Loading...
HomeMy WebLinkAboutContract 55049-CO1 CSC No.55049-COI FORT WORTH. City of Fort Worth Change Order Request Project Name HMAC Surface Overlay 2019-7 City Sec# 55049 Client Project#(s) 102804 Project Description Street Rehabilitation of various segments at Brentmoor area Contracto Advanced Paving Acquisition LTD Change Order# 1 Date 1/27/2022 City Project Mgr. Iretomiwa Otuyelu City Inspector Mark Khan Contract Time Dept. TPW Totals (CD) Original Contract Amount $850,650.00 $850,650.00 180 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $850,650.00 $850,650.00 180 Go to ADD&DEL Tabs to Enter CO Backup $0.00 50 Revised Contract Amount $850,650.00 $850,650.00 230 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST,25%) $1,063,312.50 JUSTIFICATION(REASONS)FOR CHANGE ORDER This Change Order is to add 50 calendar days to Construction Contract#55049. During the construction of this project,after all paving had been completed,there was enough money left in the contract to increase the quantity of side walks and ramps that needed repair at Terrell Ave.Approximately 4,400 sf of concrete sidewalks was added to the initial estimate of 2,000 sf.We used about 10 days for project administration,and 40 days to complete the extra work. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's Company Name Contractor(Name) Contract Signature Date Advanced Paving Acquisition Ltd Sam Garrett s�� Jan 28,2022 Inspector/Inspection Super v Date Project and Contract Compliance Manager Date APA" Jan 30,2022 ­11Jan 31,2022 Program Manager Date Senior Capital Project Officer Date Jan 31,2022 Feb 1,2022 Assistant Director(Dept) Date Director,Contracting Department(Dept) Date Lip~ Feb 1,2022 IJ1 . Feb 1,2022 Assistant City Attorney Date JAssistant City Manager Date �A 2—z,2i0I n Feb 2,2022 4 „ 1 Feb 3,2022 auncil Action(if required) M&C Number M&C Date Approved 0 ooF�RT� as ATTEST:Tgnnetfe 5.Gaa�Jgll ddj Jan-fteS.G..&11(Feb 3,20220836CST) A�o*o ' 0000p �0% Aad^^Jannette Goodall,City Secretary C-o1 �PPv8o0 *� OFFICIAL RECORD dQn�nExASapp CITY SECRETARY FT.WORTH,TX FORTWORTH City of Fort Worth 1y*`-- Change Order Additions Project Name HMAC Surface Overlay 2019-7 City Sec# 55049 Cl ient Project# 102804 Contractor Advanced Paving Acquisition LTD PM Irelomiwa Otuyelu Inspector Mark Khan Change Order Submittal# O1 Date 1/27/2022 ADDITIONS ty Unit Unit Cost Total TPW $0.00 Sub Total Additions Change Order Additions Page 2 of 5 Foa_ T�H City of Fort Worth Change Order Deletions Project Name HMAC Surface Overlay 2019-7 City Sec# 55049 Client Project# 102804 Contractor Advanced Paving Acquisition LTD PM Iretomiwa Otuyelu Inspector Mark Khan Change Order Submittal# O1 Date 1/27/2022 DELL I IONS ty Unit Unit Uostota TPW S0.00 �iub I otal Deletions Change Order Deletions Page 3 of 5 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total $0.00