HomeMy WebLinkAboutContract 55050-CO2 CSC No.55050-CO2 FORT WORTH. City of Fort Worth Change Order Request Project Name Highland Hills,Monticello and Jessamine St City Sec# 55050 Client Project#(s) 102540 Project Description The repair and reconstruction of failed sidewalks,curbs&gutter,ramps and driveways Contracto Makou Inc Change Order# 2 Date 12/17/2021 City Project Mgr. Iretomiwa Otuyelu City Inspector Curtis Hollingsworth Contract Time Dept. TPW Totals (CD) Original Contract Amount $989,095.00 $989,095.00 230 Extras to Date $48,800.00 $48,800.00 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,037,895.00 $1,037,895.00 230 Amount of Proposed Change Order $27,400.00 $27,400.00 30 Revised Contract Amount $1,065,295.00 $1,065,295.00 260 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) $27,400.00 $27,400.00 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 7.70% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST,25%) $1,236,368.75 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order is to add an additional$27,400.00 to the construction contract 55050 with revised contract amount of$1,065,295.00.Project has available funds required for this change order through the General Capital Project fund and does not need additional funding. It was found during the final stage of project that the actual quantaties of Miscellaneous utility adjustments,Driveways and SOD replacement were more than originally estimated It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's Company Name Contractor(Name) Contract Signature Date Makou Inc Magsood Khan ,�,,,�,,,�,1111n, Jan 7,2022 Inspector/Inspection Supervisor OD�rentracting ontract Compliance Manager Date 1-1111 1„ z� m 7Date Jan 6,2022 ject Officer Date Jan 13,2022 Assistant Director(Dept) Department(Dept) Date laur�n pr%P�r , 1J J an 14,2022 Assistant City Attorney Date Assistant City Manager Date WA Jan 14,2022 __ Jan 14,2022 14—2 11 14—) Council Action(if required) M&C Number M&C Date Approved 0 ATTEST:L1C��L1 cJ' �ddL2 EGG �pp44Ln�� J ette S.Goo&11(Jz n 18,202209' CST) �,4'o o�r4*Q�A Jannette Goodall,City Secretary ��O0° Y o °_o o pd o 0 OFFICIAL RECORD °°ooO000000b watt nEXASo°p CITY SECRETARY FT.WORTH,TX FORT WORTH City of Fort Worth 17'--- Change Order Additions Project Name Highland Hills,Monticello and Jessamine St City Sec# 55050 Cl ient Project# 102540 Contractor Makou Inc PM Irelomiwa Otuyelu Inspector Curtis Hollingsworth Change Order Submittal# O2 Date 12/17/2021 ADDITIONS ty Unit Unit Cost Total Miscellaneous Adjustments(Utilities) TPW 1.00000000 LS Remove Concrete Driveway TPW 680.00000000 SF 6 3213.0401 6"Concrete Driveway TPW 680.00000000 SF $7.75 Curb Address Painting TPW 100.00000000 EA 25 3292.0100 Block Sod Replacement TPW 700.00000000 BY $8.06 TPW S27,400.00 Sub Total Additions Change Order Additions Page 2 of 5 Foa_ T�H City of Fort Worth Change Order Deletions Project Name Highland Hills,Monticello and Jessamine St City Sec# 55050 Client Project# 102540 Contractor Makou Inc PM Iretomiwa Otuyelu Inspector Curtis Hollingsworth Change Order Submittal# O2 Date 12/17/2021 DELL I IONS ty Unit Unit Uostota TPW S0.00 �iub I otal Deletions Change Order Deletions Page 3 of 5 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total $0.00