HomeMy WebLinkAboutContract 55734-CO1 CSC No.55734-COI FORT WORTH. City of Fort Worth Change Order Request Project Name Shoreview and Bomber HROM City Sec# 55734 Client Project#(s) 103051 Project This Project will reconstruct the culvert crossing on Shore View Drive west of the intersection of Bomber Road to mitigate hazardous flooding of the Description roadway during significant rain events to protect the Irfe and safety of the motorists. Contracto IBCTX,LLC Change Order# 1 Date 2/2/2022 City Project Mgr. Michael Wellbaum City Inspector Steven Aguirre Contract Time Dept. TPW Totals (CD) Original Contract Amount $1,658,900.00 $1,658,900.00 180 Extras to Date $0.00 Credits to Date $0.00 Pending Change Orders(in M&C Process) Contract Cost to Date $1,658,900.00 $1,658,900.00 180 Amount of Proposed Change Order $12,284.38 $12,284.38 26 Revised Contract Amount $1,671,184.38 $1,671,184.38 206 Original Funds Available for Change Orders S414,725.00 $414,725.00 Remaining Funds Available for this CO $414,725.00 $414,725.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.74% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,073,625.00 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order provides for additional pavement needed to complete the project.This change order also provides for additional erosion control measures to protect Lake Worth that were not included in the original plans.Based on weather related delays,this change order also provides for additional contract time. This change order will also serve to reconcile all pay items and includes a credit for an unused item. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's Company Name ontractor(Name Contract Signature IBCTX Alex Hammes Feb 7,2022 Inspector/Inspection Supe visor Date Project and Contract Compliance Manager ��n Feb 7,2022 �i Feb 9,2022 Program Manager Date Senior Capital Project Officer Feb 9,2022 Feb 9,2022 Assistant Director(Dept) Date Director,Contracting Department(Dept) Date auren vneur Feb 9,2022 Feb 9,2022 �11,1 3m 12c-1 Assistant City Attorney Date Assistant City Manager Date Feb 9,2022 Feb 10,2022 ',1,-22121 m Council Action(if required) M&C Number N/A M&C Date Approved N/A ATTEST: ).�.,�f� 5' C/aa ,OD .00vbnp4 ¢n ppa OR �aa pOF°°°°°°°°,4 d OFFICIAL RECORD Jannette Goodall,City Secretary ��° °Odd o1.o 0�' CITY SECRETARY Pvo 0 P. pd�o o*dd FT.WORTH,TX dd ° 4y 4 °°°°°°°°°°° a at<�nexA5o4p FORTWORTH City of Fort Worth I---- Change Order Additions Project Name Shoreview and Bomber HROM City Sec# 55734 Cl ient Project# 103051 Contractor IBCTX,LLC PM Michael Wellbaum Inspector Steven Aguirre Change Order Submittal# O1 Date 2/2/2022 ADDITIONS ITEM DESCRIPTION DEPT City Unit Unit Cost Total 241.11 Remove Asphalt Pvmt TPW 245.00 BY $10.00 $2,450.00 Flexible Base,Type A,GR-1 TPW SY 3212.0302 2"Asphalt Pvmt Type D TPW 311.46 BY $14.00 S Asphalt Base Type B TPW SY 171.0101 4"SLD Pvmt Marking HAS(W) TPW 285.00 LF S5.00 SLD Pvmt Marking HAS(Y) TPW LF S . 9999.0007 Message Board TPW 1.00 LS S2,500.00 S2,500.00 —7799.707 Turbidity TPW LS S TPW $19,159.38 Sub Total Additions S Change Order Additions Page 2 of 4 FORT WORTH City of Fort Worth V`- Change Order Deletions Project Name Shoreview and Bomber HROM City Sec# 55734 Client Project# 103051 Contractor IBCTX,LLC PM Michael Wellbaum Inspecto Steven Aguirre Change Order Submittal# O1 Date 2/2/2022 DELL I IUNS ITEM DESCRIPTION DEF I y unit unit Cost o a an ary Sewer Pipe TPIN $6,875.00 Sub TotalDeletions Change Order Deletions Page 3 of 4 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total 1 $0.00