE, North 45 degrees, 41 minutes, 43 seconds West, a distance of 14.14 feet to a point for corner;
THENCE, North 00 degrees, 41 minutes, 43 seconds West, at a distance of 241.00 feet passing the north
line of said 34.010 acre tract and the south line of said Lot 2, continuing in all a total distance of 257.19 feet
to a point for corner;
THENCE, North 24 degrees, 51 minutes, 44 seconds West, a distance of 500.04 feet to a point for corner;
THENCE, North 00 degrees, 28 minutes, 24 seconds West, a distance of 548.40 feet to a point for corner;
THENCE, North 44 degrees, 31 minutes, 36 seconds East, a distance of 14.14 feet to a point for corner;
THENCE, North 00 degrees, 28 minutes, 24 seconds West, a distance of 711.54 feet to a point for corner;
THENCE, North 89 degrees, 31 minutes, 36 seconds East, a distance of 15.00 feet to a point for corner;
EXHIBIT “A”
SEWER FACILITY EASEMENT
Part of Lot 2, Block 2 Oak Grove Park First Filing
and part of TCRG Opportunity VII, LLC tracts
Jesse B. Renfro Survey, Abstract No. 1273
and the Jesse Teague Survey, Abstract No. 1546,
City of Fort Worth, Tarrant County, Texas
Page 2 of 2
THENCE, South 00 degrees, 28 minutes, 24 seconds East, a distance of 711.54 feet to a point for corner;
THENCE, South 45 degrees, 28 minutes, 24 seconds East, a distance of 14.14 feet to a point for corner;
THENCE, South 00 degrees, 28 minutes, 24 seconds East, a distance of 540.84 feet to a point for corner;
THENCE, South 24 degrees, 51 minutes, 44 seconds East, a distance of 499.96 feet to a point for corner;
THENCE, South 00 degrees, 41 minutes, 43 seconds East, at a distance of 23.81 feet passing the said
south line of Lot 2 and the said north line of the 34.010 acre tract, continuing in all a total distance of 264.68
feet to a point for corner;
THENCE, South 44 degrees, 18 minutes, 32 seconds West, a distance of 14.14 feet to a point for corner;
THENCE, South 00 degrees, 41 minutes, 28 seconds East, at a distance of 1,076.84 passing the said south
line of the 34.010 acre tract and the said north line of the 35.887 acre tract, continuing in all a total distance
of 1,096.66 feet to a point for corner;
THENCE, South 66 degrees, 35 minutes, 39 seconds East, a distance of 793.26 feet to a point for corner;
THENCE, South 00 degrees, 32 minutes, 29 seconds East, a distance of 447.61 feet to a point for corner;
THENCE, South 45 degrees, 32 minutes, 29 seconds East, a distance of 10.61 feet to a point for corner;
THENCE, South 00 degrees, 32 minutes, 29 seconds East, a distance of 121.54 feet to a point for corner
in the south line of said 35.887 acre tract and the north line of the said Hillwood/South Fort Worth, LTD
tract; from said point a 1/2-inch iron rod found for the most southerly southeast corner of the said 35.887
acre tract bears North 89 degrees, 25 minutes, 30 seconds East, a distance of 5.00 feet;
THENCE, South 89 degrees, 25 minutes, 30 seconds West, with the south line of said 35.887 acre tract
and the north line of said Hillwood/South Fort Worth, LTD tract, a distance of 30.00 feet to the POINT OF
BEGINNING;
CONTAINING: 2.198 acre (95,745 square feet) of land, more or less.
(A survey plat of even survey date herewith accompanies this description.)
The undersigned, Registered Professional Land Surveyor, hereby certifies that the foregoing description
accurately sets out the metes and bounds of the easement tract described.
________________________________________
Dustin C. Pustejovsky Date
Registered Professional Land Surveyor No. 6690
Pacheco Koch Consulting Engineers, Inc.
4060 Bryant Irvin Road, Fort Worth, TX 76109
(817) 412-7155
TX Reg. Surveying Firm LS-10008001
3568-19.349.doc
3568-19.349EX1.dwg DRI
06/25/2020
06/25/2020
�
3
0
X
W
�
M
�
i
�
�
�
M
/
�
O
N
0
M
U
M I
H
W `
W
2
(n .
W �W
N
WIz
J I_
H
Q I�
TCRG OPPORTUNITY VII, LLC
(CALLED 35.887 ACRES)
(INST. N0. D219207868)
SEWER FACILITY
EASEMENT
2.198 ACRE
(95,745 SF)
�
�
�
C� �
J �
J p�
J �
Q N
� o
z
W
� O
� z
Q �
� �
z
� � �/� � � �
NOTEs: MATCH LINE (SEE SHEET 1)
1. A metes and bounds description of even survey date herewith
accompanies this plat of survey.
1 /2-INCH
IRON ROD
FOUND (C.M.)
�
0
U
U
Y
a
3
�
�
z
�
�
¢
%
�
�
N
�
0
N
O
�
�
�
�
r
Y
>
0
k'
�
�
a
0
pN ��y
L��P��F ��E���
PQRO�os� E. o� �,� PR� Q�PNI
PQRpP ����1 OJ�N
ER ��lo� PSo�� ��oR
M
�P
2. Bearing system for this survey is based on the Texas Coordinate
System of 1983 (2011 adjustment), North Central Zone 4202,
based on observations made on July 31, 2019 with a combined
scale factor of 1.00012.
� �acheco �OCjh �60 BRYANT IRVIN ROAD
FORT WORTH, TX 76109 817.412.7155
TX REG. ENGINEERING FlRM F-469
TX REG. SURVEYING FIRM LS-10008001
ORA WN BY CHECKED BY SCALE DA TE ✓OB NUMBER
DRI DCP 1"=40' JUNE 2020 3568-19.349
�
�
� TCRG OPPORTUNITY VII, LLC
� (CALLED 35.887 ACRES)
(INST. N0. D219207868)
N
0 20 40 80
GRAPHIC SCALE IN FEET
LEGEND
— — — — PROPERTY LINE
EASEMENT LINE
� POINT FOR CORNER
(UNLESS OTHERWISE NOTED)
IRS - 1/2-INCH IRON ROD W/
"PACHECO KOCH" CAP SET
XS - "+" CUTIN CONCRETE SET
�C.M.� - CONTROLLING MONUMENT
SEWER FACILITY
EASEMENT
PART OF
LOT 2, BLOCK 2 OAK GROVE PARK FIRST FILING
AND THE TCRG OPPORTUNITY VII, LLC TRACTS
JESSE B RENFRO SURVEY, ABSTRACT N0. 1273
AND THE JESSE TEAGUE SURVEY,
ABSTRACT N0. 1546,
CITY OF FORT WORTH, TARRANT COUNTY, TEXAS
PAGE 2 OF 6
�l/�W���� aDopaD
3
0
X
�
M
�
I
�
�
/
�
0
N
0
M
U
�
0
U
U
Y
a
3
�
z
�
�
a
z
/
i
�
�
N
�
0
N
O
�
�
�
�
r
Y
>
0
k'
�
�
a
0
�l/�W���� aDopaD
MATCH LINE (SEE SHEET 4)
� � �
� I12.5' 15.0'
I
SEWER FACI LI TY I
EASEMENT
2.198 ACRE
(95,745 SF) I
�
_
�
�
W
z�
��
� �
Q CO
� o
� �
� O
� N
�
J
0
� z
� �
Q�
�
z
z�
Q
�
Y
U
_
N OTES:
arn
M
�
�
N
�
�
�
N
�
�
�
r
O
N
0 20 40 80
GRAPHIC SCALE IN FEET
TCRG OPPORTUNITY VII, LLC
(CALLED 34.010 ACRES)
(INST. N0. D216176075)
S 00'41'28" E
1096.66'
� 66 3S
.39 h
w
�9 �3
.
I N
�
I W
w
_
N
Iw
w
N
Iw
z
IJ
_
H
Ia
�
I TCRG OPPORTUNITY VII, LLC
(CALLED 35.887 ACRES)
� (INST. N0. D219207868)
1. A metes and bounds description of even survey date herewith
accompanies this plat of survey.
2. Bearing system for this survey is based on the Texas Coordinate
System of 1983 (2011 adjustment), North Central Zone 4202,
based on observations made on July 31, 2019 with a combined
scale factor of 1.00012.
� �acheco �OCjh �60 BRYANT IRVIN ROAD
FORT WORTH, TX 76109 817.412.7155
TX REG. ENGINEERING FlRM F-469
TX REG. SURVEYING FIRM LS-10008001
ORA WN BY CHECKED BY SCALE DA TE ✓OB NUMBER
DRI DCP 1"=40' JUNE 2020 3568-19.349
��'
I z N
W O
� N
W �„�
I N �
a O
W N
I w �
z
J O
W z
I�
��
�
� Z
�
I I
I I
LEGEND
— — — — PROPERTY LINE
EASEMENT LINE
� POINT FOR CORNER
(UNLESS OTHERWISE NOTED)
IRS - 1/2-INCH IRON ROD W/
"PACHECO KOCH" CAP SET
XS - "+" CUTIN CONCRETE SET
�C.M.� - CONTROLLING MONUMENT
SEWER FACILITY
EASEMENT
PART OF
LOT 2, BLOCK 2 OAK GROVE PARK FIRST FILING
AND THE TCRG OPPORTUNITY VII, LLC TRACTS
JESSE B RENFRO SURVEY, ABSTRACT N0. 1273
AND THE JESSE TEAGUE SURVEY,
ABSTRACT N0. 1546,
CITY OF FORT WORTH, TARRANT COUNTY, TEXAS
PAGE 3 OF 6
3
0
X
w
�
M
�
i
�
�
�
i
�
0
N
0
M
U
�
0
U
U
Y
a
3
�
�
z
�
�
¢
%
i
�
�
N
�
0
N
O
�
�
�
�
r
Y
>
0
k'
�
�
a
0
�l/�W���� aDopaD
MATCH LINE (SEE SHEET 5)
� �
10' UTILITY EASEMENT
(VOL. 388-113, PG. 1)
--- � �1----
s �
00 �•
'O �
�. �a
�
— — — — — — — — 16.1
JESSE TEAGUE SURI�EY - ABSTRACT NO. 1,�¢¢
— �.��RENFRO SURUEY - ABSTRACT NO. 1273
5/8-INCH IRON �
ROD FOUND
2.5' -
HICKMAN FAMILY
LIMITED PARTNERSHIP
(INST. N0. D204401636)
15' PIPELINE EASEMENT —
(INST. N0. D207320925)
N 45'41'43" W
14.14'
N 00'41'28" W
1106.39'
�I �
i j� 35.0
"I ///
�
M
�
�
�
�I
�
Z I
�
N
t,
c�,
��
n. ��
LOT 2, BLOCK 2
OAK GROVE PARK
— FIRST FILING — -
— (VOL. 388-113, PG. 1) — -
TCRG OPPORTUNITY VII, LLC
(INST. N0. D216176075)
�� 10' UTILITY EASEMENT
�(VOL. 388-113, PG. 1) — — — — —
23.81'
o�
c�
�
cfl
N
W
i�
�
�
�
e
�
Q
N
20' ACCESS EASEMENT
(INST. N0. D219125804)
TCRG OPPORTUNITY VII, LLC
(CALLED 34.010 ACRES)
(INST. N0. D216176075)
2 5� SEWER FACILITY
i EASEMENT
2.198 ACRE
(95,745 SF)
��
r
���
S 44'18'32" W
14.14'
S 00'41'28" E
1096.66'
_ L � _
MATCH LINE (SEE SHEET 3)
N OTES:
1. A metes and bounds description of even survey date herewith
accompanies this plat of survey.
2. Bearing system for this survey is based on the Texas Coordinate
System of 1983 (2011 adjustment), North Central Zone 4202,
based on observations made on July 31, 2019 with a combined
scale factor of 1.00012.
� �acheco �OCjh �60 BRYANT IRVIN ROAD
FORT WORTH, TX 76109 817.412.7155
TX REG. ENGINEERING FlRM F-469
TX REG. SURVEYING FIRM LS-10008001
ORAWN BY CHECKED BY SCALE DATE ✓OB NUMBER
DRI DCP 1"=40' JUNE 2020 3568-19.349
N
0 20 40 80
GRAPHIC SCALE IN FEET
LEGEND
— — — — PROPERTY LINE
EASEMENT LINE
� POINT FOR CORNER
(UNLESS OTHERWISE NOTED)
IRS - 1/2-INCH IRON ROD W/
"PACHECO KOCH" CAP SET
XS - "+" CUT IN CONCRETE SET
�C.M.� - CONTROLLING MONUMENT
SEWER FACILITY
EASEMENT
PART OF
LOT 2, BLOCK 2 OAK GROVE PARK FIRST FILING
AND THE TCRG OPPORTUNITY VII, LLC TRACTS
JESSE B RENFRO SURVEY, ABSTRACT N0. 1273
AND THE JESSE TEAGUE SURVEY,
ABSTRACT N0. 1546,
CITY OF FORT WORTH, TARRANT COUNTY, TEXAS
PAGE 4 OF 6
�
3
0
X
W
�
M
�
�
�
�
N
/
�
O
N
0
M
U
N
0 20 40 80
GRAPHIC SCALE IN FEET
c�
J � .-.
J � O
., w �
> c�� �
�QI�
� � �
z � N
� • �
� �
O � O
� o z
� W
0 J �
��
� Q z
� �� �i
�
2.5 �
Z I
��,Ai V '
v'• �
� �,�e
�� v'+
90.8� �
so
0
0
10" UTILITY EASEMENT —i-�'
(VOL. 388-113, PG. 1) �
� �
a
10' U TI L I T� A S� N��--�-�{I ;:�/ //��
(VOL. 388-113, PG. 1) � ' � �
■
MATCH LINE (SEE SHEET 4)
�
0
U
U
Y
a
3
�
�
z
�
�
¢
%
i
�
�
N
�
0
N
O
�
�
�
�
r
Y
>
0
k'
�
�
a
0
N OTES:
1. A metes and bounds description of even survey date herewith
accompanies this plat of survey.
2. Bearing system for this survey is based on the Texas Coordinate
System of 1983 (2011 adjustment), North Central Zone 4202,
based on observations made on July 31, 2019 with a combined
scale factor of 1.00012.
� �acheco �OCjh �60 BRYANT IRVIN ROAD
FORT WORTH, TX 76109 817.412.7155
TX REG. ENGINEERING FlRM F-469
TX REG. SURVEYING FIRM LS-10008001
ORA WN BY CHECKED BY SCALE DA TE ✓OB NUMBER
DRI DCP 1"=40' JUNE 2020 3568-19.349
�l/�W���� aDopaD
MATCH LINE (SEE SHEET 6)
� �
SEWER FACILITY LOT 2, BLOCK 2
EASEMENT OAK GROVE PARK
2.198 ACRE FIRST FILING
(95,745 SF) 3 ww I (VOL. 388-113, PG. 1)
� 0 35.0' N� TCRG OPPORTUNITY VII, LLC
N� �°0 (INST. N0. D216176075)
�pp N�
O � � �
N
Z
LEGEND
— — — — PROPERTY LINE
EASEMENT LINE
� POINT FOR CORNER
(UNLESS OTHERWISE NOTED)
IRS - 1/2-INCH IRON ROD W/
"PACHECO KOCH" CAP SET
XS - "+" CUT IN CONCRETE SET
�C.M.� - CONTROLLING MONUMENT
SEWER FACILITY
EASEMENT
PART OF
LOT 2, BLOCK 2 OAK GROVE PARK FIRST FILING
AND THE TCRG OPPORTUNITY VII, LLC TRACTS
JESSE B RENFRO SURVEY, ABSTRACT N0. 1273
AND THE JESSE TEAGUE SURVEY,
ABSTRACT N0. 1546,
CITY OF FORT WORTH, TARRANT COUNTY, TEXAS
PAGE 5 OF 6
N
0 20 40 80
GRAPHIC SCALE IN FEET
I � Ii
10' UTILITY EASEMENT
(VOL. 388-113, PG. 1)
3
0
X
�
M
�
�
�
�
i
�
s
N
0
M
U
�
0
U
L.I
U
Y
d
3
�
z
�
�
¢
%
�
�
N
�
0
N
O
�
�
�
�
r
Y
>
0
k'
�
�
a
0
N 89'31'36" E
15.00'
N 44'31'36" E
14.14'
3
� � /
N l,f)
N � 15.0'
O ^
Z /
U
J � �-.
J � O
_w �
>c���
�Q�
� � �
z � N
� .o
��
oCOo
� o z
� w
O J �
� Q cn
� z
U " `�
�
N OTES:
�l/�W���� aDopaD
�112. 5'
�I� I
NI�, I
00 �
N �
O I
IN
I
10' UTILITY EASEMENT
(VOL. 388-213, PG. 33)
/ I I
�5 S 45'28'24" E
14.14'
� S 00'28'24" E
540 84'
N 00'28'24" W '
548.40' I LOT 2D, BLOCK 2
35.0'
OAK GROVE PARK, FIRST FILING
SEWER FACILITY 2.5' I (VOL. 388-103, PG. 390)
EASEMENT I HICKMAN INDUSTRIAL PARK, LTD
2.198 ACRE
(95,745 SF) (INST. N0. D213240518)
� � �
MATCH LINE (SEE SHEET 5)
1. A metes and bounds description of even survey date herewith
accompanies this plat of survey.
2. Bearing system for this survey is based on the Texas Coordinate
System of 1983 (2011 adjustment), North Central Zone 4202,
based on observations made on July 31, 2019 with a combined
scale factor of 1.00012.
� �acheco �OCjh �60 BRYANT IRVIN ROAD
FORT WORTH, TX 76109 817.412.7155
TX REG. ENGINEERING FlRM F-469
TX REG. SURVEYING FIRM LS-10008001
ORA WN BY CHECKED BY SCALE DA TE ✓OB NUMBER
DRI DCP 1"=40' JUNE 2020 3568-19.349
LEGEND
— — — — PROPERTY LINE
EASEMENT LINE
� POINT FOR CORNER
(UNLESS OTHERWISE NOTED)
IRS - 1/2-INCH IRON ROD W/
"PACHECO KOCH" CAP SET
XS - "+" CUT IN CONCRETE SET
�C.M.� - CONTROLLING MONUMENT
SEWER FACILITY
EASEMENT
PART OF
LOT 2, BLOCK 2 OAK GROVE PARK FIRST FILING
AND THE TCRG OPPORTUNITY VII, LLC TRACTS
JESSE B RENFRO SURVEY, ABSTRACT N0. 1273
AND THE JESSE TEAGUE SURVEY,
ABSTRACT N0. 1546,
CITY OF FORT WORTH, TARRANT COUNTY, TEXAS
PAGE 6 OF 6
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: September 06, 2019
The Fort Worth Water Department’s Standard Products List has been developed to
minimize the submittal review of products which meet the Fort Worth Water
Department’s Standard Specifications during utility construction projects. When
Technical Specifications for specific products, are included as part of the
Construction Contract Documents, the requirements of the Technical Specification
will override the Fort Worth Water Department’s Standard Specifications and the
Fort Worth Water Department’s Standard Products List and approval of the
specific products will be based on the requirements of the Technical Specification
whether or not the specific product meets the Fort Worth Water Department’s
Standard Specifications or is on the Fort Worth Water Department’s Standard
Products List.
Table of Content
(Click on items to go directly to the page)
Items Page
A.Water & Sewer
1. Manholes & Bases/Components ........................................................... 1
2.Manholes & Bases/Fiberglass ............................................................... 2
3.Manholes & Bases/Frames & Covers/Rectangular ............................... 3
4.Manholes & Bases/Frames & Covers/Round ....................................... 4
5.Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight .. 5
6.Manholes & Bases/Precast Concrete .................................................... 6
7.Manholes & Bases/Rehab Systems/Cementitious ................................ 7
8.Manholes & Bases/Rehab Systems/NonCementitious ......................... 8
9.Manhole Insert (Field Operations Use Only) ........................................ 9
10. Pipe Casing Spacer ............................................................................... 10
11. Pipes/Ductile Iron ................................................................................. 11
12. Utility Line Marker ............................................................................... 12
B.Sewer
13. Coatings/Epoxy ..................................................................................... 13
14. Coatings/Polyurethane .......................................................................... 14
15. Combination Air Valves ....................................................................... 15
16. Pipes/Concrete ...................................................................................... 16
17. Pipe Enlargement System (Method) ..................................................... 17
18. Pipes/Fiberglass Reinforced Pipe ......................................................... 18
19. Pipes/HDPE .......................................................................................... 19
20. Pipes/PVC (Pressure Sewer) ................................................................. 20
21. Pipes/PVC* ........................................................................................... 21
22. Pipes/Rehab/CIPP ................................................................................. 22
23. Pipes/Rehab/Fold & Form .................................................................... 23
24. Pipes/Open Profile Large Diameter ...................................................... 24
C.Water
25. Appurtenances ....................................................................................... 25
26. Bolts, Nuts, and Gaskets ....................................................................... 26
27. Combination Air Release Valve ........................................................... 27
28. Dry Barrel Fire Hydrants ...................................................................... 28
29. Meters ................................................................................................... 29
30. Pipes/PVC (Pressure Water) ................................................................. 30
31. Pipes/Valves & Fittings/Ductile Iron Fittings ....................................... 31
32. Pipes/Valves & Fittings/Resilient Seated Gate Valve .......................... 32
33. Pipes/Valves & Fittings/Rubber Seated Butterfly Valve ...................... 33
34. Polyethylene Encasement ..................................................................... 34
35. Sampling Stations ................................................................................. 35
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeWater & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)07/23/97 33 05 13 Urethane Hydrophilic Waterstop Asahi Kogyo K.K. Adeka Ultra-Seal P-201 ASTM D2240/D412/D79204/26/00 33 05 13 Offset Joint for 4' Diam. MH Hanson Concrete Products Drawing No. 35-0048-00104/26/00 33 05 13 Profile Gasket for 4' Diam. MH. Press-Seal Gasket Corp. 250-4G Gasket ASTM C-443/C-361 SS MH1/26/99 33 05 13 HDPE Manhole Adjustment Rings Ladtech, Inc HDPE Adjustment Ring Non-traffic area5/13/05 33 05 13 Manhole External Wrap Canusa - CPS WrapidSeal Manhole Encapsulation SystemCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019* From Original Standard Products ListClick to Return to the Table of Content1
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)1/26/99 33 39 13 Fiberglass Manhole Fluid Containment, Inc. Flowtite ASTM 3753 Non-traffic area08/30/06 33 39 13 Fiberglass Manhole L.F. ManufacturingNon-traffic area* From Original Standard Products ListClick to Return to the Table of Content2
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)* 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 1001 24"x40" WD* From Original Standard Products ListClick to Return to the Table of Content3
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry3002424" Dia.*33 05 13 Manhole Frames and CoversMcKinley Iron Works Inc.A 24 AM24" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1272ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR- 165-LM (Hinged)ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryNF 1274ASTM A48 & AASHTO M30630" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1743-LM (Hinged)ASTM A48 & AASHTO M30630" dia.33 05 13 Manhole Frames and CoversSigma CorporationMH-144N33 05 13 Manhole Frames and CoversSigma CorporationMH-143N33 05 13 Manhole Frames and CoversPont-A-MoussonGTS-STD24" dia.33 05 13 Manhole Frames and CoversNeenah Casting24" dia.10/31/06 33 05 13 Manhole Frames and Covers (Hinged)PowersealHinged Ductile Iron Manhole ASTM A53624" Dia.7/25/03 33 05 13 Manhole Frames and CoversSaint-Gobain Pipelines (Pamrex/rexus)RE32-R8FS30" Dia.01/31/06 33 05 1330" Dia. MH Ring and CoverEast Jordan Iron WorksV1432-2 and V1483 DesignsAASHTO M306-0430" Dia.11/02/10 33 05 1330" Dia. MH Ring and CoverSigma CorporationMH1651FWN & MH1650230" Dia07/19/11 33 05 1330" Dia. MH Ring and CoverStar Pipe ProductsMH32FTWSS-DC 30" Dia08/10/11 33 05 1330" Dia. MH Ring and CoverAccucast220700 Heavy Duty with Gasket Ring30" Dia10/14/13 33 05 1330" Dia. MH Ring and Cover (Hinged & Lockable)East Jordan Iron Works 30" ERGO XL Assembly with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A53630" Dia06/01/17 34 05 1330" Dia. MH Ring and Cover (Hinged & Lockable) CISIP Industries2280 (32")ASTM A 4830" Dia.09/16/19 33 05 13.1030" Dia. MH Ring and Cover Composite Access Products, L.P.CAP-ONE-30-FTW, Composite, w/ Lock w/o Hing30" Dia.* From Original Standard Products ListClick to Return to the Table of Content4
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)* 33 05 13 Manhole Frames and Covers Pont-A-Mousson Pamtight 24" Dia.* 33 05 13 Manhole Frames and Covers Neenah Casting24" Dia.* 33 05 13 Manhole Frames and Covers Western Iron Works,Bass & Hays Foundry 300-24P 24" Dia.* 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. WPA24AM 24" Dia.03/08/00 33 05 13 Manhole Frames and Covers Accucast RC-2100 ASTM A 48 24" Dia.04/20/01 33 05 13 Manhole Frames and Covers (SIP)Serampore Industries Private Ltd. 300-24-23.75 Ring and Cover ASTM A 48 24" Dia.* From Original Standard Products ListClick to Return to the Table of Content5
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13)* 33 39 10 Manhole, Precast Concrete Hydro Conduit Corp SPL Item #49 ASTM C 478 48"* 33 39 10 Manhole, Precast Concrete Wall Concrete Pipe Co. Inc. ASTM C-443 48"09/23/96 33 39 10 Manhole, Precast Concrete Concrete Product Inc. 48" I.D. Manhole w/ 32" Cone ASTM C 478 48" w/32" cone05/08/18 33 39 10 Manhole, Precast Concrete The Turner Company 48", 60" I.D. Manhole w/ 32" Cone ASTM C 478 48", 60"10/27/06 33 39 10 Manhole, Precast Concrete Oldcastle Precast Inc.48" I.D. Manhole w/ 24" Cone ASTM C 478 48" Diam w 24" Ring06/09/10 33 39 10 Manhole, Precast (Reinforce Polymer)Concrete US Composite Pipe Reinforced Polymer Concrete ASTM C-76 48" to 72"09/06/19 33 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 60" & 72" I.D. Manhole w/32" Cone ASTM C-76 60" & 72"* From Original Standard Products ListClick to Return to the Table of Content6
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious* E1-14 Manhole Rehab Systems Quadex04/23/01 E1-14 Manhole Rehab Systems Standard Cement Materials, Inc. Reliner MSPE1-14 Manhole Rehab Systems AP/M Permaform4/20/01 E1-14 Manhole Rehab System Strong Company Strong Seal MS2A Rehab System5/12/03 E1-14 Manhole Rehab System (Liner) Poly-triplex Technologies MH repair product to stop infiltration ASTM D581308/30/06 General Concrete Repair FlexKrete Technologies Vinyl Polyester Repair Product Misc. Use* From Original Standard Products ListClick to Return to the Table of Content7
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious05/20/96 E1-14 Manhole Rehab Systems Sprayroq, Spray Wall Polyurethane Coating ASTM D639/D790* E1-14 Manhole Rehab Systems Sun Coast12/14/01 Coating for Corrosion protection(Exterior) ERTECH Series 20230 and 2100 (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications08/30/06 Coatings for Corrosion Protection Citadel SLS-30 Solids Epoxy Sewer Applications03/19/1833 05 16, 33 39 10, 33 39 20 Coating for Corrosion protection(Exterior) Sherwin WilliamsRR&C Dampproofing Non-Fibered Spray Grade (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only* From Original Standard Products ListClick to Return to the Table of Content8
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16)* 33 05 13 Manhole Insert Knutson Enterprises Made to Order - Plastic ASTM D 1248 For 24" dia.* 33 05 13 Manhole Insert South Western Packaging Made to Order - Plastic ASTM D 1248 For 24" dia.* 33 05 13 Manhole Insert Noflow-Inflow Made to Order - Plastic ASTM D 1248 For 24" dia.09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. LifeSaver - Stainless Steel For 24" dia.09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. TetherLok - Stainless Steel For 24" dia* From Original Standard Products ListClick to Return to the Table of Content9
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13)11/04/02 Steel Band Casing Spacers Advanced Products and Systems, Inc. Carbon Steel Spacers, Model SI02/02/93 Stainless Steel Casing Spacer Advanced Products and Systems, Inc. Stainless Steel Spacer, Model SSI04/22/87 Casing Spacers Cascade Waterworks Manufacturing Casing Spacers09/14/10 Stainless Steel Casing Spacer Pipeline Seal and Insulator Stainless Steel Casing Spacer Up to 48"09/14/10 Coated Steel Casin Spacers Pipeline Seal and Insulator Coated Steel Casin Spacers Up to 48" 05/10/11 Stainless Steel Casing Spacer Powerseal 4810 Powerchock Up to 48"03/19/18 Casing Spacers BWM SS-12 Casing Spacer(Stainless Steel)03/19/18 Casing Spacers BWMFB-12 Casing Spacer (Coated Carbon Steel) for Non_pressure Pipe and Grouted Casing* From Original Standard Products ListClick to Return to the Table of Content10
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13)* 33 11 10 Ductile Iron Pipe Griffin Pipe Products, Co. Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C1513" thru 24"08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co.American Fastite Pipe (Bell Spigot) AWWA C150, C151 4" thru 30"08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co.American Flex Ring (Restrained Joint) AWWA C150, C151 4" thru 30"* 33 11 10 Ductile Iron Pipe U.S. Pipe and Foundry Co. AWWA C150, C151* 33 11 10 Ductile Iron Pipe McWane Cast Iron Pipe Co. AWWA C150, C151* From Original Standard Products ListClick to Return to the Table of Content11
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Utility Line Marker (08/24/2018)* From Original Standard Products ListClick to Return to the Table of Content12
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Coatings/Epoxy 33-39-60 (01/08/13)02/25/02 Epoxy Lining System Sauereisen, Inc SewerGard 210RS LA County #210-1.3312/14/01 Epoxy Lining System Ertech Technical Coatings Ertech 2030 and 2100 Series04/14/05 Interior Ductile Iron Pipe Coating Induron Protecto 401 ASTM B-117 Ductile Iron Pipe Only01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications* From Original Standard Products ListClick to Return to the Table of Content13
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Coatings/Polyurethane* From Original Standard Products ListClick to Return to the Table of Content14
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Combination Air Valves 05/25/18 33-31-70 Air Release Valve A.R.I. USA, Inc. D025LTP02(Composite Body) 2"* From Original Standard Products ListClick to Return to the Table of Content15
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Concrete* E1-04 Conc. Pipe, Reinforced Wall Concrete Pipe Co. Inc. ASTM C 76* E1-04 Conc. Pipe, Reinforced Hydro Conduit Corporation Class III T&G, SPL Item #77 ASTM C 76* E1-04 Conc. Pipe, Reinforced Hanson Concrete Products SPL Item #95-Manhole, #98- PipeASTM C 76* E1-04 Conc. Pipe, Reinforced Concrete Pipe & Products Co. Inc. ASTM C 76* From Original Standard Products ListClick to Return to the Table of Content16
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13)PIM System PIM Corporation Polyethylene PIM Corp., Piscata Way, N.J. Approved PreviouslyMcConnell Systems McLat Construction Polyethylene Houston, Texas Approved PreviouslyTRS Systems Trenchless Replacement System Polyethylene Calgary, Canada Approved Previously* From Original Standard Products ListClick to Return to the Table of Content17
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipe/Fiberglass Reinforced Pipe 33-31-13(1/8/13)7/21/97 33 31 13 Cent. Cast Fiberglass Hobas Pipe USA, Inc. Hobas Pipe (Non-Pressure) ASTM D3262/D375403/22/10 33 31 13 Fiberglass Pipe Ameron Bondstrand RPMP Pipe ASTM D3262/D375410/30/03 Glass-Fiber Reinforced Polymer Pipe Thompson Pipe Group Flowtite ASTM D3262/D37544/14/05 Polymer Modified Concrete Pipe Amitech USA Meyer Polycrete Pipe ASTM C33, A276, F477 8" to 102", Class V06/09/10 E1-9 Reinforced Polymer Concrete Pipe US Composite Pipe Reinforced Polymer Concrete Pipe ASTM C-76* From Original Standard Products ListClick to Return to the Table of Content18
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/HDPE 33-31-23(1/8/13)* High-density polyethylene pipe Phillips Driscopipe, Inc. Opticore Ductile Polyethylene Pipe ASTM D 1248 8"* High-density polyethylene pipe Plexco Inc. ASTM D 1248 8"* High-density polyethylene pipe Polly Pipe, Inc. ASTM D 1248 8"High-density polyethylene pipe CSR Hydro Conduit/Pipeline Systems McConnell Pipe Enlargement ASTM D 1248* From Original Standard Products ListClick to Return to the Table of Content19
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13)12/02/11 33-11-12 DR-14 PVC Pressure Pipe Pipelife Jetstream PVC Pressure Pipe AWWA C900 4" thru 12"10/22/14 33-11-12 DR-14 PVC Pressure Pipe Royal Building Products Royal Seal PVC Pressure Pipe AWWA C900 4" thru 12"* From Original Standard Products ListClick to Return to the Table of Content20
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/PVC* 33-31-20 (7/1/13)* 33-31-20 PVC Sewer Pipe Certain-Teed Products Corp ASTM D 3034 4" thru 15"* 33-31-20 PVC Sewer Pipe Napco Manufacturing CorpASTM D 3034, D 17844" & 8"* 33-31-20 PVC Sewer Pipe J-M Manufacturing Co., Inc. (JM Eagle) ASTM D 3034 4" - 15"12/23/97* 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation SDR-26 and SDR-35 ASTM F 789, ASTM D 30344" thru 15"* 33-31-20 PVC Sewer Pipe Lamson Vylon Pipe ASTM F 789 4" thru 15"33-31-20 PVC Sewer Pipe Royal Building Products Royal Seal Solid Wall Pipe SDR 26 & 35 ASTM 3034 4" thru 15"01/18/18 33-31-20 PVC Sewer Pipe Vinyltech PVC Pipe Gravity Sewer ASTM D3034 4" thru 15"11/11/98 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation "S" Gravity Sewer Pipe ASTM F 679 18" to 27"* 33-31-20 PVC Sewer Pipe J-M Manufacturing Co, Inc. (JM Eagle) ASTM F 679 18" - 27"09/11/12 33-31-20 PVC Sewer Pipe Pipelife Jet Stream SDR-26 and SDr-35 ASTM F-679 18"05/06/0533-31-20PVC Solid Wall Pipe Diamond Plastics CorporationPS 46 ASTM F-679 18" to 48"04/27/0633-31-20PVC Sewer Fittings HarcoSDR-26 and SDR-35 Gasket Fittings ASTM D-3034, D-1784, etc 4" - 15"*33-31-20PVC Sewer Fittings Plastic Trends, In.cGasketed PVC Sewer Main Fittings ASTM D 303411/17/99E100-2Closed Profile PVC Pipe Diamond Plastics CorporationASTM 1803/F794 18" to 48"3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 35 ASTM F679 18"- 24"3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 26 ASTM D3034 4"- 15"3/29/2019 33 31 20Gasketed Fittings (PVC)GPK Products, Inc. SDR 26 ASTM D3034/F-679 4"- 15"9/6/2019 33 31 20 PVC Sewer Pipe NAPCO SDR 26, SDR 35 ASTM D3034 4" - 8"9/6/2019 33 31 20 PVC Sewer Pipe Sanderson Pipe Corp. SDR 26, SDR 35 ASTM D3034 8"* From Original Standard Products ListClick to Return to the Table of Content21
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Rehab/CIPP 33-31-12 (01/18/13)* Cured in Place Pipe Insituform Texark, Inc ASTM F 121605/03/99 Cured in Place Pipe National Envirotech Group National Liner, (SPL) Item #27 ASTM F-1216/D-581305/29/96 Cured in Place Pipe Reynolds Inc/Inliner Technolgy (Inliner USA) Inliner Technology ASTM F 1216* From Original Standard Products ListClick to Return to the Table of Content22
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Rehab/Fold & Form* Fold and Form Pipe Cullum Pipe Systems, Inc.11/03/98 Fold and Form Pipe Insituform Technologies, Inc. Insituform "NuPIpe" ASTM F-1504Fold and Form Pipe American Pipe & Plastics, Inc.Demo. Purpose Only12/04/00 Fold and Form Pipe Ultraliner Ultraliner PVC Alloy Pipeliner ASTM F-1504, 1871, 186706/09/03 Fold and Form Pipe Miller Pipeline Corp. EX Method ASTM F-1504, F-1947 Up to 18" diameter* From Original Standard Products ListClick to Return to the Table of Content23
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Open Profile Large Diameter09/26/91 E100-2 PVC Sewer Pipe, Ribbed Lamson Vylon Pipe Carlon Vylon H.C. Closed Profile Pipe, ASTM F 679 18" to 48"09/26/91 E100-2 PVC Sewer Pipe, Ribbed Extrusion Technologies, Inc. Ultra-Rib Open Profile Sewer Pipe ASTM F 679 18" to 48"E100-2 PVC Sewer Pipe, Ribbed Uponor ETI Company11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double Wall Advanced Drainage Systems (ADS) SaniTite HP Double Wall (Corrugated)ASTM F 2736 24"-30"11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple Wall Advanced Drainage Systems (ADS) SaniTite HP Triple Wall Pipe ASTM F 2764 30" to 60"05/16/11 Steel Reinforced Polyethylene Pipe ConTech Construction Products Durmaxx ASTM F 2562 24" to 72"* From Original Standard Products ListClick to Return to the Table of Content24
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Appurtenances 33-12-10 (07/01/13)01/18/18 33-12-10 Double Strap Saddle Romac 202NS Nylon Coated AWWA C800 1"-2" SVC, up to 24" Pipe08/28/02 Double Strap Saddle Smith Blair #317 Nylon Coated Double Strap Saddle07/23/12 33-12-10 Double Strap Service Saddle Mueller Company DR2S Double (SS) Strap DI Saddle AWWA C800 1"-2" SVC, up to 24" Pipe10/27/87 Curb Stops-Ball Meter Valves McDonald 6100M,6100MT & 610MT 3/4" and 1"10/27/87 Curb Stops-Ball Meter Valves McDonald 4603B, 4604B, 6100M, 6100TM and 6101M 1½" and 2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.FB600-7NL, FB1600-7-NL, FV23-777-W-NL, L22-77NL AWWA C800 2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.FB600-6-NL, FB1600-6-NL, FV23-666-W-NL, L22-66NL AWWA C800 1-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.FB600-4-NL, FB1600-4-NL, B11-444-WR-NL, B22444-WR-NL, L28-44NL AWWA C800 1"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.B-25000N, B-24277N-3, B-20200N-3, H-15000N, , H-1552N, H142276NAWWA C800, ANSF 61, ANSI/NSF 372 2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.B-25000N, B-20200N-3, B-24277N-3,H-15000N, H-14276N, H-15525NAWWA C800, ANSF 61, ANSI/NSF 372 1-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.B-25000N, B-20200N-3,H-15000N, H-15530NAWWA C800, ANSF 61, ANSI/NSF 372 1"01/26/00 Coated Tapping Saddle with Double SS Straps JCM Industries, Inc. #406 Double Band SS Saddle 1"-2" Taps on up to 12" 0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel) JCM Industries, Inc. 412 Tapping Sleeve ESS AWWA C-223 Up to 30" w/12" Out05/10/11 Tapping Sleeve (Stainless Steel) Powerseal 3490AS (Flange) & 3490MJ 4"-8" and 16"02/29/12 33-12-25 Tapping Sleeve (Coated Steel) Romac FTS 240 AWWA C-223 U p to 42" w/24" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST Stainless Steel AWWA C-223 Up to 24" w/12" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST III Stainless Steel AWWA C-223 Up to 30" w/12" Out05/10/11 Joint Repair Clamp Powerseal 3232 Bell Joint Repair Clamp4" to 30"Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW37C-12-1EPAF FTWPlastic Meter Box w/Composite Lid DFW Plastics Inc. DFW39C-12-1EPAF FTW08/30/06 Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW65C-14-1EPAF FTW Class "A"Concrete Meter Box Bass & Hays CMB37-B12 1118 LID-9Concrete Meter Box Bass & Hays CMB-18-Dual 1416 LID-9Concrete Meter Box Bass & Hays CMB65-B65 1527 LID-9* From Original Standard Products ListClick to Return to the Table of Content25
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13)* From Original Standard Products ListClick to Return to the Table of Content26
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Combination Air Release 33-31-70 (01/08/13)* E1-11 Combination Air Release Valve GA Industries, Inc. Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 240 - float, ASTM A 307 - Cover Bolts1" & 2"* E1-11 Combination Air Release Valve Multiplex Manufacturing Co.Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2"* E1-11 Combination Air Release Valve Valve and Primer Corp. APCO #143C, #145C and #147C 1", 2" & 3"* From Original Standard Products ListClick to Return to the Table of Content27
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14)10/01/87 E-1-12 Dry Barrel Fire Hydrant American-Darling Valve Drawing Nos. 90-18608, 94-18560 AWWA C-50203/31/88 E-1-12 Dry Barrel Fire Hydrant American Darling Valve Shop Drawing No. 94-18791 AWWA C-50209/30/87 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Shop Drawing No. D-19895 AWWA C-50201/12/93 E-1-12 Dry Barrel Fire Hydrant American AVK Company Model 2700 AWWA C-50208/24/88 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Drawings D20435, D20436, B20506 AWWA C-502E-1-12 Dry Barrel Fire Hydrant ITT Kennedy Valve Shop Drawing No. D-80783FW AWWA C-50209/24/87 E-1-12 Dry Barrel Fire Hydrant M&H Valve Company Shop Drawing No. 13476 AWWA C-50210/14/87 E-1-12 Dry Barrel Fire Hydrant Mueller CompanyShop Drawings No. 6461 A-423 Centurion AWWA C-50201/15/88 E1-12 Dry Barrel Fire Hydrant Mueller CompanyShop Drawing FH-12A-423 Super Centurion 200 AWWA C-50210/09/87 E-1-12 Dry Barrel Fire Hydrant U.S. Pipe & Foundry Shop Drawing No. 960250 AWWA C-50209/16/87 E-1-12 Dry Barrel Fire Hydrant Waterous Company Shop Drawing No. SK740803 AWWA C-50208/12/16 33-12-40 Dry Barrel Fire Hydrant EJ (East Jordan Iron Works) WaterMaster 5CD250* From Original Standard Products ListClick to Return to the Table of Content28
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Meters02/05/93 E101-5 Detector Check Meter Ames Company Model 1000 Detector Check Valve AWWA C550 4" - 10"08/05/04 Magnetic Drive Vertical Turbine Hersey Magnetic Drive Vertical AWWA C701, Class 1 3/4" - 6"* From Original Standard Products ListClick to Return to the Table of Content29
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/PVC (Pressure Water) 33-31-70 (01/08/13)01/18/18 33-11-12 PVC Pressure PipeVinyltech PVC PipeAWWA C900, AWWA C605, ASTM D17844"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR14AWWA C9004"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR18AWWA C90016"-24"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 14AWWA C9004"-12"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationTrans 21, DR 14, DR 18AWWA C90016"-24"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manifacturing Co., Inc d/b/a JM EagleDR 14"Blue Brute"AWWA C900-16UL 1285ANSI/NSF 61FM 16124"-12"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manifacturing Co., Inc d/b/a JM EagleDR 18"Blue Brute"AWWA C900-16UL 1285ANSI/NSF 61FM 161216"-24"9/6/2019 33 11 12 PVC Pressure PipeUnderground Solutions Inc.DR14 Fusible PVCAWWA C9004" - 8"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR18AWWA C90016" - 24"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR14AWWA C9004"- 12"9/6/2019 33 11 12 PVC Pressure PipeSanderson Pipe Corp.DR14AWWA C9004"- 12"* From Original Standard Products ListClick to Return to the Table of Content30
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13)07/23/92 E1-07 Ductile Iron Fittings Star Pipe Products, Inc. Mechanical Joint Fittings AWWA C153 & C110* E1-07 Ductile Iron Fittings Griffin Pipe Products, Co. Mechanical Joint Fittings AWWA C 110* E1-07 Ductile Iron Fittings McWane/Tyler Pipe/ Union Utilities DivisionMechanical Joint Fittings, SSB Class 350AWWA C 153, C 110, C 11108/11/98 E1-07 Ductile Iron Fittings Sigma, Co.Mechanical Joint Fittings, SSB Class 351AWWA C 153, C 110, C 11202/26/14 E1-07 MJ Fittings AccucastClass 350 C-153 MJ FittingsAWWA C153 4"-12"05/14/98 E1-07 Ductile Iron Joint Restraints Ford Meter Box Co./Uni-FlangeUni-Flange Series 1400 AWWA C111/C153 4" to 36"05/14/98 E1-24 PVC Joint Restraints Ford Meter Box Co./Uni-FlangeUni-Flange Series 1500 Circle-LockAWWA C111/C153 4" to 24" 11/09/04 E1-07 Ductile Iron Joint Restraints One Bolt, Inc.One Bolt Restrained Joint FittingAWWA C111/C116/C153 4" to 12"02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint Restraint EBAA Iron, Inc.Megalug Series 1100 (for DI Pipe)AWWA C111/C116/C153 4" to 42"02/29/12 33-11-11 PVC Pipe Mechanical Joint Restraint EBAA Iron, Inc.Megalug Series 2000 (for PVC Pipe)AWWA C111/C116/C153 4" to 24"08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co.Sigma One-Lok SLC4 - SLC10AWWA C111/C153 4" to 10"03/06/19 33-11-11 Mechanical Joint Retainer Glands(PVC) Sigma, Co.Sigma One-Lok SLCS4 - SLCS12AWWA C111/C153 4" to 12"08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co.Sigma One-Lok SLCEAWWA C111/C153 12" to 24"08/10/98 E1-07 MJ Fittings(DIP) Sigma, Co.Sigma One-Lok SLDEAWWA C153 4" - 24"10/12/10 E1-24 Interior Restrained Joint System S & B Techncial ProductsBulldog System ( Diamond Lok 21 & JM Eagle ASTM F-1624 4" to 12"08/16/06 E1-07 Mechanical Joint Fittings SIP Industries(Serampore)Mechanical Joint FittingsAWWA C153 4" to 24"11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.PVC Stargrip Series 4000ASTM A536 AWWA C11111/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.DIP Stargrip Series 3000ASTM A536 AWWA C11103/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Black For DIPASTM A536 AWWA C111 3"-48"03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR14 PVC PipeASTM A536 AWWA C111 4"-12"03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR18 PVC PipeASTM A536 AWWA C111 16"-24"* From Original Standard Products ListClick to Return to the Table of Content31
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15)Resilient Wedged Gate Valve w/no Gears American Flow Control Series 2500 Drawing # 94-20247 16"12/13/02 Resilient Wedge Gate Valve American Flow Control Series 2530 and Series 2536 AWWA C515 30" and 36"08/31/99 Resilient Wedge Gate Valve American Flow Control Series 2520 & 2524 (SD 94-20255) AWWA C515 20" and 24"05/18/99 Resilient Wedge Gate Valve American Flow Control Series 2516 (SD 94-20247) AWWA C515 16"10/24/00 E1-26 Resilient Wedge Gate Valve American Flow Control Series 2500 (Ductile Iron) AWWA C515 4" to 12"08/05/04 Resilient Wedge Gate Valve American Flow Control 42" and 48" AFC 2500 AWWA C515 42" and 48"05/23/91 E1-26 Resilient Wedge Gate Valve American AVK Company American AVK Resilient Seaded GV AWWA C509 4" to 12"01/24/02 E1-26 Resilient Wedge Gate Valve American AVK Company20" and smaller* E1-26 Resilient Seated Gate Valve Kennedy4" - 12"* E1-26 Resilient Seated Gate Valve M&H4" - 12"* E1-26 Resilient Seated Gate Valve Mueller Co.4" - 12"11/08/99 Resilient Wedge Gate Valve Mueller Co. Series A2361 (SD 6647) AWWA C515 16"01/23/03 Resilient Wedge Gate Valve Mueller Co. Series A2360 for 18"-24" (SD 6709) AWWA C515 24" and smaller05/13/05 Resilient Wedge Gate Valve Mueller Co. Mueller 30" & 36", C-515 AWWA C515 30" and 36"01/31/06 Resilient Wedge Gate Valve Mueller Co. Mueller 42" & 48", C-515 AWWA C515 42" and 48"01/28/88 E1-26 Resilient Wedge Gate Valve Clow Valve Co. AWWA C509 4" - 12"10/04/94 Resilient Wedge Gate Valve Clow Valve Co. 16" RS GV (SD D-20995) AWWA C515 16"11/08/99 E1-26 Resilient Wedge Gate Valve Clow Valve Co. Clow RW Valve (SD D-21652) AWWA C515 24" and smaller11/29/04 Resilient Wedge Gate Valve Clow Valve Co. Clow 30" & 36" C-515 AWWA C515 30" and 36" (Note 3)11/30/12 Resilient Wedge Gate Valve Clow Valve Co. Clow Valve Model 2638 AWWA C515 24" to 48" (Note 3)05/08/91 E1-26 Resilient Seated Gate Valve Stockham Valves & Fittings AWWA C 509, ANSI 420 - stem, ASTM A 276 Type 304 - Bolts & nuts4" - 12"* E1-26 Resilient Seated Gate Valve U.S. Pipe and Foundry Co.Metroseal 250, requirements SPL #743" to 16"10/26/16 33-12-20 Resilient Seated Gate Valve EJ (East Jordan Iron Works)EJ FlowMaster Gate Valve & Boxes08/24/18Matco Gate Valve Matco-Norca225 MRAWWA/ANSI C115/An21.15 4" to 16"* From Original Standard Products ListClick to Return to the Table of Content32
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/Valves & Fittings/Rubber Seated Butterfly Valve 33-12-21 (07/10/14)* E1-30 Rubber Seated Butterfly Valve Henry Pratt Co. AWWA C-504 24"* E1-30 Rubber Seated Butterfly Valve Mueller Co. AWWA C-504 24"and smaller1/11/99 E1-30 Rubber Seated Butterfly Valve Dezurik Valves Co. AWWA C-504 24" and larger06/12/03 E1-30 Valmatic American Butterfly Valve Valmatic Valve and Manufacturing Corp. Valmatic American Butterfly Valve. AWWA C-504 Up to 84" diameter04/06/07 E1-30 Rubber Seated Butterfly Valve M&H Valve M&H Style 4500 & 1450 AWWA C-504 24" to 48"03/19/18 33 12 21 Rubber Seated Butterfly Valve G. A. Industries (Golden Anderson) AWWA C504 Butterfly Valve AWWA C-504 30"-54" * From Original Standard Products ListClick to Return to the Table of Content33
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Polyethylene Encasement 33-11-10 (01/08/13)05/12/05 E1-13 Polyethylene Encasment Flexsol Packaging Fulton Enterprises AWWA C105 8 mil LLD05/12/05 E1-13 Polyethylene Encasment Mountain States Plastics (MSP) and AEP Ind. Standard Hardware AWWA C105 8 mil LLD05/12/05 E1-13 Polyethylene Encasment AEP Industries Bullstrong by Cowtown Bolt & Gasket AWWA C105 8 mil LLD09/06/19 33-11-11 Polyethylene Encasment Northtown Products Inc. PE Encasement fro DIP AWWA C105 8 mil LLD* From Original Standard Products ListClick to Return to the Table of Content34
Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Sampling Station3/12/96 Water Sampling Station Water Plus B20 Water Sampling Station* From Original Standard Products ListClick to Return to the Table of Content35