HomeMy WebLinkAboutContract 55988-CO1 FORT WORTH. City of Fort Worth
Change Order Request CSC No.55988-COl
Project Name Road&Parking Lot Improvements at Gateway Park and Rockwood Park City Sec# 55988
Client Project#(s)
Project Road&Parking Lot Improvements at Gateway Park,Rockwood Park,and Andrew Doc Session Community
Description
Contractor Fort Worth Civil Constructors,LLC Change Order# 1 Date 2/2/2022
City Project Mgr. Carlos M Gonzalez City Inspector Oscar Augillon
Dept. PARD Contract Time
Totals (CD)
Original Contract Amount $1,240,378.47 $1,240,378.47 120
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,240,378.47 $1,240,378.47 120
Go to ADD&DEL Tabs to Enter CO Backup $72,281.25 $72,281.25 60
Revised Contract Amount $1,312,659.72 $1,312,659.72 180
Original Funds Available for Change Orders $72,281.25 $72,281.25
Remaining Funds Available for this CO 1 $72,281.25 $72,281.25
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.83%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,550,473.09
JUSTIFICATION(REASONS)FOR CHANGE ORDER
See attachment for Justification:
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
Contractor's Company Name Contractor(Name Contract Signature Date
Fort Worth Civil Constructors,LLC Austin Alumbaugh A—v° Feb 2,2022
Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date
44 Feb 3,2022 '�r/,FO. r j.-,.�.�/ Feb 3,2022
Program ManagerDate Senior Capital Project Officer Date
t` Feb 4,2022
Assistant Director(Dept) Date Director,Contracting Department(Dept) Date
Feb 6,2022 , Feb 8,2022
Assistant City Attorney Date Assistant City Manager Date
Feb 8,2022 a�u Feb 8,2022
Council Action(if required) ad
M&C Number N/A M&C Date Approved N/A
ATTEST:��s
J a n nette S.Goodall(Fe 0,202213:52 CST) AT
Jannette Goodall,City Secretary
�,o4vnnnIlIl
oFORT�ad OFFICIAL RECORD
o °o CITY SECRETARY
9v8 a=d°
p o o c FT. WORTH, TX
FORT WORTH City of Fort Worth
-�'!'�-- Change Order Additions
Project Name Road&Parking Lot Improvements at Gateway Park and Rockwood Park City Sec# 55988
Client Project# 102012(34018-0800450-5740010-102012-3780-9999-108010199),102015(34018-0800450-5740010-102015-3780-9999-108010199)&
Contractor Fort Worth Civil Constructors,LLC PM Carlos M Gonzalez Inspector FOscar Aug illon
Change Order Submittal# Date 2/1/2022
ADDITIONS
y Unit UnitCost Total
GATEWAY PARK
PARKING LOT CHANGE ORDER-LINE C
1-26 10"Pavement Pulverization(see Page 13 of 21). PARD 7,552.00000000 SY 8.35
1-27 2"Asphalt Pvmt Type D(See Page 13 of 21). PARD 7,552.00000000 SY $16.15
1-28 Cem-Line(@32lbs/SY)(See Page 13 of 21). PARD 121.00000000 TN $283.017
1-29 Installation of 6"Concrete Parking Lot(see Page 4 of 21). PARD 52.40000000 SF 22.95
1-30 Demo Existing Concrete Parking Lot(see Page 9 of 21). PARD 1.00000000 LS $4,970.89
1-31 Installation of 6"Concrete Parking Lot(see Page 9 of 21). PARD 1,645.00000000 SF 3.90
1-32 Demo Existing Curb&Gutter PARD 1.00000000 LS $417.17
1-33 Installation of 6"Concrete Curb and Gutter PARD 86.00000000 LF $70.70
ROCKWOOD PARK
SOUTH UNIVERSITY ENTRANCE ROAD(BRIDGE UNDERPAST
2-21 10"Pavement Pulverization(see Page 13 of 21). PARD 1,985.00000000 SY $8.35
2-22 2"Asphalt Pvmt Type D(See Page 13 of 21). PARD 1,985.00000000 SY 16.5
2-23 Cem-Line(@32lbs/SY)(See Page 13 of 21). PARD 32.00000000 TN $283.017
MISC.IMPROVEMENTS
2-25 Asphalt Speed Hump-West Parking Lot PARD 26.00000000 EA $715.00
2-26 Asphalt Speed Hump-East Parking Lot PARD 8.00000000 EA $715.017
2-27 Asphalt Speed Hump Stripping PARD 34.00000000 EA $170.017
2-28 Sealcoat Parking Lot(See Page 12 of 21). PARD 13,752.00000000 SF $0.77
2-29 Low Water Crossing,Demo,Grading&Grassing PARD 1.00000000 LS 24,875.00
2-30 Installation of 6"Concrete Curb and Gutter(West Parking Lot) PARD 178.71000000 LF $62.517
2-31 Installation of 6"Concrete Curb and Gutter(East Parking Lot) PARD 18.00000000 LF $70.70
ANDREW"DOC"SESSIONS
1-01 Demo&Installation of 6"Asphalt Handicap Parking Lot. Including PARD 1.00000000 LS 31,000.00
Installation of(3)Wheelstops&Restriping Handicap Spots
PARD $404,238.75
Sub Total Additions $404,238.75
Change Order Additions Page 1 of 1
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Road&Parking Lot Improvements at Gateway Park and Rockwood Park City Sec# 55988
Client Project# 102012(34018-0800450-5740010-102012-3780-9999-108010199),102015(34018-0800450-5740010-102015-3780-9999-108010199)&
Contractor Fort Worth Civil Constructors,LLC PM Carlos M Gonzalez Inspector FOscar Augillon
Change Order Submittal# Date 2/1/2022
DELETIONS
y Unit UnitCost Total
UNIT 1 ALTERNATE BID ITEMS-GATEWAY PARK
1-02 Installation of 6"Concrete Parking Lot(see Page 4 of 21). PARD 2,040.00000000 SF $12.25
1-04 Installation of 7"Concrete Valley Gutter(see Page 4 of 21). PARD 350.00000000 SF $14.75
1-07 Demo existing Concrete Parking Lot(see Page 9 of 21). PARD 1.00000000 LS $19,260.00
1-08 Installation o Concrete Parking Lot(see Hage 9 of 21). PARD 1.00000000 LS $2b,04b.00 $2b,04b.00
UNIT 3 ALTERNATE BID ITEMS-ALLOWANCE
3-02 Gateway Park Allowance PARD 1.00000000 LS $5,000.017
3-02 Gateway Park Allowance PARD 1.00000000 LS $5,000.017
3-03 Gateway Park Allowance PARD 1.00000000 LS $10,000.00
3-04 lGateway Park Allowance PARD 1.00000000 LS $20,000.00
3-05 Gateway Park Allowance PARD 1.00000000 LS $40,000.00
3-06 Gateway Park Allowance PARD 1.00000000 LS $50,000.00
3-07 Rockwood Park Allowance PARD 1.00000000 LS $2,500.00
3-08 Rockwood Park Allowance PARD 1.00000000 LS $5,000.00
3-09 Rockwood Park Allowance PARD 1.00000000 LS $10,000.00
3-10 Rockwood Park Allowance PARD 1.00000000 LS $20,000.00
3-11 Rockwood Park Allowance PARD 1.00000000 LS $40,000.00
3-12 Rockwood Park Allowance PARD 1.00000000 LS $50,000.00
PARD $331,957.50
Sub Total Deletions $331,957.50
Change Order Deletions Page 1 of 1
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
N/A
Total $0.00
Previous Change Orders
co# DATE AMOUNT
N/A
Total $0.00
CHANGE ORDER No.1 JUSTIFICATION
During construction, several issues required changes to continue with the project.
Rockwood Park
1. The original project scope of work included re-paving the southeast park road entrance
at Rockwood Park that crosses under the University bridge. However, this portion of the
project was not included in the bid documents as the TPW Department Storm Water
Division had a Trinity River erosion control project in the same work area with an
overlapping construction schedule., However, TPW Storm Water completed their work
before the scheduled completion date allowing PARD to add the remaining 1,985 square
yards of the park road.
2. During construction, the contractor and city staff ran into issues with the public using the
parking lot as a race track. Staff proposed adding speed humps in the parking lot to
discourage further racing. Staff will also use the remaining available funds to seal-coat
and strip the remaining park road.
3. During construction, it was determined that due to drainage issues surrounding the
exiting small parking lot to the northeast, water was retained within the new paving work.
The city requested the contractor to re-grade, demo a portion of an existing sidewalk,
and install a low-water crossing to provide positive drainage in the parking lot and the
park.
4. During construction, it was determined that additional curb & gutter footage was required
to fix the new parking lot layout. This change order will add curb & gutter linear footage
quantities to the contract.
Gateway Park
1. During construction, it was determined that there was an error in the estimated
quantities. Filed Measured quantities for the asphalt replacement exceeded the
estimated quantities. The contractor agreed to completed the additional paving under
the contract unit prices.
2. During construction, it was determined that most of the existing concrete parking lot
square footage was in good condition. Therefore, this change order will deduct the
quantity not used.
Andrew "Doc" Sessions Community Center
1. Repaving the Community Center Parking lot which was included in the 2014 Bond
Program.