HomeMy WebLinkAboutOrdinance 25278-01-2022 ORDINANCE NO. 25278-01-2022
AN ORDINANCE ADJUSTIING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER& SEWER REV BOND SERIES 2021 FUND,
IN THE AMOUNT OF $606,505.00, BY INCREASING ESTIMATED RECEIPTS
AND APPROPRIATIONS IN THE MAIN 34, 100, D100 DRAINAGE AREAS SSI
PART 1 PROJECT (CITY PROJECT NO. CO2397), AND DECREASING
ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE UNSPECIFIED
PROJECT (CITY PROJECT NO. UNSPEC) BY THE SAME AMOUNT;
PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN
CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2021-2022 in the
Budget of the City Manager, there shall also be adjusted estimated receipts and appropriations in the Water
and Sewer Rev Bond Series 2021 Fund in the amount $606,505.00, by increasing estimated receipts and
appropriations in the Main 24,100, 13100 Drainage Areas SSI Part 1 project(City Project No. CO2397), and
decreasing estimated receipts and appropriations in the Unspecified project (City Project No. UNSPEC) by
the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25073-09-202 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
Mack(Jan 12,2022 21:18 CST) Jannette S.Goodall(Jan 13,2022 06:35 CS
Douglas W.Black Jannette S. Goodall nk
V r
Sr.Assistant City Attorney City Secretary / •• Q
ADOPTED AND EFFECTIVE: Jannette 11,2022
•Cll�
MAYOR AND COUNCIL COMMUNICATION MAP
60M34SSIP1 CO3-CIRCLEC
AV
i} 5 l .r
oil
Al
r
211,
.PON r �
g'S^ A.
cra 10TH
At
TEXAS
.10
LLA
r M 13TH ST
LANCASTER AVE
xrs,H � sore __ — - _THE us
130,1N - _ UP.RR
FORTWORT
. .
w
5L 2CQO
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 01/11/22 M&C FILE NUMBER: M&C 22-0041
LOG NAME: 60M34SSIP1 CO3-CIRCLEC
SUBJECT
(CD 9)Authorize Execution of Change Order No.3 in the Amount of$586,505.50 and the Addition of 250 Calendar Days to a Contract with
William J.Schultz dba Circle C Construction Company,for Main 34, 100, D100 Drainage Areas Sanitary Sewer Improvements, Part 1, Located in
the Downtown Central Business District,and Adopt Attached Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No.3 to City Secretary Contract No.53641 with William J.Schultz, Inc.dba Circle C Construction
Company in the amount of$586,505.50 and the addition of 250 calendar days for Main 34, 100, D100 Drainage Areas Sanitary Sewer
Improvements Part 1 (City Project No.CO2397)for a revised contract amount of$6,961,431.11; and
2. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Water&Sewer Rev Bond Series 2021
Fund, in the amount of$606,505.00, by increasing estimated receipts and appropriations in the Main 34, 100, D100 Drainage Areas SSI
Part 1 project(City Project No.0O2397),and decreasing estimated receipts and appropriations in the Unspecified project(City Project No.
UNSPEC)by the same amount.
DISCUSSION:
On February 18,2020, Mayor and Council Communication(M&C)20-0096,the City Council authorized a contract with William J.Schultz Inc.dba
Circle C Construction Company in the amount of$5,745,825.00 for Main 34, 100, D100 Drainage Areas Sanitary Sewer Improvements Part 1.
The contract was subsequently revised by Change Order No. 1 in the amount of$13,500.00 administratively authorized on August 3,2020 that
provided a new collection sewer main for several businesses in the Western Union Building, Change Order No.2 in the amount of$615,600.61
authorized on November 17,2020(M&C 20-0855)that provided for the replacement of the water main on Commerce Street(East 17th Street to
East 11 th Street)and the replacement of three deteriorated sanitary sewer mains located in three alleyways in the immediate vicinity.
Change Order No.3 will provide increased and additional funding for the following pay item quantities that are needed on the project due to actual
field conditions that were encountered during construction: 12-inch sewer pipe,42-inch wood box tunnel by other than open cut and increased
costs for temporary and permanent asphalt pavement repair and the change will also provide for the replacement and relocation of water meters
from inside buildings to Commerce Street in public right-of-way on the street. The change order will add an additional 250 calendar days to the
contract in order to complete this project.
In addition to the contract cost,$20,000.00(Water:$10,000.00, Sewer:$10,000.00)is required for project management, inspection,and material
testing.
Appropriations for the Main 34, 100, D100 Drainage Areas Sanitary Sewer Improvements,Part 1 project is depicted below:
Fund Existing Additional Project Total*
Appropriation Appropriations
W&S L56002 Capital Fund $146,941.00 $0.00 $146,941.00
Sewer Capital Fund- $160,227.00' $0.00 7.00 I $160,22 !
Legacy 59607 i i i
Water&Sewer Bond I$6,697,010.00 $O.001$6,697,010.00'
2020A-Fund 56017 -------,L-[ , j
W&S Rev Bonds
Series 2021 -Fund I $665,601.00, $606,505.06V 272,106.001
56019 j
Project Total ($T669,779.00 $606,505.00$8,276,284.00'
*Numbers rounded for presentation.
This project will have no impact on the Water Department's operating budget when completed.
Business Equity:A waiver of the goal for Business Equity subcontracting requirements was requested,and approved by the DVIN, in accordance
with the applicable Ordinance, because the purchase of goods or services is from sources where subcontracting or supplier opportunities are
negligible.
The project is located in COUNCIL DISTRICT 9.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified—All Funds project within the W&S Rev Bonds Series 2021
and upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the W&S Rev
Bonds Series 2021 Fund for the Sanitary Sewer Main 34, 100 project to support the approval of the above recommendation and execution of the
engineering agreement.Prior to any expenditure being incurred,the Water Department has the responsibility of verifying the availability of funds.
Submitted for Cily Manager's Office-W. Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020